Sei sulla pagina 1di 8

IEEE PES 2009 PSCE 1

Automatic Generation Control System for an


Industrial Facility with Onsite Generation
JJ Dai M. IEEE, Hugo Castro, Jianjun Guo, Tanuj Khandelwal M. IEEE,
Shervin Shokooh M. IEEE, Farrokh Shokooh Fellow IEEE
Operation Technology, Inc.

can result in interchange power deviation from scheduled


Abstract — In a competitive electrical market, an onsite values. The primary control process being unaware of
generation facility must be equipped with an on-line automatic scheduled interchange flows will be unable to compensate for
generation control (AGC) system to maintain the frequency, this deviation.
security, and economical operation within the plant while
Load Frequency Control (LFC) function is then deployed as
honoring the scheduled power exchange with the power grid. A
successful AGC system requires support from State and Load
the secondary control process to maintain the frequency and
Estimation (SLE) and Economical Dispatch (ED) engines, and a interchange errors within an acceptable bound. LFC adjusts
Load Frequency Control (LFC) scheme. This paper reports the load reference set points of governors of selected units in the
development and implementation of a comprehensive and fully control area and correspondingly adjusts their outputs.
functional AGC system in an industrial facility that has both Each control area measures the frequency and the net
onsite generation and connection to the power grid. The installed interchange, typically at every 2–4 second intervals. These
system has an advanced monitoring system to provide SLE measurements are used to evaluate the frequency and the net
results and is able to perform periodical on-line ED calculation of interchange errors. The net interchange error is defined as the
co-gens based on real-time system operating conditions and tariff
difference between the net actual and the net scheduled
with the power grid. The ED results are used as a base for LFC
to perform minute-to-minute control actions to achieve overall
interchange with the connected control areas. Schedules are
system economical and stable operation requirements. available and tracked using an Interchange Scheduling (IS)
application. The area control error (ACE) is then computed by
Index Terms—Onsite Generation Facility, Automatic taking into account the effects of frequency bias; it is the basis
Generation Control, State and Load Estimation, Interchange for the control signals sent by the control area to the
Scheduling, Economical Dispatch, Load Frequency Control, generators participating in AGC.
Power Grid Contract, Tariff. Another major operating criterion is to minimize frequency
and interchange errors while minimizing the total cost of
I. INTRODUCTION electric production, transmission, and distribution. Economic
As the system loading changes, the generator’s ability to Dispatch (ED) optimizes the available mix of generation
track the load variation is limited by physical and operational resources and, as a result, maximizes the use of low cost
considerations resulting in an imbalance between the actual sources of electricity, while recognizing any operational
and the scheduled generation levels. limits.
Any imbalance between power generation and consumption Even though ED and LFC have different time horizons,
will result in a frequency change within the network of the they are not independent. ED transfers optimal unit base
synchronous area. As a result, over time, the system frequency points and economic participation factors to LFC. This
will continue to deviate from its set-point values when left interaction between LFC and ED is aimed at minimizing the
uncorrected. The magnitude of the frequency error is an fuel cost, while reducing the area control error (ACE) and the
indication of how well the power system is capable of number of unit control actions. The AGC system discussed
balancing the system loading. consists of ED and LFC algorithms.
Within a few seconds of breaching the set point dead band, This paper describes the development and implementation
the primary speed control or governor serves to damp out the of a state-of-the-art AGC system that utilizes a data
frequency excursions and to stabilize the frequency at a new acquisition system which continuously updates a computer
value, which is different than the synchronous frequency. At based real-time system model. This system produces the
the same time, the system dispatcher may coordinate power optimum solution for generation dispatch by combining output
exchange between various control areas or the power grid from Economic Dispatch, Interchange Scheduling and Load
based on hour-ahead, day-ahead or longer term contracts. Any Frequency Control illustrated in Fig. 1.
load change within the network or area when left uncorrected

Authors are with Operation Technology, Inc. (OTI), 17 Goodyear, Suite,


100, Irvine, CA 92618, USA (JJ Dai's e-mail: jjd@etap.com).

978-1-4244-3811-2/09/$25.00 ©2009 IEEE


IEEE PES 2009 PSCE 2

understandable interface. This interface, which will be used to


operate and coordinate the system, must be graphical and
tabular with the means to visualize the electrical distribution
via the system one-line diagram. The user interface must also
provide a summary of generation, loading, frequency, and set-
points for all participating units.

IV. LOAD AND STATE ESTIMATION


To perform generation fuel cost economical dispatch,
system operating states need to be determined first. These
states include system configurations, operating loads, non-
controllable variables and their settings (for example,
transformer fixed taps, power grid operating voltage levels,
fixed generation active and reactive powers, fixed capacitor
bank var ratings, etc.). System configurations can be
determined by monitoring circuit-breaker and switch status.
Non-controllable variable settings are also readily available.
Fig. 1. AGC System Data Flow Given the vast number of loads in a typical industrial
system, it is infeasible to have meter reading at every load
II. AGC SYSTEM REQUIREMENTS point. Hence, a special estimation method has to be utilized in
The inputs required by the AGC system include real-time order to attain essential data and calculate the missing
data and network topology. System data is collected from the information to ensure that the system is observable.
data acquisition system. This real-time data includes power The traditional state estimation methods (based on least
frequency, and voltage measurements at each generation, squares minimization method) only estimate bus voltages
power grid, interchange locations, main feeders, and critical (both magnitudes and phase angles). Since this method
loads. In addition, switching device (circuit breakers, switches, demands a relatively high meter redundancy ( roughly defined
etc.) states are monitored throughout the system to provide the as the ratio of metering points to the number of buses in the
latest system configuration status. system) and is incapable of handling large numbers of
The other important parameters are the system topology and unmeasured loads, it is virtually inapplicable to industrial
electrical data. System topology and electrical data include: A) power systems.
Interconnection information for all generators, feeders, and The new method expands the system states to include loads.
loads. B) Ratings and settings for all components involved, Thus, using the available measurement data (generation,
such as tap settings for transformers, operating mode of power grid exchange, line flows, bus voltages and partially
generators (droop, Isochronous), line/cable types, measured loads), the system operating voltages and loads will
configuration, impedance, and capacity. C) Metering be estimated collectively. This method is called State and
instrumentation including potential and current transformers. Load Estimation. Equation (1) shows the objective function
for SLE:
III. AGC SYSTEM COMPONENTS

∑  ,


  
(1)
The AGC system components consist of SLE, IS, ED, and where  is a variable constrained by the load flow equation at


LFC. Real-Time data and system topology are fed to the State   
the point corresponding to each measurement  .  is the
and Load Estimation (SLE). SLE estimates the rest of the 

function of bus voltage and load . Metering point is from
missing parameters such as non-monitored power flows in less 
1 to . Apply network equation, measurement data set  ,  
critical feeders, consumption for loads, voltage levels at every and an appropriate optimization algorithm to equation (1), bus
connection point in the system. The results are then fed to the voltage v and all system loads l will be solved.
ED module as initial conditions. The ED takes the generator The one-line diagram in Fig. 2 shows a substation at an
heat rate curves to determine the efficiency of the unit with industrial facility where typically only the main feeders are
respect to the generated output power. It also utilizes the fuel metered. Assuming that the network model, topological
cost per unit and the power exchange contract as defined relationships, and electrical parameters are properly defined,
through IS application. ED then determines the optimum the loading at each load can be estimated according to the
(most economic) generator outputs which is fed to the Load equation (1) through a specially developed optimization
LFC system. LFC utilizes the ED outputs as the base settings algorithm.
and corrects them for ACE reduction where the final output is
sent to the generator control systems. The voltage set points
are fed to the AVR control and respectively.
All of the above information must be made available to the
system dispatcher in a real-time, easy-to-use, concise, and
IEEE PES 2009 PSCE 3

VI. ECONOMICAL DISPATCH


Typical ED deals with a system containing MW
controllable generators to achieve a solution with a minimal
overall generation fuel cost objective:
∑   

 ೔ (2)
subject to:
,  0 (3)
 ,    ,  (  1,. . .,   ) (4)

where ೔ is the active power generation from the  

generator, the fuel cost function of the generator,  the 
number of generators on MW control, the system state 
Fig. 2. Example of SLE in a Substation with Partially Measured Loads.  
variable, the control variable, and  the number of control
variables. Equation (3) is load flow equation, and equation (4)
SLE usually runs in a time interval of 1 to 5 seconds, is the control variable range limits.
depending on nature of system transients. In certain types of To ensure ED solution is physically feasible, steady-state
industries, such as smelting plants, where system loading is security constraints should be applied to the optimization
changed erratically, a smaller time step between consecutive problem:
SLE runs should be used to capture the load variations. ,   
,  ( ) (5)  1, .. . ,
Whereas in industrial plants with gradual loading variation,
where y is the constrained variable, usually line flow and bus
allows for a use of a larger time step between the SLE runs.
The SLE result defines a complete system operating state

voltage magnitude, and is the number of constrained
variables.
which in turn is used by the ED engine.
In an industrial power system, the network is normally
connected to one or several power grids at a common point
V. INTERCHANGE SCHEDULING
referred to as the point of common coupling (PCC). Under
In a competitive power market, industrial power systems such condition, ED optimization objective needs to be
with onsite generation are allowed to participate to a certain expanded to include the energy cost (power importing per unit
extent in the market operation depending on the regulations in of time) through the PCC boundary into the system:
the regional and national administrations. To bring in the
highest incentive as possible to its system, an industrial power
 ∑    ∑ !  "

  (6)

 

system would schedule a power exchange transaction with the where  is the power exchange at the # PCC, ! the per
ೕ


unit energy price at the PCC, and  the number of PCC. Note
power grid based on its onsite generation cost and the
that ! can be bilateral, taking a positive value when  $ 0

published energy price. The schedule specifies the location(s)
ೕ
of the transaction, type of the transaction (buy or sell), and
cost of the transaction (tariff or rate structure), as well as the (importing- power) and a negative value when  % 0 ೕ

duration of the schedule. (exporting).


The exchange schedule is dispatched via the IS system. IS Fig. 4 depicts the model of a facility with onsite generation
provides the capability to schedule energy transfer from one exchanging power with the power grid. Once the power
location to another while considering energy usage, wheeling, exchange schedule is committed via the IS system, the party
scheduling ancillary services, fuel cost, and financial tracking initiating the transaction (in this case, the industrial facility
of energy transactions. Fig. 3 illustrates a simplified data flow with onsite generation selling power to the connected power
for an IS system. grid) has to honor the contract. In this case, the ED calculation
is extended to the following constrained optimization problem:
 ∑    ∑ !  "

 

  (7)

 
  (&  1, …, )  (8)
,  0 (9)
  
, (  1,…,  ,   ) (10)
 ,   (  1,. .. ,  )
,  (11)
where equation is added to count for the specified schedule at

power exchange lines with  the scheduled power exchange

at a total of exchange lines.
Fig. 3. Interchange Scheduling System Data Flow
IEEE PES 2009 PSCE 4

VII. LOAD FREQUENCY CONTROL


Load frequency control (LFC) has to achieve two primary
objectives, which are stated below in priority order:
1. Maintain frequency at the scheduled value
2. Maintain net power interchanges with neighboring
control areas at the scheduled values
3. Match generation to load
The first and second objectives are met by monitoring an
error signal, called area control error (ACE), which is a
combination of net interchange error and frequency error and
represents the power imbalance between generation and load
at any instant. Real-time measurements are used to calculate
ACE for each defined area under various modes.
In tie-line bias control, ACE is calculated as:
Fig. 4. A Model of Industrial Power System with ACE  + + 10,- -
    (12)
Onsite Generation & Power Grid Contract. In flat tie-line flow control:
The ED calculation engine is periodically called by AGC
ACE  + +
  (13)
either at a pre-specified time or whenever the special events In flat frequency control:
are trigged such as changes in the schedules, variations in fuel ACE  10,- -
  (14)
cost, generator tripping, or major configuration changes. At
- +
where  is the actual frequency,  is the actual net
each execution, the most recent SLE result is used in the load
-
interchange;  is the scheduled frequency of the subsystem,
flow equation (9) and the schedules are applied as line
equality constraints in equation (8). The result is taken into the
+  is the scheduled net interchange of the area, , is the
frequency bias.
minimization problem of equation (7) which is solved
This raw ACE must be filtered or smoothed such that
simultaneously with other inequality constraints due to control
excessive and random changes in its value are not translated
range limits from equation (10) and steady state security limits
into control actions. Since these excessive changes are
from equation (11). In this process, schedules on the
different for different systems or subsystems, the filtered
interchange lines are honored, steady state security constraints
parameters have to be tuned specifically for each control area.
are met, and all control variables are within their limitation
The processed ACE is then used to obtain the proportional
ranges. The results from ED are the new power generation
plus integral control signal. This control signal is modified by
dispatch set points. The set points are also utilized by LFC to
limiters, dead-bands, and gain constants that are tuned to the
select a new base for the minute-to-minute generation control.
particular system. This control signal is then divided amongst
A functional flow chart for SLE and ED is presented in Fig. 5.
controllable generating units by using participation factors to
obtain unit control errors (UCE).
Do SLE?
The strategy of ACE provides a steady-state target
No according to which a control area meets its own load during
Yes
Meter Data normal conditions in the interconnection, contributes to
frequency regulation, and provides assistance to external areas
Formulate State when necessary. If there is an over generation in any area,
Estimation Model actual frequency will be higher than scheduled value and ACE
will be positive in that area. Intuitively, the action to be taken
Solve SLE Problem will be to reduce area generation. On the other hand, if there is
Eq. (2)
under-generation in any area, actual frequency will be lower
than the scheduled value and ACE will be negative in that
Do ED? area. The obvious solution will be to increase area generation.
On February 1, 1997 the North American Electric
No
Yes Reliability Council (NERC) replaced Control Performance
Load Flow Equation,
Controls, Constraints
Criteria (CPC) with Control Performance Standard (CPS). The
LFC function in addition to calculating ACE also utilizes CPS
Solve ED Problem oriented logics.
Eqs. (7) to (11) CPS1: Whenever a control area has a nonzero ACE and
there is a frequency deviation at the same time, a non zero
Set New Pg Base compliance factor (CF) is created. A positive CF means the
for LFC control area is acting as a burden to the interconnection and
Fig. 5. Functional Flow Chart of SLE and ED. vice versa. A CF value is calculated every clock-minute using
IEEE PES 2009 PSCE 5

one-minute average frequency error and ACE. At the end of


each month, the overall average CF for the past twelve months
is used to derive the area's CPS1 compliance which must have
no less than 100% compliance.
CPS2: This standard requires the average ACE for each of
the six ten-minute periods in an hour must be within a specific
limit called L10 and have compliance no less than 90%.
A two-layer control scheme was adopted for the LFC
function to satisfy NERC standards. The following diagram
(Fig. 6) shows the overall control structure deployed for this
industrial facility. CPS2, CPS1 control outputs have the same
formula:
MW  K ACE K ∑CT/60 4 ACE
Δ      (15)
Fig. 7. Control Scheme Illustration.
where CT is the LFC calculation cycle time, ACE
 is the

current calculated ACE. Defining the 10-minute moving Control outputs can be distributed to regulating generators
average ACE as 56!  , the LFC function will take action
according to the ramping rate, generation margin, and fixed
only when 56! 56!
  and  both break the threshold and
participation factors respectively.
56!  4 56! $ 0
 . The graphical-user interface allows The total adjusting power:
∆  ∆  ∑89:; (16)
system integrators to adjust the threshold to satisfy control    !

objectives. Ramping Rate Approach:


<;=>?=  89:; " ೔

∑ " ೔
∆  (17)

Margin Approach:
<;=>?=  89:;  ! ೔

∑  ! ೔
∆  (18)

The generator set points can be also be distributed amongst


generators proportional to the nameplate rating of the
machines. Operators can choose to share the real power or
reactive power. Reactive power sharing is according to set
points from ED or manual control while real power sharing is
according to their operating base settings.

VIII. AGC SYSTEM IMPLEMENTATION


A. Auto Switch Area Control Mode
The system has been implemented in a large cement facility.
The facility consists of two plants located 32 kilometers apart.
The plants are tied together through a transmission line and
are connected to the power grid at a single PCC. Plant 1 has a
total of three steam turbine generators, two rated at 18MW and
the other rated at 6 MW. At Plant 2, there are three steam
turbine generators rated at 18MW each. In order to implement
AGC, the system was divided into two control areas; Plant 1
and Plant 2 were assigned to Area 1 and the power grid as
Area 2. Fig. 8 is a simplified overview of the network:

Fig. 6. Overall Control Structure.

Fig. 7 provides a simplified illustration of the control


scheme. When ACE goes from point A to point B, the ACE

and its integration is set to 0. The generator set point is reset


and kept constant until new ACE value breaks the control
standards or new base ratings set by ED. When ACE goes
from point A to point C directly, ACE
 is reset to ACE at point

C. But the integration of ACE will start from 0 again.


Fig. 8. Simplified System Overview.
IEEE PES 2009 PSCE 6

Given the above requirements the AGC system was set up


The system operates in two different modes; 1) In parallel to operate in an auto-switching mode. Under this mode AGC
with the power grid and 2) Islanded from the power grid. One would monitor both plants and determine whether or not they
of the main requirements of the AGC system was to operate in are connected to the grid.
both operating modes. When connected to the power grid, the
maximum import from the grid is 3 MW, and the maximum IX. SYSTEM IMPROVEMENTS
export is 12 MW according to the power exchange contract. Before the implementation of the AGC system, in order to
The main reason this facility exports power to the power make the tie-line active power conform to the schedule, the
grid is to wheel power to another location (Plant 3 – not control center dispatcher had to communicate with the
shown in Fig. 10) almost 100 kilometers away. The AGC operators of the power plants by telephone. Moreover, the
system must monitor the required power at Plant 3 and set the existing manual adjustment could not trace the changes of the
export power from Plants 1 and 2 equal to the operating load different operation modes thus a large number of control
of Plant 3 plus the system losses. The facility imports power errors were observed for tie-line flows with no way to control
when any of the generation units is down. The loading in the the cost of the dispatch between the generator units.
facility is approximately 90% of the capacity of the The AGC system which was implemented at the facility had
generators. Hence, if any of the generators is down, then there the necessary control capabilities to regulate the system
is not enough generation to maintain the process requiring frequency and tie-line flow on an economical basis as
power import from the power grid. described below:
In addition to the main system generators, there are a total
of eight diesel generators used for cold start only. These A. Auto Switch Area Control Mode
generators do not play a major factor on AGC and therefore Amongst the many advantages of the implemented AGC
are excluded from the AGC scope. system is its ability to recognize changes in network topology
in real-time using a one-line diagram. This added capability
B. Data Acquisition System Network
allows the system to determine when an area under AGC is
Prior to the implementation of the AGC system at the completely isolated from the rest of the network. AGC
facility, the plants were monitored through digital relaying, controls for each area are automatically switched from flat tie-
metering and other intelligent electronic devices (IEDs) which line flow control mode (equation 13) to flat frequency control
were not networked together. Therefore, the first task was to mode (equation 14) when the area islands from the rest of the
establish a communication network amongst the various network.
plants. IEDs were networked via Modbus Ethernet and
connected to a central OPC Server. The AGC Software was B. Multi-Console AGC Control
then connected to the OPC Server for data acquisition and The facility utilizes a Power Management System (PMS)
processing. with a distributed client-server architecture. The active PMS
The required switching device statuses were collected by Server tracks and controls the addition of consoles to the PMS
four PLCs (two at each plant) including the main feeders and network. After the console is online, the active PMS Server
tie circuit breakers. This allowed for the AGC system to controls the operation of the console. It is the server’s
determine which generators are operating parallel or islanded objective to maintain an active primary console, an active
from the grid. AGC console along with other active consoles for each of the
online modules. Active console control allows an active
C. State and Load Estimation
module like AGC to migrate from one console to another.
The system visibility study was performed at the early The AGC system also handles consistency of project and
stages of the project to evaluate if sufficient metering points operational data throughout the PMS. Operational consistency
were available throughout the network for SLE calculations. addresses the following issues:
SLE result was validated by running load flow simulation and Data Mirroring – this provides the data distribution
comparing them to actual measured data. framework that allows for rapid switching between one PMS
D. Automatic Generation Control System Server and another. It also provides data distribution of project
When the plants operate in parallel to the power grid the and operational data to allow various online functionalities to
AGC system must: be moved from one console to another.
Project/Operating Data Consistency – this provides the basis
1. Determine the output of each generator based on
for changing the project database and associated operational
economic constraints.
data without the necessity of interrupting the entire complex to
2. Honor the exchange schedules with the power grid.
reload the project database.
When the plants are islanded from the power grid the AGC
system must: C.AGC View
1. Maintain the system frequency close to 50 Hz. An AGC view (as shown in Fig. 9) automatically displays
2. Determine the output of each generator based on the real-time operating data while calculating the data from the
economic constraints. AGC/ED calculations. The view automatically detects the
areas and the subsystems (isolated networks) in order to
IEEE PES 2009 PSCE 7

prepare a hierarchical list of generators and interchanges in can switch between study cases without resetting the options
each area and/or subsystem. each time.

(a) MW Control Setting.

Fig. 9. AGC View.

Alarms and warnings are displayed when frequency,


operating reserves, etc. is outside operator-defined limits. The
view also allows the operator to monitor and change generator
control modes as well as perform time error corrections.
D. Generator Control Modes
Ten generator control modes were provided with pre- (b) Line Exchange Setting.
defined logics such that the system dispatcher can quickly
Fig. 11. AGC Study Case Editor and Settings.
switch any unit from one control mode to another based on the
state of the system. Offline and Fault control modes are
X. CONCLUSIONS
automatically determined based on network topology, Manual
Base and Test modes are the manual generator control modes This paper describes an automatic generation control
while the remaining modes are used for automatic generation system suitable for industrial facilities with onsite generation.
controls that depend upon the calculated ACE. This AGC system is capable of handling multiple control sub-
areas within a given facility as well as control areas between
the facility and the connected power grids. An advanced
online state and load estimation algorithm is applied to
determine the non-metered load while calculating the system
operating parameters based on real-time data. Based on the
SLE results, onsite generation fuel cost together with the
power exchange tariff between the power grid are minimized
for economical generation dispatch at each control area while
considering the constraints imposed by interchange schedules
between the facility and the connected power grids. This
Fig. 10. Generator Control Modes. process is preformed and updated for pre-scheduled tasks or
E. User-Configurable Solution Parameters for major system changes. In addition to the economical
generation dispatch, the load frequency control module
The AGC system is user-configurable and customizable for
calculates and monitors the area exchange error to provide
any other system with the help of a study case editor (Fig. 11).
minute-to-minute generation adjustments as required. The
The AGC study case editor contains solution control variables,
AGC system described has been installed in industrial
area definitions and settings, generator participation factors,
facilities and provided economical incentives with improved
and a variety of options for power flow constraints and alerts.
operational security to the facility owners.
The PMS allows the operator or system integrator to create
and save unlimited number of study cases. The AGC
calculations are conducted and reported in accordance with the
settings of the active study case. The operator or dispatcher
IEEE PES 2009 PSCE 8

REFERENCES Hugo Castro, B.S.


Hugo Castro is a Senior Electrical Engineer for Operation Technology, Inc.
[1] Allen J. Wood and Bruce F. Wollenberg, Power Generation, Operation, He is a member of IEEE, Power Electronics Society, Tau Beta Pi (US
and Control, Wiley, John & Sons, 1996.
National Honors Society) and a member of the Society of Hispanic
[2] Yong-Hua Song, Xi-Fan Wang (Eds.), Operation of Market-Oriented
Professional Engineers.
Power Systems, Springer, 2003.
[3] North American Electric Reliability Council (NERC) "Plicy 1 -
Generation Control and Performance", in Operating Manual, Dec. 1996. Jianjun Guo, PhD
[4] IEEE Recommended Definitions of Terms for Automatic Generation Dr. Jianjun Guo is a Senior Electrical Engineer for Operation Technology, Inc.
Control on Electric Power Systems By IEEE Standards Board, IEEE He received his PhD in Electrical Engineering at the Missouri University of
Power Engineering Society, Institute of Electrical and Electronics Science and Technology in Rolla, Missouri.
Engineers, Power System Engineering Committee Published by Institute
of Electrical and Electronics Engineers, 1991. Tanuj Khandelwal, M.S.
[5] Alan Elliott Guile, William Paterson, B.Sc., Electrical Power Systems, Tanuj Khandelwal is a Project Manager and Senior Electrical Engineer for
Pergamon Press, 1977. Operation Technology, Inc. Mr. Khandelwal is an active member of IEEE
Standards Association and IEEE subcommittees and working groups.

BIOGRAPHIES Farrokh Shokooh, PhD, PE


Farrokh Shokooh is President & CEO of Operation Technology, Inc. Dr.
Shokooh is a Fellow member of IEEE and is an active member of the IEEE
JJ Dai, PhD, PE subcommittees and working groups. He is a registered Professional Engineer
JJ Dai is Vice President, Advanced Technologies for Operation Technology, in the state of California.
Inc., and President of OTI-Far East. Dr. Dai is a member of IEEE, the
chairman of the Power System Analysis Subcommittee of IEEE Industrial Shervin Shokooh, M.S., MBA, PE
Applications Society (IAS), a chapter chairman of the IEEE Brown Book, and Shervin Shokooh is Vice President of Engineering Consulting and Senior
a past chairman of the Harmonic Task Force of IAS. He is a registered Principal Electrical Engineer for Operation Technology, Inc. Mr. Shokooh is a
Professional Engineer in the state of California. member of IEEE and a registered Professional Engineer in the state of
California.

© 2008 Operation Technology, Inc. All rights reserved. Certain names and/or logos used in this document may constitute trademarks, service marks, or
trade names of Operation Technology, Inc. Other brand and product names are trademarks of their respective holders.

Potrebbero piacerti anche