TABLE OF CONTENTS
1 COST ESTIMATE........................................................................................................... 1
1.1 EXECUTIVE SUMMARY .......................................................................................... 1
1.2 GENERAL ASSUMPTIONS ...................................................................................... 3
1.3 FACTORS AFFECTING CONSTRUCTION COST ESTIMATE ......................... 4
1.4 COST ESTIMATE BREAKDOWN ........................................................................... 5
1.5 RECONCILIATION WITH PRE-CONCEPT ESTIMATE.................................. 10
1.6 CONCLUSION .......................................................................................................... 12
1 COST ESTIMATE
This Cost Report aims at providing a reasonable Cost Estimate for the construction of
Infrastructure works at Gewan Island in Qatar. Cost Estimates used in the evaluation are
based on consolidated, functional rates extracted from a Cost Database representative of
previous similar projects and reflecting the current market prices.
In this context, it is noted that the provided Cost Estimate is prepared in compliance with
Design Development stage documents; hence, it represents the fair priced estimate for the
Construction Cost of the Project - Infrastructure works at Gewan Island in Qatar.
Below table shows the estimated cost of Infrastructure Works at Concept as well as Design
Development Stage.
Design
Concept Design
Development Cost Remark
Cost Estimate (QR)
Estimate (QR)
CD Estimate is inclusive of
the R.O. Plant with
Subtotal for
estimate of QR 50.3
Infrastructure 405,612,275 359,885,810
million, which is removed
Works
in the Design Development
stage.
Preliminaries
40,561,230 35,988,580
(10%)
Included in current Design
Contingency (10%) Not Included in CD 39,587,400 Development as per
Client's Instruction
Included in current Design
Escalation (4.5%) Not Included in CD 17,814,350 Development as per
Client's Instruction
Grand Total 446,173,505 453,276,140
The below table summarizes the costs related to the project components:
COST
ITEM DESCRIPTION
QR
Accuracy of Cost Estimate: The current accuracy level of this Cost Estimate is +/-10%.
o The pricing used is intended to reflect a construction that is compliant with the
regulations and governing specifications in Qatar.
o The provided Cost Estimate represents current costs for July 2018 which shall
be subject to further refinement and modification as the Design progresses
o The Cost Estimate is based on rates extracted from a Cost Database from similar
executed Projects in addition to market prices
o The indicated cost for the District Cooling Plant is maintained as the same at
the Concept Design stage and represents the 12,000TR capacity, dedicated to
GEWAN ISLAND
o RO Plant Including Intake and Outfall is removed from scope in the current
Design Development stage
o The Estimated Construction Cost includes Labor, Material and Equipment
Costs in addition to Contractor’s management, Overhead and Profit costs,
Conditions of Contract & General Requirements
o The Conditions of Contract & General Requirements shall cover all the
Conditions, Terms and all Contractual Requirements including but not limited
to Site Temporary Facilities, preparation of As Built Drawings, cost for
submittals including Shop Drawings, preparation of Manuals and Reports,
Meetings, Testing & Commissioning, carrying out Trainings and methods,
etc...., in addition, the terms shall include the cost of Insurance, Bank
Guarantees ...etc., These costs are considered included within the rates
establishing the Cost Plan.
o This enclosed Cost Estimate is prepared on the basis of the Infrastructure Works
Design Development Report referenced Q18021-0100D-PK2-PD-RPT-PM-01
REV 0
Below are the break down for the cost for each component in the current Design Development
stage of the Infrastructure Works:
COST
ITEM DESCRIPTION
QR
Earthworks
a Earthworks for the Roads 5,250,000.00
Earthworks for Site Rough Grading (Public domain including 2,240,000.00
b
linear park & Utility buildings)
c Asphalt Pavement 1,708,500.00
d Paving-Vehicular 9,913,200.00
e Precast Concrete Kerbs 3,342,000.00
f Traffic Signs 165,880.00
g Pavement marking 258,000.00
h Grouted Rip Rap Slope Protection 1,620,000.00
i Reinforced earth wall 4,400,000.00
a Pipes 2,885,200.00
b Valves 364,000.00
c Water Meter 25,000.00
d Fire Hydrant 420,000.00
e House Connections 280,000.00
f Road reinstatement 150,000.00
g Connection to existing network 25,000.00
COST
ITEM DESCRIPTION
QR
h Connection to existing network 8,350.00
COST
ITEM DESCRIPTION
QR
f Site Irrigation Programme Controller (to be connected to the 136,500.00
main central control system)
g Complete electrical installation 1,700,000.00
COST
ITEM DESCRIPTION
QR
COST
ITEM DESCRIPTION
QR
19 LANDSCAPE 30,208,585.00
21 WAYFINDING 1,490,000.00
SUBTOTAL 359,885,810.00
A PRELIMINARIES 35,988,580.00
B CONTINGENCY 39,587,400.00
C ESCALATION 17,814,350.00
The below table lists the key variances between the previously submitted Concept Cost
Estimate for the Infrastructure works QAR 446,173,505 (including preliminaries & excluding
Contingency and Escalation) and the current Design development Cost Estimate of QAR
453,276,140.00 (including preliminaries, Contingency and Escalation). It is worth noting that
Concept Design Estimate is inclusive of the R.O. Plant with estimate of QR 50.3 million, which
is removed in the Design Development stage.
Change in Cost
Design
Conceptual Cost Design Development Cost
Works/Building Development vs Justification for the Changes in Cost
(in Million QR) (in Million QR)
Conceptual
(in Million QR)
- Change in master layout & roads as per discussion & agreement with Client
- Quantities refined in the current development stage and includes the grading of Public domain including linear park & Utility buildings only
Earthworks 9.37 7.49 (1.88)
- The site rough grading is not considered above reclamation level +3.00 within private plots such as golf course in the current design development
stage
- As per Client's comment, Basalt pavement at CD stage is replaced with Granite pavers for vehicular traffic & asphalt pavement at Design
Development stage
Roadworks 17.95 21.41 3.46
- Addition of roads in front of mixed use area
- Refinement during design development
Water Network 4.42 4.15 (0.27) Refinement during design development
Water Reservoir and Pumping Station 3.00 3.72 0.72 Refinement during design development and addition of fixed outdoor standby type generator
Wastewater Network 5.87 5.15 (0.72) DCP relocation, deletion of water park & Refinement during design development
Wastewater Pumping Stations (3No.) 2.10 2.71 0.61 Refinement during design development
- Refinement during design development
Stormwater Network 6.14 7.41 1.27
- Additional roads between mixed use & plot 2 due to change in masterplan
Back up source from existing RO is not considered due to change in DCP location; Reduction in pipe sizes/demand due to relocation of DCP outside
Irrigation Network 7.47 7.24 (0.23)
project limit
Irrigation Reservoir and Pumping Station 1.90 2.02 0.12 Refinement during design development
- Cost increase for chilled water network is mainly due to the relocation of the DCP at Plot LA-91.
Chilled Water Network and Outdoor ETS 32.50 41.26 8.76
- Minor increase in cost of HEX Building due to the additional villas (Plot 2) connected to this HEX Building, as per Client requirement
District Cooling Plant 108.00 108.00 - Indicated cost for the DCP represents the 12,000 TR dedicated to GEWAN ISLAND
RO Plant Including Intake and Outfall 50.30 (50.30) Removed at Design Development stage as per DAR's recommendation
Cost reduction is mainly due to the decrease in the LPG plant capacity since Plot 2 landuse has ben changed from Retail/F&B to Villas, as required by
Gas Network and Plant 5.00 2.43 (2.57)
Client
Power Supply (MV + LV) 18.10 19.85 1.75 Change in master plan & addition of New villas in Plot-2 as instructed by Client, electrical load variation, addition of security booth, GSM tower
Change in master plan & addition of New villas in Plot-2 as instructed by Client, electrical load variation, change in BUAs & subsequent addition of
SUBSTATIONS (3no.) 11.20 16.73 5.53
transformers
- Street lighting selection and concept is REVISED
Street and Landscape Lighting 19.50 11.00 (8.50)
- Optimisation of lighting selection at Design Development stage
Telecom, ELV & Security Network 2.80 2.23 (0.57) Refinement during design development
Site Security (CCTV Cameras) 2.80 2.13 (0.67) Refinement during design development
CCTV Monitoring Building 1.80 3.59 1.79 Design development and provision for fixed outdoor standby type generator
Solid Waste Collection Network 47.00
57.72 (0.28) - Refinement during design development
Solid Waste Vacuum Station 11.00
Landscape 35.90 30.21 (5.69) Design development
Wayfinding 1.49 1.49 -
Total 405.61 357.94 (47.67)
1.6 CONCLUSION
The cost estimate shall continue being updated to accompany the evolving design process and
shall be referred to and made use of in raising early flags on any cost overruns. This close
monitoring of the cost estimate for the Project shall allow the Project team, in coordination
with the LDC, to take the right decisions in realigning the design to the set budget.
At each stage of the design process, the estimate shall be produced to the level of accuracy that
is commensurate with the extent of available information and within tolerances and accuracy
levels that are in line with commonly accepted ranges of estimate for the level of available
design information.
1 EARTHWORKS & ROADWORKS 27,316,610.00 1 EARTHWORKS & ROADWORKS 28,897,580.00 1,580,970.00 Change in master layout & roads
Earthworks Earthworks
a Filling imported natural material under ROW 6,155,100.00 a Earthworks for the Roads 5,250,000.00 (905,100.00) Quantities updated due to design enhancement
- Quantities refined in the current development stage and includes the
grading of Public domain including linear park & Utility buildings only
Earthworks for Site Rough Grading (Public domain
b Filling imported natural material for site rough grading 3,216,500.00 b 2,240,000.00 (976,500.00) - The site rough grading is not considered above reclamation level
including linear park & Utility buildings)
+3.00 within private plots such as golf course in the current design
development stage
c Asphalt Pavement 1,708,500.00 As per Client's comment, Basalt pavement at CD stage is replaced with
c Basalt pavement 15,158,275.00 (3,536,575.00) Granite pavers for vehicular traffic & asphalt pavement at current
d Paving-Vehicular 9,913,200.00 Design Development stage
2 WATER NETWORK 4,423,375.00 2 WATER AND FIREFIGHTING NETWORK 4,149,200.00 (274,175.00) Refinement during design development
Cost Reconciliation
Q18021-0100D–PK2-PD-EST-PMC-01 REV 0
© Copyright protected Page 1 of 6
Gewan Island PK2-Infrastructure Works
a Vitified Clay pipes (Gravity Pipes) 1,366,500.00 a Vitified Clay pipes (Gravity Pipes) 805,950.00 (560,550.00)
b GRP pipes (Pressure Main) 2,224,600.00 b GRP pipes (Pressure Main) 2,321,040.00 96,440.00
c Valves 222,500.00 c Valves 232,105.00 9,605.00
d Manholes 1,092,000.00 d Manholes 1,020,440.00 (71,560.00)
e Service connection 804,000.00 e Service connection 562,800.00 (241,200.00)
f Discharge Chamber - f Discharge Chamber 53,425.00 53,425.00
g Road reinstatement 150,000.00 g Road reinstatement 150,000.00 -
h Connection to existing network 8,350.00 h Connection to existing network 8,350.00 -
Cost Reconciliation
Q18021-0100D–PK2-PD-EST-PMC-01 REV 0
© Copyright protected Page 2 of 6
Gewan Island PK2-Infrastructure Works
Cost Reconciliation
Q18021-0100D–PK2-PD-EST-PMC-01 REV 0
© Copyright protected Page 3 of 6
Gewan Island PK2-Infrastructure Works
Cost Reconciliation
Q18021-0100D–PK2-PD-EST-PMC-01 REV 0
© Copyright protected Page 4 of 6
Gewan Island PK2-Infrastructure Works
Street and Landscape Lighting 19,500,000.00 Electrical works (Street, Landscape and decorative 11,001,670.00 (8,498,330.00) - Street lighting selection and concept is revised
Lighting with control) - Optimisation of lighting selection at current Design Development
stage
Converged Network (Telecom, ELV & Security Network) 2,800,000.00 Converged Network (Telecom, ELV & Security Network) 2,234,050.00 (565,950.00)
Site Security (CCTV Cameras) 2,800,000.00 Site Security (CCTV) 2,127,000.00 (673,000.00)
Prefabricated aluminium control booth 25,000.00 25,000.00 Refinement during design development
Parking Access Control 308,000.00 308,000.00
Probing & Grouting for Utility buildings other than HEX 292,500.00 292,500.00
building
17 SOLID WASTE SYSTEM 55,000,000.00 17 SOLID WASTE MANAGEMENT 55,026,835.00 26,835.00 Refinement during design development
a Collection costs if 2 fraction cyclone & compactor system 8,000,000.00 a Collection System 11,012,195.00
18 SOLID WASTE VACUUM STATION 3,000,000.00 18 VACUUM STATION BUILDING 2,695,215.00 (304,785.00) Design development
Cost Reconciliation
Q18021-0100D–PK2-PD-EST-PMC-01 REV 0
© Copyright protected Page 5 of 6
Gewan Island PK2-Infrastructure Works
Cost Reconciliation
Q18021-0100D–PK2-PD-EST-PMC-01 REV 0
© Copyright protected Page 6 of 6