Requires Action
Travel 3Hrs
Manhours allocated 5Hrs
Shop Visit 1Hrs
Previous Current
P.O. Item Tag P.O Contractual Ras
Qty Description Shipping Shipping
No. No. Date Date
Date Date
Overall Status
% Complete
Engineering 100%
Materials 0%
Fabrication 0%
Shipping 0%
Summary / Observations:
The main purpose of the visit was to see how progress was going and get a better understanding how many
multiple shops they have to deal with in order to source the materials.
An updated schedule was provided since there was 4 emails reflecting delivery dates. The only action that
came out of this meeting is that Galperti was going to send us the activities per various manufacturers in order
for us to monitor the progress. Later updates will be provided since they just started buying the parts. It was
also determined that weekly visits would be required starting this month.
Engineering: None
Shop Expeditor’s Assessment: I did not get a good feeling that the schedule that was provided was going to
met.
Attachments:
1. Schedule