Sei sulla pagina 1di 1

OBRA: CONSTRUCCION DE PUENTE PEATONAL SOBRE EL ARROYO COYUTLA, ENTRE LAS

. CALLES VICENTE GUERRERO, PIPILA Y SALVADOR DIAZ MIRON, COYUTLA, VER. HOJA: 1
LOCALIDAD: COYUTLA, VER.
No. OBRA: 2018300510301 FECHA: 9-Abril/2018
Documento No. 4 b) Análisis Detallado de Costos Indirectos
Importe Importe
Importe / Importe / Importe
Mensual Período Total Período Total
Oficina % Oficina Oficina Oficina Oficina de
Descripción Períodos Central Participación Central Central de Campo Campo
Cálculo de Indirectos $5,941.57 $17,824.72

HONORARIOS, SUELDOS Y $5,159.00 $13,400.00


PRESTACIONES
Personal Directivo $2,010.00 $0.00
Director General 1.34 $20,000.00 7.50 $1,600.00 $2,010.00 $0.00 $0.00
Personal Técnico $1,373.50 $13,400.00
Jefe de proyectos 1.34 $12,500.00 5.00 $625.00 $837.50 $0.00 $0.00
Auxiliar de proyectos 1.34 $8,000.00 5.00 $400.00 $536.00 $0.00 $0.00
Residente de obra local 1.34 $0.00 5.00 $0.00 $0.00 $10,000.00 $13,400.00
Personal Administrativo $1,775.50 $0.00
Jefe del departamento 1.34 $10,000.00 5.00 $500.00 $670.00 $0.00 $0.00
administrativo
Contador 1.34 $9,000.00 5.00 $450.00 $603.00 $0.00 $0.00
Auxiliar de Compras 1.34 $7,500.00 5.00 $375.00 $502.50 $0.00 $0.00

DEPRECIACION, $418.75 $2,010.00


MANTENIMIENTO Y RENTAS
Edificios y Locales 1.34 $4,250.00 5.00 $212.50 $284.75 $0.00 $0.00
Bodegas 1.34 $2,000.00 5.00 $100.00 $134.00 $500.00 $670.00
Campamentos 1.34 $0.00 5.00 $0.00 $0.00 $1,000.00 $1,340.00

FLETES Y ACARREOS $0.00 $670.00


De campamentos 1.34 $0.00 5.00 $0.00 $0.00 $500.00 $670.00

GASTOS DE OFICINA $234.50 $1,744.72


Papelería y Útiles de Escritorio 1.34 $750.00 5.00 $37.50 $50.25 $500.00 $670.00
Correos, Teléfonos, Telégrafos, 1.34 $800.00 5.00 $40.00 $53.60 $500.00 $670.00
Radio
Luz, Gas y Otros Consumos 1.34 $750.00 5.00 $37.50 $50.25 $302.03 $404.72
Coias y duplicados 1.34 $600.00 5.00 $30.00 $40.20 $0.00 $0.00
Gastos de Concursos 1.34 $600.00 5.00 $30.00 $40.20 $0.00 $0.00

SEGUROS Y FIANZAS $129.32 $0.00


Primas por Seguros 1.34 $800.00 5.00 $40.00 $53.60 $0.00 $0.00
Primas por Fianzas 1.34 $1,130.20 5.00 $56.51 $75.72 $0.00 $0.00

RESUMEN

HONORARIOS, SUELDOS Y $5,159.00 $13,400.00


PRESTACIONES
DEPRECIACION, $418.75 $2,010.00
MANTENIMIENTO Y RENTAS
FLETES Y ACARREOS $0.00 $670.00
GASTOS DE OFICINA $234.50 $1,744.72
SEGUROS Y FIANZAS $129.32 $0.00

TOTAL $5,941.57 $17,824.72

A) Costo directo de la obra: 198,052.43


B) Gastos de oficina central para la obra: 5,941.57
D) Indirectos de la oficina en obra: 17,824.72

E) % indirectos de oficina central = ( B / A ) 100 = 3.00


F) % indirectos de oficina en obra = ( D / A ) 100 = 9.00

% DE INDIRECTOS = E + F = 12.00

________________________________________
María Guadalupe León Hernández
Representante Legal

Potrebbero piacerti anche