11 KV Network
Manual
BU – DISTRIBUTION
Prepared by
Distribution Strategy & Planning
11KV Network Manual
Standard Operating Procedure
DISTRIBUTION:
cc: CEO
cc: COO Distribution
cc: DCOOs
cc: Dy. Director (Transmission Network)
cc: Dy. Director (Security)
cc: Director (IM)
cc: CMO (Medical)
cc: GM (FM)
11KV Network Manual
Standard Operating Procedure
INTRODUCTION..................................................................................................................................................................13
SCOPE .............................................................................................................................................................................13
MAIN SECTIONS OF 11KV MANUAL ......................................................................................................................................13
APPLICABILITY ...................................................................................................................................................................13
OBJECTIVE ........................................................................................................................................................................15
SCOPE .............................................................................................................................................................................15
FUNCTIONS .......................................................................................................................................................................16
PROCEDURE FOR DECLARATION OF FAULTS IN 11-KV NETWORK .................................................................................................18
1. Main Cable Fault..............................................................................................................................................18
1.1 M.CF Fault Declaration Procedure ............................................................................................................................18
2. HT Linking Cable Faults ....................................................................................................................................19
2.1 HT Linking Cable Fault Declaration Procedure .........................................................................................19
3. HT Overhead Main Faults ................................................................................................................................20
3.1. HT Conductor Broken Single Phase Conductor Broken.............................................................................................20
OBJECTIVE ........................................................................................................................................................................22
SCOPE .............................................................................................................................................................................22
TEAM FORMATION .............................................................................................................................................................22
LOGISTIC ..........................................................................................................................................................................22
TOOL BOX TALK .................................................................................................................................................................22
ROLES & RESPONSIBILITIES ..................................................................................................................................................22
PPES / SPES FOR FIELD STAFF ..............................................................................................................................................23
PROCEDURE: .....................................................................................................................................................................23
1. Arrangement of Shutdown for Local Transformer ...........................................................................................23
1.1. In case of Local Transformer 11KV Switch is Single Cable ........................................................................................23
1.2. In case of Local Transformer 11KV Switch is Double Cable to feeder Local Transformer and other HT circuits ......24
OBJECTIVE ........................................................................................................................................................................28
SCOPE .............................................................................................................................................................................28
TEAM FORMATION .............................................................................................................................................................28
LOGISTIC ..........................................................................................................................................................................28
RESPONSIBILITIES ...............................................................................................................................................................28
PPES / SPES FOR FIELD STAFF ..............................................................................................................................................28
PROCEDURE: .....................................................................................................................................................................29
1. Shutdown of HT Bus Bar of a feeder sub-station .............................................................................................29
1.1. Feeders OFF TFS with Danger Board .........................................................................................................................29
1.2. Position of 11KV Switch / Isolator / RMU in sub-station ..........................................................................................29
1.3. All linking cables incoming & outgoing from far end / S/S, RMU, Knife Switch & HT Overhead ...............................30
1.4. Position of 11KV scxwitch of local transformer in sub-station where busbar is required dead ...............................30
1.5. Performance Management (TATS) ...........................................................................................................................30
1.6. Shutdown of HT Busbar of a Non-Feeder Sub-Station Definition .............................................................................31
11KV Network Manual
Standard Operating Procedure
OBJECTIVE ........................................................................................................................................................................35
SCOPE .............................................................................................................................................................................35
TEAM FORMATION .............................................................................................................................................................35
LOGISTIC ..........................................................................................................................................................................35
TOOL BOX TALK .................................................................................................................................................................35
PPES / SPES FOR FIELD STAFF..............................................................................................................................................36
PROCEDURE: .....................................................................................................................................................................36
1. In case of Local Transformer 11KV Switch is Single Cable ...............................................................................36
2. In case of Local Transformer 11KV Switch is Double Cable to feeder Local Transformer and other HT circuits
37
CHAPTER 4 - TYPE TESTING OF SINGLE & THREE PHASE STATIC METERS ..................................................................... 39
PROCEDURE ......................................................................................................................................................................40
1. Selection Of Prototype Sample Meters ............................................................................................................40
2. Security & Meter Sealing .................................................................................................................................40
3. Testing Schedule ..............................................................................................................................................40
INTRODUCTION..................................................................................................................................................................43
OBJECTIVE ........................................................................................................................................................................43
SCOPE .............................................................................................................................................................................43
APPLICATIONS: ..................................................................................................................................................................43
EARTHING / GROUNDING PROCEDURE: ..................................................................................................................................43
MEASUREMENT OF EARTH RESISTANCE: .................................................................................................................................44
RESPONSIBILITIES: ..............................................................................................................................................................45
PURPOSE:.........................................................................................................................................................................47
SCOPE .............................................................................................................................................................................47
DISTRIBUTION & RESPONSIBILITY ..........................................................................................................................................47
PREREQUISITES WITH THE PROPOSAL FOR APPROVAL .................................................................................................................47
COST BENEFIT RATIO: .........................................................................................................................................................49
CHAPTER 7 - SAFETY PRECAUTIONS FOR ISOLATION & MAINTENANCE WORK ON HT / LT POLE & OVER HEAD LINES 50
OBJECTIVE ........................................................................................................................................................................51
SCOPE .............................................................................................................................................................................51
SAFETY TOOLS (PPES) / EQUIPMENTS FOR SUPERVISOR (ELECTRICAL) AND LINE MAN ...................................................................53
PPES AND TOOLS SHALL BE PROVIDED TO EVERY FIELD PERSON AS PER NATURE OF JOB. ....................................................................53
STANDARD TOOLS / EQUIPMENTS: ........................................................................................................................................54
SAFETY PROCEDURES AND PRECAUTIONS FOR WORKING ON POLES & TOWERS .............................................................................54
SAFETY PROCEDURE & PRECAUTIONS FOR WORKING ON OVERHEAD LINES ..................................................................................55
Working on Dead line and Equipment: .....................................................................................................................55
Working on lines and equipment adjacent to live equipment or lines: ....................................................................56
Work on Double Circuit Overhead lines with one Circuit alive shall not be carried out ............................................56
11KV Network Manual
Standard Operating Procedure
CHAPTER 8 - RESTORATION OF 11-KV FEEDERS AFTER TRIPPING FROM GRID STATION .............................................. 62
INTRODUCTION: ............................................................................................................................................................63
SCOPE ............................................................................................................................................................................63
APPLICABILITY ...............................................................................................................................................................63
PROCEDURE ..................................................................................................................................................................63
1. Situation – 1.....................................................................................................................................................63
2. Situation – 2.....................................................................................................................................................64
3. Situation – 3.....................................................................................................................................................64
3.1 SINGLE CABLE FEEDER AT GRID STATION. ................................................................................................................64
In case of single cable feeder from the G/S, If EFI at the incoming of the feeder is found Operated (or the incoming
OCB/VCB of the feeder is found operated) then it means that the main cable is sound, then ..............................................64
3.2 DOUBLE CABLE FEEDERS AT GRID STATION. .............................................................................................................65
GLOSSARY OF TERMS/ABBREVIATIONS .........................................................................................................................65
DEFINITIONS .....................................................................................................................................................................66
OBJECTIVE .....................................................................................................................................................................72
SCOPE: ...........................................................................................................................................................................72
ROLES & RESPONSIBILITIES: ..........................................................................................................................................72
1. SSM Site Supervisor: ........................................................................................................................................72
2. LT Supervisor: ..................................................................................................................................................72
3. AOC Supervisor: ...............................................................................................................................................72
4. SSM Sk. Fitter / S Sk. Fitter:..............................................................................................................................73
5. SSM Karkun:.....................................................................................................................................................73
6. AM – SSM: .......................................................................................................................................................73
7. Manager – SSM: ..............................................................................................................................................73
8. GM – HT: ..........................................................................................................................................................73
PROCESS FLOWS / PROCEDURE: ......................................................................................................................74
PERFORMANCE MANAGEMENT (TATS): ........................................................................................................................75
TOOLS, EQUIPMENT& LOGISTICS: .................................................................................................................................75
GANG FORMATION &COMPETENCY: ............................................................................................................................75
MATERIAL MANAGEMENT: ...........................................................................................................................................75
OBJECTIVE: ....................................................................................................................................................................77
SCOPE: ...........................................................................................................................................................................77
11KV Network Manual
Standard Operating Procedure
OBJECTIVE: ....................................................................................................................................................................82
SCOPE: ...........................................................................................................................................................................82
ROLES & RESPONSIBILITIES: ..........................................................................................................................................82
1. SSM Site Supervisor: ........................................................................................................................................82
2. AOC Supervisor: ...............................................................................................................................................82
3. UGM Jointer Gang: ..........................................................................................................................................82
4. SSM Sk. Fitter / S Sk. Fitter:..............................................................................................................................82
5. SSM Karkun:.....................................................................................................................................................82
6. AM – SSM: .......................................................................................................................................................82
7. Manager – SSM: ..............................................................................................................................................83
8. GM – HT: ..........................................................................................................................................................83
PROCESS FLOWS / PROCEDURE:....................................................................................................................................83
PERFORMANCE MANAGEMENT (TATS): ........................................................................................................................84
TOOLS, EQUIPMENT & LOGISTICS: ................................................................................................................................84
GANG FORMATION &COMPETENCY: ............................................................................................................................84
MATERIAL MANAGEMENT: ...........................................................................................................................................84
OBJECTIVE: ....................................................................................................................................................................86
ROLES & RESPONSIBILITIES: ..........................................................................................................................................86
1. In-Charge 118: .................................................................................................................................................86
2. Manager Network: ..........................................................................................................................................86
3. Control Engineer: .............................................................................................................................................86
4. DGM SSM:........................................................................................................................................................86
5. DGM Network: .................................................................................................................................................86
6. Dispatch Supervisor: ........................................................................................................................................86
SSM CONTROL: ................................................................................................................................................................86
HT OPN CONTROL: ...........................................................................................................................................................86
1. HT AOC Supervisor: ..........................................................................................................................................86
2. SSM Site Supervisor: ........................................................................................................................................87
3. GM – HT: ..........................................................................................................................................................87
PROCESS FLOWS / PROCEDURE:....................................................................................................................................87
11KV Network Manual
Standard Operating Procedure
OBJECTIVE: ....................................................................................................................................................................90
SCOPE: ...........................................................................................................................................................................90
ROLES & RESPONSIBILITIES: ..........................................................................................................................................90
1. SSM Site Supervisor: ........................................................................................................................................90
2. AOC Supervisor: ...............................................................................................................................................90
3. UGM Jointer Gang: ..........................................................................................................................................90
4. SSM Sk. Fitter / S Sk. Fitter:..............................................................................................................................90
5. SSM Karkun:.....................................................................................................................................................91
6. AM – SSM: .......................................................................................................................................................91
7. Manager – SSM: ..............................................................................................................................................91
8. Manager – SSM: ..............................................................................................................................................91
9. GM – HT: ..........................................................................................................................................................91
PROCESS FLOWS / PROCEDURE:....................................................................................................................................92
PERFORMANCE MANAGEMENT: ...................................................................................................................................93
TOOLS, EQUIPMENT& LOGISTICS: .................................................................................................................................93
GANG FORMATION: ......................................................................................................................................................93
MATERIAL MANAGEMENT: ...........................................................................................................................................93
CHAPTER 6 - REPLACEMENT OF LT LEADS OF TRANSFORMER TO LT PANEL, LT BUS BARS, HRC FUSES, BASES AND
OUTGOING LT CABLE TERMINATION IN SUBSTATION .................................................................................... 94
OBJECTIVE: ....................................................................................................................................................................95
SCOPE: ...........................................................................................................................................................................95
ROLES & RESPONSIBILITIES: ..........................................................................................................................................95
1. SSM Site Supervisor: ........................................................................................................................................95
2. AOC Supervisor: ...............................................................................................................................................95
3. IBC Supervisor: .................................................................................................................................................96
4. SSM Sk. Fitter / S Sk. Fitter:..............................................................................................................................96
5. UGM Jointer Gang: ..........................................................................................................................................96
6. SSM Karkun:.....................................................................................................................................................96
7. AM – SSM: .......................................................................................................................................................96
8. Manager – SSM: ..............................................................................................................................................96
9. GM – HT: ..........................................................................................................................................................96
PROCESS FLOWS / PROCEDURE:....................................................................................................................................97
PERFORMANCE MANAGEMENT (TATS): ........................................................................................................................98
TOOLS, EQUIPMENT& LOGISTICS: .................................................................................................................................98
GANG FORMATION &COMPETENCY: ............................................................................................................................98
MATERIAL MANAGEMENT: ...........................................................................................................................................98
OBJECTIVE: ..................................................................................................................................................................100
SCOPE: .........................................................................................................................................................................100
ROLES & RESPONSIBILITIES: ........................................................................................................................................100
1. SSM Site Supervisor: ......................................................................................................................................100
2. LT Supervisor: ................................................................................................................................................100
11KV Network Manual
Standard Operating Procedure
OBJECTIVE: ..................................................................................................................................................................105
SCOPE: .........................................................................................................................................................................105
ROLES & RESPONSIBILITIES: ........................................................................................................................................105
OPERATION SECTION: .......................................................................................................................................................105
SSM SECTION: ................................................................................................................................................................105
UGM SECTION: ..............................................................................................................................................................105
DISPATCH SUPERVISORS OF ALL 03 SECTIONS: ........................................................................................................................105
1. Gang supervisors: ..........................................................................................................................................105
2. Control In-Charge: .........................................................................................................................................106
3. Billing Managers / AMs: ................................................................................................................................106
4. DGM & GM: ...................................................................................................................................................106
5. Security Department:.....................................................................................................................................106
OBJECTIVE: ..................................................................................................................................................................108
SCOPE: .........................................................................................................................................................................108
ROLES & RESPONSIBILITIES: ........................................................................................................................................108
1. Consumer: ......................................................................................................................................................108
2. DCDCO: ..........................................................................................................................................................108
3. GM – HT: ........................................................................................................................................................108
4. DGM – SSM: ...................................................................................................................................................108
5. Manager – SSM: ............................................................................................................................................108
6. GM – IBC: .......................................................................................................................................................108
7. DGM – Network: ............................................................................................................................................108
8. Manager Network: ........................................................................................................................................109
9. Generator Operator: ......................................................................................................................................109
10. IBC gang:....................................................................................................................................................109
ROUTINE MAINTENANCE: ...........................................................................................................................................109
PROCESS FLOWS / PROCEDURE:..................................................................................................................................110
OBJECTIVE: ..................................................................................................................................................................112
SCOPE: .........................................................................................................................................................................112
ROLES & RESPONSIBILITIES: ........................................................................................................................................112
11KV Network Manual
Standard Operating Procedure
PURPOSE:.......................................................................................................................................................................118
SCOPE: ..........................................................................................................................................................................118
Material / Equipments: ...........................................................................................................................................119
Substation Location / Site Selection:.......................................................................................................................119
Construction Requirements: ...................................................................................................................................119
Provision of Fire Extinguisher ..................................................................................................................................120
SUB-STATION CONSTRUCTION: ...........................................................................................................................................120
DOCUMENTATIONS (AGREEMENT /UNDERTAKING): ...............................................................................................................121
OBJECTIVE: .....................................................................................................................................................................123
SCOPE: ..........................................................................................................................................................................123
ROLES & RESPONSIBILITIES ................................................................................................................................................123
PROCESS FLOW AND PROCEDURE ........................................................................................................................................124
Vacation of Substation............................................................................................................................................125
Execution of Civil Works ..........................................................................................................................................126
Reinstallation of Equipments and Accessories ........................................................................................................127
PERFORMANCE MANAGEMENT (TATS) ................................................................................................................................128
TOOLS AND EQUIPMENTS ..................................................................................................................................................128
TRAINING/ COMPETENCY ..................................................................................................................................................128
SAFETY...........................................................................................................................................................................128
Provision of Fire Extinguisher ..................................................................................................................................129
MATERIAL MANAGEMENT (ISSUANCE & RETURN OF MATERIAL) ................................................................................................129
ABBREVIATION ............................................................................................................................................................130
DEFINITION .....................................................................................................................................................................130
SCOPE: .........................................................................................................................................................................133
REQUIREMENT: ...........................................................................................................................................................133
FUNCTIONS .................................................................................................................................................................135
11KV Network Manual
Standard Operating Procedure
RECOMMENDATIONS:............................................................................................................................................... 146
INTRODUCTION: ..........................................................................................................................................................151
OBJECTIVE: ..................................................................................................................................................................151
WORKING PLAN: .........................................................................................................................................................151
WORK FLOW................................................................................................................................................................151
WORK SCOPE ...............................................................................................................................................................152
TRAINING ....................................................................................................................................................................152
GANG COMPOSITION: .................................................................................................................................................152
ROLES & RESPONSIBILITIES: ........................................................................................................................................153
1. 118 Response team: ......................................................................................................................................153
2. GM IBC ...........................................................................................................................................................153
3. Fitter ..............................................................................................................................................................153
4. L.M.O / Sk. / S.Sk. Lineman ............................................................................................................................153
5. Karkun ...........................................................................................................................................................153
6. DGM Networks ..............................................................................................................................................154
7. Maintenance Manager: .................................................................................................................................154
8. Dispatch supervisor: ......................................................................................................................................154
11KV Network Manual
Standard Operating Procedure
INTRODUCTION: ..........................................................................................................................................................156
OBJECTIVE: ..................................................................................................................................................................156
WORKING PLAN: .........................................................................................................................................................156
WORK FLOW................................................................................................................................................................156
WORK SCOPE ...............................................................................................................................................................157
TRAINING ....................................................................................................................................................................157
GANG COMPOSITION: .................................................................................................................................................157
ROLES & RESPONSIBILITIES: ........................................................................................................................................158
GM IBC ....................................................................................................................................................................158
DGM Networks .......................................................................................................................................................158
Maintenance Manager: ..........................................................................................................................................158
Dispatch supervisor: ...............................................................................................................................................158
Site supervisor:........................................................................................................................................................158
MATERIAL MANAGMENT: ...........................................................................................................................................159
PERFORMANCE MONITORING: ...................................................................................................................................159
SAFETY CONSIDERATIONS: ..........................................................................................................................................159
INTRODUCTION: ..........................................................................................................................................................161
OBJECTIVE: ..................................................................................................................................................................161
WORKING: ...................................................................................................................................................................161
WORK SCOPE ...............................................................................................................................................................161
WORK FLOW....................................................................................................................................................................1
TRAINING ........................................................................................................................................................................1
ROLES & RESPONSIBILITIES: ............................................................................................................................................2
DGM- workshop: .........................................................................................................................................................2
Manager- workshop ...................................................................................................................................................2
AE/Supervisors- workshop ..........................................................................................................................................2
All other staff- workshop: ...........................................................................................................................................2
MATERIAL MANAGMENT: ...............................................................................................................................................2
SAFETY CONSIDERATIONS: ..............................................................................................................................................2
SECTION 7 ANNEXURE................................................................................................................................................. 45
Introduction
11 KV Network Manual has been prepared to Develop work procedure for Operations, Substation
Maintenance and Underground maintenance in line with safety policies & Procedure. The Manual consist
of three major sections illustrating major functions of 11KV network i-e Operations, SSM & UGM.
The first section defines the work procedure of 11KV operations including rectification / isolation of faulty
equipment, arrangement of shutdowns for any addition / alteration in existing HT / LT network, preventive
/ corrective maintenance activities, addition of new schemes, system improvement proposals, proposal for
new 11 KV feeders, new HT linking cables, placement of new RMU, 11KV switches, Isolator, LT Panels and
protective devices.
Second section outlines the work procedure of Substation Maintenance including Installation or
replacement of transformer, 11KV switches, isolator, Replacement of trolley, CT PT, RMU, cleaning of
carbonization HT busbar etc. It also covers guidelines for construction of new substation and
Reconstruction of damaged substation including the responsibilities of all the concerned departments.
Third section covers Underground Maintenance section along with its major subsections involved in
underground cable maintenance, fault rectification and installation of new cable network. This Manual also
covers the concept of Composite gangs, Universal gangs and regional workshops along with clearly defined
roles and responsibilities of all the concerned.
Scope
This Manual covers routine operations, maintenance and system improvement on 11 KV Distribution
Network (UG / OH) all over KESC.
Applicability
All KESC and 3rd Party staff.
11KV Network Manual
Standard Operating Procedure
Objective
The basic objective of this policy is to stream line procedure to devise for implementation on 11KV
distribution network. Activities related to smooth and accident free function of HT / LT network
distribution. Rectification / isolation of faulty equipment, and to arrange back feeding to the effected
consumers, arrangement of shutdowns for any addition / alteration in existing HT / LT network, preventive
/ corrective maintenance activities, addition of new schemes, system improvement proposals, proposal for
new 11 KV feeders, new HT linking cables, placement of new RMU, 11KV switches, Isolator, LT Panels, 11 KV
knife switches, Installation of EFI, capacitor banks in all regions.
This SOP is intended for implementation across all 11 KV Network operations to establish accident free 11
KV switching operations for staff working on Live / Dead Networks.
Shift Engineer will act as key person for implementation of SOP for all switching activities on 11 KV network.
Scope
This Policy covers all 11 KV Distribution operation / Maintenance / System Improvement Proposals / New
Schemes activities in KESC HT / LT Distribution Network including:
Functions
1. The 11 KV Network of each Region is to be monitored round the clock throughout 365 days by
respective shift Engineers (11 KV operation).
2. Shift engineers are responsible to take the charge from relieving shift with complete details of:
HT Main cable faults
HT linking cable faults
LT cable faults
HT O/H conductor broken and other O/H faults
PMT & local Transformer fault
11 KV switches / Isolator and RMU faults
All leads jobs and the Transient / sub-transient faults
Current status & number of feeders Tripping in hand with complete marking of operations (ON /
OFF)
Position at the HT network Distribution Drawing & it must be updated timely to check the status of
network faults list (Annex-A)
3. All shutdown request & availing departments details must be listed along with relevant formalities i.e.
A, B and C forms (Annex-B).
7. Feeder Tripping
Shift engineer must clearly dictate all 11 KV operations leading to normalization / isolation of faulty
zone to AE / Supervisor / FM at concerned operation center, later will be responsible to perform all
operation as dictated by operation control (shift engineer). AE operation center / Supervisor / FM
are responsible to maintain their relevant network and marked all the operation on network
drawing & register all details in log book / fault book / Message book. All operations performed by
the operation center must be conveyed to shift engineer. ( Detailed SOP enclosed)
SIP’s for HT / LT System Improvement Proposals for 11 V equipments / components new feeder
proposal are very important for smooth running of HT network. Proposal for new feeder may be
initiated if load on any 11 kv feeder reached to 70% or more, the proposal for additional feeder
must be consider as per system need. The basic observation for new Terminating Point of feeder
will be circulate from the Shift Engineer and field staff AE operation/AM/AM
(Admin)/Manager/DGM/GM/DCOO. The location of feeder Proposed must be not more than 2-2.5
kilometer and feeder propose at load center to relive more two feeders and provide operational
flexibility.
Similarly new HT linking Cables, for interconnection of feeders and improves isolations of feeders to
Provide feeder to feeder back feeding options. The Proposed, switches RMU, Isolator must be clear
at where the new link required to be connected.
Installation of Ring Main Units (RMUs) and Knife switches are very important the operational
concerned are required to Propose RMU at every long T-off of HT U/G / O/H network to
sectionalized the network in case of Tripping/faults. The installation of RMU/Knife switch will be
reduced the outage Time of the supply to customer.
Installation of new PMT under System Improvement Proposal from GM LT/VIBC the providing of HT
feeder must be decided by operation as per loading Position of Power Transformer, feeder and load
on HT/LT network.
Installation of Knife switches to be suggested at HT O/H Shackle points for large feeding HT O/H
feeders especially in the Orangi Town, vender, Uthal Bela the feeders of 100 or above HT spans.
This installation of Knife Switch will reduce the time for opened/closed the jumpers.
In case of HT conductor Broken more then 2-Spans must be forward to the concerned GM
(Network) for repairing of HT Spans and normalizing the area.
LT cable faults must be declared by operation with the coordination of the concerned
VIBC/Network and forward to UGM for repaired of cable special care must be taken during
repair/Back feeding of the area.
11KV Network Manual
Standard Operating Procedure
i. The first information of 11-KV feeder Tripping received from the concerned Grid station (S/D)
from the SBO to operation shift Engineer with the details of relays earth fault, Red, Yellow,
Blue, Instantaneous, with the details of surge (like light/heavy surge) observed at 11-KV VCB at
Grid-Station. Shift Engineer operation note all information at their log Book and desktop and
convey the same message to the concerned operation center and instruct to the AE/Supervisor
operation to dispatch MTL vehicle along with the line main gang.
ii. If all the relays at S/D operated then the shift engineer do not try the feeder, and field staff is
required to check the feeding of the 11-KV feeder and any information of flashover or blast on
HT/LT equipment received from the complaint center conveyed to HT operation must be check
first.
iii. If 11-KV feeder is terminating is Sub-Station VCB/OCB then the supervisor operation is required
to put OFF incoming S/D side switch of feeder in sub-station and try to check the different loops
of the 11-KV feeder and back feed at any other under load feeder with common isolations.
iv. In case of the all feeder loop found sound than the suspected Main cable fault can be declared
and conformed the Main cable fault if the main cable in back feeded at any other isolation
feeder’s feeding. If the isolation feeder tripped OFF then the main cable fault conform declared
with the remaining of back feeding operations.
v. After declaration of main cable fault the feeders 11-KV switch VCB at S/D must be at OFF,
trolley stage (TFS) rack out with Dander Board, the main cable fault also in the knowledge of
the Grid-Staff. (SBO)
vi. In Sub-Station the incoming S/D 11-KV switch trolley must be OFF trolley lower (T/L). If 11-KV
isolator than if must be OFF and Ground (E), In case of RMU incoming S/D side cable OFF and
Ground, Knife switch must be in OFF Position with loads opened and short at the knife switch,
similarly if the main cable is directly terminating at HT overhead mains cables lead must be
open and short by operational staff.
vii. After isolating the main cable from sub-station/RMU/Knife switch and S/D side with opened the
back plate of the S/D switch the job of main cable fault forwarded to concerned underground
maintenance department of R-I, II, III and IV etc.
viii. The area of the Effected main cable fault to be back feeded on the other feeders with common
isolations with the monitoring of loading position day/evening peak and must be in permissible
limit to avoid the addition of the cable faults.
ix. The operations carried out for the main cable fault of the feeder must be marked on shift
engineer network and concerned operation center network with details note in the log book.
11KV Network Manual
Standard Operating Procedure
x. In case of overloading expected during the evening peak hours the concert plan for the load
management must be observed by the Manager/Admin/AM/Shift engineer. Due to over
loading of the feeders taken the load of main cable faults feeder the rotation wise area
dumping is also the last option to save the network for further fault.
xi. The priority of main cable fault must be decided by the shift engineer/Manger
(admin)/DGM/GM as per network condition to clear the fault by UGM.
xii. After the testing procedure for U/G cable fault location pin painting of the fault, the necessary
jointing/termination and end repairing of the main cable fault, and final testing of the fault the
clearance of the main cable fault should be forwarded to concerned operation shift engineer by
the UGM.
xiii. After receiving of the clearance of main cable fault the concerned operating shift engineer
required to normalized the area of feeders at its normal feeding and standard isolation with
reversed all the performed operation and remove the back feeding of all loops.
i. Feeder Tripping information received from the concerned Grid (S/D) SBO to shift Engineer
Operation.
ii. After conformation of Main Cable fault is healthy by try the main cable at no load or back feed
at any other feeder. It’s the indication that fault occurred at the outgoing loops of the feeders
cable or other equipments like 11 KV switches, RMU, S/S bus bar, HT O/H Mains fault, PMT,
local Transformers of sub-station.
iii. At 1st Sub-Station / RMU / Knife switch / over head where the feeder is terminated, all
outgoing 11KV loops put ‘OFF’ with incoming S/D side put OFF.
iv. Main cable or feeder from the S/D put ON at no load.
v. Now the only 11KV Bus-Bar of the incoming Sub-Station put on if the feeder NOT Tripped OFF
than its means that the 11KV Bus-Bar is sound / Healthy all cable/Bus-Bar shrouds Trolley,
relays etc are in sound position if intact properly.
vi. If the feeder consists 03 Nos outgoing loops than the isolation of other feeders must be clearly
marked and clear/conformed to the field staff AE/Supervisor operation of the connected area
operation center.
vii. Try the loops one by one by reducing the relay setting at the existing feeder say two loops
found normal and the energized then the third loop do not try.
viii. Check the complete feeding of third loop if it’s the mixture of HT O/H Mains cables, Sub-Station
RMU, Knife switch etc. Then sectionalized the loop into two or more sections.
ix. If no any visible fault found than section/part of the loop one by one try if tripping occurred at
any section then, the fault, of HT linking cable must be declared clearly.
x. If fault between tow Sub-Stations occurred then the both sides of cable isolate at both the sub-
stations with OFF if switch trolley lower (T/L), if isolator/RMU then OFF and ground (OFF,E), if
O/H then open the leads at both end, if load at O/H and PMT.
11KV Network Manual
Standard Operating Procedure
xi. Job of the linking cable fault with the position of cable at the both end note in operation shift
engineer and area operation center, same fault forwarded to the Under Ground Maintenance
department (UGM) for repair purpose.
xii. The remaining area of the feeder may be back feed at any other isolation feeder with the
position of network decided by the shift engineer operation and field operation carried out by
AE/Supervisor operation of the area.
xiii. All operation must by mark at network with loading of relevant feeders. w.r.t day and evening
peak, proper schedule and load sheet must be maintain by shift engineer (OPN) and area
operation center
v. The effected loop completely isolate by the operation staff and line off and short /Earth at both
the effected ends.
vi. The area which can be back feed at any other feeder the operations performed by operation
supervisor with the isolation/loading position of feeder as per direction of shift engineer carried
out.
vii. The complete details of HT overhead fault if the No. of span broken more 2-spans to be
conveyed to network for repaired of HT O/H Mains with details of number of S/S or PMTs
effected
viii. After arrangement of proper shut down for repaired of HT O/H Mains spans by operation. The
effected portion handover the Mains (Network Department) staff and the HT conductor
repaired/Replaced by the same.
ix. After complete the task by Mains the clearance given to the operation shift engineer with the
details of short and other necessary information, same convey by operation shift engineer to
area operation for normalization of the fault with removal of back feeding
11KV Network Manual
Standard Operating Procedure
Objective
To assure arrangement of shutdown on Local Transformer of 11KV Distribution Sub-station for replacement
of local transformer, reinforcement of trafo or repair / replace / reinforcement of HT/LT cables feed to
trafo, replacement of LT panel / LT breaker or provide additional circuit to local trafo with all safety policies
and 11KV operational procedures
Scope
This SOP shall apply to all 11KV Operation Regional KESC and 3rd Party employees working on 11KV AOC and
11KV operation control rooms working on arrangement of shutdown for 11KV busbar of sub-station
Team Formation
Concerned AOC operation gang with following team formation:
Logistic
MTL
i. All operations must be clearly mention in separate sheet and C-Form duly signed by shift engineer
ii. AOC AE / Sub-engineer is responsible to carried out all the operations as directed by shift engineer
operation
iii. AOC AE / Sub-engineer responsible to completely de-energized the HT/LT feed of local transformer,
properly isolate and short all the outgoing LT circuits from LT panel
iv. AOC AE is responsible to handover the shutdown from to requesting / availing department
v. AOC AE is responsible to normalize shutdown of local transformer after completion of work and
getting clearance from requesting / availing department in writing with the instruction / clearance of
operation shift engineer
vi. AOC AE is responsible to check the all lines / circuit grounding / earth position and remove before
energization of circuits
11KV Network Manual
Standard Operating Procedure
vii. In case of any LT Circuit is required to back feed to provide supply to circuit then it should be clearly
mention and cable leads at O/H or any terminating point from S/S to be isolate properly by AE / Sub-
Engineer operation with the coordination of IBC / VIBC and LT Network
i. Uniform
ii. Safety shoes
iii. Helmet with chin strip
iv. Rubber & leather gloves
v. Live line tester
vi. Full body harness with front position belt
vii. Earth / grounding rope
viii. Danger board, safety tape
ix. Emergency light
x. Rain coats & gum boots (depending upon weather)
Procedure:
1. Arrangement of Shutdown for Local Transformer
The name of sub-station with its feeder name must be clearly communicate by shift engineer
operation to AOC AE at which the local transformer shutdown is requested
The 11KV switch for local transformer in relevant sub-station must be clearly identified by AE /
Sub-Engineer AOC with its HT feed whether its single cable or double cable
HT Cable
95 mm2
11KV Local
Incoming Transformer HT
Outgoing
11KV Feeder Circuit
Isolation
11 / .4 KV Local Transformer (500,
750, 1000, 1250 & 1500 KVA)
Single Core
HT Cable
300 mm2
Lead
Put LT
Breaker OFF LT Breaker .4 KV LT 8-Way
Panel
If LT Circuit O/H
back feed from
IBC / VIBC LT Circuit to
Leads of cable must
LT Bulk
be open & short
Supply
1.2. In case of Local Transformer 11KV Switch is Double Cable to feeder Local Transformer and
other HT circuits
Opposite
S/S PMTs
LT
Breaker
Case-C Case-B
Local
OFF T/L Transformer OFF T/L
Switch
11KV S/S
HT O/H Mains
In above mentioned drawing if local transformer 11KV switch is double cable with o/H HT circuit then the
HT/LT from the other cable must be isolate properly
11KV Network Manual
Standard Operating Procedure
Case-A
If local transformers 11KV switch is double cable local transformer outside S/S PMT then switch OFF trolley
lower (T/L) or trolley first stage (TFS) and at outside PMT HT cable leads required to be open and short
Case-B
If local transformers switch is double case local transformer HT O/H outgoing outside S/S then switch of
local transformer OFF trolley lower (T/L) for and OFF trolley first stage (TFS) for VCB with danger board
(DB). Isolate the HT cable from O/H by proper shutdown and open the leads of HT cable terminate from
sub-station to O/H with properly short & ground
Case-C
If local transformers switch is double cable local transfer HT outgoing cable to sub-station then switch of
local transformer OFF trolley lower (T/L) for OCB & OFF trolley first stage (TFS) for VCB with danger board
(DB). Isolate the HT cable from the far end sub-station put switch of local S/S side OFF T/L or TFS and back
feed the area if network loading of other feeders permitted
11KV Network Manual
Standard Operating Procedure
Objective
To assure arrangement of shutdown on 11KV Busbar of Distribution Sub-station with all safety polices and
11KV operational procedures
Scope
This SOP shall apply to all 11KV Operation Regional KESC and 3rd Party employees working on 11KV AOC and
11KV operation control rooms working on arrangement of shutdown for 11KV busbar of sub-station
Team Formation
01 Supervisory officer: AE / Sub-Engineer / Supervisor / Electrician General
01 Line Man: (S. SK L/M, L/M)
02 Karkun / Helper:
Logistic
MTL / Truck with B/L
Responsibilities
Manager / AM operation and control room shift engineers are responsible to arrange 11KV busbar
shutdown. Shift engineer will communicate all relevant 11KV operations through shutdown form and
wireless communication to AE / Sub-engineer area operation centre
i. All operations must be clearly mention in separate sheet and C-Form duly signed by shift engineer
ii. AOC AE / Sub-engineer is responsible to carried out all the operations as directed by shift engineer
iii. AOC AE / Sub-engineer responsible to completely de-energize the HT cables all incoming / outgoing
circuits and LT supply from local transformer with proper checking & grounding of circuits
iv. AOC AE is responsible to handover the shutdown from to requesting / availing department
v. AOC AE is responsible to normalize shutdown after getting clearance from requesting/availing
department with the instruction / clearance of operation shift engineer
Procedure:
1. Shutdown of HT Bus Bar of a feeder sub-station
1.1. Feeders OFF TFS with Danger Board
Get the feeder _(Name of feeder)_from relevant grid station OFF trolley first stage (TFS) and with
danger board (WDB) by operation engineer from concerned S/D SBO
OFF E
11 KV Feeder (WDB)
Terminating in OFF TFS WDB
RMU
OFF E
11 KV Feeder (WDB) OFF TFS WDB
Terminating at
Isolator
OFF &
Contact
11 KV Feeder
Ground
Terminating in Knife
Switch
K/S
OFF TFS WDB
11KV Feeder first
terminating at non-
feeding S/S then
directly to main S/S DFF T/L
(WDB)
1.3. All linking cables incoming & outgoing from far end / S/S, RMU, Knife Switch & HT
Overhead
All the HT (higher tension) linking cables terminating in the sub-station must be isolated and dead
firstly from where the same are in energized position and then in this sub-station.
1.4. Position of 11KV switch of local transformer in sub-station where busbar is required dead
11KV OCB / VCB of the local transformer OFF trolley lower / trolley first staged respectively
Put OFF LT breaker of local transformer
Pull out all the HRC fuses at the LT panel
Short all the phases and neutral to earth at LT panel with the earthing rope
Hang the danger boards flags / all the 11KV switch at far end sub-station, RMU & Knife Switch
Handover the shutdown B form to requesting / availing department by operation (AOC)
RMU
S/S-C
OFF
E
OFF TL or TFS
E 132 / 11KV
OFF OFF
&E T/L
S/S-B Incoming S/D
side switch OFF Feeder C OFF
T/L, TFS, OFF TFS WDB at S/
& Earth Isolator D
OFF TL HT B/S
or TFS Consumer Local
(WDB) Transformer
TL LT CB
LT
Panel
Pull LT
Fuse
Non-Feeder Sub-Station:
In 11KV distribution network a sub-station is called non-feeder sub-station where HT main cable
(feeder) from grid station is not directly terminate and symbolical represent as O, whereas in feeder
sub-station main cable is directly terminate in sub-station is called feeder sub-station symbolical
represent as
Identification of feeder name at which sub-station is energize when 11KV busbar shutdown of non-
feeder sub-station is required the OCB shift engineer first check the feeding point of that particular
busbar with feeder name and its isolation points
At far end sub-station, RMU, O/H mains, knife switch where the S/S in energize put incoming (source
point) as under:
At far end sub-station OFF trolley lower (T/L) with danger board (WDB) if it is OCB (oil circuit
breaker
At far end sub-station OFF trolley first stage (TFS) with danger board (WDB) if it is VCB vacuum
circuit breaker
At far end sub-station OFF trolley earth if it is isolator (put OFF source supply first also WDB)
At far end ring main unit (RMU) OFF and earth (put OFF source supply first) WDB
At far end knife switch OFF remove contact & short them
At far end HT O/H main then operation HT cable leads & short them (arrange shutdown of
overhead first)
11KV Network Manual
Standard Operating Procedure
HT O/H RMU
OFF E O/H
(WDB)
HT Cable
leads open
& short
OFF & E
(WDB) OFF TL or 11KV Feeder
OFF T/L TFS (WDB)
Grid
Station
LT
Panel
Pull LT
Fuse
Rest of operation as above explained in feeder sub-station 11KV busbar shutdown (clause #
9.1A(c)
11KV Network Manual
Standard Operating Procedure
END
11KV Network Manual
Standard Operating Procedure
Objective
To assure arrangement of shutdown on LT (.4KV) 8-way & 4-way panel feed through local transformer of
11KV General Distribution Sub-station
Scope
This SOP shall apply to all 11KV Operation Regional KESC and 3rd Party employees working on 11KV area
operation centre ( AOC) and 11KV operation control rooms working on arrangement of shutdown for .4KV
LT Panel
Team Formation
Concerned AOC operation gang with following team formation:
01 Supervisory officer: AE / Sub-Engineer / Supervisor / Electrician General
01 Line Man: (S. SK L/M, L/M)
02 Karkun / Helper:
Logistic
MTL / Truck with B/L
i. All operation must be clearly mention in separate sheet and C-Form duly signed by shift engineer. In
case of forced / emergency shutdown AE / Sub-Engineer must be follow the wireless communication
instruction of shift engineer operation and follow all the steps of operation as directed by shift engineer
ii. AOC AE / Sub-Engineer is responsible to carried out all the operation as directed by shift engineer
operation
iii. AOC AE / Sub-Engineer is responsible to completely de-energize the local transformer HT supply if
desired in shutdown, put LT breaker of local transformer OFF (if available LT breaker) check the supply
of HT by live line tester & LT by tester or test lamp and pullout the LT fuses from the LT panel circuits
with proper checking and grounding of the LT panel & LT circuits
iv. AOC AE is responsible to handover the shutdown form to requesting / availing department
v. AOC / AE is responsible to normalize shutdown after getting written clearance from requesting /
availing department with the instruction / clearance of operation shift engineer
vi. AOC AE is responsible to check the all circuit & LT panel grounding position and remove all shorts and
ground before normalization of shutdown
11KV Network Manual
Standard Operating Procedure
i. Uniform
i. Safety shoes
ii. Helmet with chin strip
iii. Rubber & leather gloves
iv. Live line tester
v. Full body harness with front position belt
vi. Earth / grounding rope
vii. LT tester or test lamp
viii. LT fuse puller
ix. Rain coats & gum boots (depending upon weather)
Procedure:
If only LT panel shutdown is required check the following position by AE AOC:
i. Is local transformer HT cable is connect as single cable with 11KV OCB or VCB?
ii. Is local transformer HT cable is connected as double cable with 11KV OCB or VCB for local
transformer or outside PMT, S/S, O/H live etc?
iii. Is LT circuit breaker installed at local transformer?
iv. Is at LT panel HRC fuses (base & grips) are available?
HT Cable
95 mm2
11KV Local
Incoming Transformer HT
Outgoing
11KV Feeder Circuit
Isolation
11 / .4 KV Local Transformer (500,
750, 1000, 1250 & 1500 KVA)
Single Core
HT Cable
300 mm2
Lead
Put LT
Breaker OFF LT Breaker .4 KV LT 8-Way
Panel
If LT Circuit O/H
back feed from
IBC / VIBC LT Circuit to
Leads of cable must
LT Bulk
be open & short
Supply
2. In case of Local Transformer 11KV Switch is Double Cable to feeder Local Transformer
and other HT circuits
Due to non-availability of switch in 11KV sub-station sometimes local transformers 11KV OCB /
VCB are made double cable with outside PMTs, O/H mains or other outgoing circuit to S/S,
RMU etc.
In such case special care is required from HT side when arrangement shutdown of local
transformer
11KV Network Manual
Standard Operating Procedure
Opposite
S/S PMTs
LT
Breaker
Case-C Case-B
Local
OFF T/L Transformer OFF T/L
Switch
11KV S/S
HT O/H Mains
In above mentioned drawing if local transformer 11KV switch is double cable with o/H HT circuit then the
HT/LT from the other cable must be isolate properly
Case-A
If local transformers 11KV switch is double cable local transformer outside S/S PMT then switch OFF trolley
lower (T/L) or trolley first stage (TFS) and at outside PMT HT cable leads required to be open and short
Case-B
If local transformers switch is double case local transformer HT O/H outgoing outside S/S then switch of
local transformer OFF trolley lower (T/L) for and OFF trolley first stage (TFS) for VCB with danger board
(DB). Isolate the HT cable from O/H by proper shutdown and open the leads of HT cable terminate from
sub-station to O/H with properly short & ground
Case-C
If local transformers switch is double cable local transfer HT outgoing cable to sub-station then switch of
local transformer OFF trolley lower (T/L) for OCB & OFF trolley first stage (TFS) for VCB with danger board
(DB). Isolate the HT cable from the far end sub-station put switch of local S/S side OFF T/L or TFS and back
feed the area if network loading of other feeders permitted
At all above cases after shutdown of HT feed to local transformer the rest of operations for LT panel to be
performed as per above procedure
11KV Network Manual
Standard Operating Procedure
Procedure
Guide line for type testing of single & three phase static meters.
The prototype meters will be approved prior to dispatching for type testing by the technical
scrutiny committee in line with recommendation given in the technical evaluation report.
Prior to the start of type tests, KESC inspection team should thoroughly verify their signature
and after that physical inspection of the offered sample meters testing would be carried
out.
If any ambiguity is found in the signature or any discrepancy during the physical inspection of
the sample meters, decision for rejection of sample are at the sole discretion of KESC inspecting
officials.
3. Testing Schedule
Prior to the departure of KESC witnessing officials, the bidder should furnish the test sequence
/ schedule duly signed from laboratory officials for all type tests.
The Tests Schedule would clearly mentioned the list of type tests to be carried out with
sequence in which these tests shall be performed on the offered prototype sample meters
in compliance with relevant IEC and KESC specification.
KESC inspecting officials should check the calibration of all tests equipment before
proceeding to type tests.
For single phase meters Clause 7.2 & 7.2.1 & for three phase static meters Clause 7.2
(Security Features), as mentioned in KESC Specification are to be carried out in
Independent Laboratory of international repute.
Verification test for functionality of software as per clause 13.4 of KESC Specification for
three phases static meters are to be carried out at Independent laboratory of
international repute.
If any tests mentioned in 2.3.3 & 2.3.4 cannot be conducted at the designated laboratory,
the KESC officials can take the decision to conduct these tests at manufacturer’s work, if
facilities for these tests are available.
11KV Network Manual
Standard Operating Procedure
Test Protocol for each test shall be signed by KESC Inspectors and bidder before start of
each test.
The KESC Inspection team should verify their signatures on the meters at any time during
the type testing.
Out of the two meters selected for type testing, if any one meter fails in one test, then the
bidder shall offer another sample for type testing, all tests (previously carried out and
remaining test shall be carried out on the new offered sample meter, if again the new
offered proto type meter (sample) fails in any test, then type testing shall be ceased and
meters shall be declared rejected being failed in type testing.
The meters under tests would be sealed daily by the KESC officials at the close of testing
activity on that day.
Everyday prior to the start of testing, KESC officials would check for the healthiness of
sealing.
KESC inspecting officials may ask for any test / tests other then specified in relevant IEC /
KESC specification to confirm the features already mentioned in KESC specification.
11KV Network Manual
Standard Operating Procedure
Introduction
The non-current carrying metallic parts in every electrical installation are connected to the underground
earthing system for safety of personnel and for discharging fault currents. The connecting of non-current
carrying metallic parts to underground earthing system are called equipment earthing (grounding).
An electrical earthing system is designed to provide safe & correct operation of the network under normal,
earth fault & transient conditions.
Objective
To provide guide lines for proper earthing / grounding of HT / LT equipments / materials used in KESC
distribution network.
Scope
This SOP covers the requirement of grounding system and need to develop for a systematic approach to its
design, installation, inspection, testing and maintenance of distribution grounding system.
Applications:
Each & every Sub-Station equipment, PMT, RMU, DO cut out, Lightning arrestors, Capacitor banks,
Knife Switches & all metallic enclosures for protective equipment, distribution & metering
equipments shall be earthed / grounded as per Annexure – C,D,E&F (Attached)
Every Fifth pole of HT / LT network shall be earthed as per Annexure – B, G,H & I (Attached)
Earth wire shall be provided for LT O/H Mains as per Annexure – G&H (Attached)
Guard wire to be provided at both sides of the pole between neutral and earth for LT O/H mains as
per Annexure G & H (Attached)
Guard wire shall be provided on HT & LT at each Railway and Road crossings.
Double Earth wire on HT O/H Mains shall be provided as per Annex’ I (Attached)’
The messenger of HT / LT Aerial Bundled Cable shall be connected to the KESC earthing system at
both ends.
Fix lug on earth plate with brass nut & bolt (as shown in sketch) of size mentioned in BOQ
Punch 70 mm² tinned copper lug on the other end of stranded 3/0 copper conductor for connection
at PMT pole base / earthing strip in S/S
Bore up to a depth of at least 21 feet with a circular diameter of 5 inch
Insert stranded copper conductor 3/0 with copper plate in the bore upto its depth from plate side
Insert ¾ inch PVC pipe in the bore up to the depth for afterward curing & maintenance of earth point
as per Annexure – B (Attached).
Take out one terminal of stranded copper 3/0 conductor and connect it with the pole at base with 70
mm² copper lug.
Fill the bore with a mixture of lime, salt & coal in the ratio of 1:2:3 respectively 18" (inches) below the
ground level. Fill 12 “concrete in the bore & finally back fill the bore with normal soil up to ground
level
Excavate trench of 6 inches width and 12 inches deep from grounding point (bore) to pole base &
from pole to pole / S/S wall. PVC pipe will also run with conductor in trench & will be terminated
slightly above pole base
Place stranded copper grounding conductor emanating from grounding pit in the trench up to pole
base & connect copper lug at pole base & at mid point with nut & bolt already welded / on earth strip
in S/S
Tee-off trench & conductor with PG clamp in run for 2nd pole for grounding of PMT. Back filling of
trench & connection of conductor with 70 mm² lug at pole base.
Fill trench with concrete up to 9 inches from the base & back fill the trench up to ground level with
normal soil
Connect ground terminals of all equipment i.e. PMT neutral, D.O. cutout, capacitor, DB, knife switch
etc & at 11 KV OCB / VCB panel , LT panel, Transformer, EFI etc in S/S
quite large and is interfering with the measurement. Repeat the resistance measurements with the
potential probe ‘P’ at 50%, 60% and 70% of the distance to ‘C’.
Responsibilities:
Detailed survey is to be conducted by the designated field staff, assigned by respective regional
DCOO’s / DD / GMs (HT / LT), which will point out the locations / equipments where grounding is to
be provided.
DGM /Manager / AM will maintain data base / record of grounding pits in their respective regions /
IBC / VIBC / HT / LT.
Designated field staff under the supervision / guidance of AM in their respective regions / IBC / VIBC /
HT / LT shall test the resistance of existing earthing points. The resistance should be 1 or less
than 1 Ω. If the resistance exceeds 1Ω, complete maintenance of earth point is to be carried out
with watering to limit the ground resistance to the defined limit.
The disconnected earth conductor in run from earthing point for PMT & Sub Station is to be repaired
in accordance to the sketch attached Annexure - K & L (Attached).
Each earthing point shall be checked & tested once in a year.
System engineering department (SE) is to provide NEW earthing for PMTs & Sub Stations only.
GM (SE) will arrange contractor / man power / field staff for providing new earthing point as per
requirement of GM IBC / VIBC & GM HT / LT.
Grounding / Earthing done by the contractor shall be tested by the SE engineers in the presence of
contractor and forwarded a test report to GM HT / LT of respective region.
GM SE will ensure proper connection of PMT neutral, D.O base, capacitor, metallic enclosures etc
with earth point after arranging shut down & likewise all earthing terminals should be looped &
connected to earth point in Sub Stations.
GM (SE) shall update the progress to concerned DCOO’s / Dir (TPRE)) / GM (HT / LT) on monthly basis.
New Connection (NC) department shall ensure all extensions in HT / LT network distribution system is
properly earthed / grounded as per this SOP & details of all earthing points along with the earth
resistance result shall be submitted to GM HT / LT of respective region prior to switching ‘ON’ the
scheme.
11KV Network Manual
Standard Operating Procedure
Purpose:
The basic objective of this policy is to stream line procedure to device and implement system improvement
proposal (SIP) related to new / Reinforcement of PMT / Distribution Transformer in S/S, HT & LT cables / HT
& LT O/H Mains, or any other associated addition / modification to the HT and LT Network.
Scope
The policy covers all system improvement proposals / activities in KESC- HT / LT Distribution network.
Objective
To assure safe work place and environment for maintenance, operation at KESC HT / LT overhead
distribution network. Promote and facilitate continuous improvement of electrical safety policies and
practices.
Scope
This SOP shall apply to all KESC employees working on HT / LT poles and lines, visitors, on-site
contractors, subcontractors and any other related person, to prevent electrical and related hazards.
Responsibility
GM HT, GM IBCs, GM NC, GM (E&C), GM (TLR) & GM HSEQ.
If the pole is defective / rusted, supervisor / lineman shall not climb on the pole before taking
safety measures as defined in this SOP. In case of above two defects are observed remove /break
the cemented pole base and dig 1 to 1 ½ feet around the pole base to physically check whether
the pole is corroded or not. Corroded poles are to be replaced.
Pole Support i.e. Stay Wire, Strut Unit, Flying Stay etc. along with Foundation shall be thoroughly
checked and if found damaged, same shall be replaced accordingly.
Healthiness of Pole Hardware’s i.e. Brackets, Clamps, and Insulators etc. shall be inspected
thoroughly. If found in deteriorated position, shall be replaced accordingly.
Special care of the Poles should be taken in conversion schemes of HT/LT overhead mains into HT
and LT ABC Schemes.
HT Operation, IBCs, E&C and TLR shall maintain record for such defected poles as per attached
Section 1 Annexure –D & E (for HT & LT Pole separately) and share with HSEQ department for
preventive action.
Procedure
Conductor Broken
To attend in line conductor broken faults, proper isolation and shut down shall be arranged by
AOC (Area Operation Center) in coordination with concerned IBC as per SOP for line isolation.
Over- head maintenance staff deputed for repair of wire broken shall confirm the opening of line
jumpers near shackle points and ensure that line is properly isolated, short and ground at all
feeding ends.
Maintenance AE / Supervisor shall ensure the healthiness of HT pole involved in the shut down as
mentioned above.
If poles are observed healthy then repair of broken conductor / conductors shall be carried out in
a way that at one instance only one conductor shall be repaired / replaced.
On the contrary if poles are observed unsecured / unhealthy, site AE / supervisor shall report to
concerned AM / Manager for further advice. If AM / Manger observed that the poles are not safe
enough to carry out repairing activity then decision will be taken in coordination with DGM/GM
for the replacement of poles / poles may be arranged.
In order to repair HT jumper / jumpers or HT Cable lead / leads in case of burnt out at HT
overhead mains, shut down shall be arranged as per SOP # SOP/D/R&D/ESP/0602 for Line
Isolation along with proper isolation and grounding of HT line /lines.
Healthiness of HT Pole wherever there is fault at shackle point shall be treated same as defined
above.
If existing HT Pole is sound enough, jumpers and cable leads can be repaired accordingly.
If the strength of HT pole is doubtful and declared by AE / AM for replacement, same information
shall be shared with manager / DGM / GM for replacement of pole.
Regional Operation / IBC / TLR / E&C / NC will maintain record for replacement of HT / LT Poles
and instructions will be issued for working with great care and precautions before the said pole /
poles are replaced as attached Section1 Annexure “D” & “E”.
11KV Network Manual
Standard Operating Procedure
The above procedure shall be followed in case of following HT/LT overhead faults / repairs:
Note: In Case of utmost urgency, where back feeding of affected area is not possible it is suggested to
use Hydraulics MTLs having buckets.
Safety Tools (PPEs) / Equipments For Supervisor (electrical) and Line Man
Before starting any work at site, Personal Protective Equipments and special tools shall be provided to each
Foreman / Sub-Engineer or as deemed necessary to concerned staff deputed to work at site.
Binoculars 1 No
Tong Tester 1 No
Stopwatch 1 No
Magnifying glass 1 No
Earth resistance Tester 1 No
High Voltage Detector (Live Line Tester) 1 No
(Handy type)
Megger 1 No
Measuring Tape 1 No
PPEs and tools shall be provided to every field person as per nature of job.
Personal Protective Equipments (PPEs) shall be in accordance with SOP/D/R&D/ESP/0601-2009.
Following are the minimum requirement of safety devices and special tools;
i. Rubber Gloves, Gauntlets and Rubber Mats(Class-2 Rubber Gloves for HT as per 5.1.2 & 5.1.3 in
addition to Rubber Sleeves)
ii. Full body harness with front position Safety Belt
iii. Safety Boots
iv. Insulated Safety Caps with chin strap (helmet with face shield for supervisory staff), Leather Protective
Gloves
v. Safety Clothing
vi. Safety goggles / Face shields
viii. Bamboo Ladders/MTL Ladders
ix. Manila Rope
x. Rain Coat
xi. Gum Boot
xii. Live Line Tester (Small one recently procured workable for HT and LT)
11KV Network Manual
Standard Operating Procedure
Rubber Insulated Gloves along with Rubber Insulated Sleeves and Rubber Insulated Mate shall be used
according to relevant KESC Standard Specification No. K/R&D/RG/50/2011
In case if more than one person is required to work on elevated place / pole, the second man should
not start climbing until the first man reaches at safe position or when descending until the first man is
on the ground.
Prior to start of work, the lineman should put his safety belt / full body harness around the pole or
some other suitable supports and make sure that the belt is properly secured. Care should be taken to
prevent the straps on safety belt coming in contact with anything that may open the snap and thus
release the safety belt. Safety belts should not be attached to insulator pins, mains wire, guard wires
etc.
Linemen's tools shall be so secured that they will not fall out of the tool belts. A lineman shall carry
only the minimum number of tools. All other tools shall be kept on the ground until they are required
and then lifted up by means of a material bag attached to a rope.
Ordinarily no lineman shall work vertically below another lineman on the same pole except under
emergencies. When this condition is necessary, extreme care should be taken to prevent tools or
other objects being dropped upon the man working just below.
When shifting wires and equipment from an existing to a new pole, the existing pole shall either be
locked with the new pole or guarded or both, as the condition may demand i.e. before start of work
i.e, before starting off loading.)
Before a Lineman cuts an overhead conductor he shall make sure that it will fall at clear place. If there
is a possibility of the falling line may came in contact with another wire or causing other damages, it
shall be lowered to ground with a manila rope.
All light equipment and tools to be used aloft shall be raised and lowered by means of a hand line and
canvas bucket, men on the ground should stand clear of overhead work to prevent being struck by
falling objects.
In no case the tools / materials shall be thrown upward from ground to a lineman working at height,
nor shall lineman throw tools and materials from working place to the ground.
No site working staff shall work in such a manner that his arms or any tools extend beyond the body of
pole.
After completion of assigned job, all broken insulators or any other sharp edged material shall not be
left in open place/ along the walk way or in the location where the hazard of cutting feet could be
caused for humans or animals, the same should be taken back to area office for proper disposal.
Extreme care should be taken when stringing wires across streets and highways, avoid interfering with
traffic which might cause injury to workmen or pedestrians. Danger signs should be placed on both
sides of the work location and where conditions warrant, flag-men shall be stationed.
Hand lines, materials, tools or equipment shall not be scattered around streets, side walks, highways,
etc. these must be kept in a neat and orderly manner simply to avoid accident.
Conductor from ground / pole shall be raised or lowered respectively with a dry hand line and extreme
care shall be exercised to prevent them from coming in contact with live lines and equipment.
Prior to the start of work, the circuit shall be properly isolated and grounded at both ends. A danger
sign board to be fixed which should be clearly visible.
After switching off the supply, before touching the lines, every one conductor shall be tested with
live line tester, in case there is no voltage then discharges the conductors by discharging rod (this
be done at the time of grounding / shorting with grounding rod). The discharging rods should be
kept at least two feet away from the body. This procedure is necessary in order to make sure that
the line to be worked on is actually the line that has been isolated. Rubber gloves along with
leather protecting gauntlet and rubber sleeve shall be used on both hands.
All the conductors shall then be shorted together and adequately grounded; this shall be done at
the points on each side of the place thereby creating a safety zone where the work is to be carried
out. Rubber hand gloves with leather gauntlets must be used while doing this work. Poles on which
work is to be carried out shall also be grounded.
All phases shall be grounded even if work is to be carried out on one phase only.
When work is to be carried out on lines of isolated conductors where grounding points are not
provided at point of work, temporary groundings should be used from the nearest available
ground.
Where two or more teams are working independently on the same line or equipment, each team
shall properly protect themselves by placing their own independent ground.
Work on Double Circuit Overhead lines with one Circuit alive shall not be carried out
Repair work on H.T. lines on poles where L.T is also running under H.T shall be carried out only after
switching off the L.T mains with ground / short effectively. Work on the L.T lines shall not be carried
out unless taking extreme safety precautions as already elaborated in clause 5.
In case of LT Breaker fault, the LT mains at that PMT if back fed from near by PMT, then a danger
board must be fixed along with proper intimation at HT operation center from LT customer center.
Some time HT is got off, for repair of LT at the same poles. If the LT emanates from the source
running on other feeder, then at the time of giving completion report, it must be reminded to
operation that LT is energized, so that L/M while going to remove short on HT must be aware of it
LT will be energized after removal of short on HT side.
After completion of the job and prior to giving clearance for switching it ‘ON’, team in-charge shall
make sure that all short and ground are removed and all equipments used had been removed from
workplace.
For further safety, lineman shall use the rubber insulating matting size 2.5'x4' and shall be placed
on conductor in front of him during work.
11KV Network Manual
Standard Operating Procedure
After repair work ensure that all shorts and grounds have been removed, prior to clearance for
switching “ON” the supply.
If circuit breaker is not installed / by passed, following shall be followed:
After wearing HT Rubber Insulated gloves along with leather protector gloves on both hands
& other PPE’s, operation AE / site in charge will Switch ‘OFF’ PMT from HT side, and check
for absence of HT Supply through HT Live Line Tester and isolate PMT by dropping HT Fuse
Link (D.O. Cutout).
Pull out the all three LT HRC Fuses from DBs / Fuse Boxes. Ensure absence of supply through
test lamp at outgoing side of DB. Short & ground all LT circuits (Phase & neutral).
Short & ground (Phases & neutral) HT & LT side of PMT at bushing terminals
It is to be ensured by the site in-charge that proper earthing / grounding is available at point
of work , in case of non-provision/existence of appropriate grounding, temporary earthing
should be used from the nearest available ground.
Now repair/replace the LT lead from Transformer LT Bushing to LT Circuit
Breaker/Distribution Box.
Remove all short & ground from both HT & LT sides after completion of job.
After getting clearance from site in-charge, insert the LT HRC Fuses in the DBs / Fuse Boxes
and then get the PMT energized from HT side.
Replacement of LT Fuses in DB
Ensure that lineman to wear proper PPEs / SPEs, especially Rubber insulated gloves class’00’ with
leather protector gloves on both hands & safety shoes before start of work, and should fastened
his full body safety harness with front position safety belt, around the pole and make sure that the
safety belt is properly secured.
IBC / VIBC A.E / Site In charge (Supervisor)/Line Man (LT) shall be responsible to supervise all the
activities.
AE/Site In charge (Supervisor)/ Line Man (LT) will put ‘OFF’ the circuit breaker at PMT.
Verify that there is no voltage at the outgoing side of the circuit breaker & pull out HRC fuses
from DBs / Fuse Boxes. Short & ground LT circuits (All phases & neutral).
Site supervisor IBC/VIBC/ Line Man (LT) will Check physically LT over head mains, identify and
remove the fault, causing for blown off fuse & replace/change blown off fuses in DBs / Fuse
Boxes.
Remove short & ground from LT circuits.
Put ‘ON’ the circuit breaker.
If circuit breaker is not installed / by passed, following shall be followed
After wearing HT Rubber Insulated gloves along with leather protector gloves on both hands &
other PPE’s, operation AE / site in charge will Switch ‘OFF’ PMT from HT side, and check for
absence of HT Supply through HT Live Line Tester and isolate PMT by dropping HT Fuse Link
(D.O. Cutout).
Pull out the all three LT HRC Fuses from DBs / Fuse Boxes. Ensure absence of supply through
test lamp at outgoing side of DB. Short & ground all LT circuits (Phase & neutral).
Short & ground HT & LT (Phases & neutral) side of PMT at bushing terminals.
It is to be ensured by the site in-charge that proper earthing / grounding is available at point of
work , in case of non-provision/existence of appropriate grounding, temporary earthing should
be used from the nearest available ground.
Site supervisor IBC/VIBC will Check physically LT over head mains, identify and remove the
fault, causing for blown off fuse & replace/change blown off fuses in DBs / Fuse Boxes.
Now replace/insert the LT HRC Fusses in Distribution Box.
Remove all short & grounds from both HT & LT sides after completion of job.
After getting clearance from site in-charge, get the PMT energized from HT side.
If fuse (s) instantly blow OFF again that will indicate a definite fault in the circuit.
If the fuse (s) blow OFF with the passage of time, it indicates circuit over loading that can be
controlled by balancing/removing the over loading. Fuse shall be replaced after that.
Clearance of LT circuit will be given by IBC/VIBC to concerned 11 KV operation center for the
replacement of LT HRC fuse(s).
11 KV operation supervisor will wear the PPEs/SPEs before the start of the following operation:
Put OFF the LT circuit breaker and ensure the absence of supply at outgoing side of the breaker / LT
panel. If LT circuit breaker is not installed/by passed, put OFF & lower the trolley of 11 KV (HT)
switch of local transformer. Check the absence of HT supply at transformer through HT live line
tester / LT with test lamp.
Short & ground All LT bus bars (Phases & neutral).
Replace the LT HRC Fuses and remove the short / ground from bus bar.
Put ON the LT circuit breaker/switch ON the transformer from HT side.
If fuse (s) instantly blow OFF again that will indicate a definite fault in the circuit.
If the fuse (s) blow OFF with the passage of time, it indicates circuit over loading that can be
controlled by balancing/removing the over loading. Fuse shall be replaced after that.
Responsibilities of Supervisor(HT/LT):
Supervisor shall brief the following to field staff before the commencement of work to be executed:
INTRODUCTION:
This document is developed as Standard Operating Procedure for restoring the tripped 11-KV feeders, so as
to avoid repeated “Tries” on the faulty feeders and flow of convulsive fault currents in the Grid Power
Transformer that may ultimately cause severe damages to the windings. This SOP is to be adopted and
followed by 11KV Distribution Operation, Grid SBO and LDC Engineers.
SCOPE
The power transformers installed in the Grid Station have crossed their maximum life and ages up to 40
years or more. The EHT system has now become redundant and it can’t be tried now and then due to the
constraints of 11 KV system. In order to manage all mentioned issues a team was formed that included all
the GMs of HT, personnel from LDC and Grid and few senior staff with vast knowledge of network. For the
same purpose, Standard Operating Procedure (SOP) is developed to avoid repeated tries on the faulty
feeders.
The SOP will be advantageous in a way that it will secure our system and the equipments installed in the
network. This will not only increase the reliability of the system but it will also ensure the safety of
equipment’s as well as the personnel working on them.
APPLICABILITY
11-KV Operation Controls, Area Operation Centers and LDC.
PROCEDURE
1. Situation – 1
In case of 11-KV feeder tripping at G/S with following condition:
a. Phase to phase relay indications,
b. RYB E-inst / time delay indications,
c. Any relay indication with heavy surge
d. Power Transformer tripped either from 11 KV or 132 KV or both sides then,
Action: Grid - SBO will inform LDC and HT Operation Shift Engineer. LDC Shift Engineer will
then inform SBO not to put “ON” the feeder, even if the HT Operation Shift Engineer
requests for a “Try”.
The status of Protection Relay shall be properly recorded by SBO at the VCB of feeder, 11KV
I/C of transformer and 132 KV breaker.
For switching “ON” such feeder, HT Operation Engineer will ensure one of the following
actions and will inform LDC through E-Mail/SMS. The LDC Engineer will inform SBO for
putting “ON” such feeder on receiving clearance from Operation Engineer and will reply to
operation engineer accordingly.
2. Situation – 2
3. Situation – 3
In case the feeder trips “OFF” again, following procedure will be adopted.
In case of single cable feeder from the G/S, If EFI at the incoming of the feeder is found Operated
(or the incoming OCB/VCB of the feeder is found operated) then it means that the main cable is
sound, then
3.1.1. Switch “OFF” the outgoing loops on which EFI has operated.
11KV Network Manual
Standard Operating Procedure
3.1.2. Switch “OFF” the incoming of feeder, Local Transformer and all outgoing switches.
3.1.3. Get the feeder Switch “ON” from the G/S, after checking the Grid VCB of the feeder by the SBO
at the G/S.
3.1.4. Check all the suspected loops on the basis of EFI operated.
3.1.6. Switch “ON” the loops one by one to normalize the Network.
3.1.7. If EFIs have not installed at the outgoing loops, check all the loops thoroughly to trace the faulty
section, isolate the faulty section and then put “ON” the healthy loops one by one, this may
again cause tripping of the feeder, if the faulty section was not traced or due to multiple faults,
then repeat the above procedure more carefully.
3.1.8. If while going through step (3.1.7) feeder tripped again then step (3.1.1 ~ 3.1.6) will be followed
according to relay operation.
3.2.2. Installed at the G/S and on tripping of the feeder the SBO will inform whether EFI has operated
or not. In case the EFI gets operated the fault will be in the feeder “A” side and if the EFI did not
operate at the G/S then the fault will be in the feeder “B” side, therefore, operation staff may
accordingly be dispatched to attend the tripping of the feeder.
3.2.3. If the feeder trips with EFI operated at the G/S, then fault is at feeder “A” side, get EFI at the
incoming of feeder “A” be checked, if it is found not operated, then declare the main cable of
feeder “A” faulty, get the faulty cable isolated and normalize the healthy one, otherwise if the
EFI is found operated then follow the instruction (3.1.2) to (3.1.7).
3.1.21. If the feeder trips without operating EFI at the G/S, then fault is at feeder “B” side. Get EFI at
the incoming of the feeder “B” be checked and if it is found not operated then declare the main
cable of feeder “B” faulty. Get the faulty cable isolated and normalize the healthy one,
otherwise if the EFI is found operated then follow the instruction (3.1.2) to (3.1.8).
3.1.22. In case EFI is not installed / faulty / timed-out due to delayed attendance, instructions (3.1.1) to
(3.1.6) will be followed by Operation engineer.
GLOSSARY OF TERMS/ABBREVIATIONS
HT = 11 KV
G/S = Grid Station
LDC = Load Dispatch Centre
VCB = Vacuum Circuit Breaker
11KV Network Manual
Standard Operating Procedure
Definitions
Approved
When applied to articles of protective equipment means that these articles have been specified for use by
permanent / contract & outsourced employees as per HSEQ
Authorized Person
An Authorized person is a person authorized to carry out such duties incidental to the distribution and
use of electrical energy, the nature of which shall depend upon the technical knowledge and experience of
the individual and he shall not be less in authority than a lineman, jointer, fitter and mechanic.
Earth
Earth means the conducting mass of earth or a conductor / strip / wire connected to it through very small
impedance.
Electrical Equipment
It means all the electrical apparatus pertaining to the distribution and utilization of electrical energy.
Emergency
Emergency means that an unusual condition exists which endangers life and or property.
Employee
Employee means a person who is in receipt of pay, salary and other benefits from the company time to
time in lieu of services render by him.
Hazard
It is any unsafe act or unsafe condition that may lead to injury of persons or damage to property.
Isolated
It means physically disconnected from all possible sources of supply.
Permit to Work
It means a form of declaration issued by an Authorized Person (PSC) to another Authorized Person (sub
distribution) for a work to be carried out on any equipment in normal & break down conditions.
Protective Devices
It means equipment specially designed for the protection of workmen and includes fire extinguishers also.
Qualified
Qualified means any person who has adequate knowledge of the hazards involved in any operation.
Working Party
It means the persons under the immediate supervision of an Authorized Person.
Working on Height
Before any work is began on any pole or tower of a high voltage overhead line, which is adjacent and
parallel to any other high voltage overhead line with conductors “alive” or any pole or tower which
supports, more than one set of high voltage conductors “alive” the following special precautions, in
addition to the foregoing, shall be taken in every case:
i. The authorized person in charge of the work shall ensure that each workman who is to work on the
poles or towers is definitely informed and thoroughly understands on which set of conductors the
work is to be carried out.
ii. A “red” flag / Caution Tape (or lamp at night) which are available with maintenance crew, shall be
displayed on the side of the pole or structure on which the conductors are “alive”.
iii. Work shall not be performed on any higher position of tower / line when a line below is energized.
Working in Sub-Stations
i. Safety Tags should be placed on all enclosures of high voltage equipment and wherever necessary
warn persons of the presence of high voltage equipment. The different safety audits to be
conducted as per guidelines provided in document
ii. Gates in switchyard fences and doors to switch gear and other enclosures containing live equipment,
or other hazards, should be kept locked at all times except when Authorized Person entered for
working inside.
11KV Network Manual
Standard Operating Procedure
iii. When carrying ladders, pipes, conduits, reinforced rods and other long material in to stations,
Switchyards, switch gear rooms and other places where there is a danger of touching the live parts,
the material should be held by two men, one at each end, and carried in the hands and not on the
shoulders.
iv. When working in the vicinity of circuit breakers or buses use every precaution to avoid injury from
arcing.
v. Area is to be guarded off wherever possible, where men are working on HT equipment.
Working on Transformer
i. When work is to be carried out on a transformer, both low and high tension breakers and isolators
shall be opened. Similarly, during isolation of transformers to which potential transformers are
connected, such potential transformers shall be isolated.
ii. Before starting any work on a transformer installation, it is important to check carefully for back
feed, abnormal voltage or other dangerous conditions. Unusual circuit conditions may exist which
require special consideration.
iii. Whenever transformers are replaced, the new transformer should be checked carefully for voltage,
polarity and phase sequence before taking into service.
iv. Area should always be cordoned off & Safety tagging should be done prior to starting the job on
transformer.
Bus-Bars
i. While working on the outdoor structure at a height more than 3 meters from the ground level, safety
equipment such as safety belts, handling, etc. should be used.
ii. No person shall stand directly below the place of work when the work is in progress in the outdoor
structure to avoid any tools or bolts or nuts or clamps etc. falling on their heads.
iii. Helmets should be invariably used while working on the outdoor structures, on the outdoor
structures, both by the men stationed at the ground and those on the structures.
Capacitors
i. Every capacitor shall be treated as hot until proved otherwise. Capacitors stores energy and are not
necessarily dead when disconnected from the line. Once charged, a capacitor may retain its charge
for several hours after it has been disconnected.
ii. When a capacitor is to be worked on, first open all cutouts or disconnecting devices to the capacitor,
then wait for at-least five minutes for the internal resistors to reduce the voltage. Next, using the
hot stick (discharge rod), short circuit and ground all terminals of the capacitors. These terminals
should remain short circuited and grounded while work is being done on the capacitor.
iii. To bring the capacitor banks back into service, first remove the jumpers with hot sticks, and then
close the cutouts.
Lightning Arrestor
i. No work shall be done on the lightning arresters unless it is disconnected from the line circuit and
grounded at both the lines and ground terminals.
ii. It’s the indication that fault occurred at the outgoing loops of the feeder’s cable or other
equipments like 11KV switches, RMU, S/S Bus Bar, HT O/H Main fault, PMT, Local Transformers of
Sub-Station.
11KV Network Manual
Standard Operating Procedure
Section B – SSM
Chapter 1 - Replacement of LT Breaker, DB, Leads or DO
Cutout
11KV Network Manual
Standard Operating Procedure
OBJECTIVE
To assure replacement of one or more of the following on 11 KV network distribution in line with all safety
policies and procedures:
LT Breaker
DB
HT – LT Leads
DO Cutout
SCOPE:
This SOP shall apply to all SSM (KESC and 3rd party) employees working on replacement of LT Breaker, DB,
HT- LT Leads, and DO Cutout.
2. LT Supervisor:
Before starting of work, give isolation from LT side and short & ground all sides as per Line
Isolation SOP.
After completion of work, remove all short and grounds from LT side.
In case of installation of LT breaker, give clearance to AOC supervisor from LT side.
3. AOC Supervisor:
Before starting of work, give shutdown from HT side and short & ground all sides as per Line
Isolation SOP.
After completion of work, remove all short and grounds from HT side.
Energize the line and put LT breaker ON.
11KV Network Manual
Standard Operating Procedure
5. SSM Karkun:
Assist Sk. Fitter / S Sk. Fitter.
Should not perform work without instruction of SSM site supervisor, Sk. Fitter or S Sk. Fitter.
6. AM – SSM:
AM to prepare debit note(s) and gate pass.
7. Manager – SSM:
Sign on debit note and gate pass.
Manage acquisition and allocation of materials to gang.
8. GM – HT:
GM – HT to oversight all above mentioned activities and fulfill requirement of tools, equipment,
PPEs, SPEs and logistics for field staff along with material management.
11KV Network Manual
Standard Operating Procedure
Replace Breaker
No
Connect both sides of LT breaker
Replace DO cutout
Replace DB / leads
Remove short & ground from all sides (HT & LT) by AOC from HT and IBC from LT
Logistics:
MTLs will be required. All vehicles should pass the fitness criteria as per KESC fleet workshop:
MATERIAL MANAGEMENT:
LT Breaker, DO Cutout & DB:
Maintain inventory record of LT breakers, DO cutouts and DBs at SSM store and update movement,
usage and record.
Analyze usage of LT breakers, DO cutouts and DBs. Identify and state requirement of critical items.
Track issuance, usage and receiving of material.
11KV Network Manual
Standard Operating Procedure
OBJECTIVE:
To assure replacement of one or more of the following in substations on 11 KV network distribution in line
with all safety policies and procedures:
Replacement of CT / PT
Cleaning of Carbonized HT Busbars
SCOPE:
This SOP shall apply to all SSM (KESC and 3rd party) employees working on replacement of CT / PT and
cleaning of carbonized HT busbars
2. AOC Supervisor:
Before starting of work, give shutdown from HT side and short & ground all sides as per Line
Isolation SOP.
Short and ground transformer HT bushing.
After completion of work, remove all short and grounds.
Energize the line.
4. SSM Karkun:
Assist the Sk. Fitter / S Sk. Fitter.
Should not perform work without instruction of SSM site supervisor, Sk. Fitter or S Sk. Fitter.
5. AM – SSM:
AM to prepare debit note(s) and gate pass.
6. Manager – SSM:
Sign on debit note and gate pass.
Manage acquisition and allocation of materials to gang.
7. GM – HT:
GM – HT to oversight all above mentioned activities and fulfill requirement of tools,
equipment, PPEs, SPEs and logistics for field staff along with material management.
11KV Network Manual
Standard Operating Procedure
No
Adjust cable (if required)
Logistics:
Truck will be required. All vehicles should pass the fitness criteria as per KESC fleet workshop:
MATERIAL MANAGEMENT:
CT and PT:
Maintain inventory record of CT and PT at SSM store and update movement, usage and record.
Analyze usage of CT and PT and identify critical items.
Track issuance, usage and receiving of material
11KV Network Manual
Standard Operating Procedure
OBJECTIVE:
To assure “Replacement of RMU” on 11 KV network distribution in line with all safety policies and
procedures.
SCOPE:
This SOP shall apply to all SSM (KESC and 3rd party) employees working on replacement of RMU.
2. AOC Supervisor:
Before starting of work, give shutdown from HT side and short & ground as per Line Isolation
SOP.
After completion of work, remove all short and grounds from HT side.
Energize the line.
5. SSM Karkun:
Assist the Sk. Fitter / S Sk. Fitter.
Should not perform work without instruction of SSM site supervisor, Sk. Fitter or S Sk. Fitter.
6. AM – SSM:
AM to prepare debit note(s) and gate pass.
11KV Network Manual
Standard Operating Procedure
7. Manager – SSM:
Sign on debit note and gate pass.
Manage acquisition and allocation of materials to gang.
8. GM – HT:
GM – HT to oversight all above mentioned activities and fulfill requirement of tools, equipment,
PPEs, SPEs and logistics for field staff along with material management.
Disconnect HT termination of RMU from all sides and disconnect earth wire
Reconnect HT termination at RMU from all sides and reconnect earth wire
Logistics:
Following vehicles will be required. All vehicles should pass the fitness criteria as per KESC fleet workshop:
MTL
Truck
Crane / Loader
MATERIAL MANAGEMENT:
RMU:
Maintain inventory record of RMU at SSM store and update movement, usage and record.
Analyze usage of RMU and state requirement.
Track issuance, usage and receiving of material
11KV Network Manual
Standard Operating Procedure
OBJECTIVE:
The purpose of this procedure is to ensure effective coordination among 118, Operations & SSM while
forwarding job to SSM.
2. Manager Network:
Manager Network to forward complaint to HT OPN.
3. Control Engineer:
Control Engineer HT OPN to forward complaint to DGM SSM.
4. DGM SSM:
DGM SSM to request commercial clearance from IBC.
DGM SSM to forward job to SSM control for rectification.
5. DGM Network:
DGM Network to give commercial clearance to DGM SSM / HT OPN Control after fulfilling the
following as and when needed:
a) Billing clearance from RPR
b) Written Undertaking from Consumer
c) Approval from DCDO
6. Dispatch Supervisor:
Dispatch supervisor to ensure that gang is dispatched with tools, PPEs, SPEs and logistics after
conducting TBT.
SSM Control:
SSM Control to fill shutdown form (B-form) which is to be signed by DGM SSM and submitted to HT OPN
control.
HT OPN Control:
HT OPN control gives receiving copy of form back to SSM control and informs HT AOC.
1. HT AOC Supervisor:
Give shutdown from HT side and supervisor from IBC to give isolation from LT as per Line
Isolation SOP.
11KV Network Manual
Standard Operating Procedure
3. GM – HT:
GM – HT to manage all above mentioned activities.
Does fault
Yes
pertain to Fault rectified by IBC
IBC?
END
No
Does fault No
pertain to Fault rectified by other department
SSM?
END
Yes
HT OPN control forwards fault to SSM control
SSM control fills B-Form and requests for HT shutdown from HT OPN control
11KV Network Manual
Standard Operating Procedure
HT OPN control gives receiving copy of form back to SSM control and informs HT AOC
TBT conducted at SSM centre and gang dispatched with necessary tools, PPEs, SPEs and logistics
SSM site supervisor will present copy of form to AOC and request for shutdown arrangement
AOC site supervisor will arrange HT shutdown as per Line Isolation SOP after conducting on-site TBT
Is LT
Yes
isolation Contact IBC and verbally
required? ask for shutdown
Yes
IBC to isolate all LT sides
as per Line Isolation SOP
No after conducting TBT at
centre and site
PERFORMANCE MANAGEMENT:
TAT for Forwarding job to SSM till shutdown: 30 minutes
Time taken to complete task to be recorded as per form A
11KV Network Manual
Standard Operating Procedure
OBJECTIVE:
To replace one or more of the following in substations on 11 KV network distribution in line with all safety
policies and procedures:
11kV switches and isolators
Trolleys (OCB/VCB)
SCOPE:
This procedure shall apply to all SSM (KESC and 3rd party) employees working on Installation of 11kV
Switches and Isolators or Replacement of Trolley in substation.
2. AOC Supervisor:
Before starting of work, give shutdown from HT side and short & ground as per Line Isolation
SOP.
Short and ground transformer HT bushing.
After completion of work, remove all short and grounds.
Energize the line.
5. SSM Karkun:
Assist the Sk. Fitter / S Sk. Fitter.
Should not perform work without instruction of SSM site supervisor, Sk. Fitter or S Sk. Fitter.
6. AM – SSM:
AM to prepare debit note(s) and gate pass.
7. Manager – SSM:
Manager to manage acquisition and allocation of materials to gang.
8. Manager – SSM:
Sign on debit note and gate pass.
Manage acquisition and allocation of materials to gang.
9. GM – HT:
GM – HT to oversight all above mentioned activities and fulfill requirement of tools, equipment,
PPEs, SPEs and logistics for field staff along with material management.
11KV Network Manual
Standard Operating Procedure
Yes
Is job for breaker
or isolator Disconnect HT cable terminations from switch
installation?
Place the switch / isolator accordance to 11 kV bus bar
arrangement of existing panel
No
Couple newly installed switch / isolator with exiting panel through HT busbar.
Yes
Rack out faulty trolley from OCB/VCB
PERFORMANCE MANAGEMENT:
TAT for installation of 11kV switches and isolators: 6 hours
TAT for replacement of trolley: 2 hours
Time taken to complete task shall be recorded as per Annexure A
Logistics:
Crane / Loader & Truck will be required. All vehicles should pass the fitness criteria as per KESC fleet
workshop:
GANG FORMATION:
Gang to be formed with respect to assigned KESC designations as stated below:
a) 01 Supervisor (A.E, EMO, Sub Engineer) c) 01 Semi Skilled Fitter
b) 01 Fitter d) 02 Karkuns
MATERIAL MANAGEMENT:
Switches and Isolators:
Maintain inventory record of trolleys, switches and isolators at SSM store and update movement, usage
and record.
Analyze usage of trolleys, switches and isolators. Identify critical makes of trolleys, switches and
isolators and state requirement of critical items.
11KV Network Manual
Standard Operating Procedure
OBJECTIVE:
To replace one or more of the following in substations on 11 KV network distribution:
SCOPE:
This SOP shall apply to all SSM (KESC and 3rd party) employees working on replacement of LT leads of
transformer to LT panel, LT busbar, HRC Fuses and Bases and outgoing cable termination in substation.
2. AOC Supervisor:
Before starting of work, give shutdown from HT side and short & ground as per Line Isolation
SOP.
Short and ground transformer HT bushing.
Remove and place HRC fuses in LT panels.
After completion of work, remove all short and grounds.
Energize the line.
11KV Network Manual
Standard Operating Procedure
3. IBC Supervisor:
Isolate LT and short and ground all sides.
6. SSM Karkun:
Assist the Sk. Fitter / S Sk. Fitter.
Should not perform work without instruction of SSM site supervisor, Sk. Fitter or S Sk. Fitter.
7. AM – SSM:
AM to prepare debit note(s) and gate pass.
8. Manager – SSM:
Sign on debit note and gate pass.
Manage acquisition and allocation of materials to gang.
9. GM – HT:
GM – HT to oversight all above mentioned activities and fulfill requirement of tools,
equipment, PPEs, SPEs and logistics for field staff along with material management.
11KV Network Manual
Standard Operating Procedure
On-site TBT
Is job for LT
busbar panels’ Yes
replacement? Remove HRC bases from panel
and LT busbars from LT panel
Reinstall LT busbars at LT
panel and HRC bases
Give clearance to AOC
Logistics:
Truck will be required. All vehicles should pass the fitness criteria as per KESC fleet workshop:
MATERIAL MANAGEMENT:
LT Leads, HRC Fuses, Bases & LT busbar:
Maintain inventory record of LT Leads, HRC Fuses, Bases and LT busbar at SSM store and update
movement, usage and record.
Analyze usage of LT Leads, HRC Fuses, Bases and LT busbar.
11KV Network Manual
Standard Operating Procedure
OBJECTIVE:
To assure “Installation of New PMT” on 11 KV network distribution in line with all safety policies and
procedures.
SCOPE:
This SOP shall apply to all SSM (KESC and 3rd party) employees working on installation of new PMT.
2. LT Supervisor:
Before starting of work, give isolation from LT side and short & ground all sides as per Line
Isolation SOP.
After completion of work, remove all short and grounds from LT side.
Give clearance to AOC supervisor from LT side.
3. AOC Supervisor:
Before starting of work, give shutdown from HT side and short & ground all sides as per Line
Isolation SOP.
After receiving clearance from SSM site supervisor, remove all short and ground from HT side.
Energize the line and put LT breaker ON.
5. SSM Karkun:
Assist the Sk. Fitter / S Sk. Fitter.
Should not perform work without instruction of SSM site supervisor, Sk. Fitter or S Sk. Fitter
(team in-charge).
6. AM – SSM:
Prepare debit note(s) and gate pass.
7. Manager – SSM:
Sign on debit note and gate pass.
Manage acquisition and allocation of materials to gang.
8. GM – HT:
GM – HT to oversight all above mentioned activities and fulfill requirement of tools,
equipment, PPEs, SPEs and logistics for field staff along with material management.
11KV Network Manual
Standard Operating Procedure
On-site TBT
Yes
Job started
Connection of HT and LT
leads
PERFORMANCE MANAGEMENT:
TAT for Installation of new PMT is 6 hours
Time taken to complete task to be recorded as per form A.
Logistics:
MTL, Crane / Loader and Truck will be required. All vehicles should pass the fitness criteria as per KESC
fleet workshop:
MATERIAL MANAGEMENT:
New PMT, DO cutout, LT Breaker and DB:
Maintain inventory record of New PMT, DO cutout, LT Breaker and DB at SSM store and update
movement, usage and record.
Analyze usage of New PMT, DO cutout, LT Breaker and DB and identify critical items.
Track issuance, usage and receiving of material.
11KV Network Manual
Standard Operating Procedure
OBJECTIVE:
To state “Master Key Handling of Substation” on 11 KV network distribution.
SCOPE:
This SOP shall apply to the following H.T sections:
Operation
SSM
UGM
Operation Section:
At each Operation center 04 Master Keys must be issued.
a) One Key for each Supervisor with the site Operation gang (Two gangs at a time)
b) One with dispatched Supervisor of the Operation center.
c) One spare Master Key at each Operation center for emergency use.
SSM Section:
04 Master Keys to be issued to each SSM section
a) One Key for each Fitter / Supervisor to be dispatched with team (Two teams at a time)
b) One with dispatch Supervisor of the Control room for emergency use.
c) One Key in Manager Custody for site inspection use.
UGM Section:
05 Master Keys to be issued to each UGM section
1. Gang supervisors:
On reporting back to the center will deposit the Master Keys to the dispatch supervisor
available in control room and also be recorded in the Master Key logbook with time, date and
signatures of both gang & dispatch supervisors.
11KV Network Manual
Standard Operating Procedure
2. Control In-Charge:
One wooden box with glass top to be fixed in each control room and its main key must be with
control in-charge available on duty. Emergency use key must be used in emergency only.
5. Security Department:
Carry out surprise visits of substations.
11KV Network Manual
Standard Operating Procedure
OBJECTIVE:
To state methodology of providing “Diesel Generators” to consumers for stand-by purposes.
SCOPE:
This SOP shall apply to all SSM (KESC and 3rd party) employees working on managing of diesel generators
for stand-by purposes.
2. DCDCO:
Decide whether payment required or not.
Forward to GM – HT.
3. GM – HT:
After receiving approval from DCDO, forward request to DGM – SSM for costing.
After receiving payment confirmation from GM – IBC, forward request of consumer to GM –
IBC and DGM – SSM.
4. DGM – SSM:
Estimate costing and forward to GM – IBC.
After receiving final decision from GM – HT, instruct Manager – SSM to make arrangements.
5. Manager – SSM:
Make arrangements for diesel generator and dispatch it along with operator.
Intimate to GM – HT about safe installation of equipment.
Before dispatching generator, ensure availability of diesel.
Ensure maintenance of generator as described in Routine Maintenance.
6. GM – IBC:
Forward costing to DGM – Network for issuance of estimate.
After receiving payment confirmation from DGM – Network, forward to GM – HT.
Instruct DGM – Network for providing changeover with leads and gang.
7. DGM – Network:
Issue estimate to consumer.
Receive copy of payment slip.
Forward payment confirmation to GM – IBC.
Instruct Manager – Network to arrange changeover.
11KV Network Manual
Standard Operating Procedure
8. Manager Network:
Dispatch changeover to site with gang with all accessories.
9. Generator Operator:
Make all arrangements as described by Manager – SSM.
Before dispatch, ensure generator is working.
Check fuel position.
Responsible for putting generator ON / OFF.
After installation, test generator before event starts.
ROUTINE MAINTENANCE:
Daily Maintenance Plan:
The generator will be checked daily for water and fuel before starting and ensure that all the wires are
tightly connected and there is no leakage of grease, oil etc
Ensure that air filter is clean, battery is charged and oil level is maintained to required level.
The generator will be checked monthly for oil and oil filter. If required, then oil filter to be changed. Besides
this, the generator should be cleaned monthly.
11KV Network Manual
Standard Operating Procedure
Is payment Yes
Forwarded to SSM for costing
required?
Confirmation of payment
END
11KV Network Manual
Standard Operating Procedure
OBJECTIVE:
To assure “Replacement of Transformer (PMT/SS)” on 11 KV network distribution in line with all safety
policies and procedures.
SCOPE:
This SOP shall apply to all SSM (KESC and 3rd party) employees working on replacement of distribution
transformer.
2. LT Supervisor:
Before starting of work, give isolation from LT side and short & ground all sides as per Line
Isolation SOP.
After completion of work, remove all short and grounds from LT side.
Give clearance to AOC supervisor from LT side.
3. AOC Supervisor:
Before starting of work, give shutdown from HT side and short & ground all sides as per Line
Isolation SOP.
After receiving clearance from SSM site supervisor, remove all short and ground from HT side.
Energize the line and put LT breaker ON.
5. SSM Karkun:
Assist the Sk. Fitter / S Sk. Fitter.
11KV Network Manual
Standard Operating Procedure
Should not perform work without instruction of SSM site supervisor, Sk. Fitter or S Sk. Fitter
(team in-charge).
6. AM – SSM:
Prepare debit note(s) and gate pass.
7. Manager – SSM:
Sign on debit note and gate pass.
Manage acquisition and allocation of materials to gang.
8. GM – HT:
GM – HT to oversight all above mentioned activities and fulfill requirement of tools, equipment,
PPEs, SPEs and logistics for field staff along with material management.
11KV Network Manual
Standard Operating Procedure
Is PMT platform No
available or work is in Make temporary arrangement
S/S?
Yes
Checking of oil level, oil leakage and condition of silica gel of new transformer
Remove short & ground from all sides (HT & LT) by AOC from HT and IBC from LT
Put LT breaker ON
END
11KV Network Manual
Standard Operating Procedure
Uniform
Safety shoes
Helmet with chin strip
Rubber and leather gloves
Live line tester
Full body harness with front position belt
Danger sign board (safety tape) for placing at road
Emergency light (depending upon time of day)
Rain coats & gum boots (depending upon weather)
11KV Network Manual
Standard Operating Procedure
Logistics:
MTL, Truck, Crane / Loader will be required. All vehicles should pass fitness criteria as per KESC fleet
workshop:
MATERIAL MANAGEMENT:
TRANSFORMER:
Maintain inventory record of transformers at SSM store and update movement, usage and record.
Analyze usage of transformers and identify critical ratings of transformers. State requirement of
critical transformers.
Track issuance, usage and receiving of material.
11KV Network Manual
Standard Operating Procedure
Chapter 11
Construction of New Substation
11KV Network Manual
Standard Operating Procedure
Purpose:
The Policy is developed for the construction of new sizes of 11 KV substations in the KESC Distribution
network, due to induction of new size 11 KV VCB Panels & Standardization of Distribution Transformer
sizes
Scope:
This policy covers construction of new sizes 11 KV Sub Station in KESC- HT / LT Distribution network (All
regions). Four different sizes of 11 KV Substations are constructed in KESC Distribution network, which are
single room (HT Switch Room) & two rooms (HT & Trafo+LT Panel Room)
This type of substation shall be constructed for the applicants applied for 11 KV bulk supply or
for switching purpose of 11 KV feeders/network
Two different sizes of single room substation are designed i-e type “A” & type “B” as below. The
selection of the substation shall be as per site/plot condition or with the mutual agreement with
the applicant
Single room substation shall consist of maximum 04 Nos. of HT/MV Panels. Size of the
substation shall be 15 x 17 x 12’, with placement of equipments as per attached drawing in
annex-A
Single room substation shall consist of maximum 04 Nos. of HT/MV Panels. Size of the
substation shall be 16’ x 14’ x 12, with placement of equipments as per attached drawing in
annex-B
This type of substation shall be constructed for the applicants applied for more than 400 KW to
800 KW load & will be constructed in the premises of applicant
Two different sizes of two room substation are designed i-e type “A” & type “B” as below. The
selection of the substation shall be as per site/plot condition or with the mutual agreement with
the applicant
Two room substation shall designed as one room for HT/MV panel (max: 04 Nos.) & second
room for Distribution transformer & LT Panel. Size of the substation shall be 26’ x 17’x12’ feet.
The placement of HT/MV and LT equipments shall be as per Annex-C
Two room substation shall designed as one room for HT/MV panel (max: 04 Nos.) & second
room for Distribution transformer & LT Panel. Size of the substation shall be 30’ x 15’x12’ feet.
The placement of HT/MV and LT equipments shall be as per Annex-D
11KV Network Manual
Standard Operating Procedure
In case, the load of the applicant increases from 800 KW, than he shall provide/construct additional room
for transformer equal to the above specified size of transformer room.
Material / Equipments:
All equipments as MV panels/ Trafo:/LT panels/MV/LV cables and hardware material used in substation
shall be confirming to relevant (Amended up to date) KESC Standard Specifications. All materials shall be
tested/inspected as per self finance policy / SOP
Proper tagging on HT- switches & route of destination of in-comings, out-goings & local transformer
cables, long-with LT circuit destination should be clearly mentioned including network name with network
code, danger signs & emergency contact numbers of Sub-station on outside front wall.
Construction Requirements:
i. Substation shall be constructed by the applicant under New Connection self finance policy
ii. The lay out plan & civil drawings shall be provided by the KESC (NC Department.) to applicant and
other utilities
11KV Network Manual
Standard Operating Procedure
iii. Overall supervision shall be done by KESC & charges will be paid by the applicant as per NC policy
define charges when it is being constructed by applicant
iv. All the Electrical Equipments & Accessories in substation shall be installed by the applicant/KESC
approved contactor under the supervision of KESC for S.F Cases
v. Earthling shall be done by the applicant as per KESC Specification and the resistance shall be
measured/checked by the KESC officials. Annexure-E
vi. During construction of substation, applicant shall call the KESCs designated engineer(s) for inspection
at the different levels.
vii. After completion of civil works & installation of equipments, the substation shall handed over to KESC,
& become the KESC Property. (Agreement / Undertaking / Deed for Handing/ Taking over of Sub-
Station)
Sub-Station Construction:
i. The sub-station is constructed on RCC framed structure. The structure is composed of beams &
column with the load being transferred into the beam via the floor and then down to foundation
through column & the walls are to be constructed by machine made blocks. The walls must have
sufficient strength to support the weight of any equipment mounted on it without collapsing
ii. The plinth level of substation shall be 3 feet from the road.
iii. The ceiling shall be of RCC Cement Concrete construction.
iv. The finish of internal wall and ceiling must be clean, smooth and must be painted (Approved by
Engineer) the floor must be impervious to any oil spillage from main transformer.
v. The sub-station floor, including trenches, conduits etc is to be formed in accordance with the position
and details shown on KESC drawing/specifications
vi. The floor must have a level steel trowelled finish
vii. If the sub-station floor is laid on natural or filled ground an appropriate waterproofing membrane is
to be placed between the underside of sub-station floor and the ground
viii. The sub-station shall be constructed using approved water proofing materials
ix. To protect the Sub-Station equipment expose to dampness / water throughout its life requires
proper site drainage and water proofing
x. Sub-station requires special attention to ventilation in order to dissipate heat losses from electrical
equipment wherever possible natural air flow to the outside of the building will be used
xi. Forced ventilation should be used where natural ventilation is not practicable. Forced ventilation by
mean of industrial fan (s) with timer switch must be designed, supplied and installed by the owner as
11KV Network Manual
Standard Operating Procedure
per KESC’s requirements (The power supply to meter shall be on account of KESC) The air flow
through the ventilation will be checked by KESC before the final approval.
xii. The position of the vent must be directly to outside air, if this is not achievable then forced
ventilation is required
xiii. Provision must be made within the sub-station to contain any oil spillage (in the unlikely event of a
transformer tank failure) and slope to a common point
xiv. A buried earthing/ grounding system is necessary for sub-station and installed equipments, the
earthing system shall be provided as per KESC’s design/specification
xv. Trench shall be RCC with RCC covers; the trench cover when laid across the trench shall be flush with
the surrounding floor level
xvi. Antitheft door with louvers type should be provided as per KESC’s design. Annex-E
xvii. The owner will supply and install the light & power distribution board and the necessary light fittings
and power outlets in the sub-station including all wiring. KESC will connect the distribution board to
the supply point on the low voltage board.
Objective:
The Policy is developed for the re-construction of 11 KV substations in the KESC Distribution network
which are in dilapidated condition.
Scope:
This policy covers re-construction of existing 11 KV substations on the same footprint includes the
dismantling of Equipments placed in a substation, demolition of existed civil structure, foundation,
superstructure, Finishing work, Completion and handing over to user for reinstallation of substation
equipments.
Substation Maintenance 11KV Network responsible to vacate substation on time for reconstruction.
After job completion electrical equipments/ accessories would be reinstalled with due safety
precautions.
Works department responsible to supervise construction activities as per the standard procedure
and civil engineering practices.
Third Party Contractor is responsible to execute and complete reconstruction of substation as per
the terms and conditions of contractual agreement.
11KV Network Manual
Standard Operating Procedure
Vacation of Substation
Process Flow Procedure Action Taken by
1. SSM survey the substation site 1. Manager
and record number of SSM
equipments with their make
SSM Site survey
and capacity
2. Operation prepare temporary 2. Manager
shifting plan with single line Operation
Operation
temporary shifting
diagram in coordination with
plan with SLD
SSM, UGM and IBC
3. Operation, SSM, UGM and IBC
3. SSM,
Operation, UGM,
workout material and overhead
Operation,
SSM & IBC
material
requirement precisely to
UGM & IBC
requirement
execute temporary shifting of
substation equipments and
Material issued via
accessories
DTN from central
store
4. SSM compile consolidated
material and overhead
4. DGM SSM
requirement for approval as
per signatory mandate by
IBC erect HT poles
for mounting PMT DDCO
5. Material to be issued via DTN
from central store
5. SSM, UGM,
6. IBC erect HT poles for
Shutdown Operation &
SSM mount
UGM/ IBC shift mounting alternate PMT than
alternate PMT
HT/ LT cables IBC
communicate in writing about
completion of job 6. Manager LT
Shutdown
Operation
7. SSM mount alternate PMT with Network
normalize
temporary
accessories
arrangement 8. UGM/ IBC get shutdown for 7. Manager
shifting of HT/ LT cables on SSM
completion communicate to
SSM dismantle SSM give 8. UGM/ IBC
transformer,
switches with
clearance to works
for start of Civil
SSM & Operation
accessories work
9. Operation get shutdown to 9. Manager
normalize the temporary Operation
arrangement
10. SSM dismantle transformer, 10. Manager
switches along with accessories SSM
accordingly
11. SSM give clearance to Works 11. Manager
department for SSM
commencement of civil work
11KV Network Manual
Standard Operating Procedure
1. 1
1. Site Visit
Dismantling &
removal of debris
2. 3
2. Demolishing of Existing
Structure
3. Layout 3. 1
Foundation 4. Excavation 4. 1
5. 1
5. PCC (1:4:8)
Plants
Tools and appliances
Implements
Ladders
Cartage
Tackles
Scaffolding
Contractor may request the Company in writing to allow the Contractor to operate any available
equipment of the Company, for the performance of the works. Material/ equipments employed for the
purposes of dismantling and excavation in the course of carrying out the works shall be the Company’s
property and may only be disposed off as directed by the Company.
Training/ Competency
Contractor
The Contractor represents and warrants to the Company that the Contractor has a requisite experience
and skill is able and willing to carry out the Works and provide any related works/ services as required by
the Company in this regard in accordance with instructions/ technical parameter of the Company to the
entire satisfaction of the Company.
Works Department
Manager Works may conduct an orientation session for Contractor, to communicate the HSEQ policy of
the Company that obligate the contractor to provide sufficient PPEs to their work force during the course
of civil construction business on site.
Works department may also highlight about the electrical hazards that may be incurred during the process
of digging.
Safety
Contractor shall comply with all applicable Health, Safety, Environment and Quality (HSEQ) laws, rules,
orders and regulations during the execution and performance of works. Contractor shall immediately
remove and replace its personnel who violate the safety provision.
Contractor solely responsible for it employees, sub-contractors and equipment in case of any accident/
danger/ hazardous condition occurring on Site and the Contractor shall provide safety equipment
including without limitation Safety belt, helmets and shoes to all it personnel as well as signage, fencing,
lighting, guarding and barricades.
11KV Network Manual
Standard Operating Procedure
i. For each room of Sub Station one unit of fire extinguisher shall be provided/ installed by the
applicant as per below specification. This unit shall be used only for minor fire especially during
and switching & preventive maintenance.
Type : CO2 Fire Extinguisher
Capacity : 5 Kg
Make : UK, USA or European origin only ( Currently Gloria and Jockel brand
are in KESC use )
Installation : One per room
Location : Inside the room near door at the height of 4 ‘- 6”.
ii. Easy access for personnel, vehicle and hoist equipment from the outside to ensure ease in
installation, maintenance and future replacement/retirement of transformer.
iii. Transformer and switch gear must be ventilated because they give off large quantities of heat.
iv. The forced ventilation system comprising fans, ducting and inlet/outlet vent must be designed,
supplied and installed by the owner. The air flow through the ventilation will be checked by KESC
before the final approval.
v. Antitheft door with louvers type should be provided as per KESC’s design.
vi. Transformer, switches and other accessories properly earth and ground as per the prevailing SOP
ABBREVIATION
GM - General Manager
DGM - Deputy General Manager
RMC - Regional Material Coordinator
IM - Inventory Management
PM - Preventive Maintenance
CM - Corrective Maintenance
HoD - Head of department
SSM - Sub Station Maintenance
D/O cut out - Drop out Cut Out
HRC fuse - High Rupture Capacity fuse
OH - Overhead
DB - Distribution Box
LT - Low Tension
HT - High Tension
SS - Sub Station
PB - Pillar Box
CG - Composite Gang
PMT - Pole mounted Transformers
DT - Distribution Transformer
SSM - Substation Maintenance
HT OPN - HT Operation
AOC -Area operation Centre
TBT -Tool box talk
PPE - Personal Protective Equipment
SPE -Special Protective Equipment
FBA -Finance and business Administration
PP - Project Procurement
Definition
Single Room S/S
11kv General Distribution S/S at which 11kv switch/ Isolator, Local transformer and LT panel
HT Bulk supply consumer panel room
3-Rooms S/S
1ST room for HT 11kv panels/ switches
2nd room for Local Distribution transformer/ Isolator
3rd room 8-way and 4-way LT panel installation with LT circuits
Local Transformer
Transformer with capacity of 500, 750, 1000, 1250 and 1500KVA to be placed in a General Distribution
Sub-station
11KV HT room
11kv Oil circuit Breaker (OCB), Vacuum circuit Breaker (VCB) and Isolator
LT Panel room
8-way and 4-way LT panel installation with LT circuits
Ventilation
The forced ventilation system comprising fans, ducting and inlet/outlet vent must be designed, supplied
and installed
Road level
Floor level of substation compare with road level
11KV Network Manual
Standard Operating Procedure
SCOPE:
This SOP is applicable to all UGM (KESC owned & 3rd party) employees working for HT / LT Cable
Maintenance & Laying Jobs being executed under supervision of UGM.
REQUIREMENT:
Manpower (KESC / Contractor/ 3rd party)
Material
Fast Moving Critical Items - Materials with high AMC and high procurement lead times and in
absence of which schemes / jobs cannot be undertaken.
Slow Moving Critical Items - Materials with low AMC and high procurement lead times and in
absence of which schemes / jobs cannot be undertaken.
Fast Moving Non-Critical Items - Materials with high AMC and low procurement lead times and in
absence of which cannot badly affect the execution / completion of schemes / jobs.
Slow Moving Non-Critical Items - Materials with low AMC and low procurement lead times and in
absence of which cannot badly affect the execution / completion of schemes / jobs
As per material management SOP # __ dated _______ and the user department has to arrange issuance
when the stock position at sub stores reaches at the quantity equivalent to average past consumption of 7
days for procurement lead times as mentioned for particular type of material
Action to Take
Close monitoring of particular material consumption trends over the past and future schemes in hand /
pending faults in hand in order to ascertain the desired quantities to avoid unwanted delays and piled up
schemes / faults.
Vehicles / Logistics
Truck / MTL
Testing Van
Shovels
Communication Equipments
Wireless Sets
Mobile Phones
11KV Network Manual
Standard Operating Procedure
Equipments / Tools
PPEs SPEs
Safety Uniform & shoes Earthing & Grounding Rod
Gum Bots Short / Ground Set
Helmet with Chin Strip Discharge Rod
Goggles Live Line Tester
Safety Harness Test Lamp
Front Positioning Belt Proper Tool Kit
Rubber / Leather Gloves
FUNCTIONS
UGM SUB UNITS:
This department comprises of 3 sub units, a control room, a testing unit and a jointing unit. There is one control
room in each region where all fault information is received from OCR. After evaluating the fault type and
determining the type of work required, it is forwarded to one of its sub units, UGM Testing Unit or UGM
jointing unit.
Coordinate with testing and jointing units for resolution of underground faults;
Maintain inventory of material required by testing and jointing units;
Arrange trucks to transport material from the material store room to fault site;
Coordinating between the CEO/City Nazims for excavation of road(s) to expose faulty cable.
Arrange road repair once the fault has been normalized;
Maintain a daily fault resolution sheet that is forwarded to the relevant OCR;
Maintain High Tension (“HT”) / Low Tension (“LT”)log book(s) and update fault status;
Maintain a jointer’s gang sheet that contains details of the location of each gang(s) and the faults they
have been assigned to;.
Email the status sheets daily to the respective regional GM and Director Operations.
Ensure visit of the testing crew to the fault site and take necessary action;
Coordinate with the contractors concerning equipment testing;
Coordinate with various civic agencies for shifting or re-location of cables during development works;
Ensure proper fault localization through suitable testing processes.
11KV Network Manual
Standard Operating Procedure
Monitoring all activities of subordinates and contractors during planning & execution of Schemes /
Proposal.
Ensures progress of the Schemes / Proposal in coordination with department and stake holders.
Resolves internal and external conflicts by providing guidelines and defined procedures.
Development of SOPs covering every aspect from conflict handling till capitalization of Scheme / Proposal.
Counter verification of invoices & bills.
Timely preparation / updating of Cable Route Sheet Soft/ Hard copy to Operations Dept.
Arranging for trainings as recommended by DGM through L&OD.
DGM
Execution scheduling & implementation to complete the projects within given timelines.
Site visit at least once a week to monitor progress of work and record checks.
Arrangement of material through Manager (Planning & Support) & assigning jobs to execution team
Monitoring targets & given assignments.
Counter verification of invoices & bills.
Monitor the stock position of material, process of material flow, stock at KESC, procurement process and
other resources availability.
Creation of required MR/SR/AUC with coordination of other departments.
Post execution evaluation after completion of task.
Manager
AM/AEE
Arrangement of site surveys along with representative from N/W Oprn. / NC department/ project
department for developing drawings & material requirement for schemes.
Check drawings and BOMs of schemes as per surveys.
Preparation of consolidated statement for the scheme.
Preparation of documents for allocation of AUC.
Issuance of material, PPEs from KESC stores.
Preparation of MRs/SRs
Verification of materials consumption / crediting statement of contractors/schemes / proposals.
Keep Attendance & staff record & maintains record of all tools & equipments in office.
Daily site surveys for execution & quality checks
Facilitating all types of trainings for human development of the department.
Enforcing compliance of all safety policies issued time by time.
Management of record keeping of execution & material issuance, consumption and balance.
Check & verify the invoices regarding material & works.
Safety assurance, Tool box talk confirmation & PPE use check at site.
Management of Sub stores.
Lineman Team:
a. Supervisory Services Officer / Supervisor
b. Lineman/HT/LT Line Maintenance Services
c. Semi Skilled Lineman
d. Karkun / Help Support Services
Step – 6 Excavation
a. Once the road cutting permission is granted (if required) from the concerned civic agencies (Town, CDGK,
KPT, DMC’s, Cantonment, Site Limited, NHA etc), excavation process begins.
b. Depth/Level of excavated ground should be as per the standards defined by IEC i.e. 1meter.
c. When laying the cable, supervisor should ensure the proper depth of the excavated ground.
d. If 1 Meter depth cannot be achieved due to any hindrance in excavation i.e. Rocky soil, Utility Lines passing
across and hard concrete floor, maximum possible excavation that could be carried out will be done. GI &
Hume pipes are to be used to pass the cable through the part of the land which will create hindrance when
excavated in future e.g. Factory gate, road crossing, Railway crossing, sewage line, and open sewage NALA
etc.
e. After the cable has been laid, warning tiles are placed over the laid cable.
f. Back filling and leveling work of ground is done in the end.
termination kit, EPR tapes, PVC tapes, 11 KV tester, etc. are sent along with the jointer’s team to repair
fault.
d. On reaching the fault location, the cable jointer will ask the laborers (outsourced) to excavate the pin
pointed area to expose the faulty cable / portion, ensuring first that road cutting intimation to concerned
Civic Agency is handy at site.
e. After re-confirmation of fault area once exposed cable jointer will cut the affected portion of the cable.
f. For terminations If only 1- core / 2- core is damaged of HT Termination only the required material of 1-
core / 2- core is used for HT Termination repairing. Also loose Bi Metallic Lugs are used wherever required
to repair the HT Termination
g. After cutting the faulty cable, the cable jointer will make termination of both ends of the cable for the
testing team to apply pressure and to reconfirm if the fault is removed or exists in the cable.
h. After confirmation from testing for the soundness of the both the cut portions cable jointer will repair
faults / make joints with relevant material (XLPE of the cable is to be cleaned precisely with Kerosene oil)
and will inform testing for final pressure to determine if fault is resolve.
i. When laying a cable piece, the bends in the cable should be minimal.
j. Contract laborers will then re fill the excavated portion of the road to cover the cable as a temporary road
repair.
UGM’s job domain also includes installing, testing, replacement, repairing and energizing new cables through
SIP Proposals & NC Proposals.
a. After the receipt of proposal for new 11 KV cables from HT operations / NC department, joint survey of
sites are to be conducted by officials of network operations / NC and UGM department for finalization of
the route of the cables.
11KV Network Manual
Standard Operating Procedure
b. Preliminary route sheets / Drawings are to be prepared and jurisdiction of respective civic agencies i.e.
KMC / CDGK, DMC, Cantonment Boards, SITE Ltd. Port Qasim, KPT authorities and NHA etc. are marked
and identified.
c. Standard KESC Drawing for cable laying & BOMs for new schemes/feeder/link proposals shall be prepared
by concern department (UGM / NC) and shall be got approved by concerned Departmental Head.
k. After submission of cheque / adjustment of claimed amount towards road cutting charges the NOC/ way
leave permission is granted by the respective agencies, enabling KESC to mobilize the pre-qualified
contractor and start the excavation work at site.
l. After getting ROW NOC from civic agency, different utility agencies like PTCL, KW&SB, Refinery Companies
and other telecommunication departments are to be intimated for the intended excavation and cable
laying work by clearly mentioning routes and dates for the same to look after and identify their services
during execution of KESC in order to avoid unexpected damages to the public utilities.
m. The arrangement for diversion of traffic if required and to get the route clear from all other
utilities/organizations before, during and after the cable laying shall be the responsibility of concerned
UGM.
CLEARANCE OF WAY
a. The concerned UGM will be responsible for clearance of all obstacles in lying before, during and after
execution including drainage/pumping of water from trench to ensure suitability of trench for cable laying
b. The clearance of Debris or any other material lying in the route of the cable shall be the responsibility of
the concerned UGM
GROUNDING OF CONDUCTOR:
The grounding conductor, and its attachment to the shield or metallic sheath, normally
at a termination or splice, should have an ampacity no lower than that of the shield. In
the case of a lead sheath, the grounding conductor must be able to carry the available
fault current over its duration without overheating. Attachment to shield or sheath is
frequently by means of solder, which has a low melting point; thus an adequate area of
attachment is required.
RECOMMENDATIONS:
Do not leave one end ungrounded, as that may create high voltages on the ungrounded end and may
jeopardize system/equipment/personnel safety.
Do not leave Ground strip disconnected.
Do not used under size wire for ground strip.
Do not use Cable Strip via binding wire at Substation.
Follow only set standards for connecting earth strip.
Inappropriate cable termination.
Follow standard operating procedure for grounding.
Strict logging for actual reasons of cable fault be maintained.
Before start of work at site, tools box talks shall be arranged by the Site Engineer/Supervisor for all staff
deputed to carrying out designated work of intended activity.
Site supervisor shall ensure that all KESC staff working at site is properly equipped with necessary
PPEs/SPEs before start of any activity at site
Caution Notice/Flags and danger board sign shall be placed near work place
Arrangement of emergency lights shall be made available for site work carried out during night
All shutdown arrangements regarding lying, jointing, terminating, testing and commissioning /energization
shall be carried out as per standard safety procedures.
To Ensure complete shutdown of cable at both ends .
Physically checking both ends of cable.
Use of SPE’S / Live line tester /discharging rod.
Proper Grounding / Earthing of instrument.
To ensure required cable is exposed clearly at least 12’ from all sides at desired place.
After identification Nail to be used for pick axing.
After pick axing, cable to be re-confirmed by HIPOT method.
HT CABLE JOINTING.
After confirmation of Isolation of Faulty cable from Operation Testing team will be dispatched on site with
applicable PPEs /SPEs and they will PP the Fault then inform the Jointing team to reach the fault location.
The first and the foremost step taken by the jointing team is to confirm the exact location of the fault and
confirm from operation that cable is isolate. The road cutting intimation Performa will be submitted in
office of concerned civic agency and if the fault is PP in late hours / night hours concerned civic agency will
11KV Network Manual
Standard Operating Procedure
be informed verbally and if not possible gang will execute the excavation work with having emergency
Performa with them.
Once the road cutting permission is granted ( if required) from the concerned civic agencies (Town, CBC ,
DHA, CDGK, KPT, DMC’s, Cantonment, Site Limited, NHA etc), excavation process begins and continue till
the faulty cable is exposed.
Jointer must ensure proper tools required for cutting/splicing the faulty cable before jointing.
Ends of the cable are made for cable pressure test for testing team.
Jointing / Termination work begins with cutting different layers of the cable as per IEC standard and precise
measurements mentioned in the joint manual.
Layers include cutting of Outer sheath, armoring, inner sheath, copper screen, outer semiconducting
tape, XLPE, inner semiconducting tape, aluminum core strands.
XLPE of the cable is cleaned precisely with Kerosene oil.
Moisture/water vapors/ air gap/ vacuum content are avoided near the jointing / termination ends.
Depending on the type of joint used (Elastimold, Raychem, heat shrink etc), different steps are taken to
ensure a proper joint.
If complete HT joint is not available due to any issue i.e. Non- availability, extreme shortage etc. Joints will
be made with loose Material i.e. HT Ferrules 300mmsq , EPR tape.
Excavation for HT- cable loop will be carried out and if HT- cable loop not found HT-cable piece will be laid
to clear the HTCF
Back filling and leveling work of ground is done in the end.
Clearance is given to the UGM- control after completion of work.
Drawings
Single HT underground cable laid in Trench
DRG No.1 K/D/TPRE/SOP/CABLE LYING …….2013
HT underground cables laid in Trench
DRG No.2 K/D/TPRE/SOP/CABLE LYING …….2013
FORMS / DOCUMENTS:
Preliminary Survey from.
Preliminary route sheets / Drawings.
ROW (Letters).
Survey from (prepared with different civic agencies representative).
Road cutting challan (receive from different civic agencies.
Approval letter from Management (for the payment / adjustment of road cutting charges)
Material (Debit / credit notes)
Gate pass.
TBT (Associate/Assistant/Sub Engineer/ Supervisor).
Material verification / Record keeping Associate/Assistant/Sub Engineer/ Supervisor.
BOM.
11KV Network Manual
Standard Operating Procedure
DEFINITIONS:
SI Shift In-charge
OCR Operation Control Room
UGM Underground Maintenance
M&C Maintenance & Complaint
CR Control Room
LT Low Tension
HT High Tension
PPE Personal Protective Equipment
SPE Special Protective Equipment
SIP System Improvement Proposals
NC New Connection
PP Pin point
AMC Average monthly consumption
CS Central Store
DHA Defense Housing Authorities
CDGK City District Government Karachi
KW&SB Karachi Water and Sewerage Board
TMA Town Municipal Administration
NHA National Highway Authority
PTCL Pakistan Telecommunication Company Limited
SSGC Sui Southern Gas Company Limited
Definition
Disconnect
Isolate the portion of network on which shutdown is to be arranged to carry out a specific job.
Isolation
A portion of network or electrical equipment that is removed from an electrical source. (HT & LT side).
INTRODUCTION:
One of the reasons for delay in fault rectification is the interdependence of maintenance gangs. Although the
scope of work for LT and HT is well defined, there remains certain LT fault for which further assistance of SSM
gangs and HT operations is necessitated, which adversely affects the TAT.
OBJECTIVE:
1. Reduction in “Fault Response Time” by increasing effectiveness of M&C gangs.
2. To improve SAIDI
WORKING PLAN:
Composite gang basically consists of nominated M&C gang reinforced with LT supervisor (trained on limited HT
operations and well versed with his area of operation, so as to obtain effective shutdown) and fitter along with
appropriate tools and material.
WORK FLOW
Composite gang work flow is defined as follows:
WORK SCOPE
Nominated Composite gangs shall give preference to attend primary faults as mentioned below over
their other routine complaints/ faults.
Attached is a standard format to record types of faults attended by Composite gang in “Annexure A”
TRAINING
DGM – M&C to conduct familiarization training on composite Gang work scope defined as above with
all safety considerations before formation of composite gang. Training shall be attended by Site
supervisor, Dispatch Supervisor, Lineman, Fitter, Karkun and concerned AOC staff.
Technical training
Work scope familiarization
· Safety training
GANG COMPOSITION:
There shall be a minimum of 3 composite gangs /IBC/day. The composition is as follows:
1. HT trained LT supervisor – 1
2. Line man – 1
3. Fitter – 1
4. Karkun – 2
2. GM IBC
· He is overall in charge of Composite gangs in the IBC
· Collect a weekly composite gang report from Manager Complains and analyze accordingly
Submit completion and evaluation outcome to DCDO & Director DS&P
3. Fitter
Responsible for installing & replacing electrical wiring, equipment and fixtures.
Ensure appropriate material is properly fixed in accordance with relevant plan and standards.
Handle faulty meter and related shifting and maintenance.
Assemble and install electrical wiring equipment, appliances and fixtures, using hand tools and
power tools
Coordinate related maintenance work
Repair of technical and electrical mains
5. Karkun
Assist the lineman in performing his work.
Maintain a favorable relationship with all KESC employees to promote harmonious working
environment
Perform any other job as and when assigned by the management
11KV Network Manual
Standard Operating Procedure
6. DGM Networks
Coordinate with GM IBC, DGM, Supervisors and gang to make sure work flow does not get
disturbed
7. Maintenance Manager:
Responsible for all activities regarding corrective maintenance.
Submit consolidated material requirement list (lugs, leads.. etc)
Make sure all necessary arrangement are made for shutdown requirement and supervisors
are coordinating accordingly
8. Dispatch supervisor:
On time and taking all the necessary material with them.
9. Site supervisor:
· Responsible for overall work on site
· Responsible for ensuring shutdown the line isolation policy before start of work.
MATERIAL MANAGMENT:
Material requisitioning and availability shall be the responsibility of respective IBC. They need
to forward consolidate material requirement list to respective Regional Material Coordinator
RMC’s). The RMC’s shall consolidate their regional demands and forward the same to GM -
Coord DS&P.
The dispatch supervisor shall ensure the following material availability with each gang before
dispatching the composite gang from IBC;
Material - leads, lugs, fuse base ,HRC fuse, LT breaker, DB, Nuts & bolts
Tools - Crimping tools, torque wrench
PERFORMANCE MONITORING:
Performance monitoring will be done on Monthly basis by IBC Manager. It is recommended to use
the standard format attached in Annexure B
Performance of GM – IBCs be evaluated against reduction in TAT of faults (assigned in the work
scope) as set by DCDO.
11KV Network Manual
Standard Operating Procedure
INTRODUCTION:
One of the reasons for delay in fault rectification is the remote areas due to distance to cover and
interdependence of HT and LT gangs. Although the scope of work for LT and HT is well defined, there
remains certain remote area where combination of HT and LT gang is necessitated, which adversely
affects the TAT.
Scope of Universal Gang is widespread covering only remote areas as mentioned below; VIBC Uthal,
Bela, Memon Goth, Gadap& Gharo.
OBJECTIVE:
3. To improve SAIDI
4. Reduction in “Fault Response Time” by combining the HT and LT gangs.
WORKING PLAN:
Universal gang basically consists of dedicated M&C gang reinforced with HT supervisor well versed in
his area of operation, so as to obtain effective shut down and fitter along with appropriate tools and
material.
WORK FLOW
Universal gang work flow is defined as follows:
Complain Received from 118,
Complaint received at CC
Telephone or Window
Universal Gang
Attend
w/o
Shutdown
WORK SCOPE
TRAINING
DGM – M&C to conduct familiarization training on work scope defined as above with all the safety
considerations before formation of universal gang. Training shall be attended by HT supervisor, Dispatch
Supervisor, Lineman, Fitter, Karkun.
Technical training
Work scope familiarization
Safety training
GANG COMPOSITION:
HT supervisor – 1
Line man – 1
Fitter – 1
Karkun – 2
11KV Network Manual
Standard Operating Procedure
GM IBC
DGM Networks
Coordinate with GM IBC, DGM, Supervisors and gang to make sure work flow does not get disturbed
Maintenance Manager:
Responsible for all activities regarding corrective maintenance.
Submit consolidated material requirement list (lugs, leads.. etc)
Make sure all necessary arrangement are made for shutdown requirement and supervisors
are coordinating accordingly
Dispatch supervisor:
On time and taking all the necessary material with them.
·Ensure Daily TBT
Site supervisor:
Responsible for overall work on site
Ensure TBT on Site
Responsible for ensuring shutdown, line isolation policy before start of work.
11KV Network Manual
Standard Operating Procedure
MATERIAL MANAGMENT:
Material requisitioning and availability shall be responsibility of respective IBC. They have to
forward consolidate material requirement list to respective Regional Material Coordinator (RMC’s).
The RMC’s shall consolidate their regional demands and forward the same to GM - Coord DS&P.
The dispatch supervisor shall ensure the following material availability with each gang before
dispatching the Universal gang;
· Material - leads, lugs, fuse base ,HRC fuse, LT breaker, DB, Nuts & bolts
· Tools - Crimping tools, torque wrench etc.
· All necessary PPEs/SPEs
PERFORMANCE MONITORING:
Performance of GM – IBCs be evaluated against reduction in TAT of faults (assigned in the work scope)
as set by DCDO.
SAFETY CONSIDERATIONS:
· Safety action will be clearly out lined in the work plan given by Manager/Supervisor
· All relevant safety procedures will be followed in letter and spirit
11KV Network Manual
Standard Operating Procedure
INTRODUCTION:
The concept of Regional workshop has been introduced to recycle un-serviceable material through this below
benefits can be obtained;
Reduction in cost of operation
Readily availability of material
OBJECTIVE:
Repair through exchange - Workshop will maintain a pool of serviceable parts/assemblies and exchange
it with unserviceable assemblies/parts provided by user department. It will provide following
advantages:
1. Time Saving
2. Cost saving
3. Focused to trade work
4. Optimum utilization of available resources
5. Better quality of workmanship
6. Assist in Preventive maintenance
WORKING:
Mainly, workshop will perform:
General repair
Cannibalization
Replacement of part
Refurbishment
Limited new manufacture
WORK SCOPE
Regional workshop to attend following jobs:
Refurbishing / repairing of OCBs &VCBs panel n trolleys of different manufacturers
Refurbishing / repairing of Isolators &Ring Main Units of various makes
Centrifuging of isolators n switchgears oil, resulting huge saving of company revenue.
Repairing of 11kv PTS(Potential Transformer) &CTs
Repairing of Low Voltage Breaker (420V).
Painting /coloring of rusty Switch Gears, RMUs body.
Preparing & paintings of name plates.
Making of L.T Bus-Bar n L.T clamp as desired & H.T bus-bar for coupling of different manufacturers switches.
Making of RMU covers , Back Plate n L.T frame support & D.Bs
Repairing of all test equipments being used in every discipline under GM HT Ops
Repairing of EFI
Fabrication and repairing of DB’s / check meter boxes
Repairing of HT/LT poles.
11KV Network Manual
Standard Operating Procedure
WORK FLOW
Regional workshop work flow is defined as follows:
TRAINING
DGM – Work shop to conduct familiarization training on Regional workshop work scope defined as
above with all safety considerations before formation of regional workshop. Training shall be
attended by Manager Workshop and all staff of workshop.
Technical training
Work scope familiarization
Safety training
11KV Network Manual
Standard Operating Procedure
DGM- workshop:
He is overall in charge of regional workshop gangs.
Collect a weekly report from Manager Workshop and analyze accordingly.
Submit completion and evaluation outcome to DCDO and Director DS&P.
Coordinate with GM IBC, DGM, and manager.
Manager- workshop
Responsible for all activities regarding work shop maintenance.
Ensure all necessary arrangement are made for material requirement and supervisors
are coordinating accordingly
AE/Supervisors- workshop
Responsible for overall work in regional workshop.
Submit consolidated material requirement list.
Responsible for overall safety measures before start of work.
MATERIAL MANAGMENT:
Material requisitioning and availability shall be responsibility of respective DGM- regional
workshop. He has to forward consolidate material requirement list to respective Regional
Material Coordinator (RMC’s). The RMC’s shall consolidate their regional demands and
forward the same to GM – Material Management.
SAFETY CONSIDERATIONS:
Safety action will be clearly out lined in the work plan given by Manager/Supervisor
All relevant safety procedures will be followed in letter
11KV Network Manual
Standard Operating Procedure
Objectives:
Improvement of system reliability by minimizing outages / faults and system downtime.
Decrease cost of corrective maintenance /replacement of damages.
Reduce accidents by controlling equipment failure)
Scope:
This SOP shall apply to HT network in all regions of Distribution network.
This is applicable to the preventive Maintenance of electrical equipment of 11 KV feeders.
Abbreviations:
GM - General Manager
DGM - Deputy General Manager
IM - Inventory Management
FBA - Financial Business Analysis
PM - Preventive Maintenance
HoD - Head of department
SSM - Sub Station Maintenance
UGM - Underground Maintenance
GSM - Grid Station Maintenance
OCB - Oil Circuit Breaker
VCB - Vacuum Circuit Breaker
CT - Current Transformers
PT - Potential Transformers
D/O cut out - Drop Out Cut Out
HRC fuse - High Rupture Capacity fuse
ACSR - Aluminum Conductor Steal Reinforce Conductor
OH -Overhead
EFI -Earth Fault Indicator
DB - Distribution Box
11KV Network Manual
Standard Operating Procedure
GM HT
Overall in charge of project in the region
Guide Manager PM of region during selection, survey, implementation, monitoring and
evaluation of whole project
Coordinate with FBA, Procurement and IM to ensure timely availability of PM materials
Submit completion and evaluation outcome of PM to DCOO and Chief Distribution Officer.
Coordinate with all GMs HT and share lesson learnt and plan for next year PM
Manager PM V/IBC
Conduct survey of selected feeders along with SSM, UGM & Manager PM HT for OH
portion of feeders as per check list and prepare material list and submit to Manager PM HT
Arrange and store PM OH materials as per timelines
Arrange manpower, tools & PPE, MTLs as per timelines
Dispatch gangs with proper supervision for execution of OH work in coordination with
Manager PM HT.
Closely monitor OH implementation part to ensure quality
11KV Network Manual
Standard Operating Procedure
Manager SSM
Conduct survey of selected feeders along with IBC, UGM & Manager PM HT for S/S & PMTs
of feeders as per check list and prepare material list and submit to Manager PM HT
Arrange and store PM SSM materials as per timelines
Arrange manpower, tools & PPE, MTLs as per timelines
Dispatch gangs with proper supervision for execution of SSM work in coordination with
Manager PM HT.
Closely monitor SSM implementation part to ensure quality
Submit completion report along with material consumption to Manager PM HT
Compile data of SSM faults on that feeder and submit to Manager PM HT on monthly basis
for PM evaluation
Manager UGM
Conduct survey of selected feeders along with IBC, SSM & Manager PM HT for UG work in
S/S & PMTs of feeders as per check list and prepare material list and submit to Manager
PM HT
Arrange and store PM UGM materials as per timelines
Arrange manpower, tools & PPE, MTLs as per timelines
Dispatch gangs with proper supervision for execution of UGM work in coordination with
Manager PM HT.
Closely monitor UGM implementation part to ensure quality
Submit completion report along with material consumption to Manager PM HT
Compile data of UGM faults on that feeder and submit to Manager PM HT on monthly
basis for PM evaluation
Scope of Work
The scope of work comprises of the activities that are split between the GSM/ Protection, HT
operations and M&C (LT Network) as stated below.
IBC / VIBC
Cleaning of excessive deposits of dust on 11 KV insulators.
Replacement of broken, chipped or tilted insulators.
Cleaning of rust/moisture on insulators and greasing.
Renewal of Jumpers- with line taps wherever necessary
Re-sagging/replacement of worn out/multiple joint conductors.
Repair/replacement of PMT bus bars.
Proper jumpering at PMT bus bar with line tape upto D.O cutout.
Replacement/reinforcement of mix and under size conductors.
Tree Pruning
Pole Painting
Repair of Pole bases
Completion of Earth conductor.
Repair of Pole earthing.
Providing additional HT shackle point if required for operational flexibility.
Erecting of new HT poles to reduce length of span where required.
Providing missing double earth wire with Aluminum (ACSR) conductor.
Providing guard wire at road/railway crossing.
Providing pole bases where required.
Check and tight loose nut and bolts of HTT brackets and clamps.
Providing additional brackets to maintain clearances from buildings/Houses etc.
Completion of Pole stay / strud jobs
Replacement of HRC fuses in PMT DBs wherever required
Repairing / replacement of DB to overhead LT leads.
Replacement of HRC fuses in PMT DBs wherever required.
Repairing / replacement of PMT to breaker/breaker to DB/ DB to overhead LT leads
with lugs.
9.2 SSM/UGM
Redressing of HT cable leads/cable ends at PMT and SS UGM
Alignment of HT cables at Switches and Panels in substations and RMU. UGM
Redressing and alignment of LT cables UGM
Visible HT/LT UGM cable loops should be properly buried UGM
Cleaning of HT/LT cable trenches with proper sealing of cable entrance points. UGM
Pump out water from cable trenches in S/S UGM/SSM
Tagging on HT cable to verify the location of cable route. UGM
11KV Network Manual
Standard Operating Procedure
a) After finalization of feeders list with feeder/sub-station/PMT names, a material list should
be prepared by Operation, Sub-station maintenance, UGM and relevant IBC / VIBC network
department, finalized and made available before start of the schedule.
2. Process Monitoring
S. No. Description Frequency Responsibility
Final Review of PM
3 Annually FBA / IM / Procurement / Corp. HSEQ
effectiveness
11KV Network Manual
Standard Operating Procedure
Section 1 – Annexure
11KV Network Manual
Standard Operating Procedure
5 Copper plate 1 EA
6 Cement 2 Bag
13 PG clamp 1 EA
11KV Network Manual
Standard Operating Procedure
ANNEX – ‘B’
11KV Network Manual
Standard Operating Procedure
ANNEX – ‘C’
11KV Network Manual
Standard Operating Procedure
ANNEX – ‘D’
11KV Network Manual
Standard Operating Procedure
ANNEX – ‘E’
11KV Network Manual
Standard Operating Procedure
ANNEX – ‘F’
11KV Network Manual
Standard Operating Procedure
ANNEX – ‘G’
Earth wire 8 SWG bare copper
Earth conductor (HDBC)
R
Y
B
SL
NE
Garud
wire 8
SWG
HDBC
FILLING
MATERIAL
LIME, SALT
21
AND COAL
FE FILLING WITH RATIO
ET
MATERIAL Earth 1: 2: 3
LIME, SALT
AND COAL
LESS THAN 1 OHM
COPPER 3/O
COPPER 3O
CONDUCTOR
Y
COPPER PLATE
COPPER PLATE 4" X 4" X 3"/8
4" X 4" X 3"/8
B
Reel Insulator
KARACHI ELECTRIC SUPPLY
SCOPE OF CONTRACTOR: COMPANY LTD – KESC
BORING UPTO 21 FEET OF 5" DIAMETER.
SUPPLY OF LABOURAR FOR EXCAVATION AND CONCRETE
DISTRIBUTION DEPARTMENT
WORK.
FILLING BORE WITH LIME, SALT AND COAL. R&D
FOLLOWING WORK IS TO BE CARRIED OUT BY SUB STATION
MAINTENANCE AFTER COMPLETION OF EARTHING UNIT SYSTEM PROVISION OF EARTH CONDUCTOR WITH
JOB.
GUARD IN B/W EARTH & NEUTRAL OF 8 SWG
1 CONNECTION OF D.O. CUTOUT WITH GROUND TERMINAL. HDBC WIRE ON TUBULAR LT POLES
2 CONNECTION OF PMT NEUTRAL WITH GROUND TERMINAL.
ANNEX – ‘H’
Earth wire 8 SWG bare copper
Earth conductor (HDBC)
R
Y
B
SL
NE
Garud
wire 8
SWG
HDBC
FILLING
MATERIAL
LIME, SALT
21
AND COAL
FE FILLING WITH RATIO
ET
MATERIAL Earth 1: 2: 3
LIME, SALT
AND COAL
LESS THAN 1 OHM
COPPER 3/O
Reel Insulator
KARACHI ELECTRIC SUPPLY
SCOPE OF CONTRACTOR: COMPANY LTD – KESC
BORING UPTO 21 FEET OF 5" DIAMETER.
SUPPLY OF LABOURAR FOR EXCAVATION AND CONCRETE DISTRIBUTION DEPARTMENT
WORK.
FILLING BORE WITH LIME, SALT AND COAL. R&D
FOLLOWING WORK IS TO BE CARRIED OUT BY SUB STATION
MAINTENANCE AFTER COMPLETION OF EARTHING UNIT SYSTEM JOB. PROVISION OF EARTH CONDUCTOR WITH
1 CONNECTION OF D.O. CUTOUT WITH GROUND TERMINAL.
GUARD IN B/W EARTH & NEUTRAL OF 8 SWG
2 CONNECTION OF PMT NEUTRAL WITH GROUND TERMINAL. HDBC WIRE ON LATTICE LT POLES
Dated: Dwg. No. K/R&D/
Rev 00
November 2012 HTPG/02/2012
11KV Network Manual
Standard Operating Procedure
ANNEX – ‘I’
IRON
D
BOL
T
12
MM
Guard wire 8
SWG HDBC
Double Earth
21 FILLING
wire 8 SWG FE MATERIAL
HDBC
ET LIME, SALT
AND COAL
WITH RATIO
1: 2: 3
LESS THAN 1 OHM
R Y B COPPER
3/O
CONDUCT
BOL E1 E2
OR
T
12
MM COPPER PLATE
NUT & BOLT 2½ X 4" X 4" X 3"/8
½ FOR HOLDING NUT &
21 EARTH COND
BOLT
FE FILLING MATERIAL 2½ X ½
ET LIME, SALT AND COAL ADDITIO CROSS ARM
WITH RATION NAL 6' X 3" X 1.5"
3"
1: 2: 3 HOLE
½” DIA
LESS
THAN 1
OHM COPPER 3/O
CONDUCTOR
COPPER
GUARD
HT LATTICE POLE GROUNDING
PLATE
5 4" 3"
X 4" X /8
WIRE 8
SWG
WITH DOUBLE EARTH WIRE 8 SWG
INCHES HDBC HDBC
SCOPE OF CONTRACTOR:
KARACHI ELECTRIC SUPPLY
BORING UPTO 21 FEET OF 5" DIAMETER.
COMPANY LTD – KESC
SUPPLY OF LABOURAR FOR EXCAVATION AND CONCRETE
WORK.
FILLING BORE WITH LIME, SALT AND COAL. DISTRIBUTION DEPARTMENT
FOLLOWING WORK IS TO BE CARRIED OUT BY SUB STATION R&D
MAINTENANCE AFTER COMPLETION OF EARTHING UNIT SYSTEM
JOB.
PROVISION OF DOUBLE EARTH CONDUCTOR
1 CONNECTION OF D.O. CUTOUT WITH GROUND TERMINAL.
2 CONNECTION OF PMT NEUTRAL WITH GROUND TERMINAL.
ON HT LATTICE POLES STRUCTURE OF 8 SWG
3 THREE NOS. GAURDS TO BE PROVIDED PER SPAN IN B/W ALONG WITH GUARD WIRES
- DOUBLE EARTH WIRE
00
Dated: Dwg. No. K/R&D/
Rev
November, 2012 HTPG/01/2012
11KV Network Manual
Standard Operating Procedure
ANNEX -‘J’
P C
Soil
DEPTH
300-500 mm
Earthing System
Under Test E Current
Probe
Potential
Probe
C1 P1 P2 C2
EARTH
TESTER
ANNEX -‘K’
11KV Network Manual
Standard Operating Procedure
ANN -‘L’
11KV Network Manual
Standard Operating Procedure
Annexure-A
Cover Sheet
SIP #: ________________
IBC: ________________
Subject: _____________________________________________________________________
Synopsis:
GM IBC GM LT GM HT
11KV Network Manual
Standard Operating Procedure
Annexure-B
SIP #: ________________
IBC: ________________
Subject: _____________________________________________________________________
1. [Comment]
(Signature)
(Designation)
2. [Comment]
(Signature)
(Designation)
3. [Comment]
(Signature)
(Designation)
4. [Comment]
(Signature)
(Designation)
11KV Network Manual
Standard Operating Procedure
Annexure-C
Certificate
SIP #: ________________
IBC: ________________
Subject: _____________________________________________________________________
1. This proposal will provide relief for the entire residential consumer.
2. It will not cater any new area development or a single consumer.
3. The over loaded PMT will be relieved and the Transformer will be prevented from getting burnt.
4. The ratio of Wire Broken cases will be minimized.
5. This scheme will not cater to the needs of any Industry.
6. After implementation of the scheme the system will improve operationally and commercially.
7. The cost will be drawn from the overall budgetary provision of the year. (not included in case of GOP
funded schemes)
_________________ _________________
Annexure-D
11KV Network Manual
Standard Operating Procedure
Annexure-E
11KV Network Manual
Standard Operating Procedure
SIP # :
_______________________
An
ne
IBC : xur
_______________________ e-E
Subject:
_______________________________________
__________________________
Nat billing
ure Chec
No of of k
Numbe U
No of illega con mete
KVA Loadin r of HC ni Re Los
S. Mont PMT legal l su r Amou
Ratin g accoun ts cov ses
No h Name connec conn me readi nt
g (amps) ts bil ery (%)
tions ectio rs ng billed
created le
ns (or (unit
d/i s) d
nd)
1Ø-
2Ø-3Ø
Adjacent PMTs'
Specifications
PMT 1
Nat b
ure Chec
illing
No of of k
Numbe
No of illega con mete U
KVA Loadin r of HC Re Los
S. Mont PMT legal l su r ni
Ratin g accoun Amou cov ses
No h Name connec conn me readi ts
g (amps) ts nt ery (%)
tions ectio rs ng bil
created billed
ns (or (unit le
d/i s) d
nd)
1Ø-
2Ø-3Ø
11KV Network Manual
Standard Operating Procedure
PMT 2
Nat billing
ure Chec
No of of k
Numbe U
No of illega con mete
KVA Loadin r of HC ni Re Los
S. Mont PMT legal l su r Amou
Ratin g accoun ts cov ses
No h Name connec conn me readi nt
g (amps) ts bil ery (%)
tions ectio rs ng billed
created le
ns (or (unit
d/i s) d
nd)
1Ø-
2Ø-3Ø
PMT 3
Nat billing
ure Chec
No of of k
Numbe U
No of illega con mete
KVA Loadin r of HC ni Re Los
S. Mont PMT legal l su r Amou
Ratin g accoun ts cov ses
No h Name connec conn me readi nt
g (amps) ts bil ery (%)
tions ectio rs ng billed
created le
ns (or (unit
d/i s) d
nd)
1Ø-
2Ø-3Ø
Continue for
Additional PMTs
Annexure-F
SIP # :
_______________________
IBC :
_______________________
Subject:
_____________________________________________________________
____
Size of
cable
Outstand
throug
Accoun Consume Tarif Connecte ing Dues
S. No Sanctioned load h
t# r# f d Load (as on
which
date)
it is
fed
Annexure-G
IBC: ____________
Subject: ________________________________________________________
Fiscal year –
1. Total Budget Allocated for SIPs (Region I, II, III & IV) Rs___________
2. No of schemes (SIPs) already approved wit the cost of Rs___________
3. No of schemes (SIPs) executed with the cost of Rs___________
4. Cost of New scheme (SIP) No.______________ Dated _________ Rs___________
5. Balance budget for System Improvement Proposals Rs___________
500 mm
1000 mm
200 mm
300 mm
500 mm
LEGEND
FINE SAND
HT CABLE
Form A:
To be filled by SSM
Form B:
To be filled by SSM
Form A:
To be filled by SSM
Form A:
To be filled by SSM
The subject job has been completed satisfactorily by the contractor for the above mentioned agreement:
__________________________________________________________________________________________________________________________
__________________________________________________________________________________________________________________________
__________________________________________________________________________________________________________________________
_____________________________________________________________________________________________________________
Section 7 Annexure
12.1 Annexure “A” - Feeder Survey Checklist
PMT WORKS
RESPONSIBILITY PMT-A PMT-B
SR.# ACTIVITIES
Work Required
1 Pole Foundation M&C Yes/No Yes/No
2 Alignment of pole M&C Yes/No Yes/No
3 Coating and Painting of pole and PMT M&C Yes/No Yes/No
4 HT Busbar M&C Yes/No Yes/No
5 HT Jamper (Busbar to D/O cutout)with Line tape M&C Yes/No Yes/No
6 PMT Maintenance (oil filling,Bushing,LT/HT) M&C Yes/No Yes/No
7 PMT Earthing M&C To be Checked To be Checked
8 H.T. Pin and Supporting Insulators (Replace/cleaning ) M&C Yes/No Yes/No
9 PMT structure % Platform M&C Yes/No Yes/No
10 Pole Painting M&C Yes/No Yes/No
11 HT / LT Cable Clamping UGM Yes/No Yes/No
12 H.T. Cable Dressing UGM Yes/No Yes/No
13 L.T Leads Dressing(PMT to Breaker,Breaker to H/O) S/S Yes/No Yes/No
14 Installation of Check meter Meter Dept Yes/No Yes/No
15 Wooden cleat S/S Yes/No Yes/No
16 D/B Mentanance S/S Yes/No Yes/No
17 D/O Cut outs with Fuse S/S Yes/No Yes/No
18 Maintenance of Piller Box S/S Yes/No Yes/No
19 Maintenace of L.T. Breaker S/S Yes/No Yes/No
20 Installation of L.T. Breaker S/S Yes/No Yes/No
21 Name Plate of PMT & Coding S/S Yes/No Yes/No
HT MAINS
S. No. ACTIVITIES RESPONSIBILITY MAINS No of Spans
6
Rain Emergency Plan - 2012
SOP-REP-Dist-001 00 5th July’12 51 of 61 Corporate HSEQ
Document No. Version Date of Version Page Issuing Department
Form “ B”
Published
Forced
Request for Availing
______________________________________
11-KV-Operation
Permission
The shutdown against the work requested above is permitted with the advice to complete the work
Within stipulated time.
Corporate HSEQ TRAINING PROCEDURE
Announcing and Conducting Training Procedure
______________________________
Underground Maintenance
Work Sequence
Work required
______________________________________________________________________
Work stated at __________________________ work finished at
______________________________
______________________________
Sub-Station Maintenance
Work required
______________________________________________________________________
Work stated at __________________________ work finished at
______________________________
Page 52
Corporate HSEQ TRAINING PROCEDURE
Announcing and Conducting Training Procedure
______________________________
Work required
______________________________________________________________________
Work stated at __________________________ work finished at
______________________________
______________________________
11-KV-Operation
Monitoring
______________________________
Page 54