Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
February 1999
Impact of increasing contribution
of dispersed generation
on the power system
- Final Report -
Members of WG 37.23 :
2 INTRODUCTION
2.1 Reasons for increasing share of DG in different countries
2.2 Objectives of the report 2
5 TECHNICAL INFLUENCE OF DG 7
5.1 Generation and Transmission System 8
5.2 Distribution system 9
5.2. l Network capacity 9
5.2.2 Connection criteria 10
5.2.3 Additional effects 10
7 CONCLUSIONS 16
8 BIBLIOGRAPHY 17
Glossary
maximum admissible increase of steady state voltage with rated po\ver injection
from DG in comparison to the situation without DG
maximum admissible amplitude of fast voltage fluctuations (e.g. caused by switch-
ing)
AG asyncluonous (induction) generator
ancillary services services related to electrical energy supply other than supply with energy and power
(e.g. balance service, frequency control, voltage control, ... )
BHPS Block heating power station
centrally dispatched SO may directly control the active and/or reactive power output
CHP Combined Heat and Power Generation
DG Dispersed generation (not centrally planned, today not centrally dispatched, usually
connected to the distribution network and smaller than 50 - 100 MW)
EHV Extra high voltage: U, > 220 kV
HT high tariff zone
HV High voltage: 50 kV < U, s 220 kV
ISO Independent system operator
LT low tariff zone
LV Low voltage: U, S 1 kV
MV Medium voltage: 1 kV < U, s 50 kV
p active power
P,. long term flicker level (average of periods longer than 30 min)
P,, short term flicker level (average of periods shorter than 30 min)
SG synchronous generator
so System operator (may also own generation facilities)
unbundled seperation (possibly only in accountancy) of generation, transmission and/or re-
taiVdistribution business in formerly vertically integrated utilities
vertically integrated integration of generation, transmission, distribution and retail business in one com-
pany
WEC Wind Energy Converter
- I -
2 Introduction
Electricity supply is challenged from deregulation and third party access to the network. In consequence of this dis-
persed generation (DG) from IPPs based on co-generation units, renewable energies or other conventional sources
increases in all countries.
Before starting the report a brief definition of what is understood as dispersed generation in the work of WG 37-23 is
given. DG as considered in WG 37-23 is
• not centrally planned,
• today not centrally dispatched,
• usually connected to the distribution network and
• smaller than 50 - I 00 MW.
Not centrally planned or dispatched means that major influences such as unit commitment or reactive power generation
are out of control of the system operator.
active power injection for reducing the voltage level on the connection point. This type of generators is usually installed
in weak grids where in case of low load and high power injection the voltage level may rise above the tolerable range.
Furthermore, this regulation can guarantee that also in case of temporary network reconfigurations, e. g. after network
failures or for maintenance, the voltage level is not lifted above the tolerable range.
WEC, which are carried out with induction generators contribute to the short circuit level in the network. The usual
contribution is in the range between 4 and 8 times of the nominal current depending on the type of generator. Further-
more, WEC usually introduce fast power fluctuations in the network. They are caused on the one hand by wind fluc-
tuations, on the other hand by disturbances of the WEC itself (mostly by the blades passing the tower). Those fast volt-
age fluctuations must be limited depending on the strength of the network on the connection point. 1'able 3.1 summa-
rizes the main characteristics of two types ofWEC which indicate the range of the possible technologies realized today.
induction generator synchronous generator
directly coupled to the grid, coupled via a pulse-width-modulated
stall regulation converter pitch regulation
~s ~s
concept
•
reactive-power-regulation sometimes compensated to coscp=l variable cos cp
active-power-regulation no regulation active regulation (limitation possible)
voltage regulation no regulation by reactive- and active power regulation
flicker usually high usually low
contribution to short-circuit current 4 ... 8 ·I, I,
peak current Imax ~ 2,5 · Ir lmax =Ir
A new concept for HVDC transmission based on VSC (Voltage Source Converter) technology opens up for d.c. con-
nection of a wind farm to the a.c. grid. The a.c./d.c. terminals, which are fully equipped FACTS components, will pro-
vide voltage regulation. The concept will be studied in a demonstration project in Denmark.
The power plant with dams, reservoirs and powerlines will have both positive and negative effects on the local envi-
ronment, however doubtlessly the generation of electricity in hydro-electric power stations causes no pollution of the
environment. The gross theoretical potential for hydropower is estimated to be around 36.000 TWh woldwide. The
exploitable potential exceeds 14.000 TWh. Around 18 o/o, or 2500 TWh of this potential is utilised. Water power is
hence probably the world's most important renewable energy resource.
As the situation is today, it \viii probably take some more years for fuel cells to become a competitive con1n1ercial tech-
nology. Due to the development within gas turbines, fuel cells are expected to become competitive only for units below
approx. 20 MW.
In case IPPs or DGs - as assumed here - are not centrally dispatched and do not provide for ancillary services but profit
from them there will be an unbalance on the market depending on the respective market structure. Furthermore DG are
often installed close to custon1er load in the distribution grid wluch in principle helps reducing the transn1iss1on losses.
On the other hand the connection to distribution nertworks may cause reinforcements in other parts of the grid. ·rhis
extra burden is not carried by DG in case they have to pay only shallow connection costs. Other types like WEC in-
crease losses on the distribution level as a result of their high penetration in rural areas with low load density. 'fhis
requires the definition of adequate transmission tariffs.
verocally integrated utility (VIU) Gen 1 Gen 2 Gen 3 Gen 4
industnal plants
!PPs
customers customers
The above mentioned circumstances lead to a different share of DG in the studied countries, as pointed out in Table 4.1.
In Average today a share of the maximum load of 5 % up to 9 % in the EU is being observed in the countries. Some
countries, e.g. The Netherlands and Denmark, have already reached values near to 40 %, which has already lead to
countermeasures as adequate tariffs, joint ventures and reconstruction of the 150/132-kV-Network.
In the long run, a much higher potential is expected, especially in Spain, where already 9000 MW of wind energy
converters and 16000 MW ofCHP are projected today. Other countries with expectation of increasing share ofDG are
Germany, Canada, Derunark. Several countries see increasing values within the next years, lead by an estimated theo-
retical potential in Canada of75%. The target of the EU in order to reduce the C0 2-emission is set to 18 % in 2010, and
a theoretical potential of 40 o/o was identified.
Today Future Potential
Australia 3%(2000 MW) 9%(9000 MW)
Belgium 10 % Up to 20 %
Canada 10%,2900MW 22000 MW~ 75,8%
Denmark 37 % (1600 MW CHP I 900 MW WEC) 2000 MW CHP, 5000 MW WEC
France less than 5%, max 8 MVA-Units EC-Rule: more than 8 MW-Units
Germany 1260 MW small CHP I 6000 MW CHP I 2400 MW WEC Up to 35 % CHP, >3600 MW WEC
NL 40% ?
Norway I% (Hydro, low prices) ?
Spain 300MW 9000 MW WEC, 16000 MW CHP
EU Targets 9% 18 % by 20 I 0, theoretical 40 %
It can be summarized that the reasons for an increasing share of DG are not directly depending on the market structure.
It can be assumed that in all countries which do not have extremely low generation costs in the bulk power (like e.g.
Norway does) DG will play an important role in the future. An open access market will support this trend but is not a
pre-condition as favourable economics and politically motivated subsidies for envirorunentally friendly technologies do
also cause this trend in traditional supply structures.
5 Technical Influence of DG
In general, many technical influences of increasing share of DG may be observed in various countries, depending on
the amount of DG and the kind of generators used as well as on the structure of the system. For example, the subsidies
-8-
for generation from \vind lead to a high increase of wind turbines in some countries and special problen1s in the con-
ventional systems.
Though it is not easy to generalise the technical impact it is attempted to draw the major consequences from the obser-
vation of the developments in several countries. The study is divided into the three parts of the system and special tech-
nical questions.
·rhe secondary reserve requirements may also be affected by the risk of a global trip of a large amount of DG connected
to the MY- or HY-network, which may occure as a result of network failures. The respective probability in relation to
other incidents related to secondary reserve requirements is expected to be very system-specific and has not been ana-
lysed yet.
Apart from the quantity of secondary reserve the procurement is affected by DG which in many cases doesn't contrib-
ute to this but replace large generation facilities which would be able to provide reserve themselves.
For the same reason scheduling of the large generation facilities will be faced with new constraints. The deterministic
approach in the optimization of unit commitment and scheduling has to be questioned when the possibly very low re-
maining load after DG-contribution is burdened with all load- and DG-fluctuations. Power trading is affected at the
same, but may also be the only sollution e.g. in situations when actual DG-production exceeds the amount which can be
used in the system after considering all constraints like reserve requirements and stable system operation.
A general characteristic of non dispatchable DG is a fluctuating power output which is usually not directly correlated
with the electrical load. The resulting network voltage fluctuations superimpose themselves on existing fluctuations
caused by changes in load and may lead to a widening of voltage bands. This widening of the voltage bands uses up
network reserve which are then unavailable for additional customers.
Adherence to voltage limits of 230V~0'; for all low voltage customers and of Un.MS ± 10% for all medium voltage
customers [4,5]. The example of Figure 5.1 shows that after deducting the max. expected voltage drop in the low volt-
age network (-5%), the local network transformers (-2,5%) and taking into consideration the stepping tolerance of the
voltage regulator on the HY/MY-transformer (-2%) a restriction of the voltage bands in the medium voltage network to
approx. 6,5% is necessary. A lower voltage drop in LY increases the capacity in MY and vice versa. Additional com-
ponents for voltage regulation installed in dispersed locations in such networks may increase the transmission capacity
from this point of view.
6
230 V + % => 16 o/o variation admissible
-10%
- l@-1----.Iro--1-----.l
HY-network MY-network LY-network
t.U 2% -->!<----- 6,5 o/o ----->!<- 2,5 % ->•~I,-- 5 % ____,
u
T
deviation voltage drop
Figure 5. I: Example for the calculation of admissible voltage drop in a MY-network
The increase of voltage bands by power injection from DG can be to a certain degree be compensated by reactive
power consumption by DG. This may also be desirable from the point of view of optimising the reactive power flow in
higher voltage levels. Thus, the power factor of DG should not generally be set to a fixed value (often l) but should be
- I0 -
regardes as a degree of freedon1 of the connection which is set in every individual case in order to meet the local re-
quirements.
The connection of DG will - if not by admissible voltage bands - be limited by the current carrying capacity of the
equipment which is determined by the thermal load it will bear. Nowadays it is normally assumed that the thermal cur-
rent limit can be exceeded for short periods - e.g. for the rapid restoration of supply after a failure. On the other hand
the generation characteristics of many types of DG with longer periods of rated power output don't allow the same
maximum current on the equipment as for typical MY-loads with its fluctuations during the day.
Especially WEC are subject to power fluctuations resulting in rapid changes of voltage and, consequently, flicker. The
disturbance caused by this is expressed as the flicker disturbance factor. Taking Germany as an example, in medium
voltage networks the long-term flicker disturbance factor must not exceed a limit of Ph.MS= 0.67 [6]. Owing to the sto-
chastic independence of disturbance signals from different customers and damping due to network impedance between
customers at a greater distance from one another, it is assumed that this upper limit for flicker is assured if P1, = 0.37 for
individual customers and P1, = 0.46 for individual DG is not exceeded (6,7]. In order to limit the effects of flicker, rapid
changes in active and reactive power must be reduced accordingly. A suitable choice of plant size and technology can
ensure that flicker does not become a limiting factor.
The maximum permissible amplitude of rapid one-time voltage changes in the medium voltage network is limited, in
Germany for example to 4% [5]. As individual voltage changes do not have a great effect on the long-term flicker level,
insufficient account is taken of them when flicker is measured. For this reason a separate analysis is necessary to ensure
that the 4% limit is adhered to. These maximum voltage changes only occur with wind energy generators and, like
flicker, depend on the type of generator.
Through the connection of DG which contribute to short-circuit current - i.e. direct coupled, synchronous or induction
generators - short-circuit power may rise above the capability of the network equipment. Short-circuit power is usually
at its greatest on the busbar of the HV/MV-transformers. Depending on the configuration of the network, it may be at
the upper limit here even if there is no additional power infeed. Accordingly, when DG are integrated, short-circuit
power must be checked on a case-to-case basis and, if necessary, kept within the permissible range using suitable plant
engineering measures (e.g. converter coupled systems) or short-circuit current limiters.
The protection of the DG-unit itself causes as a rule no special problems and can be covered by standard relaying
equipment. The main challenge lies in the design of the interface protection scheme and its co-ordination with the util-
ity network relaying and operating conditions (8).
In medium voltage networks the protective concept is nowadays predominantly based on radial branches. Using inde-
pendent overcurrent time relays which are staggered but without direction decision, selectivity is achieved, i.e. in the
event of a fault only the relevant branch will be shut down and the rest of the network will continue to operate nor-
mally. Where there is dispersed infeed all branches with power generation plants connected will feed power into the
place where the fault is located via the medium voltage busbar. This means that if the protective system fails to isolate
the dispersed generation plant from the network soon enough after detection of undervoltage the independent overcur-
rent time relays may trip unselectively in branches of the network which are not affected by the fault. Within certain
limits selectivity can be attained in such cases by raising the response thresholds of the independent overcurrent time
relays, by staggering the tripping times or by raising the response threshold of the undervoltage protective system.
However, raising the response thresholds or prolonging the tripping times of the independent overcurrent time relays is
not without problems with regard to the desirability of rapid shutdown and avoidance of the destruction of equipment
or, indeed, the safety of personnel. Apart from this, it must also remain possible to reliably detect faults with smaller
fault currents. Particularly when systems have a number of branches, there may be problems with the protection con-
cept and more radical changes are to be made (e.g. installation of uni-directional independent overcurrent time relays).
Basically, the reliability of supply is usually not increased by integrating DG without central dispatch. On the contrary,
care must be taken to ensure that DG does not affect reliability of supply. This may happen when the selectivity of the
protection system is jeopardised, the effectiveness of auto-reclosing is no longer guaranteed or there is a danger of
cables being overloaded after temporary network reconfigurations. Futhermore, the steady state voltage must not ex-
ceed the admissible limits under exceptional supply conditions. In such cases it may be necessary to isolate the DG
from the network or the DG must be fitted with automatic voltage limiters.
Changes in load flow are accompanied by changes in network losses. With low infeed the network losses will decrease,
as the utilisation period of the equipment - and accordingly the loss factor - decreases. Network losses increase when
dispersed generation greatly exceeds the load or the power factor of the dispersed infeed has to be set strongly lagging
- II -
in order to assure permissible operating conditions in the network - in particular, allowable voltage range. In principle,
network losses are not subject to any operating limits. Nevertheless, for reasons of economy they should be minimised.
As a principle it can be stated that non dispatnchable DG connected to MY- or LY-networks will increase necessary
investments in the network because they widen up the expected voltage bands and thus reduce the network capacity for
the supply of additional (load-) customers.
7
ifcos<p>0.9 --+paymentof[21- 17 ] (in%ofkWhenergy
(cos<p) 2
- 12 -
max . .1u 11 in HV 5%
(2%'0)
max. U 1t in HV 110%
min. U 1, in HY 90%
flicker !iU:>l%
max,·P.inLY
max. P 1, in MY l" 0.464 0.9
max, nu. in HV
harmonics limited limited limited
yes
12
48%P 10% 60%
12
75%P 40% 60%
secondary
tertiary
Table 6.1: Overview of network connection rules and related contracual agreements
6.2 Tools
The consideration of DG in future planning and operation of electricity supply systems will require the utilization of
new software tools on this sectors. Due to the unknown development of the installed DG power and - depending on the
technology - the stochastic power output behaviour additional uncertainties will be introduced to the system. Those
uncertainties will have to be considered in generation as well as in network planning and operation.
The following aspects have specially been identified in the work ofWG 37-23:
• Load/generation prediction: The unit commitment of the bulk power generation requires a load prediction which in
traditional systems contains an uncertainty in the range of 3 %. This uncertainty is equalized by the on-line eco-
nomic dispatch. An increasing share of non-dispatchable units with partly stochastic behaviour will necessarily lead
to an increasing uncertainty in the joint load and generation forecasts. Therefore, tools for generation forecast de-
pending on the technology (e.g. WEC or CHP) have to be developed, considering the random aspect of the respec-
tive technology. Gaining data for this purpose is a major aspect, in Denn1ark all conventional units above 2 MW and
a number of WEC are equipped with online measurements. For smaller units recorders may be a sollution. [n case
micro-generation will be installed in large numbers this aspect should be paid special sttention. Investigations con-
cerning the impact of an increasing uncertainty on unit commitment and economic dispatch should be carried out.
• Adaptation of requirements concerning reserve and installed capacity: Today's requirements concerning reserve
(primary and secondary) are based on the assumption of a traditional system structure with large bulk power gen-
eration and only a small share of non-dispatchable units. Generation units with a highly stochastic behaviour
(mostly renewables) will add generation fluctuations. Depending on the question whether network failures can lead
to a drop-out of a large number of DGs as already observed in Denmark, the probability of a drop-out of a certain
amount of generation power will be influenced. Both concern the necessary amount of primary and secondary re-
serve. Furthermore, the total amount of installed capacity has to be revised due to the fact that DGs depending on
their technology do replace only a part of their total power capacity in the bulk power generation in terms of gen-
eration reliability. Those reserve requirements will have to be adapted depending on the amount and type of DG in-
stalled in a system.
• Network planning in HY: Dispersed generation resources may have a large impact on HY-network-planning and
can appear in some situations as potential alternatives to standard network development. Considering independent
power plants, such units can avoid constraints on the grid if they have a power with a guaranteed availability per-
centage (for example 95% during winter in the standard contracts for cogeneration in France). The availability may
be time-dependent and related to the actual load situation, which should be regarded in the planning tools. For the
remaining limitations, solutions based on generators that can be started up as a function of local network require-
ments (for example in case ofunavailibility of a line) can be proposed by the network manager as an alternative to
network reinforcement. As a matter of fact, it has become compulsary for EDF to study such solutions, due to envi-
ronmental pressures. There are two possible ways of using groups:
the preventive way that consists in operating the unit over all the period when the loss of a line may lead to a
constraint,
the curative way where the group is started only when an incident occurs and generates a constraint.
For network with no overload capacity, the generation used in the curative mode does not bring any improvement in
the number of power cuts. Yet, it allows to reduce the non-supplied energy after the operating time. The preventive
solution is usually not economically interesting since the additional generation costs are not balanced by the local
profits on non-supplied energy.
For any development problem, the different solutions whether based on dispersed generation units or on network
reinforcement must be studied to assess their respective economical, technical and environmental performances.
With dispersed generation, the unavailability percentages of the units are much higher than those of lines (5·10' 2
versus '5· l o...i). For this reason the "N· l 11 rule is not sufficient and other situations have to be studied (such as the loss
or 2 or even 3 groups). In order to be able to deal with the large number of network situations, programs have been
developped.
• Network planning in MY/LY: The uncertainty in the development of the installed capacity of DG and their loca-
tions will also effect the MY- and LY-network-planning. The major influence will be that existing networks should
be utilized more efficiently using new tools which can consider DG and their influence on the load flow in distribu-
tion networks more precisely. The use of such tools will, referring to experience in the Netherlands and Germany,
allow the delay or omitting of network investments and therefore increase the overall economics.
services from anywhere (NERC-Definition). In the following the solutions as have been discussed in some countries are
suggested. In those countries, where the generation and distribution have been totally separated (e.g. UK and Scandina-
via), the accountability for ensuring these services rests with the transmission company. Some of these services n1ay
lend themselves to competition (e.g. spinning reserve) and a market mechanism has been set up or is being considered.
Other services do not lend themselves to competition (e.g. scheduling and dispatch)
Dispatch
DCJ usually are not under control of central dispatch of the SO. In the Netherlands and Denmark experiences have
shown, that a large amount of DG may lead to situations where load following with the remaining large units is not
possible anymore. Thus, a time variant price for the energy from DG was established, to encourage higher production
during high load periods to participate them in following the load curve. A higher price for the energy is paid during the
day periods with a high consumption, a lower price during the nights (three-rate-tariff, see annex).
Reserve
In order to fulfill the requirements concerning primary reseive in single (e.g. national) systems a choice of droop be-
tween 2 - 6 % on all units in operation is satisfactory [16]. In unbundled systems obligations can be made to the gen-
erators and/or a market can be established enhancing generators to contribute to primary reseive. The solution of GB
for example is as follows: Generators are paid according to a MW /Hz value proportional to their installed capacity
weighted with the yearly average (over 5 years) operating time. Payment is MW/hr x negotiated price (applicable to all
generators). Excess primary reserve could be sold on a special market. Producers state price and volume of available
primary reserve exceeding obligations, generators without the respective capability should be obliged to buy the neces-
sary reserve from other generators. In such a system DG can be included just as any other generators in case they are
registered by the SO.
In hydro dominated systems the secondary reseive is available in sufficient quantities; eventually it could be problem-
atic in thermal dominated systems (compare the example of the Netherlands). In case a regulation power market exists a
buy/sell of capacity for the secondary control (short term and long term) is possible. DG may participate in such a mar-
ket, in case there is not enough reserve available in the system (e.g. due to a momentary or permanent lack of large
generators or limited transmission capacity) obligations may be necesary.
Voltage control
Voltage quality is closely related to the short circuit power which is guaranteed by proper system design and dispatch.
For voltage control in HV and above the SO instructs producers to generate reactive power in the quantity required for
stable network operation and minimal losses. DG in general do not participate in voltage control. In case generators
under SO-control are obliged to participate in voltage control without payment there should be an equivalent fee for
DG.
Operation of the System
The operation of the system, switching of lines, scheduling of power stations, planning maintenance of lines and sta-
tions, meter reading, billing has to be done by the system operator. The same applies for all those technical or organisa-
tional measures which are done to locate outages, to prevent outages and blackouts. Generators have to participate in
measures for the restoration after eventual black outs (black start capability), and so also DG should do.
Summary
The development of adequate prices for system services is still an ongoing process in many countries. Some of these
services may lend themselves to competition (e.g. spinning reserve) and a market mechanism can be set up. If this is the
case, DG just as any other generators may participate in the market or not. In case there are obligations without proper
payment an equivalent fee should be set up for DG in order to avoid discrimination.
With auto generations, autonomous generation, the heat consun1er bears the economic burdens of combined heat and
power generation and incurs the relevant charges and risks. The joint-venture formula, however, can offer a number of
benefits to the heating customer.
• The heat user is sure of his electricity supply : the risk of outages is minimal.
• Moreover the price of electricity is more stable than with auto generations generation and less dependent on varia-
tions in the price of fuel.
• Combined heat and power units are complex, requiring substantial investments that take a long time to recoup.
Many companies will not, or cannot, make these investments. They want a high return on high-risks investments
that are not pertinent to their core business.
These strategies will not decrease the number of DG in the system but will give utilities more influence on the genera-
tion, thus making it not dispersed with regard to dispatch or even reserve. A long-term strategy can help utilities by
achieving this aim. The activities could be the following [ l 7]:
• Influence the development of DG (location, timing) through appropriate transmission tariffs (if possible) and mar-
keting assessments. This comprises the Development of transmission dervice tariffs that will influence DG siting,
the development of an understanding of the DG driving forces, the identification of potential customer self-
generation and the production of customer profiles.
• Integrate the utilization of DG in the Transmission Company's planning activities. This comprises the development
of network connection rules, the analysis of DGs' impact and positive or negative influence on the system (s.a. sec-
tion 5), the development of new planning tools for managing DG on the system (s.a. section 6.2) and the develop-
ment of methodologies to assist in identifying preferred locations for new DG.
• Manage relationships with customers, suppliers and industry to insure awareness of transmission tariffs and connec-
tion requirements. This comprises the development of information packages concerning this matter and the ex-
change of information with partners as mentioned above.
The overall aim of such a strategy is not to hinder the development ofDG but to get influence on as much DG as possi-
ble to make system planning and operation more easy and to profit from economically favourable facilities.
7 Conclusions
Experiences in the whole world show a rapid increase of dispersed generation, either promoted from political influ-
ences, such as subsidies, or promoted from the increasing competition in open markets. WG 37-23 has summed these
developments in this report.
Available technologies are co-generation units, wind energy converters, hydro power stations, conventional generators,
PY-systems, fuel-cells and micro-generation units, either alternative motors (diesel or gas) or micro turbines. Gas fired
turbines have got an increasing share of the industrial market (above 50 MW) and for !PP; reasons for this are the
modularity, which leads to extremely short erection times, and short capital return duration. Resulting from the high
number of units being constructed, the price per kW has reduced very much. In addition to this, low gas prices, subsi-
dies and the opening of the markets in nearly all countries promote the installation of turbines at customers' sites. Re-
cent developments in the area of microgeneration show the possibility, that very small turbines with electrical power of
50 kW and less may be used for generating electrical energy at private customers.
The kind of the market, either monopoly or open structure, and more the level of price for power and energy, influ-
ences the portion of !PP as well as DG and also the velocity of change For example the law in Germany guaranteeing
high prices for renewable generation has caused a rapid increase of WEC-capacity from nearly 0 in l 990 to more than
2000 MW at the end of l 997. Similar developments take place in many countries. The opening and changing of the
market structure leads to a rapid change of the generation structure. As observed in several countries many of the
conventional generation is substituted within a few years, if the driving forces (competition, price difference, ... ) are big
enough. On the other hand, in countries with low energy prices, like Norway with high hydro capacity, the expected
increase of dispersed generation is very low.
DG in large amounts will have major impacts on nearly all parts of the electrical energy supply system. The uncertainty
of their power output and sometimes even the lack of knowledge about their installed capacity requires strong but also
more flexible networks up to EHV, where the need for power and reserve trading may increase. The substitution of
energy and power from large units by DG affects network operation, reserve requirements and procurement and aspects
such as scheduling or frequency control. In distribution networks the additional installation of DG may increase the
necessary network capacity and cause additional costs for planning. If dispatchable their may be a positive influence
such as increasing the reliability under certain conditions.
Four strategies can help dealing with DG and integrating them in the existing system even in large amount. Precondi-
tion in any case is the exact knowledge about location and type of all DG. The development of network co1U1ection
- 17 -
rules helps dealing with technical questions in the nearby grid. l'wo different approaches exist here: In every case the
coherence \vith customer requirements and technical constraints is analysed or simplified connection rules are derived,
the latter with the disadvantage of underestimating the network capacity in son1e cases and with the advantage of re-
ducing planning costs significantly. Examples of network connection rules are given in this report. The second strategy
is the development of tools which consider also DG in system planning and operation. Need for new developments
were found in joint load- and DG-generation-prediction, reserve planning, network planning in HV and network-
planning and operation in MV/LV. In addition to these planning stages it is desirable to set the competition between
classical generation and DG on a non discriminatory base, forcing DG to contribute to system services in the same way
as other generators or establishing equivalent fees. The last strategy is the cooperation with DG-operators, offering
services such as planning, dispatch etc. which will provide the SO with more information on the DG installed. All
strategies should be followed hand in hand with each other, not aiming at the reduction of DG but at the integration at
its best but without discrimination of any player on the market.
This leaves open questions for the future: Network connection rules are in many systems still under development, the
tools helping system planners and operators to deal with DG are partly existing but the development still has to be en-
hanced and extended to be useful in other systems. Last but not least in many systems the market structure has to be
adopted to an increasing number of DG especially concerning an adequate participation in the services required from
the generators as a whole.
8 Bibliography
[ l] Petrella, A. J.
Issues, impacts and strategies for distributed generation challenged power systems
CIGRE Neptun conference, 1997
[2] Eunson, E.; Backman, T.; Casazza, J.; Glende, I.; Mallet, P.; Popple, C.; Ray, C.; Salvaderi, L.; Schwarz, J.
Power system planning and open trading
on behalfofCIGRE WG 37-20
[6] VDEW
Grundsiitze far die Beurteilung von Netzriickwirkungen
VWEW-Verlag, Frankfurt/M., 1992
[7] VDEW
Technische Richtlinien - Parallelbetrieb von Eigenerzeugungsanlagen mil dem Mittelspannungsnetz des Ener-
gieversorgungsunternehmens (EVU)
VWEW-Verlag, Frankfurt/M., 1994
[8] Ziegler, G.
Protection of Distributed Generation - Current Practice
on behalfof SC34
- 18 -
[ 11 J Engineering recommendation G. 75
Recommendation for the connection of embedded generating plant to public electricity suppliers ' distribution
systems above 20 kV or with outputs over 5 MW
ElectricityAssociation, Engineering and Safety Division, London, 1996 (draft)
(12] VDEW
Paral/elbetrieb van Eigenerzeugungsanlagen mil dem Mittelspannungsnetz des Elektrizitiitsversorgungsun-
ternehmens (EVU)
I. Ausgabe, VWEW-Ver!ag Frankfurt, 1994
B REFERENCES 43
- 19 -
A. I Australia
The main power systems of South and Eastern Australia are illustrated in fFigure A. l. The power systen1 of New South
Wales, Victoria and South Australia are presently interconnected with the likelihood of further interconnection of the
Queensland system.
Queensland DETAIL
South ~
~
Australia
Proposed
Adelaide Interconnection
Melbourne Transmission
Tasmania CJ backbone
The electricity supply industry in Australia has gone through significant structural reform which culminated in the de-
velopment of a National Electricity Market (NEM) with the market operation to be commenced by the end of 1998.
Major components of the reform process has included the separation of the transmission business from generation busi-
nesses and the establishment of a competitive wholesale electricity in which individual generators compete for dispatch.
Until recently each Australian state had a large government owned utility comprising both generation and transmission
while in some states the utility also included distribution. The industry is now open_ed up to private ownership of gener-
ating plants and distribution.
Connection to the electrical network by participants in the National Electricity Market will require a connection agree-
ment. Under the national electricity market rules, any generator with a license to participate will have to offer their
energy to the market via bids or through bilateral contract arrangements. Generators will not be able to have interests in
transmission or distribution due to conflicts of interest in market trading. The development of a competitive electricity
market in Australia has led to significant uncertainty in transmission planning due to the impact of competitive bidding
by generators.
A.1.2 development of DG
Cogeneration has existed in Australia since the introduction of electricity, in particularly in the sugar, paper, alumin-
ium, oil refining and remote mining operations. With the deregulation of energy market in Australia, an increasing
installation of dispersed power generation can be expected. This will mostly be cogeneration units with connection to
the distribution grid. Under the National Electricity Market rules, cogenerators can compete directly selling power
generated into the market or by having buy-back arrangement with distribution companies. This has greatly enlarged
the potential for cogeneration ..
a) Cogeneration status
In 1995 the Australian Cogeneration Association undertook a survey of all known cogeneration plants and produced a
co generation plant register [ 1]. A recent update of the cogeneration plant register in 1997 has indicated that the capacity
of cogeneration currently operating and under construction is 1814 MW. This represents about 3 % of total installed
generation capacity in Australia and a reduction in greenhouse gases of about 7-8 millions tonnes per annum. Accord-
ing to the Australian Cogeneration Association, market evidence has showed that distribution companies are looking at
cogeneration to provide them with alternative source of power. With the impending deregulation of energy market an
- 20 -
increasing nun1ber of cogeneration projects is expected. It is anticipated that the total potential capacity for cogenera-
tion could approach 6000 MW in the long term.
b) Environ1nental performance
According to research carried out by the Australian National Greenhouse Gas Inventory Conunittee, electricity genera-
tion produces about 50°/o of Australia's greenhouse gas emissions. This is due to the low conversion efficiency of con-
ventional electricity production. By combining power production to thermal loads, cogeneration can eliminates much of
energy wastage and improve environmental performance. As embedded generators are generally located at their load
source, they have the ability to reduce transmission losses and thus reduce energy costs.
Two companies, the National Electricity Code Administrator Limited (NECA) and National Electricity Market Man-
agement Company Limited (NEMMCO), were formed in May 1996 by the Australian states governments to implement
the National Electricity Market (NEM).
NECA will supervise, administer and enforce the National Electricity Code and the NEMMCO will manage and facili-
tate the wholesale electricity market in accordance with the Code. The National Electricity Code defines the terms of
participation in the wholesale electricity market for generators transmission and distribution network owners and serv-
ice providers, retailers and customers. Specific Code chapters deal with registration of participants with NEMMCO,
rules for the operation of the central dispatch process and spot market, security arrangements for the power system,
network connection access arrangements including network pricing, metering of market participants, and the admini-
stration of the Code itself through enforcement, dispute resolution, and a Code change process.
Under the National Electricity Market rules, all generators are required to register with the NEMMCO unless they are
granted an exemption [2]. Special rules exist to classify a generator into four different categories depending upon their
size and whether they are required to participate in the wholesale electricity market. The four categories are :
• Scheduled Generator - a generator with a nameplate rating above 30 MW at one site is required to have its output
scheduled by NEMMCO.
• Non-Scheduled Generator - a generator with a nameplate rating of less than 30 MW at one site is not required to
have its output scheduled by NEMMCO.
• Market Generator - a generator whose sent out output is not purchased in its entirety by a local retailer or by a cus-
tomer located at the same network connection point. A Market Generator is required to sell all of its sent out output
through the spot market managed by NEMMCO.
• Non-Market Generator - a generator whose sent out output is purchased in its entirety by a local retailer or customer
located at the same network connection point.
A.2 Belgium
The co-operative company CPTE is the materialisation in which the two companies SPE (the public sector electricity
producer) and ELECTRABEL 1 pooled their technical operations for electricity generation and transmission. The new-
est nation wide Equipment Program for Electricity Production and Transmission Facilities for the period 1995-2005
was drafted by the Electricity Companies Management Committee. This program embodies a vision of the future since
it is frugal (only the necessary but all that is necessary) and prudent. It is based on piloting demand, an altogether inno-
vative approach, and reserves a yerv substantial. but realistic place for decentralised production.
CPTE has handed over the management of the transmission to ELECTRABEL, under a mandate. The transmission
network covered the tension from 380 kV to 30 kV. The communes are the holders of the legal monopoly of electricity
distribution within their territory for power demands up to 1000 kW, in practice raised to 4000 kW, for the Walloon
Region raised to 10000 kW by device.
C:uston1ers exceeding 4 (or 10) MW, are normally supplied on the mediun1 voltage network (6 to 26 kV) and can di-
rectly apply to one of the generating companies (SPE, ELECl'RABEL) and thus becoming "direct custon1ers". Exer-
cising their n1onopoly rights, the Belgian communes aln1ost chose for the systen1 "Intercon1n1unale Mixte" : a "n1ixed"
company involving, on one hand, a number of communes, and, on the other hand, the private company
ELECTRABEL. As a rule, the mixed company leaves the operating of the distribution, and often even the manage-
n1ent, to the private partner.
The small DG (less than 15 MW) is usually connected to the distribution network (up to 26 kV). Specific rules for
connecting these units are described in a note "Prescriptions techniques pour le fonctionnen1ent en parallele d'installa-
tions de production decentralisCe sur le reseau de distribution" (separately sent by fax). These rules are edited in the
spirit of protection of the distribution network, the specific rules for protection of the power unit are not mentioned. The
larger DG (above 15 MVA) is normally connected to the transmission network (from 30 kV to ... ).
A Working Group is at the present time occupied to edit a paper on this matter.
A.2.2 development of DG
The total load of the Belgium network was 12263 MW during the winter 1996/ 1997.
The installed DG on 01.01.1995 is shown in table A.I.
Classic Fossil 863.0 MW2
Recuperation Recuperation energy 25.0MW
Waste 72.0 MW
Renewable Biomass 1.5 MW
Sun 4.5 kW
Wind energy 5.2MW
Hydraulic 96.0MW
1063.0MW
In the newest nation wide Equipment Program for Electricity Production and Transmission Facilities for the period
1995-2005 a very substantial place for the decentralised production is foreseen.
We answer later on this question, when the conclusions of the Working Group who studies the guidelines for connec-
tion DG are approved by our Direction.
A.3 Denmark
The Danish electricity supply industry is characterised by two grids without interconnection and by consumer owner-
ship. There are some l 06 distribution undertakings, each having the exclusive right of supply within its area. The dis-
tribution undertakings in a region are owners of the regional electricity utility. Besides, the distribution undertakings are
owners of the two system operators, Eltra and Elkraft, who represent the western and eastern part of Denmark, respec-
tively.
HVOC
"
~:::;:-SWEDEN
Elk raft
MAXIMUM LOAD
VDC 2800MW
·-ea·
200'
HVDC
GERMANY
Figure A.2: Denmark divided into the Eltra and Elkraft service areas
So far, the electricity supply industry has been characterised by vertically integrated monopolies. However, as a conse-
quence of the EU's directive to liberalise national electricity markets, the Jutland-Funen area has embarked on a proc-
ess involving the unbundling of electricity generation from transmission. The Danish Electricity Supply Act as
amended in 1996 specifically mentions that Elsam and Elkraft are the system operators in their respective areas. How-
ever, on January I, 1998, Elsam spun off both its transmission activities and its role of independent system operator
into a new company, Eltra. This means that Eltra and Elkraft are responsible for the maintenance of the power balance
and the voltage quality in the power system.
The Danish electricity supply industry is highly regulated. Eltra and Elkraft carry out the planning, but the Danish En-
ergy Agency must approve new plants of a certain size. The approval of the authorities is not limited to a discussion of
utility proposals. On several occasions the authorities have established directions for choice of technologies and fuels.
Examples are the use of wind turbines, local combined heat and power (CHP) and biofuels for environmental reasons.
Lately, the electricity supply industry has been instructed to prepare biennial plans for integrated resource planning
(!RP).
A.3.2 development of DG
8000
6000 • Consumption
4000
• Off shore wind
turbines, capacity
Figure A.3: I)ispersed generation and consumption in Denmark in 1990 and 1998 as well as govemn1ental forecasts for
2005 and 2015
'""""QllliY Ow~l !
0 i=t;.,attyowned
""' - ollkYowned
~ ~i=t;.,attyowned
- --------'
'"' - !
~""' JI
200'
100 ;
,~_ELlJ~
_Jj '"'"I
·:J •• El
,.,
E3 Fl
2-10
E3 =--Il
''"" ""'"'
2-10 10.25
0-1 1·2 10-25
'"" ""'"'
Figure A.4: Local CHP stations in Denmark at the end of 1996 divided into six classes according to the size of the
units. The total capacity is 1198 MW in the Eltra area and 439 MW in the Elkraft area
Figure A.4 shows the installed capacity in the two parts and the private and the utility-owned parts, respectively. Utility
ownership has some advantages, such as a higher degree of standardisation of equipment and maintenance of the CHP
units, which leads to a better technical performance to match the needs of the power system.
• Wind
At the end of 1997 the total number of wind turbines installed in Denmark was above 4000 with a total capacity of
1000 MW.• 80 per cent of this power is privately owned and 20 per cent is utility-owned. The primary reason is that the
utilities have left the initiative to private power producers. However, as wind turbines are subsidised, it is reasonable
from a societal point of view that consumer-owned utilities and not private power producers establish the wind turbines.
Thus, the utilities intend to increase their involvement in wind power. More than half of the turbines in Denmark are
smaller than 150 kW. However, development is fast. Turbines established in 1996 and 1997 have a rated power of 400-
600 kW, but prototypes of 1.5 MW turbines have been in operation for three years and are expected to become com-
mercial soon.
As regards co1U1ection of wind turbines and CHP units to the transmission network, the energy authorities and the utili-
ties have worked out some guidelines. The following will list requirement specifications, recommendations and main
reports within the technical part of the guidelines. Apart from the utilities the following organisations in particular have
contributed to the technical research activities:
• Risa National Laboratory
• DEFU - the Research Association of the Danish Electric Utilities
• NORD EL - an association for Nordic electric power cooperation.
CHP Units
- 25 -
In 1995, NORDEL gave their recommendations for production units below 100 MW in the report "Operational Per-
formance Specifications for small Thermal Power Units" [3]. DEFU has published a report on relay protection for local
CHP units [4]. Based on a large number of references, i.a. (4], [5] and [3], Eltra has worked out and applies:
• Specifications for CHP units below 2 MW (in Danish) [6]
• Specifications for Cl-IP units between 2 and 50 MW (in Danish) [7]
• Specifications for CI-JP units above 50 MW [8]
\Vind 'furbines
The main document concerning connection to the transmission network is I)EFU report KR 111 "Grid connection of
wind turbines" (in Danish), [5,9]. The Riso National Laboratory and DEFU have cooperated on the project "Power
quality and grid connection of wind turbines"(in Danish),[ I OJ. The report consists of three parts;
• Part l: "Stationary voltages"
• Part 2: "Flicker"
• Part 3: "Harmonics and operation of variable speed wind turbines"
The remaining part of this report deals with aspects of CHP units in the Danish power system. Wind power is not in-
cluded any further in this draft.
Generation Profile and Forecast
From the very start the direct coupling of heat and power production was a major concern of the power utilities. A
situation in which many CHP units made the base load electricity production and the large extraction and condensing
power stations were to be dispatched by the power pool at peak load was not considered a satisfactory solution, neither
by the utilities nor by society. The planning tool to overcome this problem has been the three-rate tariff shown on
Figure A.5.
fiDil Peak
EB Medium
~ Off-peak
0 4 8 12 16 20 24
Time of day
Figure A.5: Demand profile and three-rate tariff for CHP units (only weekdays). In weekends and on holidays the off-
peak tariff applies around the clock
This tariff has been very decisive for the layout of the CHP units. The result has been the following:
Local CHP units are designed to meet a certain part of the local heat demand. According to the standards laid down by
the authorities, the local CHP units are to be designed to meet at least 95 % of the yearly demand for district heating.
This criterion is satisfied with a heat capacity of approximately 60 % of the maximum heat demand. A CHP unit de-
signed this way will have a yearly production factor (time if production were 100 %) of 4500-5000 hours. An exception
is waste-fired CHP units, the yearly production factor of which may exceed 8000 hours.
To optimise the yield according to the three-rate tariff heat accumulators have been installed in almost all CHP units.
These heat accumulators give a temporal decoupling between power and heat supply. This partial decoupling is used as
far as possible to place the heat and power production in periods when the power production has the highest value. The
accumulators can only be used in CHP areas where and in periods when the CHP capacity allows simultaneous satis-
faction of the heat demand and charging of accumulators. By means of heat accumulators a large part of the CHP units
may be disconnected in off-peak periods on ordinary nights and in weekends outside the coldest period in winter. With
heat accumulators the CHP units can be run on/off, and thus exploit the high maximum load efficiency of the CHP
units and the high value of peak load production.
Most heat accumulators are designed to handle approximately l 0 hours of maximum heat production. However, waste-
fired CHP units make an exception, because their production is mainly determined by the amount of waste to be dis-
posed of.
The operational impact of the three-rate tariff has been quite large, as explained in the following:
- 26 -
·ro fit in the production from local CHP units in an appropriate way the units are divided into groups with different tin1e
intervals. An example of the resulting production for some of the tariff-controlled units is shown in Figure A.6. It ap-
pears that the units largely follow the indicated tariff periods.
MW
"j Gou~1
""
'"" !1 ~\
""
"
T Im e
" '" "
Figure A.6: Example of the resulting production for the tariff-controlled units within the Eltra area
The principle of controlling the production from local CHP units by means of time-differentiated tariffs has thus turned
out to be a useful way to encourage operation according to the load profile [4].
As a result of the link to the heat demand, the forecast for electricity production must be based on a forecast for heat
demand in the local area, and therefore the forecast for electricity production from these units suffers from almost the
same uncertainties as the weather forecast. The long-term forecast for the weekly production from dispersed CHP units
is rather crude - the 95 % confidence interval is as large as ± 40 % of the forecasted value. For the short-term forecast
the uncertainties can be substantially reduced. Based on experience and the actual weather forecast the hourly power
production for the next day can be forecasted with an uncertainty of approximately± 10 % of the installed capacity.
Characteristics of Power Generation throughout the Year
The CHP units' link to the heating basis gives large seasonal fluctuations in the electricity production of the units.
Figure A.7 and Figure A.8 are representative of the production profile from local CHP units on weekdays and in week-
ends in a summer month and a winter month, respectively. The figures show average and standard deviation for meas-
urements made in the periods August 1-31, 1996 and December 1-31, 1996. The capacity of the measured units makes
up a total of 1030 MW.
From Figure A.7 and Figure A.8 it appears that;
• local CHP units typically produce between 20 % and 60 o/o of their maximum production in the daytime on week-
days in a summer month. In the nighttime and in weekends the production is I 0-20 %
• local CHP units typically produce between 80 % and 90 % of their maximum production on weekdays in a winter
month. In the nighttime and in weekends the production is 60-80 %.
%
IOO f
"t
wj
-- 80
6-0
l
"t 40
20 + - - - - - - + - - - - + - - - - - - + - - - - - ·
20 + -
" "··:·'.
ol- 0
00.00 06.00 12.00 18.00 0000 00.00 06.00 12.00 18.00 0000
Summer Winter
Figure A.7: Production(% of installed capacity) from local CHP units in weekends/on holidays in the summer and the
winter (average and standard deviation)
- 27 -
'"'
•. .•.
"'°
so
""
"'
0 0
00 00 06 00 12 00 ''°o 00 00 00 00 06 00 12 00 '800 0000
Surruner Winter
Figure A.8: Production (% of installed capacity) from local CHP units on a weekday in the summer and the winter
(average and standard deviation)
The production in o/o of the installed capacity of the power stations in winter and summer months tells something about
the CHP units' power value to the system. However, the power value also depends on the CHP units' robustness to-
wards faults in the network.
System Protection and Power Value
On the basis of experience (4], Eltra has set some requirements on relay equipment and settings at local CHP units.
Units ranging from 0 to 50 MW must satisfy the requirements shown in Table A. I.
Type ofrelay Settings Trip Time
Positive-sequence undervoltage U 1 <U 10 +30% t$50ms
Three-phase overvoltage U>U"+ 10% t,; 50 ms
U > U 0 + 6o/o t: 30-60 s
Three-phase undervoltage U<U,+ 10% t:2-!0s
Overfrequency f > 53.0 Hz t ~ 300ms
Underfrequency f<47.0 Hz t ~ 300ms
Overcurrent I>> t,; 50 ms
Table A.1: Required relay protection at dispersed CHP units in the 0-50 MW range within the Eltra service area
The above relays protect consumers and the network against unacceptable influences from the generator and the gen-
erator against out-of-phase reclosure in case of reclosure after network faults. As additional protection in order to fur-
ther protect the generator the following types of relays, of. Table A.2, may be used, provided that the specified settings
are satisfied.
Type of Relay S~ttings Trip Time
ROCOF df/dt > 2.5Hzls 80-100 ms
df/dt < -2.5Hzls
Phase shift U > 8° 3-phase momentary
U > 30° I-phase
Negative-sequence I, > 5-20 % 3 - 10 s
current/voltage
Zero-sequence voltage 20% 60 s
Table A.2: Additional protection of local CHP units ranging from 0 to 50 MW within the Eltra service area
The risk of damage to dwellings and at units is minimised by protecting the unit agains islanding and against out-of-
phase reclosure. Eltra practices 3-pole fast reclosure in case of most multi-phase short-circuit faults in the 400 kV, 150
kV and 60 kV transmission systems. However, in case of fast 3-pole reclosure local CHP units may be islanded during
the dead time, and to avoid unit damage affected units are tripped before reclosure (0.3 s). It is impossible to apply time
selectivity. Therefore, as primary protection an undervoltage relay is used which measures the positive-sequence volt-
age, possibly supplemented with a ROCOF relay.
The positive-sequence undervoltage relay functions before islanding occurs, and dependent on the type of fault and the
relevant coupling and operational situation a large number of local CHP units may be tripped even though they would
- 28 -
not all have entered into island operation. The ROCOF relay has given rise to quite a lot of forced outages of local CHP
units. The reason is partly that some types of relays are sensitive to the phase shift resulting from short circuits and
couplings in the network and partly that Eltra originally recommended too sensitive settings on the ROCOF relay (df/dt
> 1.5 Hz/sand df/dt< -0.7 Hz/s)
However, the strategy for system protection may have to be revised. 10-12 times per year Eltra experiences simultane-
ous forced outages of many local CHP units. A specific case is illustrated on figure 8.
On February 18, 1996, the Jutland-Funen area experienced a 2-phase fault in the 150 kV network. Dispersed CHP units
at a distance of up to 150 km from the fault were disconnected.
80
40r--
2o!
j
0
00.00 12.00 00.00 12.00 00.00
Saturday 17-02 Sunday 18-02
Figure A.9: Production in % of installed capcity at CHP units > 2 MW within the Jutland-Funen area on February 17
and February 18, 1996. The total cpacity (100 %) is 841 MW. On Sunday, February 18 at 7:30 a.m. more
than half of the local CHP units in operation experienced forced outage (the flash indicates the location of
the fault, the dots indicate the location of the disconnected units)
The outage affected a total of 47 local CHP units > 2 MW as well as an unknown number of wind turbines and local
CHP units < 2 MW. The power value of local CHP units is thus a weighing of their seasonal wellknown production
profile (see section 2.3.1) against their robustness in view of network faults. The larger part the local CHP units make
up of the total installed capacity, the more important it is that their robustness in view of network faults is increased.
Power System Planning
• Impact on the Danish Power Pools
With a very large part of the electricity production linked to the heat demand and another major part depending on the
momentary wind, a large degree of flexibility is needed from the remaining production system. At all times the spin-
ning reserve must be adjusted according to the forecast and actual production from CHP units and wind turbines. To
secure the balance between production and demand the dispatcher must ensure the spinning reserve and the possibility
of reducing production from power stations when production from CHP units and wind turbines increases.
In the winter when heat demand is high and wind production may be substantial, the electricity production from wind
turbines, CHP units and large extraction units exceeds the total electricity demand in the area. In such situations the
excess electricity production must be exported or the production reduced by disconnecting some extraction units and
producing the demanded heat on district heating boilers. This is called technical power overflow. In 1996, the technical
power overflow amounted to approximately 0.4 TWh in the Jutland-Funen area. In the year 2000 the power overflow is
forecasted to be 1.0 TWh.
All things considered, the large part of uncontrollable and to some extent unpredictable electricity production increases
the requirements on the flexibility of the remaining production system.
• Impact on Overall Network Planning
The appearance of local CHP units in Denmark has influenced the network expansion of recent years. At 10 kV and 60
kV level the task of the network is no longer just to distribute energy - the many CHP units and wind turbines also
mean that the network must be able to collect the energy where it is produced. All things considered, this has increased
the network expansion at the 10 kV level, and in a few cases also at the 60 kV level.
However, at the 132 kV, 150 kV and the 400 kV levels the network has been relieved in certain areas, which is why the
expansion has been postponed. Within the Eltra service area the 150 kV and 400 kV networks are interconnected. Due
to experience concerning the production profile of dispersed CHP units, the local units are ascribed a production per-
centage of 75-85 % in network analyses in the daytime in the winter and 30-50 % in the daytime in the summer. The
network analyses are supplemented with risk assessments of situations with simultaneous forced outages of many local
- 29 -
CIIP units. However, the expansion of the 400 kV network in Denmark has not ceased. The reason is in part that elec-
tricity consumption continues to rise, in part that the local CHP units do not have full power value and in part that a
restructuring of the 150 kV and 132 kV networks is being carried out. The restructuring is a consequence of a general
v,1ish from the public for fewer overhead lines.
In the long run dispersed generation may speed up the expansion of the transmission network. The latest energy plan
from the Danish government operates with the installation of 4000 MW of offshore wind turbines in the year 2030.
Such an amount cannot be integrated in the system without reinforcing the network.
A.4 France
The main electricity utility in France is state owned Electricite de France (EDF). EDF is in charge of generation, trans-
mission and distribution of electricity; it co-ordinates the dispatch of electricity produced by other generators, delivers
electricity to independent distributors and co-ordinates power exchanges across the national borders. EDF operates
roughly 90 % of all installed capacity. Its total capacity is about 100 GW (roughly 59 % nuclear, 24 % hydro, 17 %
fossil fuel).
In 1995, EDF produced 444 TWh (81 % of which were nuclear, 15 % hydro), and other producers 27 Twh. A decree
dated 1955 obliged EDF to purchase the excess power produced by autoproducers, under the following conditions:
• the obligation of purchase must ,,not result in any obstacle to the smooth operation of the supply";
• the energy is purchased by EDF under a standard contract lasting at least three years (five years in the case of sim-
plified contracts) or for the period of amortisation of the producer's installation (at the producer's request);
• the maximum capacity of the power plant must not exceed 8 MVA; this limit however does not apply to local
authorities owned plants supplying a district heating system or burning urban waste.
In case these conditions are fulfilled, the decision to start or not by EDF. Electricity is bought by EDF at a price re-
flecting ,,avoided costs" and are therefore based on long run marginal costs. Tariffs used for the purchase of electricity
are deduced from tariffs applied to consumers by simply deducting a varying amount, of about 10%, which corresponds
to management costs and losses on the network. It means that the price per kWh depends on the location of the genera-
tor and the voltage level at which it is connected. This decree was frozen for a period of three years in 1996. The obli-
gation of purchase was however kept for generation produced with renewables and cogeneration (Combined Heat and
Power).
For cogeneration, new regulations were adopted in December 1996, allowing for contracts spanning over a 12 year
period, and including installation of more than 8 MVA capacity. Electricity bought off cogenerators by EDF is still
based on ,,avoided costs", but taking as reference equipement of combined cycle gaz turbines. These prices will be
subject to variation in the price of gaz. Like all countries of the European Union, France will have until the end of 1998
to translate into French law the European act on Internal Electricity Market, adopted by the European parliament in
December.
A.4.2 development of DG
The voltage level of the input network is determined by a rule depending on the power of the DG. This rule is general
but some derogation demands are possible. They must be approved for each case by the chief engineer in charge of the
network control.
The voltage level for the network connection is given by the following rule:
• P < 10 MW: medium voltage
• 10 MW,; P < 40 MW: high voltage< 225 kV
• P;, 40 MW: high voltage;, 225 kV
The technical requirements available concern mainly the MV network and the requirements for the other cases are still
being defined in 1997. Tue technical rules for DG on MV network are described in an official text published in the
,,journal officiel de la repblique Francaise" of the 14 April 1995. It concerns the following items.
l. The maximal intensity on cable and line: A table gives the maximal intensity for each type of line. This value con-
cerns the steady state with the production of the DG.
2. The impact of the voltage drop of the network (low variations): The voltage level of each point of the MV network
must be maintained between -5% and +5% of the contractual value.
- 30 -
3. Checking of the 175 Hz remote-control signal: The remote controlled frequency is used for different categories of
tariffs. A minimal rate of this signal must be still there when the DG is producing.
4. Harmonic and unbalance: The maximal harmonic rates are defined by the official document describing the technical
requirements (for instance harmonic 3:2%). The variation of the unbalance rate must not be greater than 2o/o.
5. Reacitve power: The producer must provide a n1inin1al reactive power equal to 40% of is nominal power.
6. Protective relay for disconnection: The rule contains the detailed description of the disconnection protective relays
that must be used. The relays must work for a internal fault of the DG or for a fault on the network.
A.5 Germany
man industry BDI and industrial energy sektor VIK contains a voluntary system for transmission tariffs [14]. The gen-
eral idea is a point-to-point-tariff which contains distance-depending components. On the transmission level there is a
distance depending elemnt of the tariff, in distribution there has to be paied a part of the fee for the higher levels in case
a certain distance between generator and customer is exceeded. The system services (frequency control, voltage control,
restoration, operation) are added on customers' bills, the model for this in the distribution area is not fixed yet. Genera-
tors providing system services are paid accordingly.
There is an exemption rule for renewable energy: Utilities (network operators) are obliged to purchase their energy,
their price shall be at least 65-90% of the average revenue per kWh from delivery of electricity to all final consun1crs
(summing up energy-costs and network-access), depending on type and size of the generation facility.
A.5.2 development of DG
The most important DO-types at the moment are BHPS and WEC. Small BHPS have reached a total capacity of
1260 MW (=2197 units) at the end of 1996, which is an increase of 40% within 2 years. Cogeneration in total sums up
to more than 6000 MW in 1996/1997 and experiences a similar increase rate. WEC have increased from 300 M\\l
(1993) to 2400 MW (middle Of 1998).
According to VDEW for 2005 3600 MW of WEC are expected. Higher numbers seem possible when summing up the
expectations of the utilities in Germany. CHP may increase up to 35% of peak load in Germany, but not all of them are
going to be dispersed.
a) Network interference
The topic of network interference can be subdivided into four different types:
• voltage interference, covering the steady-state influence of dispersed generation on voltage control,
• var-compensation, covering the reactive power behaviour of the dispersed generation units,
• voltage distortion, covering the dynamic influence of dispersed generation on fast voltage fluctuations, which re-
sult into flicker, asynunetry, and harmonic distortion and the
• influence of single events on voltage quality, of which synchronising of dispersed generation units with synchro-
nous or asynchronous generators is the most important.
Voltage interference is measured by the voltage dip after switching on a dispersed generation unit related to the nomi-
nal voltage, which is almost equal to the nominal power of the dispersed generation unit related to the short-circuit level
at the connection point:
d _ LiU _ k ·Sr.gen
-u;:-- Sk
with k = 1 for synchronous generators and inverters, k =•1:x for asynchronous generators, where Im.ax is determined
by measurements. The var-compensation is prescribed by demanding a resulting power factor from the dispersed gen-
erator. This demand is defined from the point of view of the network operator, i. e. cos qi = 0,9 ind means delivering
inductive reactive power to the network. Voltage distortion is measured in flicker, harmonics and asymmetry. The
long-time flicker factor A]t should not exceed the I 0 % value of the threshold of flicker perceptibility (A]t = l ).
This flicker factor is calculated using:
)~}
3
A1t = ( C · --s;:- ·
Sr.gen (
COS ljl network + qi gen
with c being the flicker-coefficient of a dispersed generation unit, which is system-specific and values approximately 20
for an wind energy conversion unit with asynchronous generator and I for an installation with synchronous generator.
The flicker factor A1t can also be measured, using the so-called flickermeter [15]. Harmonics should not exceed acer-
tain level. According to the German connection criteria, this level should not exceed 0.2 %·Ur for the 5th order har-
monic, 0.1 %·Ur for all other orders.
Synchronising is regulated by the following rule: a synchronous generator should not be switched parallel to the net-
work, unless the following constraints are fulfilled:
LiU < 10%
M < 0.5Hz
Liqi < 10°
- 32 -
b) Protective relaying
To prevent any damage to the generation unit by influences from the neh·vork all units should trip on abnorn1alities in
the network. For this purpose, a short-circuit protection like an over current relay has to be installed. Protection against
influences of the generation unit on the net\vork is in most cases only installed on agreement with the local utility. If
demanded, over current relays or - in special cases - neutral voltage displacen1ent, earth fault or reverse power detec-
tions are installed. Isolated operation is generally prohibited. To prevent from this situation, slow over and under volt-
age (three phase) and over and under frequency relays (one phase) are installed. These relays should be parameterised
as defined in table A.3.
relay setting
U< 1.0 ... 0.7 u,
U> 1.0 1.15 u,
f< 50 ... 48 Hz
f> 50 ... 52 Hz
table A3
c) Special requirements
Some special requirements concerning operation and protection of dispersed generation units are made, according to
the operation and protection scheme of the network, in which these units are integrated. In German medium-voltage
overhead line networks a three phase short-circuit interruption is present. Dispersed generation units feeding into a
network fault could interfere with this short-circuit interruption and therefore have to trip that fast, that the duration of
the short-circuit interruption is not influenced by them.
No interference with the audio-frequency remote control system is allowed. To guarantee the operation of this control
system, the impedance of the dispersed generation unit at the broadcast frequency should be high enough. This can be
realised by installing filters at the generation sites. Also a harmonic distortion of maximal 0,1 o/o·U 0 is allowed for the
harmonic orders in the neighbourhood of the broadcast frequency.
Ttable A.4 provides with an overview of the main aspects of the guidelines to connect dispersed generation to the me-
dium-voltage grid.
- ~] -
c:ritcrion
net\vork interference
voltage interference d,; 2 % (MV, HV: 3 %)
var-con1rensation • control, no fixed capacitors
• only at operation
• cos <p = 0,8 ind ... 0,9 cap
voltage distortion • flicker: Ai 1 < 0, I
• harmonics limited
synchronising • synchr. generator: t.U < l 0 %, t.f < 0,5 Hz, liqi < l 0°
• asynchr. generator: no load,
speed at 95 % ... 105 % of nn
protective relaying
influence from network short-circuit protection
influence on network short-circuit, over current
isolated operation t.U (3-), M(l-)
special requirements I no interference with:
remarks
• short-circuit interruption
• audio-frequency control
A.6 Netherlands
An Electricity Act, from 1989, regulates the organization of the public electricity supply in the Netherlands. The act
describes the way of coordination between the four generating companies and Sep (the Dutch Electricity Generating
Board), and defines the relations and requirements up to the customers. The Electricity Act asks for an Electricity Plan
in which must be stated how the generation companies and Sep intend to take care of the generation and transmission
over the coming decade, and has to be specified the plant which are going to be used for it. This should be based on the
forecast of the total national demand for electricity and the trend in decentralized capacity. The decentralized capacity
consists of those plants which are installed at private autoproducers, industrial plants and distribution companies; so it is
all of the production capacity not owned by the four generating companies. In the last years the amount of small decen-
tralized plants grew very fast as a consequence of state subsidies for CHP. This caused an overcapacity that urged to a
moratorium on further construction of new plants.
On the moment decentralized capacity meets about 25% of the national demand for electricity. It is foreseen that the
amount could grow further. The functioning of the present organization has let to a debate on the responsibilities and
commitments of all parties involved in the planning process. A new law is in preparation and will probably be in serv-
ice from 1999, which will give more freedom to both clients and producers. The effect on the amount of decentralized
generation is quite uncertain; in each case the definition of what decentralized means will change.
A,6.2 development of DG
[n the following table the total amount of decentralized power generation in the Netherlands is given, according to the
present situation. Maximum national load is about 15.000 MW; maximum Sep load in 1996 was 11.320 MW. Total
installed capacity in the Netherlands is about 20.000 MW; so DG with 4.750 MW installed capacity represents 24.8%.
0-1 1-5 5-15 15-30 > 30 total installed capacity
MW MW MW MW MW (MW)
The technical rcquire111ents arc \vrittcn dO\Vll in an official publication of Encrgu:Ncd (Association of Energy l)istribu-
tion Co111panics). ·rhcsc have been dcveloppcd in n1utual cooperation between the responsible utilities.
The n1ain differences con1parcd to the Sep requiren1cnts for production units are:
• DG units are seen as negative loads; so no unit con1n1itment
• prin1ary regulation is pcrforn1ed only in case of severe frequency deviations(> 150 mI-lz)
• no secondary response
• voltage support only in agreen1ent with local utility
• design margins for voltage and frequency deviations are more narrow.
• For some of the bigger industrial plants with a relative high capacity operational agreements have been made with
Sep.
A.7 Norway
Generation, transmission and sales are the three basic conunercial functions of the power supply system. The transmis-
sion network is divided into three levels:
• the main grid (usually 420 kV, 300 kV and 132 kV)
• the regional grids (usually 132 kV and 66 kV)
• the distribution grids (usually 22 kV and l l kV)
The main or central grid constitutes the «motorways» of the power supply system, and links together production and
consumption in various parts of the country. It is also connected to the transmission lines to other countries. Regional
grids are connected to the main grid, and form links between generating companies, the central grid and distribution
grids. A distribution grid is a local network that distributes power to the end users.
Electricity generation plants are generally connected to the central grid or a regional grid. However, a number of small
installations are connected directly to a distribution grid. The 1991 Energy Act sets out the framework for the organi-
sation of the power supply system in Norway. It encourages competition within power generation and trading. The
prices for use of the transmission network are regulated by NYE (the Norwegian Water Resources and Energy Admini-
stration), which is responsible for monitoring monopoly (grid) operations.
Statnett SF (the Norwegian Power Grid Company) owns 80 % of the main grid. Statnett SF is a state enterprise, i.e. it is
a 100 % state owned company. Private companies, counties and municipalities own the remaining 20 % of the central
grid, but leases it to Statnett SF. Municipalities and county municipalities own most of the regional and distribution
grids. Municipalities and county municipalities own about 55 % of Norway's generating capacity, Statnett SF about 30
% and private companies about 15 %. Norway presently has approximately 845 hydro power stations with a total pro-
duction capacity which exceeds 27.200 MW (mean annual energy production capacity is approximately 110 TWh). In
addition, thermal power stations have a capacity at present of 278 MW. Norway is the sixth largest hydro-power pro-
ducing country in the world. The transmission network consists of approximately 200.000 km of overhead lines and
25.000 km of underground and submarine cables.
There are various types of power utilities:
• distribution utilities: The distribution utilities own the local distribution grid. They trade power in the market and
sell it to end users in their geographical area. The distribution utilities' trading operations are exposed to competi-
tion, since the end users may buy power from any supplier in the country. Some distribution utilities have entered
into contracts with end users in geographical areas served by other power utilities. There are approximately 100
distribution utilities in all.
• vertically-integrated utilities: Vertically-integrated utilities own both the local distribution grid and production
facilities. They may also own regional grids and some own parts of the central grid. The utilities sell electricity to
end users in the area where they own the distribution grid, and often compete for customers in the areas served by
other power utilities. There are close to 100 vertically-integrated utilities in Norway.
- 35 -
• wholesale utilities: Wholesale utilities have been established in a number of regions, and may own both parts of the
regional grid and production facilities. Their original purpose was to generate and purchase electricity for resale to
local distribution companies. There are 20 - 25 wholesale utilities in Norway.
• production con1panies: There are almost 130 production companies, i.e. con1panies whose operations are confined
to electricity generation. They do not own any part of the transmission or distribution systcn1.
• industrial companies: There are 57 industrial companies in the country. They supply pO\VCr mainly to an industrial
enterprise of which they form a part.
In recent years companies have been established solely to buy power for resale to end users and power utilities (trading
companies). Companies have also been established to negotiate power contracts (po\ver brokers). Statnett SF are re-
sponsible for the power system planning and operation of the main grid. The different power utilities are responsible for
the power system planning and operation of the grids in their respective supply area. Most power is now traded
bilaterally between producers and distribution utilities or large customers, or between the generation and distribution
sections of vertically-integrated utilities. Power is also sold in markets organised on the exchange principle, for which
Nord Pool ASA is responsible.
The power market is often divided into the wholesale market and the end user market.
• The wholesale market: The wholesale market is where producers and large-scale purchasers of power buy and sell
electricity. All the power utilities and others who buy power for resale participate in the wholesale market. Large
end users can also enter into contracts in the wholesale market instead of buying power through a utility or a trader.
• The end user market: An end user is someone who buys power for his own use. Only customers who require large
amounts of electricity buy directly in the wholesale market. Power-intensive industries and other major industrial
enterprises may also have their own power generation facilities. Most end users buy power through a power utility.
• The organised markets: Nord Pool ASA manages purchases and sales to producers and consumers on several
markets and is a neutral marketplace. Nord Pool ASA currently markets power in three different ways:
!. In the 14-hour market, or spot market, where contracts for individual participants are set up for one day at a
time.
2. The weekly market is a new market for future supplies. Two types of contracts are traded in the weekly market,
for base-load power and for peak-load power. These may be registered up to two years in advance.
3. In the regulatory market, which is a tool for maintaining a stable frequency and a continuous balance between
production and use of power. Once prices and quantities have been fixed in the spot market, Nord Pool ASA in-
vites offers for regulation of the amount of power generated (up or down). It must be possible to regulate power
generation at short notice, for example in the case of the sudden failure of a power station or transmission line,
or if there are sudden, unexpected changes in demand.
Nord Pool ASA now also organises financial trade markets.
Dispersed power generation (DG) in Norway must be defmed as micro-, mini- and small power stations (presently
hydro and to a minor extent wind turbines) connected to the distribution network (:5 22 kV). Furthermore, they are
planned and dispatched locally, i.e. not by the regional grid utility in the area. The stations can be utility or privately
owned. Micro-, mini- and small types of power stations are defined in table A.6.
0- IOOkW: micro power station
100 - 1000 kW: mini power station
1000 - 10000 kW: small power station
table A.6
Ttable A. 7 shows hydro power stations in operation per January I, 1996. Since a large portion of the power stations in
the 1 - 10 MW interval (small power stations) are connected to the regional grids, these stations cannot be considered as
DG.
- 36 -
.I - I LlO 55 0.2
I - 10 233 829 3.0
10 - 100 244 8879 32.5
100 - 76 17582 64.3
Total 853 27350 100.0
table A.7
The present wind turbine production in Norway is shown in table 3.2.11.3. The total installed capacity is 3885 kW.
From this it can be deduced that the total DG capacity in Norway does not amount to more than l - 2 % of the total
production capacity. The utility operating the regional grid to which a distribution grid with local production (DG) is
connected, will stipulate a fixed production for the DG in question when forecasting the short-term electricity trade. If
the DG production should deviate from the stipulated value, this difference must be balanced out in the regulatory mar-
ket. (The same principle applies if a distribution grid owner with local production is operating entirely on the spot mar-
ket). Nord-Trondelag Elektrisitetsverk is at this time planning a I MW wind turbine generator also at Vikna.
Type Make Expected energy Construction Location Owner
prod. (GWh/yearj5 year
table A.8
a) Technical requirements
5 Estimated average
- J7 -
[n practice FEB 91 applies to small installations and FEF 88 for larger installations. Ho\vcvcr, «Operational Regulations
for Low Voltage Installations>) and «Operational Regulations for High Voltage Installations)) applies for all installa~
tions. All installations with a systen1 (nominal) voltage$ 1000 V ac are defined as low voltage installations. Power
stations with generators with a nominal voltage > 1000 V ac are subject to a licensing procedure in accordance \vith
«l"he energy Act» (plant license).
Hazards:
It is an element of risk present for erroneously connecting small generators to the network during a disconnection in the
distribution system due to maintenance. This will cause voltage to be connected back on the system, and this represents
a hazard for the maintenance personal. FEB 91 have regulations in order to avoid such hazards. Furthermore, it should
be impossible to connect the generator to the system if the voltage and frequency values causes malfunctioning of the
protective relaying.
Public inspection
• Dams, gates and pipes
Public inspection includes the construction, operation and maintenance of dams, gates and pipes. NVE shall carry out
the inspections. In accordance with «The watercourse Act» § 144 NVE must have free access to all plant structures
subjected to public inspection. The site/plant owner must provide all relevant information to the inspectorate. Plans
must be reported to NVE when construction works are initiated on installations subjected to public inspection. The
plans must be approved by NYE before any works can be initiated. The plans should include:
• flood calculations and dimensioning of the flood discharge
• information about the dam construction material and the foundation conditions
• description of the planned works
• drawings of the dam
Where constructions are not subjected to public inspection the owner will be responsible for the safety in accordance
with «The watercourse Act»(§§ 108, 115 and 120).
• The electrical installations
Generators> JO kV A are subjected to public inspection by «The Electrical Inspectorate» in accordance with FEF 1988.
«The Electrical Inspectorate» in the region and the local utility must be notified prior to initiations of construction
works.
• General safety
As far as the general safety at the construction site is concerned it must be clarified with the local «The Labour In-
spectorate» if it is necessary with a notification and public inspection.
Other
The power station construction will depend on whether it is a high or low head plant, stored or run of river scheme, etc.
One should seek simple solutions for micro- and mini power stations in order to keep the costs down. However, all
operational safety requirements must be met. It is important to choose a correct turbine (type, capacity) in order to ex-
ploit the run of water in the watercourse optimally. The power station, if necessary, also includes the transformer and
the switchgear installations/high voltage installations. The network connection will depend on local conditions and the
size of the power station. There are four constellations for network connection (figure A. JO).
~
Utilily Iv network
Utility hv network
figure A. IO
- 38 -
• A generator'.','.; 25 kW connected directly to the lo\v voltage network should not cause any problen1s.
• A generator :-:;: I 00 kW connected directly to a sufficiently dimensioned low voltage network should normally nor
cause any problen1s within a few hundred n1eters from the supply station.
• Generators> 100 kW should be connected to a supply station. If the distance is too long it will be necessary to build
an hv transn1ission and a separate supply station.
b) Protection scheme
There are at this time no standards for protective relaying schemes. It is common practice to follow contractor recom-
mendations. However, automatic disconnection of the power station when ground fault occurs in the distribution net-
work should be standard.
No standards or regulations are at this time imposed on DG plants nor are they likely to be in the future.
d) Control systems
Generally the control equipment for operating and monitoring should be as simple as possible in small power stations.
Small hydro power stations are either equipped with synchronous generators or induction generators. A synchronous
generator equipped with a frequency regulator can be connected to an isolated network. Standards allow the voltage
level to vary between ± 5 °/o. The frequency variation limits varies in steps according to operating conditions; ± 0, 1 o/o
during normal operation. Otherwise no standards are adopted at present time. In many cases regulation of the water
level should be considered.
Local power generation in the distribution system will reduce the losses and contribute to voltage support. This cer-
tainly applies for rural distribution systems in Norway, characterised by long feeders with small cross-sections and
scattered and small loads. Synchronous generators can be connected to an isolated network if equipped with a fre-
quency regulator. Thus local generation will have positive effects both on the quality and security of supply. This im-
plies that DG must be taken into account in power system planning, and DG can be an alternative to conventional sys-
tem reinforcements (new lines, substations)
The annual mean production in hydro power plants < 10 MW is about 4 TWh and the total installed capacity somewhat
less than 900 MW. The potential for new production capacity is stipulated to be about 8 TWh. However, only a fraction
of this are likely to be utilised. And only a portion of this again could be defined as DG.
The present trend is a large interest from private entrepreneurs (landowners) to develop small watercourses on their
property for hydro power production. Project plans utilising alternative energy sources have also been launched, e.g.
wind turbines, tidal power plants and small combined heat plants burning waste. This interest for power plant develop-
ment was triggered by high prices for energy on the spot market during the autumn and winter 1996/97. Even so, only
a limited number of these projects are expected to actually be realized. Hence, DG are still expected to account for less
than 2 % of the total production capacity in Norway in a short- and medium- term perspective. Even on long-term the
contribution of DG to the total production capacity are likely to be negligible. The dominant share of DG are going to
be hydro power also in the future.
Small hydro power stations usually have limited reservoirs thus producing whenever water is available. The price on
the spot market will often have severe impact on the production planning in plants with sufficient storage capacity. A
trend toward larger utility units (mergers and cooperations) will make it easier to conduct centralised production plan-
ning in the future.
A.8 Poland
Since the year 1990 the power industry restructuring process has been taking place in Poland, modelled on what was
done in England.
- 39 -
All the sector was divided into three areas of operation - generation, transn1ission and distribution of energy - carried
out by three types of companies (first State-owned ones but meant for privatisation in the future).
In April this year Polish Parliament approved new Energy Law that accepts implementation of a n1arket-orienting re-
form. Introduction of the new Energy Law will bring about a radical acceleration of the power industry reform process.
lJtility companies will require licenses in their operation. Price control will be resigned - prices will be now fixed by
individual companies and approved by the Regulator Office of Energy that is being introduced by the new Law. The
new Law provides for wholesale, spot and contract markets of energy. Three part access is guaranteed. It does not pro-
vide for State subsidies offered to the power industry. Government will remain responsible for creation of the State
power policy.
A.8.2 development of DG
The so-called Power Grid System Integrated Development Planning is being elaborated within organisational frame-
work of the Polish Power Grid Company. According to updated demand electricity projections the new power plants
will be required around year 2007. Significant attention is paid in said projections to introduction of gas as an environ-
mentally friendly fuel used by the power industry.
Currently many power and cogenerating plants are being modernized in particular in the province of their economic
effectiveness and solutions that come friendly to natural environment. Gas will be used in modernization of cogenerat-
ing plants. The first contract has been signed already with the Gorz6w Cogenerating Plant. Other contracts are in prepa-
ration. Signing of the first contract is expected in reference to construction of a new power plant at Nowa Sarzyna by an
independent generator. New cogenerating plants and new power plant at Sarzyna are the facilities of some 100-
200 MW that will generate electricity for local markets. Development programmes take into account smaller gas-fired
power plants of a combined steam-gas cycle. Polish Power Grid Company is empowered to sign contracts that provide
for new generation capacities.
A.9 Spain
Table A.9
Red Electrica de Espana is in charge of the daily operation and planning of the high voltage network (transport) and it
does not have any sort of customers. Planning, operation, etc. for distribution systems are done by the rest of Utilities
within their area of concern.
Spain is now in a free and competitive market for electricity. The characteristics of the new situation are:
• Power Generation, Transport, Distribution and Commercial tasks are different units of business.
• Customers are free to set conunercial agreements with any "agent" or to buy energy to the pool.
• Red Electrica is only the high voltage network operator, with no control on production (set by the daily market).
• Planning, quality and others for distribution networks are carried out by distribution companies within its own area.
A.9.2 development of DG
Installed:
CLASSIFICATION BY TYPE
TC GENERATOR TYPES MW
RS RI AG
M-i Oo/n 2°/0 8% AG WIND FARMS 108.5
1•AGI FU FUEL-OIL UNITS 211.3
1•FU GA BIOGAS 3, 1
10GA. !
HR ' 0GN1I
1 GN NATURAL GAS 619, 1
6%
GR
'•GR! GR REFINERY GAS 102,0
7%
;.H<j HR HYDRO> 5MW 87,5
,.M-i: MH HYDRO< 5MW 238,6
l:;J RI
RS
INDUSTRIAL SOLID WATE FUELS
URBAN SOLID WASTE FUELS
26,5
0,7
TOTAL 1397.4
•<1M/V
CLASSIFICATION BY TYPE
RS SO
AT
71°/o
TC GENERATOR TYPES MW
AG WIND FARMS 1919,3
FU FUEL-OIL UNITS 249,5
GA Bl OGAS 32,2
GN NATURAL GAS 1051,6
HR HIDRO > 5MW 81, 1
MH HIDR0<5MW 80,6
RA FARM WASTE FUEL 21,2
RI INDUSTRIAL WATE FUEL 30,0
CLASSIFICATION BY PRODUCED POWER
RS URBANOS WASTE FUEL 110,0
<1 MW
so PHOTOVOLTAIC 0,2
1% TOTAL 3575,6
>1 y <5Mv\'
10°/o >JOMN
'•>30MvV
34%
.>20 y <30Mv\'I
10%
0. >10 y <20~ POWER MW
10>5 y <10Mv\' 1164,0
>30MW
~
>1y<5fvfN
>10 y <20 <) 20 y <30MW 763,4
<1 MW
MW >20 y <30 ----- --- <) 10 y <20MW 873,1
24%
MN
<) 5 y < 10MW 360,6
21°/o
<) y < 5MW 365,1
<1 MW 49,4
TOTAL 3575,6
a) Technical requirements
Technical requirements are under 2 State regulations in which the rules are fixed for the connection of all kinds of DG.
These rules are now in a revision process.
b) Protection scheme
The common protection scheme is the following. (In several units other devices can be arranged).
- 42 -
• An increasing in the grid voltage of 2.0 % when running is forbidden. In the same way a variation of 5 % if it
changes from generation to loading.
• An IPP connection to the grid is rejected if is power is higher than the 10 % of the short circuit power at the con-
necting point.
• A power factor no beneath of0.8 (lead or lag) is required. When wind farms this should be higher of0.86.
• No contribution to system transient stability has been established.
• The utility can review the correct status of all of the protection devices, remote data acquisition systems, etc. in-
stalled in the !PP plant.
d) Control systems
In case of IPP's no control is done from the electrical company dispatching excepting signals for locking and tripping
the station breaker, if necessary.
A.10 UK
Since the privatisation of the electricity supply industry in 1990, the industry has been organised as three primary busi-
nesses. The generation of electricity is a totally open and competitive market. There are currently some 30 generating
companies in the UK. The bulk transmission of electricity (400 kV and 275 kV) is carried our by the National Grid
Company (NGC) operating as a regulated monopoly. The distribution of electricity is again a regulated monopoly busi-
ness carried out in England and Wales by twelve Regional Electricity Companies (RECs). (Note that the arrangements
are different in Scotland an N. Ireland).
DG will, almost without exception, be connected to a REC distribution system. The REC operates under a Public Elec-
tricity Suppliers's licence. This licence places many obligations on the REC including the obligation to offer to connect
DG to its system.
Most generators also have to be licenced under current legislation. A generation licence brings with it a range of obli-
gations including the obligation to trade electricity through the common electricity pool. However, for many DGs this
licence is not required so that there is greater freedom to trade electricity in the area local to the plant. This is one rea-
son why DG has grown in recent years.
- 43 -
The UK RECs have a con1n1on code of practise, the Distribution Code, that sets out the way in which the distribution
systen1s are planned and operated. This code is supported by a number of engineering reco1nmendations and standards.
'fhcsc cover a range of issues including supply security, voltage control and harmonics.
There are two engineering recon1mendations that apply directly to DG. The first, ER G59-l, applies to DGs of less than
5 MWe being connected at 20 kV or below. l'he second, ER G75, applies to DGs larger than this or connected to higher
voltages.
'rhese two engineering recommendations set out the technical requirements for DGs. A potential DG developer will
have to make a detailed application to the REC clearly showing that the proposed connection meets the required stan-
dard particularly in tem1s of the protection scheme.
The RECs have a statutory obligation to plan their distribution systems in an economic manner whilst providing con-
nections for generation and demand and achieving required security and supply quality standards.
Generation is not planned in the UK market. No single party has a statutory obligation to actually supply electricity to a
customer. It is assumed that the normal market rules of supply and demand will prevail and that the market will provide
sufficient generation capacity to meet the demand.
B References
[IJ Westwood, M.
Cogeneration in Australia : An Untapped Resource For Economic Development Environmental Improvement.
paper presented on 26-27 February 1997 at "Cogen '97" Conference in Brisbane, Queensland, Australia
[3] NORD EL "Operational Performance Specifications for small Thermal Power Units", 1995
[4] DEFU: "Relay protection for local CHP units", technical report 293, 2'' edition (in Danish)
[5] DEFU: "Voltage quality in low-voltage transmission networks", Recommendation no. 16 (in Danish)
[6] ELSAM: "Power Station Specifications for Plants< 2 MW" (in Danish), SP91-515h
(7] ELSAM: "Power Station Specifications for Plants between 2 and 50 MW" (in Danish), SP92-0J 7a
[9] DEFU: "Grid connection of wind turbines", Commitree Report 111, 1998 (in Danish)
[IO] Rise+ DEFU: "Power quality and grid connection of wind turbines", Parts I, 2 and 3 (in Danish), Rise-R-853
and DEFU-TR-362
Cependant, le CIGRÉ ne pourra en aucun cas être tenu responsable des préjudices ou dommages de quelque
nature que ce soit pouvant résulter d’une mauvaise utilisation des informations contenues dans cette brochure.
Copyright © 2000
Toute reproduction, même partielle, par quelque procédé que ce soit, est interdite sans autorisation préalable.
Cette interdiction ne peut s’appliquer à l’utilisateur personne physique ayant acheté ce document pour
l’impression dudit document à des fins strictement personnelles.
Pour toute utilisation collective, prière de nous contacter à sales-meetings@cigre.org
The greatest care has been taken by CIGRE to produce this digital technical brochure so as to provide you with
full and reliable information.
However, CIGRE could in any case be held responsible for any damage resulting from any misuse of the
information contained therein.
Published by CIGRE
21, rue d’Artois
FR-75 008 PARIS
Tel : +33 1 53 89 12 90
Fax : +33 1 53 89 12 99
Copyright © 2000
All rights of circulation, translation and reproduction reserved for all countries.
No part of this publication may be produced or transmitted, in any form or by any means, without prior
permission of the publisher. This measure will not apply in the case of printing off of this document by any
individual having purchased it for personal purposes.
For any collective use, please contact us at sales-meetings@cigre.org