Sei sulla pagina 1di 7

Power-Factor Correction

B y L . W. W. M O R R O W *
Member A.I.E.E.

Review of the Subject. — Poiver factor correction has Cost analyses should be made to determine the type of
become a commercial problem of major importance, and correction to use and to decide upon the location of corrective
technical knowledge and corrective equipment are available equipment. But they should not be used for rate making
to make correction a part of the activities of the electrical purposes. A study of the types of systems in existence shows
industry. Fiehd studies on several properties show power that in general correction is most economically and most
factor correction can be obtained without difficulty. effectively instituted at the loads. Also experience indicates
Conditions can be improved by requiring all new business the greatest effect of correction is to improve voltage regula­
to be installed for high power factor operation and a co­ tion and service quality.
operative movement should be made to bring about this Different types of rates and billing methods have been
condition. The situation on existing systems can be improved used, but a study of the art shows the kv-a. demand charge
in either a wholesale or retail manner depending upon and the kw. energy charge can be used most successfully to
conditions. secure power factor correction.

T HE effects of low power factor on the oper­


ations of the electrical industry have been
discussed for many years and much experi­
ence in the institution of corrective measures has
worth while. Y e t little actual progress in power-
factor correction can be seen because of many
obstacles, mostly imaginary, set up in the minds
of executives, engineers and customers. Some of
been had. Yet on an industry-wide scale the evils these are: the inertia encountered when proposing
associated with low-power-factor conditions become any changes in a going business which is prosperous
greater each year, even though the incentives for and follows time-tried methods; difficulties met in
the institution "of corrective measures increase. attempting to evaluate the costs of either low or
Low power factor has come to be recognized as the high power-factor operation; fears introduced by
major handicap to better and more efficient electric the necessity for instituting new or changed rates
service, and men of the industry are striving ac­ and billing methods; difficulties encountered in
tively for a commercial and engineering method for attempts to make people understand the meaning
its correction. of power factor; obstacles encountered in attempts
An analysis of the data and experiences of those to devise a correction scheme for universal appli­
properties which have instituted power-factor cor­ cation, and technical difficulties met with in con­
rection leads to the conclusion that operation under nection with the selection and location of corrective
high-power-factor conditions improves both the equipment. The literature of the industry is filled
quality and the efficiency of the service rendered with objections to power-factor corrective measures
by the utilities and used b y their customers. Cor­ and with elaborate technical and cost analysis, and
rection of power factor has its greatest influence in very few data or opinions of a constructive char­
improving the voltage regulation and through this acter have been obtained to show that most of the
action enables the utility to give better service and obstacles to correction result from misconceptions
the customers to secure better use of the service. and lack of actual experience with it in commercial
Secondary gains resulting from power-factor cor-, practice.
rection consist of the release of system capacity The fact is that many properties have instituted
with a consequent reduction in investment and a correction successfully and made it a profitable part
reduction in system losses with a resultant reduc­ of their business. They have done this without any
tion in operating charges. Thus correction tunes the difficulty and did not find any great complexity or
system and makes it cheaper and easier to give major changes introduced in their operating routine.
service of the quality desired in modern industry. Thus the time is ripe and the methods are available
Actual experience shows that power-factor cor­ for eliminating low-power-factor conditions in the
rection can be instituted successfully as a part of electrical industry. The rewards are ample, and the
the business activities of light and power companies necessity for this move becomes greater with the
and as a part of the normal operating activities of growth of electrical systems.
industrial users of electricity. It does not require Correction is a business problem and not a tech­
an elaborate or costly departure from customary nical problem. The technical features of power-
business activities, and it secures returns to the factor discussions begin nowhere and end at the
producer and the user whose value is tangible and same place, and they have little if anything to do
with the business-like application of corrective
*Managing editor the Electrical World.
measures. N o one can define electricity or power
Presented at Regional Meeting of District No. 2 . Washington,
D. C, January 23-24, 1 9 2 5 . factor, yet definite laws enable engineers to use

150
Feb. 1925 MORROW: POWER FACTOR CORRECTION 151

resistance, inductance and capacity in circuits or in good business and do more to help their customers
machines to secure any desired power factor at any secure quality service and co-operate more closely
definite place. Also, engineers understand fully the to sell quality equipment. It would seem easy to
influence of lagging and leading current on system organize a local co-operative committee for each
regulation and machine stability. Technical utility to secure the desired results. This would be
mastery of power factor prevails, and what is. needed composed of power salesmen, electrical manufac­
is commercial mastery. turers' representatives, electrical contractors, and
In order to obtain commercial mastery two sug­ perhaps consulting engineers, and might well be
gestions are offered which will apply to every part of the activities of the local electrical leagues
electrical system-: already instituted in so many cities. National
1. Require high-power-factor operation of all agencies are already available in the N. E. L. A . ?

new business served. Power Club and other associations, but their at­
2. Correct low-power-factor conditions on exist­ tention must be given to this problem.
ing systems either : (a) promptly and in a wholesale There is no handicap to the manufacture and sale
manner, or (b) slowly and by steps. of electrical equipment and service on a quality
MAKE N E W BUSINESS GOOD BUSINESS
rather than a price basis in an industry whose prod­
uct is popular, is necessary to industry and is the
Any consideration of the first suggestion, in the
cheapest and best element ever introduced into in­
light of the growth of the electrical industry and the
dustrial processes. When the cost of power is such
increasing importance of service quality, shows its
a small fraction of the cost of manufacture of most
logic, and there remains then the use of definite
industrial products, it is false economy to talk first
methods to secure the desired results.
cost of service or of equipment to purchasers.
A light and power company is a public utility and Thus very little organized effort should institute
cannot enforce any rule requiring customers to in­ as industry-wide practice the custom of obtaining
stall high-power-factor equipment before it will give only high-power-factor business in each new load
service, so this direct and self-evident method must added to existing systems. The principle to apply
be replaced by methods which are co-operative and is that service to customers should be given before
educational in character. The j o b . requires the co­ they install equipment and ask for electrical energy
operation of utility men, electrical manufacturers from a utility.
and customers and must be done for each new busi­
ness prospect on each property, and in addition work THE CORRECTION OF E X I S T I N G CONDITIONS

must be done on a national basis. It is not a diffi­ The second suggestion for power-factor correction
cult task, for both means and methods are available is that existing conditions be bettered either by
for doing the work quickly and efficiently. making corrections quickly on a wholesale basis or
The co-operative element in the work calls f o r : by improving conditions slowly and in steps. In
1. Closer contact between central-station power many respects the slow and detailed method is best
salesmen and prospective customers whereby guid­ for those systems inexperienced in correction, but
ance and expert knowledge are made available to past experiences show that it is not difficult to do the
customers. whole j o b quickly on the entire system provided
2. Closer contact between central-station execu­ proper analyses are made and workable methods are
tives and electrical manufacturers so the manu­ adopted before correction is actually instituted.
facturers may be encouraged to build high-power- Whatever decision is made has little influence upon
factor equipment and to sell this equipment on a the methods used or the results obtained and pre­
quality rather than a price basis and with greater dominantly influences only the time required to
consideration for the engineering requirements of secure improvements in conditions. The situation
the purchaser. on each system will determine the best procedure
to use, for operating and financial requirements
These two co-operative suggestions are already
must be met by individual properties.
in operation in large degree, but conscious execu­
tive attention should be given to their application Three things only are needed to institute correc­
in order to secure complete commercial results tion on an existing s y s t e m :
rapidly. The j o b requires that each new customer 1. Decisions as to the location of corrective
install available electrical equipment from the equipment.
standpoint of his own economic production require­ 2. Decisions as to the corrective equipment to
ments. Both power factor and quality apparatus be used.
will inevitably follow every real economic analysis 3. The establishment of a rate system which
of an industrial electrical application, and central- takes power factor directly or indirectly into
station men and manufacturers' representatives account.
must give up the slogan that any new business is The first two requirements largely involve engi-
152 MORROW: POWER FACTOR CORRECTION Journal Α. I. Ε. E.

neering and economic data and decisions to be se­ tions, transmission lines, substations, transformers
cured within a utility organization, but the third and distribution systems.
requirement must take into consideration the utility,
the customers and the regulatory commissions and GENERATING S T A T I O N CORRECTION

involves public relations, economics and education. The evaluation o f the reduction of the reactive-
kv-a. load on a generating station due to power-
L O C A T I O N S FOR C O R R E C T I V E EQUIPMENT
factor correction is difficult because so many condi­
A study to determine the locations in which to tions must be considered. There is much more to
install corrective equipment on existing systems the problem than raising a station power factor from
shows that the decision is somewhat influenced b y 70 per cent to 90 per cent in order to make available
the type o f system and by local conditions. Usually approximately 20 per cent increase in station
corrective equipment should be located at all low- capacity.
power-factor loads, in some cases at substations at
In hydroelectric plants if is usually desirable to
a distance from generating stations, particularly
have reactive kv-a. available for line regulation, and
if voltage regulation is desirable, and in very few
in addition it is usual to find an excess of capacity
instances in generating stations. The source of low
installed in order to meet stream-flow conditions.
power factor is at the load, and analyses will show
Therefore, generally, no value can be placed on
that corrective equipment is best and most econom­
power-factor correction for such stations. Also, in
ically used in this location.
large systems using steam and hydro stations in
Some of the types of systems encountered in this
combination with interconnected high-tension lines,
country and some of the elements faced in locating
lagging current is often an operating asset, and in
corrective equipment are enumerated below:
this case also correction is seldom or ever desirable
1. A hydroelectric system containing long high- for generating stations.
voltage transmission lines with one or more distri­
In the large steam stations feeding a power sys­
bution systems located at the ends of the lines.
tem concentrated in a comparatively small area
2. A combination system having both steam and power-factor correction may improve regulation and
hydro stations, many high-tension lines and widely operation, but here again the savings in station costs
distributed load centers. are sometimes very small and must be evaluated for
3. A hydroelectric system with standby steam the conditions encountered. These plants are usually
stations containing capacity idle a great part of the designed for 85 to 90 per cent power-factor oper­
time and made up of networks of high-tension lines ation at the stations, and a little study will show
supplying a scattered territory. that cost decreases are difficult to secure. Offhand
4. A metropolitan system containing several it may be said that every kv-a. of station capacity
large steam stations and made up of both overhead means the release of fixed charges on at least $6 of
and underground transmission circuits. investment and every reduction of a per cent in
5. A system already operating and designed for losses from the normal 2 per cent of output kw.-hr.
a power factor of 80 to 85 per cent. can be credited in dollars and cents o f operating
6. A system designed to operate at a power charge. But there are some other factors that must
factor of 90 to 95 per cent. be considered before these sums mean anything or
7. Systems which are growing rapidly in magni­ will stand the examination of a court or commission ;
tude of load and extent of territory covered and for example, in connection with stations in modern
those which have reserve capacity through inter­ systems :
connections. (a) Most systems increase their installed station
It is seen that each system is a specific study for capacity in units of large size and seldom permit
power-factor correction at other places than at the their peak to approach a value equal to installed
load sources of low power factor, and the choice of capacity. For example, station additions are made
location of corrective equipment at other locations in units of 30,000 kw. up to 200,000 kw. and ample
must be made after economic and operating studies. reserve is held at all times.
The making of cost evaluations for a particular (b) Every metropolitan system often introduces
system should be decided upon only after careful large losses into its normal operations in order to
study, for they are difficult and are useful only in insure reliability o f service ; for example :
serving as guides for the location of corrective (1) A station having several large units is
equipment. They serve no purpose in rate making likely to continue all of them in operation even
as cost-of-service rates are now obsolete in the at very light load in order to reduce the starting
utility industry. However, if cost analyses are de­ hazard and the time element involved in warming
sired in some cases, the usual approach to deter­ up a large unit and synchronizing it with the
mining fixed and operating charges is to evaluate system.
the cost of capacity and o f losses in generating sta­ (2) In order to control voltage and load division
Feb. 1925 MORROW: POWER FACTOR CORRECTION 153

it is common practice on systems having multiple for each unit has become popular, and it is difficult
stations to operate generating units with large to conceive of this type of station operating with
lagging or leading currents. a i r b u s e s in parallel at one voltage or to devise a
(c) It is a difficult, if not impossible, task to deter­ switching and bus arrangement for throwing the
mine actual station power-factor conditions during synchronous condenser on any feeder requiring
a twenty-four-hour period for the different stations regulation. In addition, the cost of the corrective
in a large metropolitan network. A n y method of equipment used for regulation exceeds that of volt­
determining power factor and of determining the age regulators, which have the added advantages of
value of losses is subject to criticism as to its tech­ being automatic in their operation and of having a
nical accuracy, and the values obtained cannot be greater voltage range.
divided easily between power factor, load division In the general case, therefore, seldom will it be
and regulation requirements. In fact, for a given found economical to institute power-factor correction
load power factor as defined and as measured by in generating stations.
different methods will vary 10 to 30 per cent in value.
SUBSTATION CORRECTION
The actual capacity cost of the reactive load on a
generating station not loaded to capacity is usually The installation of corrective equipment at sub­
very little even though the cost of the increased stations reduces the kv-a. load on transmission lines
capacity of alternators, exciters, switch gear, buses and transformers between the substations and the
and building is determined. Seldom would this cost generating stations and improves the voltage reg­
exceed $6 per reactive kv-a., and any added operat­ ulation. This would seem desirable in all cases, but
ing expense due to low power factor is very debat­ a little study shows it is often very uneconomical
able. For some specific installations, however, and usually not the best way to secure complete
where the peak load is equal to the station capacity correction.
or where the load power factor is lower than that In modern systems reliability of service, provision
for which the station equipment was designed, it for future growth and maintenance practices dictate
may be well to institute power-factor correction as the use of multiple feeders to substations and
a temporary economical expedient for securing ca­ multiple transformer installations. Also, modern
pacity to carry the load. Load factors, future sys­ practice tends to the use of standardized ratings for
tem growth and other elements, however, must be lines and transformers on the transmission system.
considered. These requirements call for the installation of a
In most other cases, however, it is cheaper and greater number and an excess of line and trans­
easier to buy, install and operate alternators, buses former capacity, which makes it very difficult to
and exciters with a higher rating than it is to buy, show the economic value of substation corrective
install and operate corrective equipment and its con­ equipment.
trol. For example, the increment cost of a 35,000- Moreover, it must be borne in mind that future
kv-a. alternator over a 30,000-kv-a. unit as compared load requirements, structural needs and legal limita­
to the cost of a 5,000-kv-a. synchronous condenser tions have a direct bearing on both overhead and
and its control equipment is in favor of the alter­ underground line installations. The overhead line
nator. In most stations generating capacity can must have a certain size o f pole, a conductor suffi­
usually be obtained more cheaply than by the use ciently large to be strong mechanically, a large
of corrective equipment. number of poles per mile and very often a legal
Very few operating costs are affected by low voltage limitation. These elements often must be
power factor because the copper losses inside a sta­ weighed carefully when discussing the release of
tion amount to an inappreciable sum. A t light load line capacity b y the use of substation corrective
the usually lowest power-factor condition increases equipment. In underground cable installations it
the losses in proportion to the kw. output. This in­ has become customary to install reserve ducts and
dicates the advisability of fixing a power-factor cables and to standardize greatly, so the number
charge that varies with output. This charge should and the capacity of installed cables at a given time
be greatest at minimum-load conditions in some is very often determined by other things than the
cases and at peak-load conditions in other cases. magnitude of the kv-a. loads. It must be considered,
A very small increment in energy charges seems the however, that the overload capacity of an overhead
only businesslike way to cover these station losses line is very great as compared with that of cables
due to low power factor as at a maximum they and transformers.
comprise only 2 or 3 per cent of the system losses. Thus any cable or transformer that has reached
The practical possibility and the dollar value of its limit in capacity while operating at a low power
regulation b y power-factor correction inside large factor is capable o f carrying an increased load and
steam stations is very dubious. The unit type of consequently earning more revenue if correction is
installation with the unit bus and a group of feeders applied at substations. The cost o f the corrective
154 MORROW; POWER FACTOR CORRECTION Journal Α. Ι. Ε. E.

equipment may be less than the installation of an­ at least as a temporary move, until full consumer
other line and more transformers, and regulation correction has been established.
is improved, so that more load may be carried on a
CONSUMER CORRECTION
given circuit. In other words, correction will, for
the same line loss, increase either the economic The analysis for determining the proper location
distance of transmission or the amount of load pos­ of corrective equipment leads inevitably to the con­
sible to transmit. In such cases the substation cor clusion that most of it should be placed on the
rection may be economical, but it is an expense premises of consumers and that consumers using
which must be paid for in fixed charges, while a new high-power-factor equipment are operating most
line provides a revenue-producing and useful element economically from their own standpoint and from
for the present and future system. A system using that of the central station. From the angle of the
a ring high-tension network and having multiple central-station consumer correction relieves the
generating stations and several large substations system of the necessity for correction at other loca­
on the ring may use corrective equipment in distant tions, releases the transformer and cable capacity
substations to advantage to reduce losses, release where it is most valuable from income and load-
capacity and control regulation, but the economic factor standpoints, reduces losses where they are
value of this practice must be ascertained for each greatest and improves regulation where it is most
particular case. desirable to have good regulation.
Thus in very few cases will the release of system From the angle of the consumer correction of his
capacity justify substation correction; therefore equipment or the replacement of low-power-factor
either decreased losses or improved regulation must equipment with high-power-factor equipment will
be evaluated to make a case. The reduction in line secure several tangible and intangible results. It
and transformer losses by the use of corrective will reduce the losses inside his premises, for which
equipment increases the load at which the invest­ he pays a high rate; it will improve his voltage
ment cost per kv-a. transmitted is a minimum and regulation and reduce his voltage drop, so that his
reduces the direct operating cost of energy losses. machinery will operate faster and more smoothly;
On an average system the line energy losses will it will give him better-quality production, better
be around 10 per cent of the total output while the lighting, fewer rejections of manufactured product,
transformer losses should not exceed 5 per cent. faster machine-starting conditions and secure for
These losses therefore represent a direct money him a direct decrease in his power bill if he buys
loss, which, if reduced, results in an appreciable under a proper rate system.
saving. Assuming that correction decreases these Experience shows that operating complexity is
losses even 20 per cent, it often becomes profitable not increased and that the industrial plant corrected
to install corrective equipment. for bad power-factor conditions reaps very decided
For example: Assume an energy cost of 1 cent tangible and intangible benefits. Needless to say,
per - kw.-hr. and a system output of 100,000,000 it is useless to attempt an itemized cost evaluation
kw.-hr. with total losses of 15 per cent in lines and for correction at load locations, because the com­
transformers. If it is assumed correction will re­ plexity of modern distribution systems, the variety
duce the losses 20 per cent, the yearly value of of loads and services and the many assumptions
correction i s : 100,000,000 χ 0.15 χ 0.20 χ 0.01 necessarily made all combine to give inaccurate re­
= $30,000, or a return of 15 per cent on an invest­ sults. In a broad way, however, based on the actual
ment of $200,000. cost of the distribution system, the cost of voltage
Losses in corrective equipment must be considered regulation and the cost of losses, an analysis in
in a financial analysis of this character and their dollars will show very decided inducements for in­
cost determined. If synchronous condensers should vesting power-factor correction at the source.
be used, this value would be changed, since the con­
KINDS OF CORRECTIVE EQUIPMENT
denser has losses which must be charged against the
The corrective equipment to install at locations
saving produced in lines and transformers. If static
condensers are used, the value of the losses in the decided upon is determined largely by each local
corrective equipment is very small. In either case, situation, but there are applications for all available
particularly if the voltage at the substation is high, types at low-power-factor loads ; i. e. :
the losses in the transformer bank supplying the (a) The synchronous motor.
corrective equipment should be evaluated and (b) The synchronous condenser.
charged against the cost of correction. (c) The high-power-fajctor commutating motor
The general conclusion is that substation correc­ of the Fynn-Weichsel type.
tion, considering the value of losses, capacity and (d) The static condenser.
regulation, is usually warranted for those substa­ Investment charges on existing installation?/
tions located at a distance from generating stations, production requirements, fixed and operating
Feb. 1925 MORROW: POWER FACTOR CORRECTION 155

charges on corrective equipment and the skill re­ thought was taken on its ultimate effects on the
quired to operate the equipment influence the deci­ utility business. Rates were made on a watt-houi
sion to be made for each load considered. basis and the cheap, accurate watt-hour meter be­
For substation correction the same types of came the standard measuring device for electric
corrective equipment are available, but the syn­ service. Then came the induction motor and it was
chronous condenser and group static condensers early noticed that the product of current and volt­
predominate. The decision as to which type to use age did not equal the registration of the meter.
at substations is influenced by cost analyses and by Thus power factor was discovered, and. until recently
load and voltage regulation requirements. the utilities decided that it was better to suffer its
Experiences on properties give evidence that the effects than to attempt to improve conditions or to
choice of equipment for correction is quite readily charge for service by methods involving the use of
made for a particular location. Each system should other units than watt-hours. Power factor was
be studied as a whole and each power customer con­ difficult to define accurately, difficult to measure and
sidered if good results are desired. The utility still more difficult to explain to customers and
engineers can readily determine the substation cor­ executives.
rection to use, but greater difficulty is encountered However, there is a tendency today actually to
in the correction of power customers. The installa­ measure power factor or to meter customers by
tion of each customer must be studied in detail if a methods which will take power factor into account.
real engineering j o b is to be done, and this requires The first trend is indicated by the development of
time, skilled engineering and an expenditure of kv-a. meters, the use of reactive and active watt-
money. Production processes, motorization, wiring hour meters and the use of power-factor meters.
and testing are elements in the study, and a great Any of these meters or metering methods are sub­
deal of education and co-operation must be had. ject to objections from an economic, a technical and
For these reasons a slow process of customer cor­ an operating standpoint. The cost, the complexity
rection is usually advisable. Utility power sales­ of the billing and the difficulty of obtaining and
men, consulting engineers, factory engineers and maintaining reliable and accurate measurements by
electrical manufacturers' salesmen and engineers any of these means have so far prohibited their use
should co-operate in these customer studies. In except for large power customers having a tech­
actual practice no great difficulty or high costs have nical staff or sufficient consumption to warrant the
been encountered in attempts to institute customer cost and the trouble. Nothing very promising is on
corrections, because the great majority of them can the horizon in the way of directly measuring either
be made adequately b y an over-all factory test or by kv-a. or power factor on a universal commercial
competent engineering inspection. V e r y frequently basis.
zone studies or piecemeal areas are correcteS with One metering authority has recently suggested
very little trouble. that it would be advisable to meter customers on
the old ampere-hour basis since all service is at
POWER-FACTOR RATES
practically constant voltage and the ampere-hour
Electric service is a business and as such must meter, besides being cheap and accurate, is a true
institute power-factor correction as a part of busi­ and readily understood measure of both energy and
ness activity. Thus a rate of some form must be capacity use. Multiplying ampere-hours by the
used to secure power-factor correction, and it also voltage of the supply would permit of billing on a
follows that metering and billing accompany the kv-a.-hour basis very readily. Thus a system could
institution of a rate. Experience with energy and be developed which would use an ampere demand
power-factor rates over many years shows that com­ meter and an ampere-hour meter only for direct
mercial rates cannot be made upon the basis of cost measurement on any three-phase or single-phase
of service. Experience also shows that financial circuit. It is argued that this method is sufficiently
inducements are the best stimuli to industrial ac­ accurate, is easy to institute, is logical and that its
complishments. Rates, billing systems and meter­ results compare well in accuracy with those from
ing methods are largely matters of tradition and any existing method of measurement.
commercial application, but should be simple, under­ The ultimate approach to power-factor correction
standable and easy to use in business. for customers is by means of rate making. This
When alternating current was first used the has generally taken the form o f :
wonderful Thomson-Houston meter was invented (a) The use of power-factor clauses.
and installed. This meter measured watt-hours and (b) The use of kv-a. demand clauses.
eliminated the necessity o f measuring ampere-hours (c) The use of kv-a.-hour clauses.
and multiplying b y the normal voltage of the service (d) A combination of two of the foregoing.
as had hitherto been practiced. It was an ideal in­ All these methods have been used and all have
strument for measuring lighting loads, and no worked more or less successfully, but all are sub-
156 LEE: PAPER INSULATED CABLE TESTING Journal Α. I. Ε. E.

ject to very definite criticisms. Years of effort rates, but should be accounted for in the kv-a. de«
proved the impossibility of developing utility rates mand charge. This rate can be used to secure
on a cost-of-service basis, and, however reluctantly, power-factor correction on any system very satis*
rate makers have admitted its impossibility and factorily and does not necessarily involve the us*
impracticability for modern conditions of utility of a kv-a. demand meter. Power customers eau
service. No cost-of-service basis can be found, be tested under normal operating conditions, and
therefore, for the making of any type of power- the power contract can then be written for a period
factor rate, and each property must evolve a rate of time with a kw.-hr. meter and a kw. demand
which can be instituted and operated to suit con­ meter to serve as checks and for energy billing. In
ditions encountered. A fundamental in power-factor other cases the installation of a power-factor meter,
rate making would be to secure a simple rate, one normally out o f circuit, in combination with ordinary
that could be applied to all customers, one that watt-hour meters can be used to check customer
needed little maintenance or supervision and one conditions and to meet billing requirements.
that offered a financial inducement to customers to However, every type of power-factor rate has
maintain and correct power-factor conditions. been used and used successfully, so the necessity
Viewing the art in its technical and commercial of a rate to secure power-factor correction is not β
aspects and basing opinions on practical experi­ real obstacle to the institution of correction. Ii
ences, the best form of power rate today should use must be remembered that grand average results
a kv-a. demand charge to cover capacity costs and only are to be expected and that precision method?
an energy charge to cover production costs. Power and analyses must be modified by commercial con
factor, as such, should not appear in the customer siderations.

Testing High-Tension Impregnated-Paper-


Insulated, Lead-Covered Cable
BY EVERETT S. LEE*
Associate, Α. I. Ε . E .

Synopsis,—The increase in voltage of cables has necessi­ been made available. This includes sine-wave generators, adequate
tated that the tests to assure satisfactory cable be more adequate than testing transformers, appropriate cable testing terminals.
as standardized at present. This has resulted in an intensive study Data is given from which conclusions are drawn as to the magni­
of the tests previously standardized, development of new tests, and the tude and^duration of test voltages. The adequacy of these values will
design and manufacture of suitable testing equipment to meet the new become known through experience. The need for field testing is
testing requirements. shown.
Measurements are made upon cables to determine the following Dielectric Power Loss and Power Factor: The tendency is to
properties of the insulation: extend the measurement of dielectric power factor to include each reel
length to be shipped. The Schering Bridge for making such meas­
Insulation Resistance
urements is described. The need for standardizing the testing
Dielectric Strength
procedure for power factor measurements is shown.
Dielectric Power Loss and Power Factor Testing Installed Cable: The study of so-called "current-time
Capacitance curves" for rating installed cable should be continued. Preliminary
Ability to Withstand Bending measurements made at high frequencies as a means of rating in­
Insulation Resistance: This measurement is being made in the stalled cable did not show the results to be immediately usable.
same way on cables of all voltage rating. The results of the test on Testing With Direct Current: Data is given to show the d-c. to
high-tension cables are of doubtful value as a criterion of the suit­ a-c.-ratio of breakdown voltage of some samples of 12 kv.-3-conductor.
ability of cable for use. Continued study of this measurement should cable. Tests indicate that the d-c.-to a-c.-ratio will depend upon
be made. many conditions such as nature and structure of the material,
Dielectric Strength: Suitable testing equipment for satisfying the thickness of the material, temperature of the material, shape and
requirements of the increased voltages in dielectric strength tests has size of electrodes, and rate of application of the applied potential.

T H E report of the Transmission and Distribution


Committee of the Α . I. Ε. E. for 1923-1924 con­
tains the following significant statement: 1
year has been, the evidence that the cable specifications
of the N . E. L. A . and the present Standards of the
Α. I. Ε. E. do not insure satisfactory cable for the
" T h e most important development during the past higher operating voltages. '
*General Engineering Laboratory, General Electric Co., "This subject is now receiving attention from the
Schenectady, Ν. Y. manufacturers as well as the users of high voltage
1. For References see Bibliography. cable and as a result of these studies, it is hoped that
Abridgment of Paper to be presented at the Midwinter Convention
it will be possible:
of the A. I. E. E., New York, Ν. Y., February 9-12, 1925. Com­
plete copy to members on request. First to make the necessary changes in manufacturing

Potrebbero piacerti anche