CRONOGRAMA VALORIZADO

PROYECTO: MEJORAMIENTO, REHABILITACION DE PISTAS Y VEREDAS DE LA AV. SANTOS CHOCANO, DISTRITO DE CARMEN DE LA LEGUA REYNOSO - CALLAO - CALLAO
CLIENTE: MUNICIPALIDAD CARMEN DE LA LEGUA REYNOSO - CALLAO - CALLAO
FECHA: DICIEMBRE DEL 2016

PERIODO DE EJECUCION ( 90 DIAS)


Item Descripción Partida UND METRADO PRECIOS S/. PARCIAL S/.
MES 1 MES 2 MES 3
01 OBRAS PROVISIONALES 4,780.29
01.01 TRANSPORTE DE EQUIPOS, MATERIALES Y HERRAMIENTAS glb 1.00 3,000.00 3,000.00 S/.3,000.000
01.02 OFICINA, ALMACEN Y CASETA DE GUARDIANIA glb 1.00 800.01 800.01 S/.800.010
01.03 CARTEL DE IDENTIFICACION DE LA OBRA DE 2.40 X3.60m und 1.00 980.28 980.28 S/.980.280
02 OBRAS PRELIMINARES 72,431.96
02.01 DEMOLICION DE VEREDAS m2 3,530.18 15.10 53,305.72 S/.26,652.859 13326.430 S/.13,326.43
02.02 LIMPIEZA MANUAL DE TERRENO m2 5,372.54 2.28 12,249.39 S/.12,249.391
02.03 TRAZO, NIVELACION Y REPLANTEO m2 5,372.54 1.28 6,876.85 S/.6,876.851
03 MOVIMIENTO DE TIERRAS 109,816.75
03.01 CORTE SUPERFICIAL MANUAL (HASTA 20CM) m3 682.40 7.43 5,070.23 S/.2,535.116 2535.116
03.02 EXCAVACION DE ZANJAS PARA SARDINEL SUMERGIDOS m3 146.32 34.46 5,042.19 S/.2,521.094 2521.094
03.03 PREPARACION DE SUB RASANTE PARA VEREDAS, PISOS Y RAMPAS m2 5,372.54 4.42 23,746.63 S/.11,873.313 11873.313
03.04 AFIRMADO DE 4" PARA VEREDAS Y PISOS m2 3,921.13 9.33 36,584.14 S/.18,292.071 18292.071
03.05 ELIMINACION DE MATERIAL EXCEDENTE m3 1,494.82 26.34 39,373.56 S/.19,686.779 19686.779
04 OBRAS CONCRETO SIMPLE 222,503.19
04.01 PISO DE CONCRETO E=4" CONCRETO f'c 175 kg/cm2 PULIDO Y BRUÑADO m2 3,921.13 42.94 168,373.32 117861.323 S/.50,511.995
04.02 CONCRETO f'c= 175 kg/cm2 PARA SARDINELES SUMERGIDOS m2 82.26 370.65 30,489.67 21342.768 S/.9,146.901
04.03 ENCOFRADO Y DESENCOFRADO DE SARDINELES SUMERGIDOS m2 435.42 42.63 18,561.95 12993.368 S/.5,568.586
04.04 JUNTAS DE DILATACION CON ASFALTO m2 925.00 5.49 5,078.25 3554.775 S/.1,523.475
05 OBRAS DE CONCRETO ARMADO 49,336.84
05.01 CONCRETO f'c= 175 kg/cm2 PARA SARDINEL DE BORDE m2 65.31 333.14 21,757.37 13054.419 S/.8,702.946
05.02 ACERO DE REFUERZO fy=4,200 kg/cm2 EN SARDINEL DE BORDE m2 1,618.86 5.13 8,304.75 4982.847 S/.3,321.898
05.03 ENCOFRADO Y DESENCOFRADO DE SARDINELES DE BORDE m3 371.74 51.85 19,274.72 11564.831 S/.7,709.888
06 VARIOS 52,757.76
06.01 SUMINISTRO E INSTALACION DE CAJAS REGISTRO DE AGUA POTABLE und 176.00 64.81 11,406.56 S/.5,703.280 S/.5,703.28
06.02 SUMINISTRO E INSTALACION DE CAJAS REGISTRO DE DESAGUE und 176.00 59.81 10,526.56 S/.5,263.280 S/.5,263.28
06.03 PINTURA EN SARDINELES m 2,056.47 4.35 8,945.64 S/.4,472.822 S/.4,472.82
06.04 JARDINERIA CON ARBOL und 102.00 214.50 21,879.00 S/.10,939.500 S/.10,939.50
01 OBRAS PROVISIONALES 2,102.69
01.01 TRANQUERAS DE MADERA 1.20MX1.10M P/DESVIO DE TRANSITO VEHICULAR und 1.00 287.81 287.81 S/.287.810
01.02 CINTA PLASTICA SEÑALIZADORA P/LIMITE SEGURIDAD DE OBRA m 1,890.50 0.96 1,814.88 S/.1,814.880
02 OBRAS PRELIMINARES 21,667.10
02.01 TRAZO, NIVELACION Y REPLANTEO m2 9,524.03 1.28 12,190.76 S/.12,190.758
02.02 NIVELACION PERMANENTE Y REPLANTEO FINAL m2 9,524.03 0.68 6,476.34 S/.6,476.340
02.03 TRANSPORTE DE EQUIPOS, MATERIALES Y HERRAMIENTAS glb 1.00 3,000.00 3,000.00 S/.3,000.000
03 MOVIMIENTO DE TIERRAS 241,707.65
03.01 DEMOLICION DE PAVIMENTO EXISTENTE m3 9,779.92 10.10 98,777.19 S/.39,510.877 S/.59,266.315
03.02 CORTE A NIVEL DE SUB RASANTE C/EQUIPO m3 1,955.98 10.21 19,970.56 S/.7,988.222 S/.11,982.333
03.03 PERFILADO Y COMPACTADO DE SUB - RASANTE m2 9,524.03 4.12 39,239.00 S/.15,695.601 S/.23,543.402
03.04 ELIMINACION DE MATERIAL EXCEDENTE m3 3,178.47 26.34 83,720.90 S/.33,488.360 S/.50,232.540
04 PAVIMENTACION 414,117.76
04.01 BASE DE 0.20 m m2 7,705.95 13.99 107,806.24 S/.43,122.496 S/.64,683.744
04.02 IMPRIMACION ASFALTICA RC-250 m2 7,705.95 4.86 37,450.92 S/.14,980.370 S/.22,470.555
04.03 COLOCACION DE CARPETA ASFALTICA EN CALIENTE 2" m2 7,705.95 34.89 268,860.60 S/.107,544.238 S/.161,316.357
05 PINTURA DE SEÑALIZACION 29,392.25
PINTADO DE PAVIMENTOS: LINEA DE CARRIL m 315.00 6.15 1,937.25 S/.1,937.250
PINTADO DE PAVIMENTOS: LINEA DE BORDE CONTINUA m 1,666.50 7.22 12,032.13 S/.12,032.130
PINTADO DE PAVIMENTOS LETRAS Y SIMBOLOS. m2 447.35 27.40 12,257.39 S/.12,257.390
TACHAS DELINEADORAS REFLECTIVAS BIDIRECCIONALES und 108.00 29.31 3,165.48 S/.3,165.480
06 INTERFERENCIAS 59,298.81
06.01 EXCAVACION,PARA TENDIDO DE TUBERIAS
06.01.01 EXCAVACION DE ZANJAS CON EQUIPO EN TERRENO NORMAL. m 369.48 35.00 12,931.80 S/.12,931.80
06.02 REDES DE DESAGUE
06.02.01 LINEAS DE ALCANTARILLADO
06.02.01.01 INST. DE TUB. PVC-UNION FLEXIBLE S-25 DN 200 HASTA 2. PROF. T.N. m 369.48 84.41 31,187.81 S/.31,187.81
06.02.02 CONEXIONES DOMICILIARIAS DE DESAGUE
06.02.02.01 CONEXION DOMICILIARIA DE DESAGUE DN150 TERRENO NORMAL und 20.00 758.96 15,179.20 S/.15,179.20
COSTO DIRECTO 1,279,913.05 311,598.30 590,639.713 377,675.03
GASTOS GENERALES (8%) 102,393.04 24,927.86 47,251.18 30,214.00
UTILIDAD (7%) 89,593.91 21,811.88 41,344.78 26,437.25
SUB TOTAL 1,471,900.00 358,338.04 679,235.67 434,326.28
IGV (18%) 264,942.00 64,500.85 122,262.42 78,178.73
TOTAL PRESUPUESTO 1,736,842.00 422,838.89 801,498.09 512,505.00
AVANCE 24.345% 46.147% 29.508%