Sei sulla pagina 1di 28

Licensed copy: University of Teknologi Mara, University of Teknologi Mara, Version correct as of 13/07/2010 04:34, (c)

BRITISH STANDARD BS 6990:1989


Including
Amendment No. 1 not
issued separately

Code of practice for

Welding on steel pipes


containing process
fluids or their residuals
BSI

ICS 25.160.10
Licensed copy: University of Teknologi Mara, University of Teknologi Mara, Version correct as of 13/07/2010 04:34, (c)
BS 6990:1989

Committees responsible for this


British Standard

The preparation of this British Standard was entrusted by the Welding


Standards Committee (WEE/-) to Technical Committee WEE/21, upon which
the following bodies were represented:

Associated Offices Technical Committee


British Gas plc
British Non-Ferrous Metals Federation
British Steel Industry
Electricity Supply Industry in England and Wales
Engineering Equipment and Materials Users’ Association
Health and Safety Executive
Heating and Ventilating Contractors’ Association
Institute of Refrigeration
Institution of Gas Engineers
Institution of Mechanical Engineers
Joint Industry Board for Plumbing Mechanical Engineering Services in
England and Wales
National Association of Plumbing, Heating and Mechanical Services
Contractors
Power Generation Association (BEAMA Ltd.)
Stainless Steel Fabricators’ Association of Great Britain
BSI

Tubes Investments Limited


United Kingdom Atomic Energy Authority
Water Tube Boilermakers’ Association
Welding Institute
Welding Manufacturers’ Association (BEAMA Ltd.)

The following bodies were also represented in the drafting of the standard,
through subcommittees and panels:

Association of Consulting Engineers


British Institute of Non-destructive Testing
This British Standard, having Department of Energy (Petroleum Engineering Division)
been prepared under the
direction of the Welding Institution of Production Engineers
Standards Committee, was Pipeline Industries Guild
published under the authority
of the Board of BSI and comes United Kingdom Offshore Operators Association
into effect on
28 February 1989
Water Research Centre

© BSI 04-1999

First published as DD 39, Amendments issued since publication


July 1974
First published as BS 6990,
February 1989 Amd. No. Date of issue Comments

9772 February 1998 Indicated by a sideline in the margin


The following BSI references
relate to the work on this
standard:
Committee reference WEE/21
Draft for comment 86/78728 DC

ISBN 0 580 16672 4


Licensed copy: University of Teknologi Mara, University of Teknologi Mara, Version correct as of 13/07/2010 04:34, (c)
BS 6990:1989

Contents

Page
Committees responsible Inside front cover
Foreword ii
Section 1. General
1 Scope 1
2 Definitions 1
3 Information, items to be approved and items to be agreed and to
be documented 2
Section 2. Safety considerations
4 Legal requirements 4
5 Preliminary considerations 4
6 Factors affecting safety 4
Section 3. Welding
7 Pipe thickness, temperature and internal pressure 6
8 Pipe material 6
9 Fitting material 6
10 Welding equipment 6
11 Electrodes and filler metals 6
12 Shielding gases 7
13 Approval and testing of welding procedures 7
14 Approval and testing of welders 12
15 Preparation of pipe 12
BSI

16 Inspection of fittings 13
17 Fusion faces 13
18 Preparation for encirclement fitting 13
19 Preparation for set-on fitting 16
20 Alignment of flanged fittings 16
21 Working clearance 17
22 Stray arcs 17
23 Weather conditions 17
24 Preheating 17
25 Sequence of welding 17
26 Inter-run cleaning 18
27 Inspection 18
28 Non-destructive testing acceptance criteria 19
29 Rectification of welds 19
Figure 1 — Typical fittings 3
Figure 2 — Typical longitudinal weld preparation for fitting: dimensions
and tolerances 14
Figure 3 — Attachment of run-on/run-off plates to backing material 15
Figure 4 — Typical yoke-type clamp for encirclement tee fittings 16
Table 1 — Welding procedure details 10
Table 2 — Changes affecting procedure approval (essential variables) 11
Publications referred to Inside back cover

© BSI 04-1999 i
Licensed copy: University of Teknologi Mara, University of Teknologi Mara, Version correct as of 13/07/2010 04:34, (c)
BS 6990:1989

Foreword

This British Standard Code of Practice has been prepared under the direction of
the Welding Standards Committee. It is based on an up-dating of Draft for
Development DD 39 which is withdrawn. It reflects the latest knowledge in the
welding on steel pipelines and pipework which contain or have contained process
fluids or the residuals of such process fluids, and covers welding operations where
attachments are required and where it is not necessary or practical to
decommission and/or decontaminate the system.
This method of attachment is sometimes, but incorrectly, termed “hot tapping”.
Reference to current legislation is essential before any attempt to undertake work
of this nature, and to follow the details of this code.
Since the preparation of DD 39 in 1974 considerable experience has been gained
as the result of both on-shore and off-shore North Sea developments. To this
knowledge has been added the expertise gained in the process plant field,
resulting in an unified code which covers both spheres. Although new
developments and refinements can be expected to emerge in the future,
particularly with regard to off-shore exploration, the methods and
recommendations in this code are considered to reflect up to date knowledge and
sufficient experience of practical use to merit their adoption.
The up-dating has been extensive, covering practically every aspect of the
technical changes in materials, welding technology and non-destructive testing.
The main purpose of this code is to give general details for welding, testing and
acceptance criteria. Since the design, choice of materials and methods of
construction are not covered by this code, reference should be made to the
appropriate standards, such as CP 2010-2, BS 4515, BS 2633, BS 4677 and
BS 8010-1.
BSI

To ensure that the workmanship and welding follow the details of this code, it
would be normal for the contractor as well as the organization undertaking this
specialist work to have and employ a suitable quality control system such as is
recommended in BS EN ISO 9000.
Because of the wide range of pipelines and pipework and the products that can be
conveyed and the range of attachments that may be required, general guidance
has been given on some aspects. Specific details will be for agreement between the
contracting parties after due consideration of the prevailing service conditions.
The techniques and equipment described herein require extensive facilities and
specialist personnel and as such should not be attempted without such specialist
equipment and personnel.
The use of the words “imperfection” or “flaw” or other phrases containing the
words “imperfection” or “flaw” in this code is not intended to imply a defective
condition or any lack of integrity of the weld as it is known that all welds contain
certain features described as artefacts, flaws, imperfections or discontinuities.
The acceptance criteria have been based on the present technical analysis of the
various types, sizes, shapes and positions of these anomalies and on the
suitability of the whole weld for its specific service.
Pipe dimensions. Unless otherwise qualified, for the purposes of this code
nominal values of outside diameter and thickness of pipe apply.
It has been assumed in the drafting of this code that the execution of its
provisions is entrusted to appropriately qualified and experienced people.

ii © BSI 04-1999
Licensed copy: University of Teknologi Mara, University of Teknologi Mara, Version correct as of 13/07/2010 04:34, (c)
BS 6990:1989

A British Standard does not purport to include all the necessary provisions of a
contract. Users of British Standards are responsible for their correct application.
Compliance with a British Standard does not of itself confer immunity
from legal obligations. (See clause 4).
BSI

Summary of pages
This document comprises a front cover, an inside front cover, pages i to iv,
pages 1 to 20, an inside back cover and a back cover.
This standard has been updated (see copyright date) and may have had
amendments incorporated. This will be indicated in the amendment table on
the inside front cover.

© BSI 04-1999 iii


Licensed copy: University of Teknologi Mara, University of Teknologi Mara, Version correct as of 13/07/2010 04:34, (c)
BSI

iv
blank
Licensed copy: University of Teknologi Mara, University of Teknologi Mara, Version correct as of 13/07/2010 04:34, (c)
BS 6990:1989

Section 1. General

1 Scope 2.3
inspector
This code covers operations relating to and
involving arc welding on ferritic steel and austenitic the body, association or employee that ensures that
stainless steel land or offshore pipelines and process the materials and construction are in accordance
plant pipework which contain or have contained a with this code
process fluid and which are at least 5 mm thick. It 2.4
gives details of procedures prior to, during and after statutory authority
all these operations.
the body or organization that, through the power
vested in it by Government Statute, regulates the
NOTE 1 Welding on pipes of thickness below 5 mm is not requirements with which particular pipelines or
covered by this code although it can be undertaken. pipework have to comply
The code covers manual, semi-automatic and NOTE One way in which such requirements may be
mechanized arc welding by the following processes promulgated is by making reference to British Standards.
or combination of processes: 2.5
a) manual metal-arc welding; joint
b) MIG/MAG welding; the completed weld joining two sections of pipe, a
c) TIG welding; section of pipe to a fitting or two fittings
d) flux cored arc welding; 2.6
e) non-shielded welding. welding procedure*
It is essential that the items listed in clause 3 should a specific course of action followed in welding,
be fully documented and followed. including a list of materials and, where necessary,
tools to be used
Welding operations needing post-weld heat
treatment for adequate weld quality are not within 2.7
BSI

the scope of this code. welding procedure test


This code is not applicable to a pipeline or pipework the making and testing of a welded joint,
that has been fully isolated and decontaminated or representative of that to be used on an actual job, in
has not been commissioned. These are covered by order to prove the feasibility of a welding procedure
other standards such as BS 2633, BS 4677 and NOTE This term is not usually applied to any tests that may
BS 4515. have been made during the development of a welding procedure.

This code does not relate to a pipeline or pipework 2.8


containing a process fluid or its residuals that will approved welding procedure
become explosively unstable upon the application of a documented welding procedure that has been
heat or will affect the pipe material by rendering it approved by an inspecting authority either by
susceptible to ignition, stress corrosion cracking or means of a welding procedure test or as a result of
embrittlement. authentic documented experience gained with the
NOTE 2 The titles of the publications referred to in this code welding of joints similar to that to which the welding
are listed on the inside back cover. procedure applies
2 Definitions 2.9
welder*
For the purposes of this code the definitions given in
BS 499-1 apply together with the following. the operator who performs the welding
NOTE Terms marked with an asterisk (*) are taken from 2.10
BS 499-1. approved welder
2.1 a welder who has demonstrated his ability to
employer produce welds meeting the details of this code
the owner of the pipeline or pipework 2.11
NOTE The employer may act through a consultant, an root run*
inspector or other authorized representative.
the first run deposited in the root of a multi-run
2.2 weld
contractor
NOTE Also known as a “stringer bead” in vertical-down
the firm undertaking the contract and any welding.
subcontractors engaged in work covered by this code

© BSI 04-1999 1
Licensed copy: University of Teknologi Mara, University of Teknologi Mara, Version correct as of 13/07/2010 04:34, (c)
BS 6990:1989

2.12 3.2 Items to be approved by the employer


positional welding The following items to be approved by the employer
welding wherein the pipe or assembly is held should be fully documented and followed.
stationary a) The minimum tensile strength of weld metal
2.13 for fillet welds when this need not be as high as
semi-automatic welding* the minimum specified for the parent metal
welding in which some of the welding variables are [see 11.1 b)].
automatically controlled, but manual guidance is NOTE The agreement of the statutory authority may also be
required.
necessary
b) Electrodes and filler metals to be used
2.14 (see 11.1).
mechanized welding*
c) Documentation relating to welding procedure
welding in which the welding parameters are approval (see 13.3).
controlled mechanically or electronically and may
d) Use of diameter and thickness grouping for
be manually varied during welding to maintain the
welding procedure approval [see 13.4 b)].
required welding conditions
e) Use of a plate butt joint to simulate a
3 Information, items to be approved longitudinal butt weld for welding procedure
and items to be agreed and to be approval [see 13.4 c)].
documented f) The welding procedure used for repairing
defects in an encirclement fitting (see 18.1).
3.1 Information to be supplied by the employer
g) The thermal cutting method for making large
The following information to be supplied by the modifications to the radius of a set-on fitting
employer should be fully documented and followed. (see 19.1).
a) The location and identification of the pipeline h) Repair or rejection of arc strikes
BSI

or pipework. (see clause 22).


b) The type of process fluid and its temperature, i) Non-destructive testing procedures (see 27.1).
pressure and flow rate. (See also 5.3 and 5.8.)
j) Inspection personnel (see 27.1).
c) The composition of the pipe material if known.
3.3 Items to be agreed
d) The type of fitting to be used and its position on
the pipe. The following items to be agreed between the
contracting parties should be fully documented and
NOTE Typical fittings are shown in Figure 1.
followed.
e) Whether batch testing of electrodes and filler
metals is required (see 11.1). a) The minimum pipe thickness on which welding
is to be carried out when the conditions are other
f) The interval before testing the test welds if than those detailed in clause 7 (see clause 7).
other than 24 h [see 13.2 4) ii)].
b) The specification of the material for a fitting
g) The period for which records of approved (see clause 9).
welding procedures should be kept (see 13.3).
c) The definition of a batch when batch testing of
h) Whether prevailing weather conditions are electrodes and filler metals is required (see 11.1).
such that welding is not to be carried out
(see clause 23).
NOTE This information may not be able to be supplied until
the appropriate stage of the work is reached.
i) The methods of non-destructive testing
(see 27.1, 27.3, 27.4 and 27.5) and the
Examination Level to be used when ultrasonic
examination in accordance with BS 3923-1 is to
be applied (see 27.5).
NOTE The agreement of the statutory authority may also be
required.

2 © BSI 04-1999
Licensed copy: University of Teknologi Mara, University of Teknologi Mara, Version correct as of 13/07/2010 04:34, (c)
BSI

© BSI 04-1999
Figure 1 — Typical fittings

3
BS 6990:1989
Licensed copy: University of Teknologi Mara, University of Teknologi Mara, Version correct as of 13/07/2010 04:34, (c)
BS 6990:1989

Section 2. Safety considerations

4 Legal requirements 5.5 In all cases, where potential hazards are


identified, the first consideration should be to
All persons involved in welding operations on steel
remove the hazardous substances and to ensure
pipes have a duty to make themselves aware of all
that any remaining inside the pipe will no longer
current legislation relative to their industry.
present a risk to health and safety.
5 Preliminary considerations 5.6 However, circumstances do arise when the
removal of the process fluid may not be practicable,
5.1 The application of heat to a pipe containing a may cause operational difficulties or may in itself
process fluid or a residue during preheating or create hazards greater than those presented by the
welding operations can be, potentially, very welding operation. In these circumstances, and if
hazardous. Flammable substances may explode, the risks associated with welding are known to be
toxic materials may escape and some chemicals acceptably small, welding operations may be carried
when heated may react with the metal of the pipe out.
itself. For these reasons all such operations should
5.7 Text deleted
always be carefully considered before any work is
started so that the risks are known and fully 5.8 If toxic or reactive substances are present in the
understood. pipe detailed guidance should be sought on the safe
approach to the welding operation. In many cases
5.2 Before any work is started involving the
this advice will be available from the owner of the
application of heat to a pipeline or pipework that
contents in the pipe, the factory occupier or the
may contain or have contained a process fluid, it is
pipeline operator. In other instances the advice may
essential to identify the relevant chemical and
be available from HM Factory Inspectorate.
physical characteristics of the process fluid, or any
residue it may leave and of any contaminant that
may arise and be present inside the pipe. This may
6 Factors affecting safety
include hydrogen present in the pipe material 6.1 General
introduced as a product of corrosion or other
BSI

In drawing up a safe system of work there are a


reactions. If there is any doubt as to the nature or number of factors that need to be taken into account.
the properties of the fluid inside the pipe, work In all cases procedures should be written down and
involving the application of heat should not start fully understood by those involved in the operation.
until that doubt is resolved, by sampling and Documents should include not only the details of the
analysis if necessary. welding procedures but also safety instructions and
5.3 Once the chemical and physical properties of all an indication of who is responsible for each of the
substances inside the pipe have been established, it items. The list that follows is intended to be a check
is essential that expert advice is taken as to the list, not detailed guidance, and expert advice should
effect of heat on those properties, including any always be sought.
reaction between the pipe metal and the substances 6.2 Initial requirements
and any long or short-term effect on the corrosion
resistance and integrity of the finished weld and the a) Establish the necessity for welding on pipe
heat-affected zone. containing a process fluid or residuals.
5.4 Pre-heating or welding operations should not be b) Identify the pipe and process conditions (fluid
carried out on pipes that contain the following. content and its pressure, temperature and flow
rate) and verify that adequate experimental work
a) Mixtures of gases or vapours within their
has been completed to prove the safety of the
flammable range.
operation.
b) Substances which undergo any reaction or
c) Ensure compliance with legal requirements.
decomposition that leads to a dangerous increase
in pressure, explosion, or attack or embrittlement d) Produce detailed plan of action, including the
of the metal. responsibilities of each individual, taking into
account the requirements of a permit to work and
c) Any chemical that may cause corrosion or
any exemption certificate.
stress corrosion cracking.
e) Confirm welding procedure, services required,
In particular welding operations should be avoided
approval requirements, equipment required and
on pipes containing acetylene, other unsaturated
fittings required.
hydrocarbons, oxygen, hydrogen or ammonia.

4 © BSI 04-1999
Licensed copy: University of Teknologi Mara, University of Teknologi Mara, Version correct as of 13/07/2010 04:34, (c)
BS 6990:1989

f) List the services required (e.g. communications, 6.5 Emergency services


cranage, compressed air and gases, electrical a) Ensure first aid is available.
power). It is particularly important that a
communication system is established between b) Ensure firefighting equipment is available.
the proposed work site and the pipeline control c) Ensure breathing apparatus is available.
centre in order that pipeline or pipework d) Ensure resuscitation equipment is available.
conditions may be controlled prior to and during
6.6 Action immediately prior to welding
welding.
a) Check pipe is correct one and that the required
6.3 Documentation
non-destructive testing has been carried out.
a) Provide location plan showing access routes b) Check process conditions (pressure,
including emergency access. temperature, flow rate and fluid) are within
b) Prepare drawing or sketch of work area limits authorized.
showing excavations, obstructions and any other c) Check all approved welders and supervisors
adjacent pipes including the proximity of drains have a clear understanding of the approved
and ducts where hazardous liquids and vapours welding procedure.
may be present and valves which are carrying
hazardous liquids. d) Check provision of portable ammeter for
accurate measuring of welding current.
c) Check notice of entry to site.
e) Check welding cables are routed away from
d) Ensure compliance with employer’s areas containing flammable fluids.
requirements and procedures.
f) Check adequate quantities of the correct
e) Check distribution of procedures to necessary welding consumables are available and that they
personnel and establishment of communications. are stored under correct conditions.
f) Issue courtesy notices to common wayleave g) Check temperature of pipe wall and fitting.
users (e.g. gas, electric, oil, chemical and water)
BSI

and to all affected landowners and occupiers, fire h) Re-check to ensure hazard-free conditions still
and police. exist.
g) Provide emergency procedures. 6.7 Action during welding
6.4 Site preparation Whenever possible the pressure, temperature and
flow rate in the pipeline should be monitored during
a) Provide good access to and from site. the welding operation. Where these exceed the
b) Ensure adequate excavation and shoring or previously agreed and authorized limits, welding
scaffolding where necessary. If possible access by should cease.
ramp is preferable to step ladders, particularly
6.8 Action on completion
for escape routes.
c) Provide adequate support for pipe — preferably a) Prior to reinstatement, check all work and
testing is completed.
of non-combustible materials.
b) Restore work site to original condition.
d) Check provision for removal of ground water
and protection from the weather. c) Install marker posts if necessary.
e) Ensure the welding area is adequately d) Prove area is hazard free.
ventilated. e) Stand down emergency services.
f) Provide adequate lighting. f) Advise all necessary persons of completion and
remove all equipment.
g) Clean and test all equipment used prior to
return to storage.
h) Carry out de-briefing among key personnel.

© BSI 04-1999 5
Licensed copy: University of Teknologi Mara, University of Teknologi Mara, Version correct as of 13/07/2010 04:34, (c)
BS 6990:1989

Section 3. Welding

7 Pipe thickness, temperature and 10 Welding equipment


internal pressure The contractor should maintain all welding plant
It is necessary to ensure that during the welding and ancillary equipment in good working order.
operation the material in the region of the weld pool Welding plant, instruments, cables and accessories
has sufficient strength to contain safely the internal should comply with the requirements of
pressure and avoid a blow-out. The risk of blow-out the appropriate British Standard where it exists,
is a complex interaction of welding conditions, pipe e.g. BS 638, BS EN 167, BS EN 168, BS EN 169,
material, pipe thickness, pipe temperature and hoop BS EN 60974-11 and BS EN 60974-12.
stress. Experience and research show that for Adequate means of measuring current should be
materials of yield strength not greater available, either as part of the welding plant or by
than 450 N/mm2, operating at temperatures of not the provision of a portable ammeter. In the case of
greater than 350 °C and with a hoop stress of not mechanized and semi-automatic welding, means
greater than 72 % of the specified minimum yield should be provided for measuring the arc voltage.
stress, blow-out can be prevented during welding All instruments should be calibrated regularly
provided the minimum pipe thickness is not less (see BS EN 30012-1). The welding equipment
than 5 mm. For other materials or conditions, a should be capable of controlling the parameters
minimum pipe thickness of 5 mm or greater should given in Table 2 to within the limits stated in that
be agreed between the contracting parties, based on table.
either specific previous experience and/or data from The return current cable connecting clamp should at
trials. all times be connected to the work at a point as close
NOTE For some products, due to chemical reaction, the safe as possible to the actual weld. Return paths via pipe
pipe temperature may be much lower than 350 °C, see 5.4.
hangers, steelwork or structures should not be used.
8 Pipe material
11 Electrodes and filler metals
Under no circumstances should any welding be
BSI

11.1 General
undertaken on pipe of an unknown material.
Normally the type and condition of the pipe material The electrodes, filler wires or rods used should
can be obtained from records. If this is not possible, produce weld metal that has a minimum tensile
it is essential that sufficient information is strength either:
determined about the pipe material to enable a a) at least equal to the minimum specified for the
welding procedure to be developed. The following parent metal, or;
are examples of features that can be checked for this b) as an alternative, for fillet welds only, a level
purpose: approved by the employer lower than the
a) chemical composition, e.g. by wet chemical, minimum specified for the parent metal.
chromatographic, radiation pattern or NOTE The agreement of the statutory authority may also be
spectrographic analysis; required.
b) hardness (portable hardness tester); In the case of joints between dissimilar metals, the
c) microstructure (replica technique); weld metal should have a tensile strength at least
equal to that of the lower strength parent metal.
d) colour;
Particularly when welding austenitic stainless steel
e) magnetism;
or low alloy ferritic steel pipes, the weld metal
f) reaction to chemical etchants (identification should be of a composition which is compatible with
kits). that of the parent metal.
Only electrodes and filler metals which have
9 Fitting material received the prior approval of the employer should
The specification of the material for a fitting should be used. When required by the employer batch
be agreed between the contracting parties. The testing of electrodes and filler metals should be
selection of the material for a fitting should take carried out, in which case the definition of a batch
account of the composition of the pipe, the operating should be agreed between the contracting parties.
conditions and the process fluid. Guidance on the appropriate British Standards
covering suitable types of weld metal for welding
carbon, carbon-manganese and low-alloy ferritic
steels is given in BS 2633.

6 © BSI 04-1999
Licensed copy: University of Teknologi Mara, University of Teknologi Mara, Version correct as of 13/07/2010 04:34, (c)
BS 6990:1989

Guidance on suitable types of weld metal for 13 Approval and testing of welding
welding similar and dissimilar austenitic stainless procedures
steels is given in BS 4677, including the relevant
British Standard designations. 13.1 Safety considerations in formulating a
welding procedure
11.2 Storage and handling
13.1.1 General. The development of a welding
Electrodes, filler wires and rods should be stored procedure for welding on pipe containing a process
and handled so as to avoid damage or deterioration fluid or residuals requires the careful consideration
to them and to the containers in which they are of a number of items and some of these should be
transported. When the electrode manufacturer verified experimentally. Detailed consideration of
makes specific recommendations for re-drying the metallurgy and welding are also required.
and/or storage of electrodes, the contractor should
follow such recommendations. Electrodes, filler Detailed consideration of the metallurgy and
wires and rods that show signs of damage or welding are also required.
deterioration should not be used. The final welding procedure chosen will be a balance
between the safety of the technique on one hand and
12 Shielding gases the prevention of unsatisfactory material properties
on the other. Safety is obviously of paramount
12.1 General
importance and this will involve, among other
Where appropriate, gases or gas mixtures of the considerations, limiting the maximum heat input to
following quality should be used: avoid blow-out. However, with a low heat input it
a) argon complying with BS EN 439; may not be possible to avoid high cooling rates in the
weld area and this could give unsatisfactory
b) carbon dioxide complying with BS EN 439;
hardness. Thus a compromise has to be reached and
c) gas mixtures that have been proved to be if the maximum heat input allowable for safety is
satisfactory as a result of procedure approval insufficient to provide adequate material properties,
tests.
BSI

then additional precautions, e.g. preheating or weld


When a gas mixture is used which has specified bead placement, will have to be included.
additions, e.g. 2 % O2, 5 % CO2, the variation of such There will be many instances where the allowable
addition should not exceed ± 10 % of that stated. heat input will be adequate to provide good
Moisture content should correspond to a dewpoint properties and the above balance will not be critical.
of – 30 °C or lower. However, there may be occasions where the desired
12.2 Storage and handling balance is unobtainable and under these
circumstances it may be necessary to reduce the
Shielding gases should be kept in the containers in pressure or flow rate of the product to maintain safe
which they are supplied and these should be stored operation.
away from extremes of temperature.
13.1.2 Welding processes and consumables. The
In the field, only gases specified in 12.1 as supplied most common process is manual metal-arc welding;
by the manufacturers, in specially marked it is also the best documented. Other processes have
containers, should be used. Gases that are of been investigated, e.g. MIG/MAG and flux cored arc
questionable purity and those in containers which welding, but these are in less common use. An
show signs of damage should not be used. increased safety factor may be attained by the use of
There should be no mixing of gases in the field, basic, low hydrogen electrodes where the depth
unless this is an integral part of a mechanized penetration of this type of electrode is less than with
process which utilizes a fail-safe cut-off when the others, thus reducing the possibility of blow-out: the
proportions fall outside those specified in the low hydrogen deposit is also of advantage where the
approved welding procedure. weld and heat-affected zone may be of high
hardness. In MIG/MAG welding, the use of
argon/CO2 mixtures reduces penetration as
compared to pure CO2.
13.1.3 Welding parameters. The principal welding
parameters of concern in formulating a safe
procedure are welding current and travel speed.

© BSI 04-1999 7
Licensed copy: University of Teknologi Mara, University of Teknologi Mara, Version correct as of 13/07/2010 04:34, (c)
BS 6990:1989

The welding current and travel speed should be Chemical analysis and thickness of both pipe and
adjusted to ensure that the penetration is fittings will influence the hardness. Comparisons of
insufficient to cause blow-out but sufficient to avoid hardness may be made between materials welded
lack of fusion. The principal means of determining under identical conditions by comparing carbon
these parameters is by experimentation on similar equivalent values but, because of the influence of
materials under simulated pressure. the product flow, absolute values can only be found
The travel speed is less easy to control than the by experimentation.
welding current, but a minimum travel speed The welding process can affect the micro-structure:
should be determined to avoid heat build-up. It may MIG/MAG welding is a low heat input process and
be advisable to control or eliminate the weld weave thus the hardness tends to be high but it has the
to ensure limited local heating. One successful way advantage of being a low hydrogen process. Manual
of controlling travel speed is to utilize vertical-down metal-arc welding with basic electrodes will have
welding where the speed of travel is controlled by comparatively moderate hardness and the low
the fluidity of the weld pool, rather than the use of hydrogen characteristics are of advantage.
vertical-up welding where the speed is a function of Preheating can have a considerable influence upon
the welder’s personal performance and where the micro-structure but unfortunately there can be
excessive weaving may be practised. difficulties in applying preheat as it is affected by
Electrode polarity can also be used effectively to the temperature and flow rate of the product which
reduce penetration. If the electrode is made may rapidly remove the heat. It may be necessary to
negative then penetration may be reduced by up develop special preheating techniques with this
to 25 %. phenomenon.
13.1.4 Operating conditions. Product pressure and Normal methods of post-weld heat treatment are
flow rate can have a considerable influence upon the usually impossible to apply as the strength of the
safety of welding. High pressure will increase the material decreases at higher temperatures and the
possibility of blow-out but it is less significant than pipe probably will not be able to withstand the
BSI

other factors. The flow rate, coupled with the nature internal pressure. However it is possible to
of the product, can greatly influence the heat influence the hardness of the weld and in particular
extraction rates from the preheated area and from the weld toe by the judicious placement of weld
the weld pool. A low flow rate may allow a greater beads and/or the use of heating electrodes to
build-up during welding which may have a lower “temper” the weld toe.
safety factor. 13.2 Stages in obtaining approval
The flow conditions during welding should be
Before a contractor carries out welding in
maintained within the range used for procedure
accordance with this code he should either:
development to avoid such increases in cooling rates
or build-up of heat which could affect the a) obtain exemption from making welding
heat-affected zone micro-structure or the safety of procedure tests by submitting previously
the pipeline or pipework. approved welding procedures for inspection by
the employer, or
13.1.5 Prevention of unsatisfactory micro-structures.
The flow of product through the pipe may exert a b) satisfactorily carry out the relevant welding
considerable cooling effect upon the weld area which procedure test(s) as detailed below.
may result in the weld and/or its heat-affected zone When required as in b) above, the approval and
having an unsatisfactory micro-structure. High flow testing of welding procedures should consist of the
rates and consequent rapid cooling may lead to following stages.
excessive hardening and the possibility of 1) The contractor should submit to the employer
associated hydrogen cracking in ferritic steels. details of the proposed welding procedure.
Consideration should be given to the effect of heat 2) The employer should indicate his acceptance of
input on the in-service performance of corrosion the proposed welding procedure, after any
resistant pipe. A reduction in the corrosion discussion with the contractor.
resistance of the internal surface can result from
3) Before site welding begins, a test weld using
microstructural changes and oxide scaling.
the procedure should be made by the contractor.
NOTE Welding procedure approval tests carried out in
accordance with this code and witnessed by an independent
inspector may be offered for consideration by other employers
provided that all the provisions have been fulfilled.

8 © BSI 04-1999
Licensed copy: University of Teknologi Mara, University of Teknologi Mara, Version correct as of 13/07/2010 04:34, (c)
BS 6990:1989

4) The quality of the test weld should be NOTE Although it is not always possible to simulate content of
determined by non-destructive and destructive pipe, temperature of pipe and its contents, and pressure and flow
rate (see items t), u) and v) in Table 1), these are parameters
testing after the weld has been allowed to cool to where changes can affect the relevance of a welding procedure to
ambient temperature in simulated site conditions a particular situation (see items q), r) and s) in Table 2), and
and held for either: should therefore always be carefully checked.

i) 24 h after completion of welding; or Procedure approval tests should be carried out


using a pipe and fitting of similar specification and
ii) a duration specified by the employer.
composition as those for the pipe and fitting on the
If water spraying to cool the pipe will be used on actual job. Procedure approval tests should be
site to facilitate rapid inspection the same carried out on one of the following:
conditions should be simulated in the welding a) a pipe and fitting of the same respective
procedure approval. outside diameters and thicknesses as those to be
5) For the procedure to be approved, the results of used for the actual job; or
the tests on the welds should show that sound
b) when approved by the employer, a pipe and
welds having the required mechanical properties
fitting of diameters and thicknesses from the
can be made using these procedures.
same respective groups in Table 1 c) and
6) Recorded details for each welding procedure Table 1 d) as those to be used for the actual job.
approval test should be submitted by the c) when approved by the employer, use of a plate
contractor to the employer for his acceptance
butt joint to simulate a longitudinal butt weld.
(see 13.3).
All weld runs should be cleaned until free from slag
7) The agreement of the statutory authority
and visible flaws prior to the deposition of
should be obtained when required.
subsequent runs. Weld stop/start positions should
13.3 Records be staggered.
The details of each approved procedure should be Welds should be inspected by the employer during
recorded and should show the complete results of the deposition of individual weld runs to ensure, as
BSI

the procedure approval tests. All documentation far as possible, that the procedure employed is
relating to procedure approval welds including the consistent with that specified.
test results (see 13.6) should be submitted to the 13.5 Changes affecting procedure approval
employer for acceptance prior to the commencement (essential variables)
of the approval of welders. The documentation
should include authenticated results of mechanical When any of the changes given in Table 2 are made
tests and a chemical analysis carried out on the to a welding procedure, it should be regarded as a
parent metal used for procedure approval. new welding procedure and as such should be fully
re-approved.
The period for which records should be kept should
be specified by the employer. 13.6 Testing of joints for procedure approval
13.4 Welding procedure Except for the hardness survey, procedure approval
test joints should be tested and assessed in
During the establishment of a welding procedure,
accordance with BS 4515 or BS EN 288-3 as
sufficient development work should be done, appropriate. Consideration should be given to
including such simulation as is necessary, to show carrying out any special tests relevant to the service
that the procedure is safe. Alternatively it should be
conditions, e.g. corrosion.
shown that there is adequate documentary evidence
from authenticated sources that the procedure is For the hardness survey for ferritic steels the
safe. testing method and requirements should be in
accordance with BS 4515.
Where welding procedure tests are undertaken they
should adequately reflect the conditions that would
be encountered when the welding is done. In
particular the effect on weld quality and service
performance of such parameters as the product, its
flow, pressure and temperature, should be
considered. If the simulation test uses actual
product it is essential that the safety of the
simulation is carefully considered (see section 2).
The welding procedure should include those items
detailed in Table 1.

© BSI 04-1999 9
Licensed copy: University of Teknologi Mara, University of Teknologi Mara, Version correct as of 13/07/2010 04:34, (c)
BS 6990:1989

Table 1 — Welding procedure details


a) Welding process The specific arc welding process using a manual,
semi-automatic or mechanized process or a combination of
those processes.
b) Material specification Pipe and fitting specifications.
c) Pipe diameter group and fitting diameter The groups for outside diameter of pipes and inside
group (see 13.4) diameter of fittings are:
Up to and including 114.3 mm
Over 114.3 mm
d) Pipe thickness group and fitting thickness The thickness groups for pipes are:
groups (see 13.4) 5 mm up to and including 12.5 mm
Over 12.5 mm up to and including 25.0 mm
Over 25.0 mm
The thickness groups for fittings are:
Up to and including 12.5 mm
Over 12.5 mm up to and including 25.0 mm
Over 25.0 mm
e) Joint configuration 1) Longitudinal joint preparation including shape of
groove, angle(s) of bevel, size of root face, width of root gap
and use of backing material.
2) Shape and dimension of fillet welds.
f) Filler metal and number of runs 1) Size, trade name and classification of filler metal for
each run.
2) Number and sequence of runs.
BSI

g) Shielding gas and flow rate Composition of gas and flow rate.
h) Electrical characteristics Current (a.c. or d.c.), polarity, voltage and current value
for each size of electrode or filler metal.
The type and model of the welding power source and the
type and length of the secondary cable should be recorded.
i) Pipe and fitting position For pipe:
1) Within 20° of horizontal. Pipe containing test weld to be
fixed horizontally.
2) Within 20° of vertical. Pipe containing test weld to be
fixed vertically.
3) Between 20° to vertical and 20° to horizontal. Pipe
containing test weld to be fixed at 45° to vertical.
For fitting:
For any of above pipe positions, fitting to be positioned as
for actual job.
j) Direction of welding Vertical-up or vertical-down; torch or gun leading or
trailing.
k) Number of welders See item r).
l) Partially completed weld Minimum number of runs before joint is allowed to cool to
ambient temperature.
m) Cleaning Whether by power driven or hand tools.
n) Preheating Method, minimum and maximum temperatures,
temperature control and method of temperature
measurement [see item s)].
o) Interpass temperature Minimum and maximum temperatures.
p) Temper bead technique Technique details when applied.
q) Welding heat input Full details of relevant parameters, including run-out
length, weaving and speed of travel.

10 © BSI 04-1999
Licensed copy: University of Teknologi Mara, University of Teknologi Mara, Version correct as of 13/07/2010 04:34, (c)
BS 6990:1989

Table 1 — Welding procedure details


r) Sketches and tabulations Sketches on separate detail sheets showing diameter and
thickness of pipe and fitting, joint configuration, weld run
sequence, number of welders and electrical
characteristics.
s) Ambient temperature Minimum ambient temperature below which preheating
is to be applied [see item n)].
at) Content of pipe Product conveyed by the pipe.
au) Temperature of pipe and its contents Temperature range of pipe and its content at the time of
welding.
av) Pressure and flow rate of content of pipe Pressure range and flow rate range of content of pipe at
the time of welding.
a
These parameters cannot always be simulated in a welding procedure test, but should always be carefully checked, as any
changes may affect welding procedure approval (see note to 13.4 and items q), r) and s) of Table 2).

Table 2 — Changes affecting procedure approval (essential variables)


a) Welding process Any change from one arc welding process to another.
b) Material specification Any change in specification of steel for pipe or fitting.
c) Outside diameter of pipe or inside Any change in diameter or thickness of pipe or fitting,
diameter of fitting or thickness except as permitted in 13.4.
d) Joint configuration Any change in joint configuration outside specified
tolerances.
BSI

e) Filler metal type A change from one trade name or classification to another.
f) Filler metal size An increase or decrease in diameter of electrode or filler
metal.
g) Shielding gas and flow rate Any change in gas, gas mixture or flow rate.
h) Electrical characteristics Any change in type of current (a.c., d.c.) or change in
polarity.
i) Pipe and fitting position Any change in pipe position outside the group in which
approval was obtained [see Table 1 i)] or any change in
fitting position greater than 20°.
j) Direction of welding Any change in direction.
k) Number of welders Any change in the number of welders.
l) Partially completed weld Any change in minimum number of runs.
m) Preheating Any change to the approved procedure.
n) Interpass temperature Any change to the temperatures.
o) Temper bead technique Any change to the approved procedure.
p) Welding heat input Any change in the welding parameters that would result in
a change of heat input greater than 10 %.
q) Content of pipe Any decrease in the flash point of the product conveyed by
the pipe.
r) Temperatures of pipe and its content Any change beyond the range specified in the temperature
of the pipe and its content at the time of welding.
s) Pressure and flow rate of content of pipe Any increase in pressure or any change in flow rate of
content of pipe at the time of welding to outside of the
specified range.

© BSI 04-1999 11
Licensed copy: University of Teknologi Mara, University of Teknologi Mara, Version correct as of 13/07/2010 04:34, (c)
BS 6990:1989

14 Approval and testing of welders The fitting should be located to avoid minor flaws in
the pipe. Where circumstances do not permit a
14.1 General
change of location, precautions should be taken to
It is essential that any welder appointed to work on prevent the serviceability of the pipe being affected.
pipe containing hazardous fluids is familiar with the 15.4 Prior to welding the weld area should be
precise techniques involved. For the purpose of this properly identified and non-destructively inspected
code, the welder who makes the approved manual for:
welding procedure test is considered to be
sufficiently experienced in the appropriate welding a) diameter and ovality where applicable;
process and technique not to require testing in b) actual pipe thickness;
accordance with this clause. c) presence of external or internal corrosion;
When there is any doubt on this matter the welder d) laminations or inclusions in the region where
should satisfactorily carry out a demonstration welding will be carried out (see 15.6);
weld. Consideration should be given to the need for e) soundness of any existing weld in the vicinity
an approval test in the special techniques referred of the welding area in cases where the distance to
to in the approved procedure. the nearest weld is less than 6 times the
14.2 Butt welds thickness of the thicker material;
A welder appropriately approved on either a butt f) build-up of process of deposits or fouling inside;
joint or a branch connection to BS 4515 or particular attention is required for dead ends of
BS EN 287-1 should be considered approved for pipes where deposits may restrict the flow.
welding butt joints to this code within the extent of Ultrasonic and radiographic examination should be
his approval. used for the inspection prior to welding. Previous
14.3 Fillet welds inspection reports should also be evaluated, in order
to assess the soundness of the pipe material in the
A welder appropriately approved on a fillet weld to
vicinity of the welding area.
BSI

BS 4515 or BS EN 287-1 should be considered


approved for making fillet welds to this code within 15.5 The area of pipe beneath the fitting location
the extent of his approval. A welder approved on a should be examined ultrasonically to ensure
butt joint to BS EN 287-1 should not be considered freedom from lamination which might interfere
approved for making fillet welds to this code. with plugging operations.
14.4 Branch connections The area should be scanned on a 75 mm square grid,
and ultrasonic testing practice should be in
A welder appropriately approved on a branch accordance with BS 5996. Lamination of an area
connection to BS 4515 or BS EN 287-1 should be exceeding 500 mm2 should be considered
considered approved for welding branch connections unacceptable for welding.
to this code within the extent of his approval.
15.6 The areas where the attachment welds are to
15 Preparation of pipe be made should be subject to 100 % ultrasonic
examination and magnetic particle flaw detection
15.1 The identity of the pipeline should be over a band of 150 mm minimum width centred over
confirmed as being correct and a tag should be the proposed weld locations to check freedom from
attached. Paint or wrapping material should be laminations which might prejudice welding and to
carefully removed from the pipe in the proposed confirm adequate pipe thickness. Where seamless
area of attachment on each side of the proposed pipe is under examination penetrant testing
location of the fitting to ensure that there is no (see 27.4) may be used as an alternative to magnetic
interference with the welding operation. particle inspection. The ultrasonic technique should
15.2 The exposed pipe should be checked to ensure be as in 15.5 and the magnetic particle flaw
that the dimensions are within acceptable limits detection as in 27.3. Lamination should not
related to the fitting to be used at that particular exceed 25 mm in any direction.
location.
15.3 The section of pipe to which the fitting is to be
attached should be thoroughly cleaned with a wire
brush for a distance extending 150 mm on each side
of the location of the fitting. After cleaning, the pipe
should be visually examined for surface
imperfections, pitting and any signs of mechanical
damage.

12 © BSI 04-1999
Licensed copy: University of Teknologi Mara, University of Teknologi Mara, Version correct as of 13/07/2010 04:34, (c)
BS 6990:1989

15.7 Positive confirmation of pipe thickness should 17 Fusion faces


be obtained over the complete length of the weld. If
Immediately prior to welding, the fusion faces and
the measured pipe thickness is less than the
the adjacent material should be free from fins,
nominal pipe thickness, allowing for the negative
planar defects not complying with clause 28, tears,
tolerance, the employer should undertake a design
study to determine whether such a thickness is moisture, scale, rust, paint, grease or other foreign
acceptable. If the measured pipe thickness is less matter. Cleaning to base metal should extend for at
least 25 mm from the edge of the fusion faces on
than 5 mm the conditions are outside the scope of
both the internal and external surfaces of the parts
this code.
to be welded.
15.8 Where there is a delay of more than 48 h
between the operations specified in 15.3 to 15.7 18 Preparation for encirclement
inclusive and the start of welding, consideration fitting
should be given to repeating some of these checks
before the start of welding. 18.1 Any alteration to a weld preparation profile
15.9 When a fitting that is to be subsequently supplied on a fitting should be carried out by
drilled after attachment is being located on a grinding to a smooth finish with a disc grinder. A
pipeline, care should be taken to avoid where typical weld preparation is shown in Figure 2.
possible weld seams within the drilling area. If the Any defects should be removed by grinding and
pipeline is constructed of longitudinally or spirally repaired where necessary by welding to a procedure
welded pipe, then the choice of location should be accepted by the employer.
made so that the area where the pilot drill will 18.2 If backing material, permanent or temporary,
penetrate is clear of the weld seam. is to be used, it should be compatible with the fitting
15.10 The reinforcement of any welds to be covered material and should be slid into the machined recess
by the fitting should be ground flush with the pipe at the roots of the longitudinal seams before
surface over a length extending 50 mm beyond each clamping the two halves of the fitting together.
BSI

side of the fitting. This operation should be carried Permanent backing material should be of a
out under constant supervision. sufficient length to provide at least 50 mm overlap
It is preferable for fittings not to be located at or at each end of the fitting. To each overlap steel
within a distance of 6 times the thickness of the plates should be attached to form run-on/run-off
thicker material to existing welds in the pipe. plates at the ends of the longitudinal seams, as
shown in Figure 3.
15.11 The area should be thoroughly cleaned in
preparation for the next operation. Where there is The following types of backing material should not
undue delay between this cleaning and the start of be used.
welding, the appropriate areas should be suitably a) Backing material with integral projections or
protected and re-cleaning should be carried out if spacers intended to facilitate the establishment
necessary. and maintenance of root gap.
b) Backing material fitting tightly into machined
16 Inspection of fittings recesses with square or sharp corners.
The following checks should be carried out on the c) Backing material of a shape that restricts
fitting to be attached. contraction.
a) Dimensional check of the fitting. 18.3 The two halves of the tee fitting should be
b) A check that the correct certificate for the clamped together around the pipe. A typical yoke
fitting is available. type clamp is shown in Figure 4.
c) A check that all weld preparations are clean After clamping the tee fitting, all visible surface
and are in accordance with the fitting grease in and around the recess of the branch flange
specification. should be removed.
The gap where the branch abuts the pipe should be
packed with clean rag to prevent any grease
contained within the recess melting during
preheating and running down on to the pipe and
into the longitudinal weld preparations.

© BSI 04-1999 13
Licensed copy: University of Teknologi Mara, University of Teknologi Mara, Version correct as of 13/07/2010 04:34, (c)
BSI

14
BS 6990:1989

Figure 2 — Typical longitudinal weld preparation for fitting: dimensions and tolerances

© BSI 04-1999
Licensed copy: University of Teknologi Mara, University of Teknologi Mara, Version correct as of 13/07/2010 04:34, (c)
BSI

© BSI 04-1999
Figure 3 — Attachment of run-on/run-off plates to backing material

15
BS 6990:1989
Licensed copy: University of Teknologi Mara, University of Teknologi Mara, Version correct as of 13/07/2010 04:34, (c)
BSI BS 6990:1989

Figure 4 — Typical yoke-type clamp for encirclement tee fittings

19 Preparation for set-on fitting 19.2 The fitting should be set up on the pipe with a
root gap where appropriate. The fitting should be
19.1 Any alteration to the radius of a fitting where
fixed in position by clamping or tack welds. All tack
it contacts the pipe should be carried out by
welds should be made using the welding procedure
grinding, or, for large modifications, by a thermal
to be employed for the root run and the ends should
cutting method approved by the employer. The final be dressed to a taper to ensure full fusion with the
preparation should be a smooth finish using a disc root run.
grinder.
20 Alignment of flanged fittings
When welding a flanged fitting to a pipe, care should
be taken to ensure that the flange is kept parallel
and square to the pipe.

16 © BSI 04-1999
Licensed copy: University of Teknologi Mara, University of Teknologi Mara, Version correct as of 13/07/2010 04:34, (c)
BS 6990:1989

NOTE During manufacture of the fitting strict tolerances 24 Preheating


should have been maintained regarding the alignment of the
flange to the branch and the branch to the body of the fitting. To preheat pipelines or pipework effectively,
particularly where product flow is maintained for
21 Working clearance safety reasons during welding and associated
The working clearance around the pipe at the weld operations, heat input may need to be high. It is
should be not less than 400 mm. important therefore that careful consideration is
given to those factors that may affect the quality
When the pipe is welded in a trench the bell hole
and strength of the subsequent weld and to the
should be of sufficient size to provide the welder or
safety of the preheating operation (see section 2).
welders with ready access to the joint. (See also 6.4.)
The detailed procedure should take into
22 Stray arcs consideration the following factors.
Arcs shall be struck only on fusion faces and contact a) The maximum preheating temperature.
of the electrode or of the non-insulated parts of the b) The minimum interpass temperature, below
electrode holder with the outer surface of the pipe or which no welding may proceed.
fitting should be avoided. c) Any soak periods to ensure adequate
An earth saddle making good electrical contact with through-wall heating.
the workpiece should be placed conveniently near to d) The type and size of the heating source.
the weld for striking the electrode where this is e) The method of control of heating, including
necessary for removing slag from the tip or to emergency shut-down procedure.
facilitate the starting of the arc. Electrode holders
should be of the fully insulated type. f) The extent of the zones to be preheated
including the limits of any localized heating
Places where any stray arcs have accidentally applied as welding proceeds.
occurred should be either repaired or rejected, as
approved by the employer. g) The type and distribution of temperature
BSI

measuring devices.
Where permission to repair arc strikes has been
given by the employer, the procedure should h) The frequency of temperature measurement.
include, but not necessarily be limited to, the i) Details of any supplementary heating placed
mechanical removal of the affected material, upstream of the preheating zone.
blending of the excavation, checking by magnetic
particle or penetrant inspection as appropriate and 25 Sequence of welding
confirmation that the thickness of the pipe or fitting 25.1 As the type of fitting used may vary
is within permitted tolerances. considerably, it is not possible to give definitive
Where the minimum thickness is below tolerance, rules to suit each fitting. The following are basic
repairs to an approved welding procedure may be guidelines.
carried out and subjected to further non-destructive a) The amount of in-situ welding should be kept
testing. to a minimum, i.e. a maximum amount of
pre-fabrication should be carried out off site by
23 Weather conditions normal welding techniques. This work should be
The employer should state when welding should not subject to thorough inspection, and where
be done because prevailing weather conditions practicable, pressure testing. Certification to
would impair the quality of the completed weld. cover this work should be available.
Welding should not be done when the quality of the b) Clamping is preferred to tack welding. When
completed weld would be impaired by airborne tack welding is necessary it should be made in
moisture, blowing sands or high winds. positions that do not restrict expansion or
Where necessary protection from the weather can be contraction of the fitting along the longitudinal
provided, welding may be continued. axis of the live or pressurized pipe.
25.2 The in-situ welding may be divided into two
types:
a) Welds which involve a direct connection on to
the live or pressurized pipe.
b) Welds which are separated from the live or
pressurized pipe by an air gap or backing
material.

© BSI 04-1999 17
Licensed copy: University of Teknologi Mara, University of Teknologi Mara, Version correct as of 13/07/2010 04:34, (c)
BS 6990:1989

In general b) type welds will be made before a) type All inspection personnel should have been approved
welds. Every effort should be made to offset by the employer. A record of approved personnel
distortion effects during the welding of b) type should be kept by the employer. This record should
welds, e.g. back-step welding and balanced welding include inspection procedures in which each person
techniques. It is important that after completion of is approved, the authority granting the approval
the first fillet weld the fitting be allowed to cool to and the date of approval.
ambient temperature before welding commences on The method of non-destructive testing used should
the fillet weld at the opposite end of the tee. be capable of producing indications of imperfections
When applicable, run-off plates should be used to which can be accurately interpreted and evaluated
prevent over-welding on to the live or pressurized in order to assess whether the acceptance criteria
pipe. specified in clause 28 have or have not been
NOTE Run-off plates should be removed in a controlled manner obtained.
so that there is minimal damage to the pipe. Operators of all types of non-destructive
For type a) welds, welding without weave and with examination equipment should be required to
strict control of electrode diameter, current and demonstrate to the approval of the employer the
travel speed, are normal requirements. capability of the examination procedure to detect
Bridge welding of gaps between the fitting and rejectable imperfections and their ability to make
pipe is not recommended unless the gap is less correct interpretations of the indications given by
than 1.5 mm. Weld buttering techniques should be the equipment.
used to reduce any gap. The results of the non-destructive examination
With both a) and b) weld types, weld stop-start should be recorded and should include a clear
positions should be overlapped and should not indication of the location, size and nature of all flaws
coincide between adjoining weld layers. Where detected.
necessary, grinding should be carried out to 27.2 Visual examination
maintain a smooth profile.
BSI

Visual examination (see BS 5289) should be


26 Inter-run cleaning maintained throughout the welding cycle, including
checking that preheating requirements are met,
Each run of weld metal should be thoroughly inter-run cleaning is properly carried out and an
cleaned, either by hand or power tools, before a acceptable weld profile is being achieved.
further run is applied.
All welds should be visually examined on
Visible flaws such as cracks, cavities and other completion and should have a good profile with
deposition faults should be removed and particular positive reinforcement. The acceptance criteria in
attention paid to the cleanliness of the junctions clause 28 should be applied.
between the weld metal and the fusion faces before
27.3 Magnetic particle flaw detection
deposition of further weld metal.
Clusters of surface porosity, stops and starts and When required by the employer, magnetic particle
high points should be removed by grinding. flaw detection, as described in BS 6072, should be
applied, using an appropriate technique.
Stop and start positions in adjacent runs should be
staggered by at least 20 mm. 27.4 Penetrant testing
When required by the employer, for welds on
27 Inspection austenitic stainless steel pipe, penetrant testing as
27.1 General described in BS 6443 should be used.

All welds should be inspected by visual examination 27.5 Ultrasonic examination


during and after welding. On completion of welding, When required by the employer, ultrasonic
visual examination should be followed by a method examination should be applied to welds as described
or combination of methods of non-destructive in BS 3923-1 using an Examination Level stated by
testing as specified by the employer. the employer, supplemented as appropriate with
NOTE The agreement of the statutory authority may also be the relevant requirements of BS 4515.
required.
Non-destructive testing procedure specifications
should be submitted to the employer for approval
and should be approved prior to the commencement
of welding, usually on procedure weld tests.

18 © BSI 04-1999
Licensed copy: University of Teknologi Mara, University of Teknologi Mara, Version correct as of 13/07/2010 04:34, (c)
BS 6990:1989

28 Non-destructive testing acceptance The form, nature, and size of the imperfection
criteria should be assessed by an appropriately qualified
and experienced person before repairs are carried
The acceptance criteria for non-destructive testing out. It is advisable that the pipe internal pressure is
should be in accordance with the standard to which reduced to 85 % of that during the original welding
the pipeline or pipework was originally constructed, (or to the pressure giving the equivalent of 30 % of
e.g. BS 4515, BS 2633, BS 4677. the specified minimum yield stress of the pipe if the
flaw is of a cracklike appearance) and maintained at
29 Rectification of welds this level until the repair is completed.
29.1 Butt welds An individual repair procedure for the specific flaw
The requirements of BS 4515 should be taken into should be formulated by an appropriately qualified
account but with the following provisos: and experienced person. The details of this should
include, but not be limited to, the following
a) it is preferable to make a local repair to a joint;
information:
b) if the size or nature of the flaw requires
a) maximum internal pressure during repair;
removal of a weld then the entire fitting should be
removed, remachined and the reweld treated as a b) method of flaw removal;
completely new weld. c) depth of flaw that can be removed (advisable to
29.2 Fillet welds be related to a) above);
29.2.1 Imperfections confined to the weld metal d) action to be taken if flaw depth exceeds c)
alone. The requirements of BS 4515 should be above;
followed except that extensive flaws may be e) method of restoring wall thickness.
repaired in sections to retain the preheating If there are any doubts as to the safety of such a
temperature within a manageable area. repair option then the entire weld and fitting should
29.2.2 Imperfections positioned within the original be abandoned and an alternative course of action
BSI

pipe surface. Imperfections found which extend taken.


below the original pipe surface should be treated
with utmost caution.

© BSI 04-1999 19
Licensed copy: University of Teknologi Mara, University of Teknologi Mara, Version correct as of 13/07/2010 04:34, (c)
BSI

20
blank
Licensed copy: University of Teknologi Mara, University of Teknologi Mara, Version correct as of 13/07/2010 04:34, (c)
BS 6990:1989

Publications referred to

BS 499, Welding terms and symbols.


BS 499-1, Glossary for welding, brazing and thermal cutting.
BS 638, Arc welding power sources, equipment and accessories.
BS 679, Specification for filters for use during welding and similar industrial operators.
BS 2633, Specification for Class I arc welding of ferritic steel pipework for carrying fluids.
BS 3923, Ultrasonic examination of welds.
BS 3923-1, Methods for manual examination of fusion welds in ferritic steels.
BS 4105, Specification for liquid carbon dioxide, industrial.

BS 4515, Specification for welding of steel pipelines on land and offshore.


BS 4677, Specification for arc welding of austenitic stainless steel pipework for carrying fluids.

BS 5289, Code of practice. Visual inspection of fusion welded joints.

BS 5996, Specification for acceptance levels for internal imperfections in steel plate, strip and wide flats,
based on ultrasonic testing.
BS 6072, Method for magnetic particle flaw detection.
BS 6443, Method for penetrant flaw detection.
BS 8010, Code of practice for pipelines.
BS 8010-1, Pipelines on land: general.
CP 2010, Code of practice for pipelines.
BSI

CP 2010-2, Design and construction of steel pipelines in land.


BS EN 167, Personal eye protection — Optical test methods.
BS EN 168, Personal eye protection — Non-optical test methods.
BS EN 169, Specification for filters for personal eye-protection equipment used in welding and similar
operations.
BS EN 287-1, Approval testing of welders for fusion welding — Part 1: Steels.
BS EN 288-3, Specification and approval of welding procedures for metallic materials — Part 3: Welding
procedure tests for the arc welding of steels.
BS EN 439, Welding consumables — Shielding gases for arc welding and cutting.
BS EN 30012-1, Quality assurance requirements for measuring equipment — Part 1: Metrological
confirmation system for measuring equipment.
BS EN 50078, Torches and guns for arc welding.
BS EN 60974-11, Arc welding equipment — Part 11: Electrode holders.
BS EN 60974-12, Arc welding equipment — Part 12: Coupling devices for welding cables.
BS EN ISO 9000, Quality management and quality assurance standards1).

1)
Referred to in the foreword only.

© BSI 04-1999
Licensed copy: University of Teknologi Mara, University of Teknologi Mara, Version correct as of 13/07/2010 04:34, (c)
BS 6990:1989

BSI — British Standards Institution


BSI is the independent national body responsible for preparing
British Standards. It presents the UK view on standards in Europe and at the
international level. It is incorporated by Royal Charter.

Revisions

British Standards are updated by amendment or revision. Users of


British Standards should make sure that they possess the latest amendments or
editions.

It is the constant aim of BSI to improve the quality of our products and services.
We would be grateful if anyone finding an inaccuracy or ambiguity while using
this British Standard would inform the Secretary of the technical committee
responsible, the identity of which can be found on the inside front cover.
Tel: 020 8996 9000. Fax: 020 8996 7400.

BSI offers members an individual updating service called PLUS which ensures
that subscribers automatically receive the latest editions of standards.

Buying standards

Orders for all BSI, international and foreign standards publications should be
addressed to Customer Services. Tel: 020 8996 9001. Fax: 020 8996 7001.

In response to orders for international standards, it is BSI policy to supply the


BSI implementation of those that have been published as British Standards,
unless otherwise requested.

Information on standards
BSI

BSI provides a wide range of information on national, European and


international standards through its Library and its Technical Help to Exporters
Service. Various BSI electronic information services are also available which give
details on all its products and services. Contact the Information Centre.
Tel: 020 8996 7111. Fax: 020 8996 7048.

Subscribing members of BSI are kept up to date with standards developments


and receive substantial discounts on the purchase price of standards. For details
of these and other benefits contact Membership Administration.
Tel: 020 8996 7002. Fax: 020 8996 7001.

Copyright

Copyright subsists in all BSI publications. BSI also holds the copyright, in the
UK, of the publications of the internationalstandardization bodies. Except as
permitted under the Copyright, Designs and Patents Act 1988 no extract may be
reproduced, stored in a retrieval system or transmitted in any form or by any
means – electronic, photocopying, recording or otherwise – without prior written
permission from BSI.

This does not preclude the free use, in the course of implementing the standard,
of necessary details such as symbols, and size, type or grade designations. If these
details are to be used for any other purpose than implementation then the prior
written permission of BSI must be obtained.

If permission is granted, the terms may include royalty payments or a licensing


agreement. Details and advice can be obtained from the Copyright Manager.
BSI Tel: 020 8996 7070.
389 Chiswick High Road
London
W4 4AL

Potrebbero piacerti anche