Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
• Introduction on Column
• Introduction on Re Boiler
15 July 2010
Column & Re Boiler Piping
2
INTRODUCTION ON COLUMN
Column is a cylindrical vessel used for distillation process.
• Fractionation
Due to difference on the gravity between liquid phase & vapor phases,
the Liquid Runs down the column cascading from tray to tray while the
15 July 2010
Column & Re Boiler Piping
4
Representation and Types of columns.
15 July 2010
Column & Re Boiler Piping
8
Information needed to arrange the column piping
1. Plot plan gives:
• The physical location of a column and its relationship to other equipment.
• Main access
• Main pipe run or pipe rack.
• Location of pumps.
2. P&ID and Technical specification of column provide:
• Process data showing interconnected equipment and piping.
• Pipe sizes and pipeline components.
• Steam tracing and insulation thickness.
• Tower elevations and differences in related equipment levels.
• P&ID for nozzle connections, NPSH of bottoms pump, Instrumentation, line blinds, relief valves etc.,
3. The basic layout and general engineering specification describe:
• The minimum access, walkways, platforms width and headroom requirements.
• Maximum rise of ladder.
• Pipe-system requirements such as open or closed relieving systems.
• Minimum line-size and required hose-stations.
• Access to valves and instruments.
15 July 2010
Column & Re Boiler Piping
11
Sequence of Column piping study.
7. Platforms on towers are required for access to valves, instruments, blinds
and maintenance accesses. Platforms are normally circular and supported
by brackets attached to the side of the tower. Following drawing illustrates
the platform requirements.
9. For platform with control stations, the width of platform shall be 900mm
plus the width of control station.
10. The platform for manholes and maintenance access, adequate space for
swing the cover flange must be provided.
15 July 2010
Column & Re Boiler Piping
12
Sequence of Column piping study.
13. A Davit usually handles heavy equipment such as large size relief valves
and large diameter blinds. If the davits is at the top of the tower, it can also
serve the for lifting and lowering the tower internals to grade.
14. Clearance for lifting tackle to all points from which handling is required and
good access should be provided.
15. Re boiler lines elevations are determined by the draw off and return
nozzles and their orientation is influenced by thermal flexibility
considerations. Re boiler lines and the overhead lines should be as simple
and direct as possible.
Thermal Insulation
Thermal insulation of the exterior of a column may be required in order to
reduce the heat loss. Insulation may be inadequate to maintain the
required temperature distribution in these circumstances, a reboiler is
used.
15 July 2010
Column & Re Boiler Piping
13
Typical tower area division for various facilities
Presentation title
February 11
ORIENTATION OF NOZZLES & ACEESS
15 July 2010
Column & Re Boiler Piping
15
15 July 2010
Column & Re Boiler Piping
16
15 July 2010
Column & Re Boiler Piping
17
Column Piping
15 July 2010
Column & Re Boiler Piping
19
CROSS SECTION OF PIPERACK & COLUMN
15 July 2010
Column & Re Boiler Piping
20
COLUMN PIPING SUPPORTS
15 July 2010
Column & Re Boiler Piping
21
PHOTOGRAPH OF COLUMN AND PIPING
15 July 2010
Column & Re Boiler Piping
22
Re Boiler
• Re Boiler is a large heat transfer unit that is generally located outside
the distillation column.
• This are required for tall columns, and for columns operated at high
temperatures, which are subjected to appreciable loss of heat.
15 July 2010
Column & Re Boiler Piping
23
Schematics of Reboiler.