Stations Distance in (m) RL of Ground RL of formation depth

25 1000 51 52 1
26 1040 50.9 51.8 0.9

27 1080 50.5 51.6 1.1 Calculation of Earth Work


28 1120 50.8 51.4 0.6
29 1160 50.6 51.2 0.6
30 1200 50.7 51 0.3
31 1240 51.2 50.8 -0.4
32 1280 51.4 50.6 -0.8
33 1320 51.3 50.4 -0.9
34 1360 51 50.2 -0.8
35 1400 50.6 50 -0.6

Stations Distance in (m) depth mean depth(d) central area area of sides total area distance b/w Quantity =(bd+sd²)*L
in m (B*d) in m (s*d²) in m² ( Bd+sd²) station (L) banking m³ cutting m³
25 1000 1
26 1040 0.9 0.95 9.5 1.81 11.31 40 452.20
27 1080 1.1 1 10 2.00 12.00 40 480.00
28 1120 0.6 0.85 8.5 1.44 9.94 40 397.80
29 1160 0.6 0.6 6 0.72 6.72 40 268.80
30 1200 0.3 0.45 4.5 0.40 4.90 40 196.20
1217 0 0.15 1.5 0.04 1.54 17 26.26
31 1240 -0.4 -0.2 2 0.06 2.06 23 47.38
32 1280 -0.8 -0.6 6 0.54 6.54 40 261.6
33 1320 -0.9 -0.85 8.5 1.08 9.58 40 383.35
34 1360 -0.8 -0.85 8.5 1.08 9.58 40 383.35
35 1400 -0.6 -0.7 7 0.74 7.74 40 309.4
TOTAL= 1821.26 1385.08