Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
2, May 2014
potentially successful1: Bozen [8], or in Turning Chaos into Success [9] user
1) Self-organization and personal individual motivation are involvement is essential agile approach.Understanding what
important, as well as interaction and co-operation customers really want requires their constant involvement in
2) Working solution, visible output the project. And agile assume changes in the customer
3) Customer Collaboration requirements within the project life cycle.
4) Responding to changes
B. Empowered Team to Manage from down –to–up
Meaning of these points is a conclusion, that the agile
approach is a working solution, through the management By Kelly Watters, the project team must be empowered to
strategy context (vision, goals, funding), a release context make decisions in order to ensure that it is their responsibility
(estimation, back-log), an iteration and daily plans (review, to deliver the product and that they have complete ownership.
retrospective, standups, component acceptance) and through Any interface with the project team is discruptive and
the continuous integration and collaboration. Agility is reduces their motivation to deliver [7].
bringing values in adaptability, transparency, unity and User involvement comparison is showed in Table IV.
simplicity as well as visibility in time-spend, overall testing TABLE IV: USER INVOLVEMENT COMPARISON
and project status. These meanings should be transformed PMBOK and Prince2 Agile Principle
into the agile principles. Project Methodology accents
Manage by exception approach – project Product Ownersgip is
manager has a strict budget and all established on the project
important changes must be reviewed by management level
III. AGILE PRINCIPLES board. It takes time and additional effort.
Put simply, agile principles are a different way of Interference with the board reduces Requirements are priorities
managing IT development teams and projects. In this paper, a motivation by the team level of and evaluate in the team
differentiation and significance from the product-based and management level of project managment
strict processes project management methodologies will be
accented. PMBOK and Prince2 guidelines, as It is an agile principle, that the team must establish and
cross-referenced project management methodologies are clarify the requirements together, prioritise them together,
selected. agree to the tasks required to deliver them together and
estimate the effort involved together.
A. Active User Involvement
C. Flowing Requirements
Active user involvement is basically an agile imperative.
(Please see Table III as a comparison between the agile In agile development, requirements evolve, but timescales
principle and other project management methodologies). It‟s are fixed. Recognizing that customers require maximum
not always possible to have users directly involved in flexibility and ability to rapidly adjust their solution capacity,
development projects, particularly if the agile development and also wants to have fixed budget and fixed scope, is going
project is to build a product where the real end users will be opposite against each other. Please see the requirements
external customers or consumers. In this event it is dealing comparison in Table V.
imperative to have a senior and experienced user TABLE V: REQUIREMENTS DEALING COMPARISON
representative involved. PMBOK and Prince2 Agile Principle
Project Methodology accents
TABLE III: USER INVOLVEMENT COMPARISON Change Management is established as a Changes are usual part of
PMBOK and Prince2 Agile Principle rigors process and change is typically the project.
Project Methodology accents exceptional
Role of the Senior user is part of the Role of the Product owner,
steering board (projectboard) or project who is accountable for Fixed budget, fixed scope, following plan Requirements evolve,
committee maximize product‟s value budget burn-chart
and team‟s work
No or low requirement prioritization, Requirements prioritization
Active user involvement is slightly Active users are part of the there is only Business Requirement in each iteration, planning at
accented development team itself Statement baseline each iteration start
Assure the user involvement primarily Increasing visibility to the Traditional or plan-driven approach with Periodic teamwork with
through the reporting process project through the known requirements and comprehensive focus on „value-up‟through
integrated team of the cost–benefitanalysis and established quick delivery of working
customer and the supplier development plan software,unknown
requirements
Visibility of the project is high in the Overall project visibility is
initiation phase, low in the build phase stable Project Requirements aligned with Agile Development teams
and high again in the acceptance stage or project plan must be approved by project capture high level
closing phase board requirements in workshops,
working together in a highly
According to the research at this field, e.g. By Center for collaborative way so that all
team members understand
Applied Software Engineering at the Free University of the requirements as well as
each other.
1
According to the definition of a successful project is one whose output By research of requirements prioritization strategies [10]
was achieved on time and within defined quality and within the approved which define also Agile plus (Agile approach with
budget
173
Lecture Notes on Software Engineering, Vol. 2, No. 2, May 2014
consideration of cost in addition to value) and Hybrid have a separate test phase as such.
strategy (A combination of PB and Agile plus with variable Product-based methodologies accent the integration
iterationsizes), the most relevant factor for requirements testing as a final proof of shippable solution. In this case,
prioritization is dynamism, defined as the percentage of partial tests seem to be inadequate. However, regarding the
requirements change per month – the more dynamics project Agile SW testing in a large-scale project research [11], the
and the more question in requirements, the better usage of the project team cut by an order of magnitude the time required
agile approach in the overall project success will be. to fix defects, defect longevity, and defect-management
Agile works on the premise that requirements emerge and overhead. Even on such a large-scale project, the team
evolve, and that however much analysis and design team do, achieved full regression testing at each iteration and
this will always be the case because team cannot really know developer testing. It also resolved all defects over a
for sure what they want until they see and use theoutput. significant time period that included both personnel changes
Summarized, agile requirements are ideally visual and and team growth. This research and its data show that agile
should be barely sufficient, i.e. the absolute minimum testing works.
required to enable development and testing to proceed with
G. Collaboration between All Stakeholders
reasonable efficiency [8].
Agile culture always stresses on cultivation
D. Quick, Small, Incremental Releases and Iteration (understanding the need and possibility of the change),
This principle logically continues on requirements competence (motivation, individualities, continues attention
evolving. In product-based projects, the (simplified) lifecycle to technical excellence), control and customer collaboration.
is Analyze, Develop, Test–first gathering all known In this context, agile principle accents that business people
requirements for the whole product/output, then developing and developers (team members) must work together daily
all elements of the software, then testing that the entire through the project); the best architectures and clear
product is fit for release. In agile software development, the functional requirements and its design emerge from
cycle is Analyze, Develop, Test; Analyze, Develop, Test; self-organizing teams; and the most efficient and effective
doing each step for each feature, one feature at a time, as method of capturing information is face-to-face conversation.
showed in Table VI.. The collaboration comparison is showed in Table VII.
TABLE VI: A RELEASE AND AN ITERATION COMPARISON TABLE VII: COLLABORATION COMPARISON
PMBOK and Prince2 Agile Principle PMBOK and Prince2 Agile Principle
Project Methodology accents Project Methodology accents
Initiate – plan – manage product delivery Iteration in several days, Heavy-weight documentation with both Keeping requirements and
– close the project check the requirements, the process plans and rich content documentation
attest the function and lightweight, and
review with the customer acknowledging that change
is a normal and acceptable
Traditional release Incremental release reality in software
development
By [4], [8] the advantages of this iterative approach are:
Multi-level management and strict Reducing project roles
1) Reduced risk: clear visibility of what‟s completed to date communication and reporting activities
throughout a project
2) Increased value: delivering some benefits early Defined stakeholder management N/A
3) More flexibility/agility: can choose to change direction
or adapt the next iterations based on actually seeing and Agile principles of collaboration include keeping
using the software requirements and documentation lightweight, and
4) Better cost management: if, like all-too-many projects, acknowledging that change is a normal and acceptable reality
you run over budget, some value can still be realized. in software development [1], [2], [8]. This makes close
collaboration particularly important to clarify requirements
E. Complete Firt, than Move to the Next
just-in-time and to keep all team members (including the
Features developed within iteration, should be 100% product owner) „on the same page‟ throughout the
complete by the end of the Sprint [5]. All requirements are development.
moving to the backlog2 and must be developed or completed
by its priorities. By this principle, the one iteration could not
merge into the other one. In product-based methodologies, IV. CONCLUSION
phases can overlap.
Agile is bringing solution and values to the various
F. Test Early and Often projects, characterized by a large degree of ignorance in the
As its definition [8], in agile approach, testing is integrated total requirements in a changing environment. In comparison
throughout the lifecycle; testing the output continuously with traditional methods, agile gives clear instructions,
throughout its development. Agile development does not clearly functioning in the real project practice, leading to
increased visibility, adaptability, and business value and
2
decreasing of the project risks.
Product Backlog: Prioritized requirements list with estimates to turn
them into completed functionality
Agile management is certainly subject to further
174
Lecture Notes on Software Engineering, Vol. 2, No. 2, May 2014
examination and testing for specific projects at specific [8] C. Martina and S. Alberto, “Project Management in Plan-Based and
Agile Companies,” IEEE Computer Sociaty, 2005, ISSN: 07407459.
delivery. Without a doubt, agile management cannot be [9] J. Johnson, “Turning Chaos into Success,” Software Magazine, Dec.
simply adjusted to all kinds of IT projects without deeper 1999, pp. 30.
consideration and research based on exact data coming from [10] D. Port and B. Tung, “Simulating mixed agile and plan-based
requirements prioritization strategies, proof of concept and practical
particular projects. implications,” European Journal of Information Systems, 2009, pp.
317-331, ISSN: 0960085X.
REFERENCES [11] D. Talby, O. Hazzan, Y. Dubinsky, and A. Keren, “Agile SW Testing
in a Large-scale project,” IEEE Software, Published by the IEEE
[1] Wikipedia. Agile Software Development. [Online]. Available: Computer Society, 0740-7459/06, 2006.
http://en.wikipedia.org/wiki/Agile_software_development
[2] G. M. Weinberg, “Iterative and Incremental Development: A Brief Jan Juricek was born in Prague, Czech Republic in
History,” Computer, vol. 36, ISSN: 0018-9162, 2003. 1980. Mr. Juricek graduated from the University of
[3] K. Beck, A. Cockburn, R. Jeffries, and J. Highsmith. Agile manifesto. Economics in Prague, Faculty of informatics and
[Online]. Available: http://www.agilemanifesto.org, 2001, 12-4-2002. statistics in major specialization of information
[4] J. Highsmith, Agile Software Development Ecosystems, Boston, MA: management.
Addison–Wesley, 2002. Besides his PhD studying, he is currently working as
[5] D. J. Fernandey, “Agile Project Management – Aligism versus a head of PMO in the business sector and is active in
Traditional approaches,” The Journal of Computer Information professional project management practices for 8 years.
Systems, 2008, ISSN: 088-74417. Mr. Juricek is the holder of the international certification for project
[6] B. Kent et.al., “Manifesto for Agile Software Development,” Agile management practices – ©Prince2 Practitioner, is lecturing techniques of
Alliance, 2010. project management and is a member of professional associations for project
[7] K. Watters. All about agile. [Online]. Available: management in Czech Republic.
http://www.allaboutagile.com/agile-principle-2-agile-development-tea
ms-must-be-empowered/
175