SUPPLY & SERVICES SCOPE

SL. NO. DESCRIPTION UOM 15 MW PROJECT, 15 MW PROJECT, MK


SANKESHWAR HUBLI SUBSTATION,
SUBSTATION, HUKKERI KITTUR TALUKA
TALUKA

1 Land Development Works completely as per KPTCL Standards


1.1 Levelling by cutting and filling by mechanical means including pre-watering of soil, excavation of Cu.m. 48 48
soils, depositing the soils in filling areas , spreading soils, breaking clods, sectioning and
consolidation with three wheel 8 to 10 MT static Road Roller @ OMC to meet requirement as per
standard specification , including Murrum soil of 300mm shall be used for filling and all hire and
operational charges of T&P and seigniorage charges, complete for finished item of work as per
the directions of Engineer In Charge and KPTCL (Payment will be made based on level for finished
item of work).

1.2 Storm Water Drainage for Line Bay Nos. 1 1


2 Foundations & Civil Works (including all material supply):
Construction of Civil Foundations including Marking, Excavation, Refilling, including Sand,
aggregate, Cement, Steel, Shuttering Material with all lifts and leads as per KPTCL Drawing and
Specifications and as per the directions of Engineer In Charge & KPTCL

2.1 Foundation for 33 kV Tower Nos. 2 2

2.2 Foundation for 33kV Isolator Nos. 2 2

2.3 Foundation for 33 kV CPL - 1 phase Nos. 12 12


SUPPLY & SERVICES SCOPE

SL. NO. DESCRIPTION UOM 15 MW PROJECT, 15 MW PROJECT, MK


SANKESHWAR HUBLI SUBSTATION,
SUBSTATION, HUKKERI KITTUR TALUKA
TALUKA

2.4 Foundation for 33 kV Bus Post Insulator - 1 phase Nos. 3 3

2.5 Foundation for 66kV Circuit Breaker - 3 phase Nos. 1 1

2.6 Cable Trench with Covers and Sand Filling. Mtrs. 30 30

2.7 Foundation for ABT Twin Metering Box Nos. 1 1

2.8 Foundation for Bay Marshalling Kiosk Nos. 1 1

2.9 Kerb Wall for the Switch Yard Area Mtrs. 30 30

2.10 Providing anti weeding treatment including supply of HDPE Sheet, chemical and stone metal as Sq.m 108 108
required and spreading stone metal (for 100 mm depth) as required as per KPTCL standards

3 Supply, Unloading, Storing, shifting, Erection, Testing & commissioning of GI Structures & Out
Door Equipment as per the Drawings & Specifications and as directed by Engineer In Charge &
KPTCL:

3.1 GI Structure (Equipment Structure, Gantry) MT 5.7 5.7

3.2 GI Bolts & Nuts including foundation bolts & nuts MT 0.6 0.6
SUPPLY & SERVICES SCOPE

SL. NO. DESCRIPTION UOM 15 MW PROJECT, 15 MW PROJECT, MK


SANKESHWAR HUBLI SUBSTATION,
SUBSTATION, HUKKERI KITTUR TALUKA
TALUKA

3.3 33 kV Isolator - 3 Phase (With & Without E/S - including Post Insulators ) complete with all Nos. 2 2
accessories
3.4 33 kV, 3 Phase Circuit Breaker complete with all accessories Nos. 1 1

3.5 33 KV, 1 Ph Protection CT complete with all accessories Nos. 3 3

3.6 33 KV, 1 Ph Metering CT complete with all accessories Nos. 3 3

3.7 33 KV, 1 Ph Metering PT complete with all accessories Nos. 3 3

3.8 30kV, 10kA Lightning Arrester complete with all accessories Nos. 3 3

3.9 33 kV Bus Post insulators Nos. 3 3

3.10 CT/PT Marshalling Box Nos. 1 1

3.11 Lighting DB- Out Door Nos. 1 1

3.12 Lighting Fixtures (125W LED) Nos. 5 5

3.13 ACSR Coyote/Drake Conductor-Stringing/Jumpering Mtrs 60 60

3.14 Bay Marshalling Kiosk Nos. 1 1


SUPPLY & SERVICES SCOPE

SL. NO. DESCRIPTION UOM 15 MW PROJECT, 15 MW PROJECT, MK


SANKESHWAR HUBLI SUBSTATION,
SUBSTATION, HUKKERI KITTUR TALUKA
TALUKA

3.15 100 mm dia PVC Conduit Mtrs 100 100

3.16 GI Cable Tray - 300mm width (Ladder/perforated Tray) including support angles & channels Mtrs 30 30

3.17 T - Clamp for ACSR conductor Nos. 15 15

3.18 Terminal Connectors for Switchyard equipments Nos 50 50

3.19 7/3.15 HTGS Earth Wire Metre 100 100

3.20 Tension Clamp for 7/3.15 HTGS Wire Nos 6 6

3.21 Lightning Spike for LP - 2 mtr Nos. 1 1

4 Supply, Unloading, Storing, shifting, Laying & Termination Testing & commissioning of the Cables
(including supply and services cable glands,lugs & gala sleeves) as per the drawings, schedules,
specifications and as per the directions of engineer in charge and KPTCL.

4.1 Copper Control cables of size 4C x 6 Sq mm Metre 500 500

4.2 Copper Control cables of size 10C x 2.5 Sq mm Metre 500 500
SUPPLY & SERVICES SCOPE

SL. NO. DESCRIPTION UOM 15 MW PROJECT, 15 MW PROJECT, MK


SANKESHWAR HUBLI SUBSTATION,
SUBSTATION, HUKKERI KITTUR TALUKA
TALUKA

4.3 Copper Control cables of size 19C x 2.5 Sq mm Metre 1000 1000

4.4 Copper Power Cable of size 3C x 2.5 Sq mm Metre 1000 1000

5 Supply, Unloading, Storing, shifting, Erection, Testing & commissioning of Indoor Equipment as
per the Drawings & Specifications and as directed by Engineer In Charge & KPTCL:

5.1 33 kV Feeder C & R Panel along with LIU and Patch Chords Nos. 1 1

5.2 110V, 100 AH Battery system Nos. 1 1

5.3 110 V DC Battery Charger Nos. 1 1

5.4 Hard wiring & interfacing of CRP with existing RTU through RS485 Communication Cables & Job 1 1
Copper Control Cables & suitable terminations.

6 Supply, Unloading, Storage, Shifting, Erection / Laying of Earth Mat including excavation, welding
with required , refilling etc, including all material completely as per KPTCL Specifications as per
the directions of Engineer In Charge & KPTCL. (Subject to change as per design submitted by
KPTCL)

6.1 75x8mm MS Earth Flat MT 1 1


SUPPLY & SERVICES SCOPE

SL. NO. DESCRIPTION UOM 15 MW PROJECT, 15 MW PROJECT, MK


SANKESHWAR HUBLI SUBSTATION,
SUBSTATION, HUKKERI KITTUR TALUKA
TALUKA

6.2 75x8mm GI Earth Flat for Equipment Earthing MT 0.75 0.75

6.3 50x6mm GI Earth Flat MT 0.5 0.5

6.4 100MM Dia, 9.5mm Thk 2.75m Long CI Pipe Earth pit, including RCC Collars-complete & complete Nos. 12 12
backfill graphite based chemical compound & necessary accessories

6.5 40mm x 8 mm, 300 mm long Earth bonds dipped galvanized copper braided Nos. 8 8
SUPPLY & SERVICES SCOPE

SL. NO. DESCRIPTION UOM 15 MW PROJECT, 15 MW PROJECT, MK


SANKESHWAR HUBLI SUBSTATION,
SUBSTATION, HUKKERI KITTUR TALUKA
TALUKA

6.6 Waterering arrangement for earthing system including pipe, taps,bends etc Job 1 1

7 BUS EXTENSION IN BAY END SWITCHYARD

7.1 Land Development Works completely as per KPTCL Standards

7.1.1 Levelling by cutting and filling by mechanical means including pre-watering of soil, excavation of Cu.m. 18 18
soils, depositing the soils in filling areas , spreading soils, breaking clods, sectioning and
consolidation with three wheel 8 to 10 MT static Road Roller @ OMC to meet requirement as per
standard specification , including Murrum soil of 300mm shall be used for filling and all hire and
operational charges of T&P and seigniorage charges, complete for finished item of work as per
the directions of Engineer In Charge and KPTCL (Payment will be made based on level for finished
item of work).

7.2 Foundations & Civil Works (including all material supply):


Construction of Civil Foundations including Marking, Excavation, Refilling, including Sand,
aggregate, Cement, Steel, Shuttering Material with all lifts and leads as per KPTCL Drawing and
Specifications and as per the directions of Engineer In Charge & KPTCL

7.2.1 Foundation for 66 kV Towers. Nos. 2 2


SUPPLY & SERVICES SCOPE

SL. NO. DESCRIPTION UOM 15 MW PROJECT, 15 MW PROJECT, MK


SANKESHWAR HUBLI SUBSTATION,
SUBSTATION, HUKKERI KITTUR TALUKA
TALUKA

7.2.2 Kerb Wall for the Switch Yard Area Mtrs. 10 10

7.2.3 Providing anti weeding treatment including supply of HDPE Sheet, chemical and stone metal as Sq.m 30 30
required and spreading stone metal (for 100 mm depth) as required as per KPTCL standards

7.3 Supply, Unloading, Storing, shifting, Erection, Testing & commissioning of GI Structures & Out
Door Equipment as per the Drawings & Specifications and as directed by Engineer In Charge &
KPTCL:

7.3.1 GI Structure (Equipment Structure, Gantry) MT 1 1

7.3.2 GI Bolts & Nuts including foundation bolts & nuts MT 0.2 0.2

7.3.3 ACSR Coyote/Drake Conductor - forming Bus & Equipment Jumpers Mtrs 40 40

7.3.4 Insulator string (Tension type) with necessary accessories and hardwares Nos. 6 6

7.3.5 Insulator string (Suspension type) with necessary accessories and hardwares Nos. 3 3
SUPPLY & SERVICES SCOPE

SL. NO. DESCRIPTION UOM 15 MW PROJECT, 15 MW PROJECT, MK


SANKESHWAR HUBLI SUBSTATION,
SUBSTATION, HUKKERI KITTUR TALUKA
TALUKA

7.3.6 Jumpering for bus extension with required accessories Nos. 3 3

7.3.7 7/3.15 HTGS Earth Wire Metre 50 50

7.3.8 Tension Clamp for 7/3.15 HTGS Wire Nos 50 50

7.3.9 Lighting Fixtures - 125W LED (including supply of bent pipe) & complete accessories including Nos. 2 2
point wiring

7.4 Supply, Unloading, Storage, Shifting, Erection / Laying of Earth Mat including excavation, welding
with required , refilling etc, including all material completely as per KPTCL Specifications as per
the directions of Engineer In Charge & KPTCL. (Subject to change as per design submitted by
KPTCL)

7.4.1 75x8mm MS Earth Flat MT 0.3 0.3

7.4.2 75x8mm GI Earth Flat for Equipment Earthing MT 0.2 0.2

8 MCR EXTENSION IN BAY END SWITCHYARD

8.1 Excavation m3 0 0
SUPPLY & SERVICES SCOPE

SL. NO. DESCRIPTION UOM 15 MW PROJECT, 15 MW PROJECT, MK


SANKESHWAR HUBLI SUBSTATION,
SUBSTATION, HUKKERI KITTUR TALUKA
TALUKA

8.2 Backfill m3 0 0

8.3 RCC m3 0 0

8.4 PCC m3 0 0

8.5 Brickwork m3 0 0

8.6 Reinforcement kg 0 0

8.7 Channels kg 0 0

8.8 Angles kg 0 0

8.9 Chequered Plate kg 0 0

8.10 Doors & Windows m2 0 0


SUPPLY & SERVICES SCOPE

SL. NO. DESCRIPTION UOM 15 MW PROJECT, 15 MW PROJECT, MK


SANKESHWAR HUBLI SUBSTATION,
SUBSTATION, HUKKERI KITTUR TALUKA
TALUKA

8.11 Plaster m2 0 0

9 ABT Meters in line with the KPTCL specifications, relevant IS & approved KPTCL Vendor & Model Nos. 2 2
No. and as per convienient testing provision available with DISCOM MRT Team

10 Supply, Unloading, Storage, Shifting, Erection of ABT Meter Box & ABT Meters, Mounting Job 1 1
structure, GI Pipes between Meter Box and MCTs & MPTs, Bending & Threading at Site, Making
Holes to BOX and JBS professionally with Hole Saw Cutting Machines, Fixing Pipes with Check Nuts
on both the sides of Panel Wall / JB Wall, Laying of Copper Wire/Cable from CT/PT to ABT Meter
Box - complete in all respects as per the directions of KPTCL & DISCOM and Under the supervision
of KPTCL / DISCOM officials. ABT meter box is to be provided with Shed/Canopy as per KPTCL
requirement.

Main Meter & Check Meter to be installed & tested

11 Testing & Commissioning

11.1 Testing & Commissioning: Testing & Commissioning of all equipment, assisting to Equipment Job 1 1
Vendors during gas filling of CB, and extending services to KPTCL MRT Team & DISCOM M&P Team
during testing & commissioning.
SUPPLY & SERVICES SCOPE

SL. NO. DESCRIPTION UOM 15 MW PROJECT, 15 MW PROJECT, MK


SANKESHWAR HUBLI SUBSTATION,
SUBSTATION, HUKKERI KITTUR TALUKA
TALUKA

12 Preparation & Submission of Electrical & Civil drawings, documents & calculations for information Job 1 1
& approval of KPTCL. Liasioning and Coordination with KPTCL/DiSCOM for approval of drawings.

1. Bay earthing drawing


2. Cable trench layout
3. Lightning Protection layout
4. Civil Layout drawing
5. Electrical layouts
6. Power and Control cable schedule
7. Control room layout
8. Illumination layout
9. Any other drawing not mentioned above but required for execution

13 Liasioning with KPTCL/ DISCOM for Site Inspections, Testing and all other statutory requirements. Job 1 1
SUPPLY & SERVICES SCOPE

SL. NO. DESCRIPTION UOM 15 MW PROJECT, 15 MW PROJECT, MK


SANKESHWAR HUBLI SUBSTATION,
SUBSTATION, HUKKERI KITTUR TALUKA
TALUKA

14 FIELD APPROVALS (BAY END) Job 1 1

1. Inspection of all bay end equipments at works as well as at site


2. Metering CT,PT and ABT meter testing at OEM works, Calibration at KPTCL approved testing lab
and site testing including precomissiong to commissioning upto sealing.
3. Work completion certification (If applicable as per Transco)

15 Successful erection, testing & commissioning of complete Plant and handover. Job 1 1
15 MW PROJECT, REMARKS SUPPLY /FREE SERVICE unit rate unit rate Total Total MK Total
GULEDGUDDA ISSUE Supply Erection Sankeshwa Hubli Guledgudd
SUBSTATION, r a
GULEDGUDDA
TALUKA

- - -
48 __ Service - - -

1 Service - - -

- - -

2 Service - - -

2 Service - - -

12 Service - - -
15 MW PROJECT, REMARKS SUPPLY /FREE SERVICE unit rate unit rate Total Total MK Total
GULEDGUDDA ISSUE Supply Erection Sankeshwa Hubli Guledgudd
SUBSTATION, r a
GULEDGUDDA
TALUKA

3 Service - - -

1 Service - - -

30 Service - - -

1 Service - - -

1 Service - - -

30 Service - - -

108 Service - - -

- - -

5.7 Supply Service - - -

0.6 Supply Service - - -


15 MW PROJECT, REMARKS SUPPLY /FREE SERVICE unit rate unit rate Total Total MK Total
GULEDGUDDA ISSUE Supply Erection Sankeshwa Hubli Guledgudd
SUBSTATION, r a
GULEDGUDDA
TALUKA

2 Free Issue Service - - -

1 Free Issue Service - - -

3 Free Issue Service - - -

3 Free Issue Service - - -

3 Free Issue Service - - -

3 Free Issue Service - - -

3 Free Issue Service - - -

1 Supply Service - - -

1 Supply Service - - -

5 Supply Service - - -

60 Conductor shall be as per Supply Service - - -


existing system

1 Supply Service - - -
15 MW PROJECT, REMARKS SUPPLY /FREE SERVICE unit rate unit rate Total Total MK Total
GULEDGUDDA ISSUE Supply Erection Sankeshwa Hubli Guledgudd
SUBSTATION, r a
GULEDGUDDA
TALUKA

100 Supply Service - - -

40 Supply Service - - -

15 Supply Service - - -

50 Supply Service - - -

100 Supply Service - - -

6 Supply Service - - -

1 Supply Service - - -

- - -

500 Cable Qty shall be as per Supply Service - - -


Actual Marking at site

500 Cable Qty shall be as per Supply Service - - -


Actual Marking at site
15 MW PROJECT, REMARKS SUPPLY /FREE SERVICE unit rate unit rate Total Total MK Total
GULEDGUDDA ISSUE Supply Erection Sankeshwa Hubli Guledgudd
SUBSTATION, r a
GULEDGUDDA
TALUKA

1000 Cable Qty shall be as per Supply Service - - -


Actual Marking at site

1000 Cable Qty shall be as per Supply Service - - -


Actual Marking at site
- - -

1 Free Issue Service - - -

1 Free Issue Service - - -

1 Free Issue Service - - -

1 __ Service - - -

- - -

1 Earthing Size & Qty shall be Supply Service - - -


as per KPTCL R&D Team
Design submitted.
15 MW PROJECT, REMARKS SUPPLY /FREE SERVICE unit rate unit rate Total Total MK Total
GULEDGUDDA ISSUE Supply Erection Sankeshwa Hubli Guledgudd
SUBSTATION, r a
GULEDGUDDA
TALUKA Earthing Size & Qty shall be
as per KPTCL R&D Team
Design submitted.

0.75 Supply Service - - -

0.5 Supply Service - - -

12 Supply Service - - -

8 Supply Service - - -
15 MW PROJECT, REMARKS SUPPLY /FREE SERVICE unit rate unit rate Total Total MK Total
GULEDGUDDA ISSUE Supply Erection Sankeshwa Hubli Guledgudd
SUBSTATION, r a
GULEDGUDDA
TALUKA

1 Supply Service - - -

- - -

- - -

18 __ Service - - -

- - -

2 Service - - -
15 MW PROJECT, REMARKS SUPPLY /FREE SERVICE unit rate unit rate Total Total MK Total
GULEDGUDDA ISSUE Supply Erection Sankeshwa Hubli Guledgudd
SUBSTATION, r a
GULEDGUDDA
TALUKA

10 Service - - -

30 Service - - -

- - -

1 Supply Service - - -

0.2 Supply Service - - -

40 Conductor shall be as per Supply Service - - -


existing system

6 Supply Service - - -

3 Supply Service - - -
15 MW PROJECT, REMARKS SUPPLY /FREE SERVICE unit rate unit rate Total Total MK Total
GULEDGUDDA ISSUE Supply Erection Sankeshwa Hubli Guledgudd
SUBSTATION, r a
GULEDGUDDA
TALUKA

3 Supply Service - - -

50 Supply Service - - -

50 Supply Service - - -

2 Supply Service - - -

- - -

0.3 Supply Service - - -

0.2 Supply Service - - -

- - -

20 __ Service - - -
15 MW PROJECT, REMARKS SUPPLY /FREE SERVICE unit rate unit rate Total Total MK Total
GULEDGUDDA ISSUE Supply Erection Sankeshwa Hubli Guledgudd
SUBSTATION, r a
GULEDGUDDA
TALUKA

17 __ Service - - -

14 Service - - -

3.1 Service - - -

4.5 Service - - -

1500 Service - - -

65 Service - - -

190 Service - - -

300 Service - - -

7 Service - - -
15 MW PROJECT, REMARKS SUPPLY /FREE SERVICE unit rate unit rate Total Total MK Total
GULEDGUDDA ISSUE Supply Erection Sankeshwa Hubli Guledgudd
SUBSTATION, r a
GULEDGUDDA
TALUKA

125 Service - - -

2 Supply Service - - -

1 Supply Service - - -

- - -

1 __ Service - - -
15 MW PROJECT, REMARKS SUPPLY /FREE SERVICE unit rate unit rate Total Total MK Total
GULEDGUDDA ISSUE Supply Erection Sankeshwa Hubli Guledgudd
SUBSTATION, r a
GULEDGUDDA
TALUKA

1 __ Service - - -

1 __ Service - - -
15 MW PROJECT, REMARKS SUPPLY /FREE SERVICE unit rate unit rate Total Total MK Total
GULEDGUDDA ISSUE Supply Erection Sankeshwa Hubli Guledgudd
SUBSTATION, r a
GULEDGUDDA
TALUKA

1 __ Service - - -

1 __ Service - - -

- - -