Sei sulla pagina 1di 5

SME Annual Meeting

Feb. 21 - 24, 2016, Phoenix, AZ

Preprint 16-078

ROOF CONTROL, PILLAR STABILITY, AND GROUND CONTROL ISSUES IN UNDERGROUND STONE MINES

D. Newman, Appalachian Mining & Engineering, Inc., Lexington, KY

ABSTRACT crosscut widths, mine orientation with respect to horizontal stresses


and the sill pillar thickness between adjacent ledges. A thorough
The U.S. stone industry is in a transition from surface quarries to understanding of the regional geology is critical to underground mine
single and multiple level underground stone mines. The factors driving planning. Regional geology includes structural features (faults, folds),
this transition include surface quarries; horizontal stress orientation, and depositional features (pinch-outs,
→ reaching their economic stripping ratio, bentonite beds, calcite or other mineral intrusions). It is assumed that
these items have been quantified during the exploration phase of a
→ encroaching on the mineral reserve boundary where the
project and will not be discussed further.
remaining reserves are below the active pit,
→ dust, noise, and blast vibration concerns as suburban Since most limestone deposits in the Midwest and south are
neighborhoods and development move into formerly rural sufficiently thick to have multiple levels, the selection of the upper back
areas. horizon must be carefully chosen because it sets the sequence of
mining for the limestone bed which may be multiple hundred feet thick.
Ground control is critical to the success of a safe and productive,
The interdependence of the parameters is presented using case
mining operation. The primary focus of the ground control engineer in
histories.
an underground stone mine is the stability of the roof or back,
development and benched pillar stability, stability of the sill pillar The end use (DOT grade aggregate, lime, cement, wet FGB
between vertically adjacent mining levels, and floor stability. scrubber stone for power plants, chemical or agricultural lime, coal
mine "rock dust", or filler) of the limestone drives the selection of the
Roof stability begins with the selection of a stable back horizon
economically mineable horizon. Once the economically mineable
based upon the presence of a thin shale parting, stylolite, or other
horizon is defined the back horizon of the upper level is selected.
discontinuities from which the production shot can easily "peel" away
leaving a stable back stratum. Room width and the decision of Selection of Appropriate Back Horizon
whether to bolt the roof, the bolt length, bolt type, bolt diameter, and The selection of an appropriate back horizon for any level is a
spacing of the support is controlled by the thickness, fracture spacing, balance between;
jointing, and material properties of the back strata. Horizontal stress
controls the header and crosscut azimuth as to avoid driving 1) Limestone material properties if the end use is for crushed stone
perpendicular to the maximum horizontal stress direction. or aggregate,
2) Chemistry (CaCO3, MgO, SiO2) composition of the limestone if
Stable pillar dimensions depend upon the interaction of the; the end use is an industrial application to ensure deleterious
waste material does not come with the production shots,
→ vertical stress resulting from overburden thickness and
3) Geology where a;
multiple level interaction of overlying level(s),
a) thin shale parting or stylolite band is present to provide a
→ mining height during development and the final mining height discontinuity so the production shot will "peel" away from the
after floor shots are taken while benching, back and avoid "back break" and fracturing of the back,
→ presence of faults, folds, or joints passing through the pillar, b) thick bed is present in the immediate back to provide rigidity
and against gravity induced sag and if excess horizontal stress is
→ stone lithology recognizing that the presence of oolitic present, resistance to stress induced fracturing.
bands, shale partings, and bentonite beds create zones of 4) Rock mechanics where the combination of fracture spacing and
weakness that can destabilize an otherwise competent pillar. material strength properties ensure a competent back.
Floor stability is typically not a significant issue for underground The process of back selection is illustrated in a case history of
stone mines because the bearing capacity of the stone exceeds the multiple level development at Mine A. The selection of a back horizon
vertical pressure transferred through the pillar. However, floor heave at Mine A involves the selection of the back horizon for Level 2. Mining
can be a ground control issue where shale partings, moisture sensitive on Level 1 is reaching exhaustion as the workings are approaching
strata, weak stone bands, or horizontal stress is present. Roof stability property boundaries. Level 1 operates at 1,000-feet of overburden
and pillar stability problems can be initiated as the floor heave enables with 60-foot x 60-foot pillars spaced on 100-foot centers. The 39-foot
the pillar and roof to settle. mining height reflects a 25-foot development height and 12-foot to 13-
The ground control issues for underground stone mines are most foot floor shot that bottoms on a shale unit. A 50-foot mining height
clearly presented through a series of case histories. The case was chosen for Level 2 based upon a balance between reserve
histories presented in this paper are a mix of ground failures and recovery and the pillar dimensions required by the combination of the
successful mining. The focus is on the geotechnical data required for overburden depth and the stress interaction between the levels.
underground stone mine ground control for roof, pillar, and floor design An in-mine drilling program identified two potential horizons for
and stability analysis. Level 2 at 28-feet and 31-feet below the Level 1 floor. Both horizons
INTRODUCTION have stylolite partings and would easily separate from a production
shot. The 28-foot horizon, shown in Figure 1, was chosen because
The successful planning of an underground limestone mine is a there were no significant discontinuities in the interburden between it
balance between rock mechanics, geology, chemical qualities and and the Level 1 floor. Rock strength (uniaxial compressive, tensile)
physical properties of individual ledges. For each level, the selection and physical property (elastic modulus, Poisson's ratio, density) was
of back horizons, mining heights, pillar dimensions, header and conducted on the immediate back and main back strata. A summary

1 Copyright © 2016 by SME


SME Annual Meeting
Feb. 21 - 24, 2016, Phoenix, AZ

of the rock testing including the 58% reduction for use in finite element illustrates that the failure develops in the Level 1 pillars and along the
modeling is shown in Table 1. interface between the two limestone beds.

Figure 3. Finite Element Analysis of the 28 foot Sill Pillar between


Levels 1 and 2 of Mine A.
Figure 1. Level 2 Back Horizon - 28 feet Below the Level 1 Floor
The Level 1 pillars illustrate the development of "hour glassing".
Table 1. Summary of Rock Strength Test Results. This is the classic pillar failure mode in limestone where the rock in the
middle of the pillar sloughs rendering the pillar area smaller. Because
the effective pillar area at mid-pillar is smaller the pillar continues
sloughing until the pillar eventually disintegrates leaving the bottom
half as a cone. It should be noted that maintaining stability in Level 1
is not a requirement as access to this Level will not be necessary other
than for the Level 1 - Level 2 decline and ventilation raises. The
greatest concern is the connection of failed/yielded material between
Levels 1 and 2 in the sill pillar. The worst condition occurs when the
Level 1 header directly overlies the Level 2 header.
The conclusion is that the 28-foot header is not feasible from a
rock mechanics perspective although from an operations perspective,
the proposed back horizon provides a clean separation along the back
line. This horizon traceable throughout the reserve as it is found in all
the exploration core holes.
The selection of the back horizon was refined to identify a suitable
The close interval between the Level 1 and the proposed Level 2 horizon with an increased sill pillar thickness. Another stylolite and thin
requires numerical modeling to supplement analytical calculations and shale parting was found approximately 60-feet below the Level 1 floor.
empirical approaches. A two-dimensional finite element model was The results of the finite element analysis are shown in Figure 4. It is
constructed along a profile taken through the center of Level 1. As clear that the 60-foot thick sill pillar is stable and there should not be a
seen in Figure 2, the pillars on Levels 1 and 2 are not columnized. connection or failure between the overlying levels should be
Columnization is infeasible because; anticipated. The Level 1 pillar stability is similar to that encountered in
the 28-foot sill pillar. The Level 2 pillar stability with a 60-foot sill pillar
1. The different mining heights on Level 1 and Level 2 create has deteriorated in comparison with a 28-foot sill pillar. It is likely that
different width-to-height (w/h) ratios and different pillar at 60-feet the Level 2 pillars are not in the stress shadow of the Level 1
behavior, mine workings and the overburden depth has increased by 32-feet.
2. The Level 1 pillars do not rigidly conform to the 100-foot
pillar centers and 60-foot x 60-foot pillar dimensions, and
3. The difference in overburden depth between the Levels
requires Level 2 to have larger pillars.

Figure 4. Finite Element Analysis of a 60 foot Sill Pillar between


Levels 1 and 2 of Mine A.
The Level 2 pillars shown in Figure 3 are 90-feet x 90-feet and
spaced on 130-foot centers. At this point changes to improve Level 2
pillar stability will focus on reducing the depth of the floor recovery.
This increases the w/h ratio and improves pillar stability.

Figure 2. Finite Element Mesh for Analysis of 28 foot Sill Pillar PILLAR DESIGN AND MINING HEIGHT
between Levels 1 and 2.
Pillar design and mining height are related in that the mining
The result of the finite element analysis of the 28-foot sill pillar is height controls the pillar width. Pillars are required to support the
shown in Figure 3. The horizontal line in the bottom 1/3 of the Level 1 overburden based upon tributary area loading. Different than coal
pillars is the interface between two limestone beds. In Level 2, the mines, limestone pillars are designed for long-term stability. Although
immediate back is bolted with 6-foot long fully grouted resin bolts the failure of 4-foot to 10-foot coal pillars can initiate surface
installed on 6-foot centers while Level 1 is not bolted. Figure 3 clearly subsidence and structural damage, the failure of a 60-foot to 70-foot
high limestone pillar has catastrophic consequences. Therefore, a

2 Copyright © 2016 by SME


SME Annual Meeting
Feb. 21 - 24, 2016, Phoenix, AZ

pillar safety factor of 1.80 is a widely accepted value for limestone achieve higher recovery in mines where high horizontal stress or
mine (Esterhuizen, et al., 2008). where floor bearing capacity is a concern. Rectangular pillars enable
greater extraction parallel to the major horizontal stress direction in
Typical of all pillars irrespective of the mineral, pillar stability is a mines where there is a preferred horizontal stress orientation and
function of the width-to-height (w/h) ratio. Pillars with a w/h ratio of where the horizontal stress is an integer multiple of the vertical stress.
less than 0.8 (ibid) begin to fail by "hour glassing" where the center of The crosscut width is perpendicular to the major horizontal stress
the pillar spalls creating a concave geometry as shown in Figure 5 orientation and is narrow relative to the headers.
(Esterhuizen, et al., 2008a). Spalling of rock slabs is initiated in the
middle third of the pillar where there is no confinement. Movement in Figure 7 provides an example of the preferred orientation of
the upper and lower third of the pillar is confined by the frictional headers and crosscuts when the horizontal stress orientation is known.
resistance along the interface between the pillar and the back and For Mine B, the principal horizontal orientation was measured as
floor. The spalling reduces the pillar area in the middle third of the N77oE (Kuhnhein and Ramer, 2004). Mine B had experienced back
pillar which in turn increases the stress and propagates continued falls in the crosscuts that are oriented N26oW which is 13o from being
slabbing or spalling of rock. perpendicular to the major principal horizontal stress orientation. Since
a shift in the mine orientation was infeasible, Mine B reduced the
crosscut width in the unfavorable orientation from 40-feet to 30-feet
and in increased the header width in the favorable orientation from 40-
feet to 50-feet. The intersections were changed from four-way to
three-way to reduce the opportunity for back instability to propagate
along the crosscuts.

Figure 5. Classic "Hour Glass" Pillar Failure Mode (after Esterhuizen


et al., 2008)
Ultimately the pillar fails by disintegrating and the overburden load Figure 7. Changes in Opening Width and Intersection Geometry to
is transferred to adjacent pillars. If the adjacent pillars are of similar Address Horizontal Stress - Mine B
size, the pillar failure is propagated until a barrier pillar or solid area of
sufficient size to bear the overburden stress is encountered. Although Weak floor is an infrequent condition in underground limestone
the stress transfer may occur slowly, because limestone is brittle, the mines. However, in Mine C the immediate floor in Levels 2 and 3 is
failure of similarly sized pillars can be rapid and violent. Examples of weak. The combination of pillar geometry, overburden stress, and the
massive pillar collapse include a Georgia marble mine (Phillipson, regional fracture orientation result in floor heave in preferred
2012) and more recently at a Pennsylvania limestone mine (Pittsburgh orientations. The floor heave was not well controlled in Level 2 and
Post Gazette, 2015) where violent pillar failure occurred over a short caused pillar sloughing as the base of the pillar moved into the header.
time. It provides an excellent starting point for further analysis. When floor heave started in Level 3, the pillar geometry was changed
to rectangular pillars oriented perpendicular to the preferred direction
The NIOSH S-Pillar (Esterhuizen, et al., 2008) program is a of floor heave as shown in Figure 8. The crosscuts were staggered so
widely accepted empirically based approach to limestone pillar design. that were floor heave to initiate, it would terminate against the long
Figure 6 illustrates the 130-foot pillar centers and 90-foot x 90-foot dimension of the rectangular pillars. The approach to combating floor
pillars cited in the Mine A case history. It is important to note that heave was successful and is identical to that used in Mine B to
although the safety factor meets the 1.80 criterion for a 50-foot mining address horizontal stress initiated back falls.
height at 1,000-feet of overburden and the w/h ratio > 0.8, the S-Pillar
program is intended to analyze single level pillar stability.

Figure 8. Rectangular Pillars Used to Stop Floor Heave.


Figure 6. Pillar Stability Calculation for Level 2 at Mine A. MULTIPLE LEVEL PLANNING
It is widely recognized that rectangular pillars are stronger than Many limestone formations are of sufficient thickness to develop
square pillars of the same width. Rectangular pillars can be used to multiple levels. All levels within a multiple level mine should be planned
3 Copyright © 2016 by SME
SME Annual Meeting
Feb. 21 - 24, 2016, Phoenix, AZ

prior to the development of the upper level. The location of the upper Mine D is a three level mine terminated at the base of a 50-foot
level within the geologic column and mining height control and thick shale interval. Future levels are planned but at this time only the
constrain the options for underlying levels. Stone quality and physical initial three are of concern. The maximum overburden above Level 1
characteristics are the initial focus as the engineer wants to avoid is relatively light at 196-feet. The mine was planned based upon the
having a high calcium or comparably valuable ledge left in the pillars on Level 3. The overlying Levels are columnized because of the
interburden between two levels. thin sill pillars as shown in the cross section of Figure 11.
Geology is important to planning a single level mine and critical to
multiple level mine planning. Specifically, joint and fracture orientation
and the presence of calcite veins and or forms of mineral intrusion
should be determined from a surface exposure or active underground
level. The joint and fracture orientations should be measured using a
Brunton or Clar compass and corrected for the local magnetic
declination. A rosette diagram, shown in Figure 9 illustrates the
preferred joint and fracture orientation.
Limestone is typically strong so failures will occur along joint,
fractures, or other discontinuities. The objective is to orient the upper
level and those below it so that the headers and crosscuts intersect
joints at an angle, minimizing the exposure of these structural defects
in the mine openings. The intent is to have the joints pass through and
not parallel to the mine openings so they are supported by the pillars.

Figure 11. Case History of Multiple Level Mine Planning - Mine D.


Finite element analysis was used to quantify pillar stability within
each of the Levels and the sill pillars between vertically adjacent
Levels. The approach is similar to that used for Mine A. The layout of
the finite element mesh is shown in Figure 12. Each color denotes a
different limestone bed or zone with different material properties.

Figure 9. Preferred Joint Orientation as Measured in Surface Quarry


Adjacent to Mine D.
Once the economically valuable ledges are identified, the focus is
on the selection of the back horizon, final mining height, and by default
the floor horizon for the upper level. The correlation between the back
horizon (painted orange) as chosen in the core and as it exists in the
field is shown in Figure 10. The next decision is whether to columnize Figure 12. Finite Element Mesh Layout for the Three Levels of Mine
pillars on vertically adjacent levels. The sophistication of multiple level D.
planning is directly related to the interburden thickness and rock
strength. Columnization of pillars becomes less of a concern when the The safety factor shading is shown in Figure 13. It is clear that
interburden between vertically adjacent levels exceeds 100-feet or is the sill pillars between the Levels are competent. The Level 1 pillars
competent as in the example from Mine A. However, the pillar stability are anticipated to spall at mid-pillar with full extraction and the total
on each level should be quantified by hand calculation or by the well- mining height of 60-foot is exposed after the floor is taken. A similar
accepted NIOSH S-Pillar program. conclusion is reached for Level 2. Here the pillar ribs are more stable
due to stronger limestone and less spalling should occur. However, in
Level 3 the combination of multiple Level interaction and higher
overburden creates a situation where the ribs spall heavily. The safety
factor of the pillar core is marginally stable. The solution is to reduce
the floor recovery in Level 3 from a 60-foot mining height to 40-feet.
This will leave a higher w/h ratio and consequently stronger pillars.
The results can be seen in Figure 14 where the Level 3 pillar stability
resembles that of the overlying Levels.

Figure 10. Correlation Between Mine D Back Horizon in Core and in


the Field.

4 Copyright © 2016 by SME


SME Annual Meeting
Feb. 21 - 24, 2016, Phoenix, AZ

Figure 13. Safety Factor Results for the three Levels of Mine D.

Figure 14. Finite Element Analysis With a 40-Foot Mining Height on


Level 3 - Mine D.
REFERENCES
1. Esterhuizen, G.S., Dolinar, D., and Ellenberger, J., (2008), "Pillar
Strength and Design Methodology for Stone Mines", 27th
International Conference on Ground Control in Mining, West
Virginia University, Morgantown, WV., pp. 241- 251.
2. Esterhuizen, G.S., Dolinar, D., and Ellenberger, J., (2008a),
"Assessment of Stable and Failed Pillars in Underground
Limestone Mines", Mining Engineering Nov; 60(11), pp: 43-48.
3. Ibid.
4. Phillipson, S.E., (2012), "Massive Pillar Collapse: A Room-and-
Pillar Marble Mine Case Study", 31st International Conference on
Ground Control in Mining, West Virginia University, Morgantown,
WV.,
5. Pittsburgh Post Gazette, "Big Blast of Air Injures Three Limestone
Miners - Roof Collapses, Causes Air Blast That Knocked Out
Miners", April 29, 2015
6. Kuhnhein, G. and Ramer R. (2004), "The Influence of Horizontal
Stress on Pillar Design and Mine Layout at Two Underground
Limestone Mines", International Conference on Ground Control in
Mining, West Virginia University, Morgantown, pp. 311-317.

5 Copyright © 2016 by SME

Potrebbero piacerti anche