Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
• Avoiding total bespoke negotiation & its costs (though of course the
largest projects will have substantially bespoke arrangements).
• Possibly not so good: The growing tendency of standard forms – and FIDIC
2017 amendments no exception – to over-legislate and micro-manage, with
longer and more complex provisions. Sub-Cl 3.7 is arguably an example of
detail taken too far: it also potentially revives the question posed
[unsuccessfully] by the appellant contractor in AMEC v Secretary of State for
Transport as to whether the Engineer acts in a quasi-judicial capacity and
hence must observe the rules of natural justice.
• Change which is arguably counter-productive:
• Sub-cl. 15.6 deals with valuation once there has been a termination under
Sub-cl. 15.5 and this comprises the value of work done (15.6(a)) and the
amount of any loss of profit (15.6(b)) and then the words ‘…or other
losses and damages…’
Clause 16: Suspension and Termination by the
Contractor.
Again, there are new grounds:
Simon Hughes QC
Keating Chambers
The 2017 Revisions to the Rainbow Suite:
the FIDIC Approach
• An increased likelihood that if you fail to follow the rules, you lose the
right to make a claim.
• To rationalise behaviour;
• As a sounding board;
• Accountability;
• Does the 2017 Form really have sufficient teeth to summarily enforce
DAAB Decisions?
• Will the Employer pay?
• 13 DAB Decisions and then an international arbitration?
• Cost.
• Attitude of JICA: the Employer’s share for DB cost is eligible for JICA’s
financing under its ODA Loan.
The 5 FIDIC Golden Principles
• GP4: All time periods for parties to perform their obligations and
exercise their rights must be of reasonable duration.
• GP4: All time periods for parties to perform their obligations and
exercise their rights must be of reasonable duration.
• Recommendation 84:
“The legislation should void a contractual term that purports to make a
right to claim or receive payment, or a right to claim an extension of
time, conditional upon giving notice where compliance with the notice
requirements would:
a) not be reasonably possible; or
b) be unreasonably onerous; or
c) serve no commercial purpose.”
• There is no FIDIC BIM Protocol. Note the Second Edition of the CIC
Protocol came out in April 2018.
• FIDIC has identified the key risk areas on any BIM-enabled project:
• Misunderstanding of scope of services.
• Use of data for an inappropriate purpose and reliance on inappropriate
data.
• Ineffective information, document or data management.
• Cyber security and responsibility for “holding” the models or data.
• Definition of deliverables, approval and delivery.
• Notices: the Sub-Clause 4.20 Progress Report and the Sub-Clause 8.3
Programme cannot be Notices.
• Claims for time and/or delay damages must be made in accordance with
Sub-Clause 20.2.
• “New” Sub-Clause 14.3(c): every payment application must include the monthly
Progress Report including a detailed description of progress.
Concurrent Delay
Sub-Clause 8.5:
“In any event, I am clearly of the view that, where there is an extension of time
clause such as that agreed upon in this case and where delay is caused by two or
more effective causes, one of which entitles the Contractor to an extension of time
as being a Relevant Event, the Contractor is entitled to a full extension of time.”
Mr Justice Akenhead
Walter Lily v MacKay & Others, [2012] EWHC 1173 (TCC)
“The acting law recognizes situation when the loss suffered by one party was
caused by both parties’ reasons and so called “composed fault” exists. In such
case, the court is obliged to determine which party is liable for the loss to what
extent and to determine its amount proportionally to such extent.”
• 1999:
“The Contractor shall design (to the extent specified in the Contract),
execute and complete the Works in accordance with the Contract and
with the Engineer’s instructions and shall remedy any defects in the
Works.”
• 2017:
“The Contractor shall execute the Works in accordance with the
Contract. The Contractor undertakes the execution of the Works and
the completed Works will be in accordance with the documents
forming the Contract, as altered and modified by Variations.”
Sub-Clause 4.1 – Design
• 1999:
“The Contractor shall design, execute and complete the Works in
accordance with the Contract and shall remedy any defects in the Works.
When completed the Works shall be fit for the purposes for which the
Works are intended as defined in the Contract.”
• 2017:
“The Contractor shall execute the Works in accordance with the
Contract. When completed, the Works (or Section or Part of major item
of Plant, if any) shall be fit for the purpose(s) for which they are intended,
as defined and described in the Employer’s Requirements (or, where no
purpose(s) are so defined and described, fit for their ordinary
purpose(s)).”
Contractor’s and Employer’s General
Obligations
“[…]’s error is perhaps a sad reflection of the fact that modern day
contracts of this kind are so complicated that nobody (not even the
consultants) bothers to check the actual documentation being signed.”
Mr Justice Coulson
Borough of Milton Keynes v Viridor (Community Recycling MK) Ltd
[2017] EWHC 239
Other Fitness for Purpose Points
“The Contractor shall also indemnify and hold harmless the Employer against
all acts, errors or omissions by the Contractor in carrying out the Contractor’s
design obligations that result in the Works (or Section or Part or major item of
Plant, if any), when completed, not being fit for the purpose(s) for which they
are intended under Sub-Clause 4.1 [Contractor’s General Obligations].”
• If the Engineer exercises any authority for which the Employer’s approval is
required then deemed approval has been given.
• Introduction of the concept of good faith and mutual trust in all dealings.
• Enhanced anti-corruption provisions.
• Not entirely complementary to the 2017 Rainbow Suite.
• Sub-clause 3.3.1: Consultant shall “have no other responsibility than to
exercise the reasonable skill, care and diligence to be expected from a
consultant experienced in the provision of such services for projects of
similar size, nature and complexity”.
• Sub-Clause 1.7.5 gives the Consultant the ability to “revoke any licence” on 7
days’ notice if the Employer is in payment default.
• Sub-Clause 3.9: contract administration, the Consultant shall act “fairly”
when exercising judgment or determining any matter under the works
contract.
• Clause 4: Programming Obligations. Needs to tie in with any BIM Protocol.
• FIDIC is a contract written by Engineers for Engineers.
Some Feedback on the new FIDIC Form:
FIDIC Regional Infrastructure Conference,
Georgia 2018
• Positive reaction, welcoming the new
Form.
• Some confusion over the enhanced
roles of the Engineer and DA/AB:
who does what.
• Overwhelming view in favour of the
new detailed step by step processes.
• Brought clarity to what was needed
from all parties.
• All parties, including Employer Reps
supportive of DA/ABs.
• Should result in less formal disputes.
Thank you
Simon Hughes QC
shughes@keatingchambers.com
Jeremy Glover
jglover@fenwickelliott.com