REQUEST FOR INFORMATION

RFI : OO5

Attention : Anantha Chittur , Kiran Acharya Fax:


Email:
Company : BAYAWEAVER Page: 1 of 1

Cc :Palanivelu P N , Aum Mavi , Sundar Kandasamy , Tobias Hartmann , Ajay Gupta , Mujeeb Attachments: 1 page(s)

Business Sector / Project : Buildings Project Nos: I1252

Discipline Key Word:


Civil Tower-A area , Retaining wall detail Date Response Required 0 2 - 0 8 - 2 0 1 8
Structural Location / Area:
Architectural Bassemet - 2 Internal Review initial

Mech Doc. No (Drg / Specs):


E&I Construction Manager
Others (specify) Engineering Manager
Date: 30-07-18
By: Sanjay Shee

Tower-B, Bsement - lvl. - 2

1. We refer to attached site level plan along with sections for edge condtitions showing capping beam and retaining wall levels. The dwg. also highlights the
extent of capping and retaining wall that has been cast till date. Also attached is the retaining wall structural detail that has been followed at site. Please advise if
we can adopt the same structural detail for retaining wall casting for balance portion.

Note: No earth filling has been done above capping beam level at site.

Response with / without * Attachments. No(s) of Attachment

Name: Position: Signature: Date:

Review by Engineering Manager Y N Estimated


Does Response Close out RFI? Time *
Yes Cost *
No if not issue New RFI (state New RFI No.)

Name: Signature: Date:


Time or Cost Impact Authorisation
Proceed Authorised By: Date:
Do not Proceed
Distribution
Client Construction Manager Commercial Manager
Project Manager Consultant others (specify)
* Incl. Attachment if necessary

Jul ' 18 Page 1 of 1