5
months)
TR replacing outage cycle (5.5 months) Rev.8 Optional
PROJECT : [1708-238-01] Supply , Installation & Commissioning of Four(4) Nos. -100MVA Generator Transformer at Riffa Power Station (Tender No.2017-030-PM-EPD) 2018-07-06
2018 2019 2020
DESCRIPTION REMARKS
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
Milestone Approval Erection Completion
Signing of Contract Contract Site Test
1. Existing foundations certified works
Safety/validity/appropriacy of the foundation

2. Existing Transformer (Alstom)


88MVA 220kV Transformers x 4
* This schedule is changeable according to the
Preperation works for Dismantling #1
schedule of client request.
Preperation works for Dismantling #2
Preperation works for Dismantling #3
Preperation works for Dismantling #4
Dismantling work #1
Dismantling work #2
Dismantling work #3
Dismantling work #4
Shifting from Riffa station to Sitra Yard * Transformer replacement is planned in outage
Erection cycle 2018-2019, which is starting from October-
Oil filtration 2018 till May-2019.
88MVA 220kV Transformers x 2 (replaced)
Preperation works for Dismantling
Dismantling work
Shifting from Riffa station to Sitra Yard
Erection
Oil filtration

3. New Transformer (Hyundai) * Bushing must be approved within


100MVA 220kV Transformers #1, #2 HSP (or ABB) Bushing arrive in Factory. (6 months ) 1 week after the Contract.
Design The schedule shall be confirmed depending on the
Manufacturing bushing delivery.
Shop Test Procedures
Inspection & FOB * Hyundai comply erection period in 1month each
Sea Transportation transformer.
Custom & Inland Transportation
Erection TR #1
Erection TR #2
Site Test
Water Deluge System (Re-route)
Erection (Re-route) #1, #2

100MVA 220kV Transformers #3, #4


Manufacturing
Shop Test Procedures
Inspection & FOB
Sea Transportation
Custom & Inland Transportation
Erection TR #3
Erection TR #4
Site Test
Water Deluge System (Re-route)
Erection (Re-route) #3, #4

HYUNDAI ELECTRIC Co., Ltd. Prepared by Project Management Department

1/1