LM2X WATER INJECTION SYSTEM OPERATION


TABLE OF CONTENTS

WATER INJECTION SYSTEM


2

Flow Through Filter and Pump


3

Flow Through Main Skid


3

Gas Purge 4

Monitoring During Operation


4

WATER INJECTION SYSTEM

Demineralized water from a customer source is pressurized by water injection pumps and
piped to the main skid through customer interface [1]. The water injection system is
sequenced and controlled automatically by the control system. The operator’s role is to
ensure pre-start checks and permissives have been satisfied, monitor the startup and
operation of the system, and respond to any abnormal conditions. A typical operator
interface display of an LM2500 water injection system is shown below.

During a typical start sequence, permissives must first be satisfied to enable a water injection
system start. Typically these permissives include sufficient water supply temperature
and pressure to the pumps, and the turbine running with no shut down signals issued.

Flow Through Filter and Pump

(Refer to GE AEP Drawing xxx260)

Customer-supplied demineralized water is supplied to the water injection skids at customer


connection [79] at 31 gpm (1.96 L/s), 30-40 psig (207-275 kPaG) , 40-140 °F (4-60 °C),
and pre- filtered to 10 µ absolute. The water injection skid includes a simplex filter
assembly which also filters the water to 10 µ absolute. Pressure differential transmitter
PDT-2073 monitors the condition of the filter assemblies.
Water pressure at the pump intake is measured by pressure transmitters PT-2074.
Pressure indicator PI-2074 displays pressure readings in the range of 0-100 psig (0-689
kPaG). Alarm PAL-2074 is activated at pump suction pressures of 10 psig (69 kPaG)
or lower. Shutdown PALL-2074 is initiated at pump suction pressures of 5 psig (34
kPaG) or lower. Shutdown PAHH-2074 is initiated at pump suction pressures of 60
psig (414 kPaG) or higher.

The water injection pump is a positive displacement, axial piston pump, rated for a flow rate
of
31 gpm at 800 psig (5516 kPaG) when running at 1750 rpm. The pumps are driven by
electric motors MOT-2075, which are 3-phase, 20 hp motors rated for 460 or 380 VAC and
60 or 50 Hz.

Water temperature at the pump discharge is monitored by temperature elements TE-2077.


Alarm TAH-2077 is activated at temperatures of 140 °F or higher. Shutdown TAHH-2077 is
initiated at temperatures of 150 °F or higher. Discharge pressure is regulated by pressure
control valve PCV2076, set at 800 psig (5516 kPaG). Pump discharge pressure is also limited
by pressure safety valve PSV-2076 set at 850 psig (5861 kPaG). Both the pressure control
valves and the pressure safety valves allow excess water to leave the skid at customer
connection [3 3B].

Demineralized water passes through a 100-mesh strainer, a locked-open ball valve, and a
check valve as it leaves the water injection skid and enters the main skid via a flexible
hose.

Flow Through Main Skid

Demineralized water pressure is monitored at the main skid by pressure transmitter PT-207
1. Pressure indicator PI-207 1 displays water pressure in the range of 0-1000 psig (0-6895
kPaG).<} Alarm PAL-2071 is activated at pressures of 800 psig (5516 kPaG) or higher.
Shutdown PALL-
2071 is initiated at pressures of 950 psig (6550 kPaG) or higher.

Electrically-operated flow control valve FCV-2019 modulates the water flow according to
signals sent from the TCP. Solenoid valves SOV-2016 and SOV-2017 fail closed to stop
water flow during shutdowns, and can be opened and closed as necessary when draining
and purging the fuel manifold and water injection systems. Water injection flow is
monitored by flow
element FE-2003, which sends data to the TCP via flow transmitter FT-2003. Flow is
totalized at
the TCP and displayed at flow indicator FI-2003 in pph/gpm.
Water passes through another check valve before entering the secondary fuel manifold.
Water temperature and pressure are monitored at the fuel manifold by temperature element
TE-2035 and pressure transmitter PT-2030, respectively. Alarm TAH-2035 is activated at
temperatures of
400 °F (204 °C) or higher. CDLO shutdown TAHH-2035 is initiated at temperatures of
700 °F ( 371 °C)or higher.
Water can be drained from the secondary fuel manifold by opening solenoid valve
SOV-2010. Water that passes through this valve leaves the main skid at customer
connection [7].

Gas Purge

Natural gas from the fuel system is used to purge water from the fuel manifold. Gas is
bled from the fuel system downstream of FCV-2001 through a 3/4” line. The gas passes
through a check valve and enters the feed lines to the secondary fuel manifold.

Monitoring During Operation

During operation, the incoming water supply pressure and temperature (to the water
injection system) is monitored at all times. If the temperature of the incoming water
supply goes beyond alarm setting, an alarm/shut down will be issued.

Differential pressure across the incoming demineralized water supply filter is


monitored during operation, and if it exceeds the alarm set point, an alarm will be
issued.