Rate Of Analysis

Side: NBSC (Natinal Bank Staff College) Location: Lucknow, Kanpur Road
Subject: Removing of wooden flooring at conference hall of NBSC, Lucknow
Removing of existing wooden flooring stacking of survival material and disposal material
And disposal within 50 meter led and floor cleaning as per required

S.NO Particular Qty Unit Rate Amount

1. Labours:
Wooden flooring removing and
Shifting-

a) Carpenter 3 x 600 = 1800


b) Helper 6 x 450 = 2700 --- Job 4500 4500

Total = 4500/-

2. Floor grinding and cleaning


180 Sqm 22 3960

3. Floor filling and levelling


180 Sqm 12 2160

4. Skirting removing & filling levelling and


cleaning 180 Sqm 14 2520

Total 13140
C/P 15% 1971
GST (Total +C/P) 18% 2719
Grand Total 17830