Bridgeport, Conneticut, collapsed during construction. . This collapse spurred a large scale, eight day, rescue attempt and ultimately left 28 workers dead.(Moncarz, 1992) This 16 story building, 13 apartment levels over 3 parking levels, was being CASE STUDY ON POSSIBLE constructed using the lift-slab method. CONSTRUCTION FAILURES THAT CAUSED THEORY 1: The lift-slab method consists of Instability of the wedges THE COLLAPSE casting post-tensioned floor slabs, supporting the 12th floor and roof package one on-top of another, at ground level -Thornton Tomasetti Engineers and then hydraulically jacking each Thornton-Tomasetti Engineers' concluded the epicenter of the collapse was a core column, 3E, of level into place. At approximately the west building. Wedges supporting the 12th floor and roof package at the column were unstable and 1:30pm on April 23rd a loud bang was started the collapse. They state in their "Collapse Scenario" that a wedge supporting the 12/R package rolled heard and within the next 2-10 out leaving the shearhead at this level supported by a single wedge. The horizontal load from the jack used to seconds the entire building crashed to plumb the building caused the remaining wedge to roll slightly as evidenced by rounding and bending in the the ground. The collapse launched west weld block of the shearhead. Additional movement of the slabs may have caused the remaining wedge to several investigations but was quickly roll completely out. settled out of court ending all THEORY 2: investigations and leaving the exact Jack rod and lifting nut slipped out due to a deformation of an overloaded steel angle cause of the collapse unknown. welded to a shear head arm channel Although the exact cause of the -National Bureau of Standards (NBS collapse remains unknown, five viable The NBS concluded in their investigation that the failure began at the building's most heavily theories have been proposed in the loaded column, E4.8 or the adjacent column, E3.8, as a result of a lifting assembly failure. At each column the years since the collapse by various shearhead reinforces the concrete slab, transfers vertical load from the slab into the column, and provides a experts on building failures. place of attachment for the lifting assembly. Steel channels are cast in the slab, allowing room for the lifting angle. Lifting rods, raised by hydraulic jacks above them, are passed through holes in the lifting angle and fastened with lifting nuts. (Scribner, 1988) THEORY 3: Improper design of post-tensioning tendons -Schupack Suarez Engineers, Inc The Schupack Suarez Engineers examined the unusual layout of the post-tensioning tendons in the west building. The east building's tendons were run in a typical two-way banded layout, uniform tendons running North - South carry the slab load to the East- West Column line, where the E-W banded tendons then "pick up" the load and transfer it to the columns. However, at column 4.8E in the west building, the E-W tendons split around the column line. The absence of tendons in Line E due to the split at the column added increased load into the structure. The design details also did not include the location of the shear walls or the openings for the walls at Columns 11A, 8A, and 2H. Finite-element analysis determined that the tensile stresses along Column Line E, east of Column 4.8E, exceeded the cracking strength of the concrete. By this reasoning once a crack was initiated it would spread immediately to Column 4.8E. The finite-element analysis also showed that even under ideal lifting circumstances column 2H would have had unsuitably high compressive and punching shear stresses. THEORY 4: Substandard welds and questionable weld details -Occupational Safety and Health Administration (OSHA) OSHA stated that two weld design details were questionable. These welds were the 1/2 in. single- bevel-groove weld between the arm channel and the lifting angle in the shearheads, and the one-sided square-groove weld connecting the header bar and header channel at the shearhead. Both welds were of unknown and unspecified penetration depth and therefore had an unpredictable strength. The single-bevel- groove weld could also have been further weakened from flush grinding. The one-sided square-groove welds are even more questionable due to the fact that they were not among the American Welding Society prequalified joints. THEORY 5: Global instability caused by lateral displacement -Failure Analysis Associates, Inc. (FaAA) FaAA consultants focused on the response of lateral loading and overall torsional instability. The shearhead connection is rotationally stiff when the concrete slab is temporarily resting on the wedges and when it is fully welded in its final position it becomes a rigid connection. However, when the slab is lifted off the wedge it can rotate freely. In the absence of lateral loading the building would be completely stable. In the presence of lateral loading or displacement, such as that from the horizontal jacking just after lunch, the slab could be lifted off a wedge and the building would become laterally flexible. FaAA used 3D computer modeling (ANSYS) and nonlinear stability modeling to investigate this possibility. Upon analysis of their modeling FaAA concluded that lateral instability was the cause of collapse for both the west and east buildings.
A Short Guide to the Types and Details of Constructing a Suspension Bridge - Including Various Arrangements of Suspension Spans, Methods of Vertical Stiffening and Wire Cables Versus Eyebar Chains