Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
In addition, great attention should be paid to accurately some activities must be handled in strict sequence while oth-
defining the scope of work since scope definition in and of ers may be executed simultaneously. For still others, a num-
itself provides a means of identifying areas where planning ber of options may exist. One of the most advantageous for-
for changes (as discussed later in this chapter) should take mats for arraying activities is the critical path logic diagram.
place. The most effective tool to use in ensuring that all work In this format, arrows or nodes representing each component
scope is planned is the work breakdown structure (WBS). or activity are displayed in logical sequence, showing
The WBS is a tree structure of successively further break- dependencies among all activities where an actual constraint
downs of work scope into component parts for planning, is present (e.g., one activity cannot start before another is fin-
assigning responsibility, managing, controlling, and report- ished). Since several ways of handling the overall project
ing project progress. All planning efforts should be organized may exist, it may be appropriate to develop two or more logic
to the WBS developed for the project. diagrams and then test each option. Figure 12.1 contains a
simple logic diagram for marketing a new project manage-
Planning takes place in numerous categories, but the most ment software program.
important of these are time, cost, resources, and quality.
After the logical display is complete, a duration is assigned to
Time Planning each activity, based either on data contained in a software
Time planning entails developing plans, usually in the form of program or on experience of the planning participants. Then,
summary schedules, to accomplish all elements of an objective using critical path techniques (as discussed in chapter 13), the
within an established time period. Later in the life cycle, these total time requirement for the endeavor is determined. If the
summary schedules are developed into detail schedules for total exceeds the available time, planners must reevaluate
accomplishing discrete tasks. This process begins with estab- their work and take whatever action is needed to meet time
lishing a need date or other milestone at which all actions must objectives: perhaps optional activities can be dropped and
be complete, and works backward from that point. others can be shortened by applying more resources or other
schedule compression techniques. The results of time plan-
The second step in time planning is dividing the total effort ning can be displayed in numerous ways: the critical path
into component parts. After components are identified, they logic diagram mentioned above, a bar chart, or a simple time
should be arrayed in the order of their accomplishments. table. Scheduling is discussed in greater detail in chapter 13.
This goes beyond merely preparing a list, however, since
ns
tio
ca
re pli
pp
hu p
lica
oc l A
Layout
Sp int
Br ecia
Special
tio
Pr
ns
Applications
Brochure
12.3