Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Assignment 1
Creating a Project Schedule
By submitting this assignment, I declare that this assignment is my work and that I am the above-named
student and that I have retained a back-up suitable copy of this assignment, have not previously
submitted this work for assessment and have ensured that it complies with university and school
regulations, especially concerning plagiarism and copyright.
Signed/Date: _______05/06/2018_____________________
(Signature for the above statement is assumed to have been provided by the student named above when submitting electronically)
1. Introduction………………………………………………………………………………………………………………….4
4. Managing a Variation……………………………………………………………………………………………………11
5. References…………………………………………………………………………………………………………………….16
6. Appendix……………………………………………………………………………………………………………………….17
Time is the one crucial constraint of the iron triangle (i.e. cost, time and scope triangle) in project
management. Time management in project assists to develop, plan and manage project schedule (PMI
2013).
This report represents the development of project schedule for family holiday, where the family is
travelling to some countries in Europe. The family consists of 4 members viz; father (H), mother (W), son
(B) and daughter (G). The family is decided to explore and visit Spain, Sweden and England. This project is
not just a holiday, as the father has to attend and represent a paper at the International conference to be
held on 29 October for 3 days in Stockholm, Sweden. Since, the annual leave granted to the father is of 3
weeks, the family decides to stay for at least 5 days in each country. The trip starts from Barcelona in
Spain, then to Stockholm in Sweden and finally ends their trip in London, England.
The first section in the report demonstrates the work breakdown structure of the holiday as per the
planned schedule. The second section describes the activities based on different dependencies along with
proper explanation about the effort drive task. The third section elaborates how the variation is managed,
and a new schedule is planned. The Gantt charts for both planned schedule and new schedule managing
the variation is represented in the appendix.
A WBS logically defines all the activities in the project schedule. The sequencing of these activities is done
via a network. The aim of the network is to visually demonstrates the relationship of all the activities with
each other (Knutson and Bitz 1991). According to PMI (2013), there are two types of dependencies viz;
Mandatory dependencies (Hard dependencies): In this case, the activities must be completed in
a specific sequence. Thus, here the predecessor drives the successor.
Discretionary dependencies (Soft dependencies): This type of dependency is determined by the
experience of the PM and availability of the resource (PMI 2013).
There are 4 types of dependencies in this report each defined in PMI 2013.
1. Finish to Start:
This dependency is the most frequently occurring dependency in a project schedule. Here, the
successor activity cannot commence before the completion of the predecessor activity. For
example, the family wants to watch a football match (activity 1.3). But before they witness the
match (activity 1.3.6). the father must buy the match tickets (activity 1.3.1).
2. Start to Start:
Here, the successor activity cannot commence before the predecessor activity starts. For
example, in the activity of preparing meatballs (activity 2.2.3). The daughter cannot add garlic,
cheese etc. (activity 2.2.3.2) unless different types of meat are mixed well by the mother (activity
2.2.3.3).
3. Finish to Finish:
In this type of dependency, the successor activity cannot finish until predecessor activity is
completed. For example, in the activity of stitching royal costumes (activity 3.1.2). The son cannot
finish the task of gluing fabrics, laces and ribbons (activity 3.1.2.4) until the sewing of the cloth by
the daughter is completed (activity 3.1.2.3).
4. Start to Finish:
This dependency is hardly found in the schedule of a project. Here, the successor activity cannot
finish until the predecessor activity commences. For example, in the activity of pedal-boat
sightseeing (activity 2.2.4). The mother cannot stop pedaling the boat (activity 2.2.4.1) until the
son starts pedaling the boat (2.2.4.2).
As per Biafore (2014), effort driven task resembles definitive work, where the duration of the task depends
on the flexible resources. In effort driven tasks, the length of the task decreases or increases depending
upon the number of resources appointed for it. However, the work of the task remains fixed. Practically,
if the number of resources (people) assigned for the task are increased then, the work gets divided among
them. Thus, decreasing the task duration.
The effort driven task selected from this project is the task of baking a cake such that they can enjoy the
cake at the Kensington palace (activity 3.4).
Assumption:
If the cake is prepared by the mother alone them it would take 5 work-hour to prepare a cake. However,
if the son and the daughter accompany the mother then the task of baking a cake can be completed within
2 hours. As the task duration can be calculated using the formula below (Biafore 2014),
𝑤𝑜𝑟𝑘 (𝑝𝑟𝑒𝑝𝑎𝑟𝑒 𝑎 𝑐𝑎𝑘𝑒)
Duration =
𝑢𝑛𝑖𝑡𝑠 (𝑝𝑒𝑜𝑝𝑙𝑒)
Thus, the above example clarifies that the task duration can be varied based on the resources appointed
for the task.
4. Managing a Variation:
Biafore, Bonnie. 2014. Microsoft Project 2010: The Missing Manual. Sebastopol: O'Reilly Media,
Incorporated. ProQuest eBook Central.
Knutson, Joan., and Ira Bitz. 1991. Project Management: How to Plan and Manage Successful Projects.
Amacom.
Project Management Institute. 2013. In A Guide to the Project Management Body of Knowledge.
Pennsylvania: Project Management Institute.
GANTT CHART:
GANTT CHART: