MSOLWA UJAMAA IRRIGATION SCHEME

BILL OF QUANTITY

ITEM DESCRIPTION AMOUNT


Eur
GRAND SUMMARY

Bill No. 1 PRELIMINARIES AND GENERAL

Bill No. 2 MAIN SUPPLY CANAL :

Bill No. 3 NIGHT STORAGE RESEIVOIR

Bill No. 4 SECONDARY CANAL

Bill No. 5 ROADS

Bill No. 6 DRAINS

GRAND TOTAL
BILL OF QUANTITIES – IRRIGATION INFRASTRUCTURE WORKS

Item Description Unit Quantity Rate (EUR) Amount (EUR)

BILL NO: 1 PRELIMINARY AND GENERAL

Fixed Preliminary and General Charges

1.1 Contractual Requirements Sum 1


1.2 Establishment, Mobilization at site and demobilization
Sum 1
after completion of works
1.3 Provide, erect and maintain contract sign boards in
No 2
accordance with specification
1.4 Allow for material and quality tests (Provisional) PS 1
1.5 Allow for overheads and profit to the PS (Item A1.4) % 5,000.00
Contractors Obligations
1.6 Allow for the insurance of works, plants and materials
Sum 1

1.7 Allow for insurance against accident or personal injury or


death to workmen and third party Sum 1

SUB-TOTAL CARRIED OVER TO GRAND SUMMARY


SECTION 2 – Msolwa Ujamaa Irrigation Scheme

Item Description Unit Quantity Rate (EUR) Amount (EUR)

Civil works
BILL NO: 2 MAIN SUPPLY CANAL :
2.1 Site clearance Sqm 67,200
2.2 Striping area Sqm 32,100
Headworks
2.3 Supply Stop Log set (50mm x 100mm x 600mm) to suit No. 3
opening for full closure
Location C2 – C3
2.4 Repair Masonry canal and make good (no leaks), without m 210
altering shape of canal by applying( 1:3 mortar)

2.5 Replace or Repair and make good Sluice gate valves No. 2

2.6 Supply Stop Log sets(50mm x 100mm x 400mm) to suit No. 6


opening for full closure
2.7 De silt structures to enable good operation. Clean out silt No. 2

Location C3 – C4
2.8 Fill existing canal section, compact, excavate to profile m 270
and grade, construct parabolic canal with 75mm thick
concrete. Chamfer joint to connect existing road syphon
crossing.

Location C4- C5

2.9 Clean existing canal, repair cracks and leaks(apply 1;3 m 205
mortar).
Location C5 – W
2.10 Fill existing canal section, compact, excavate to profile m 2015
and grade, construct concrete canvas. Chamfer joint to
drainage line crossing at C6. Chamfer to syphon crossing
at C7.

2.11 Construct drop falls, as per drawings( No 10


Location S
2.12 Construct off take structure as per drawing (with No 4
reinforced concrete class A)
Location T
2.13 Construct off take structure as per drawing (with No 4
reinforced concrete class A)
Location U
2.14 Construct off take structure as per drawing (with No 4
reinforced concrete class A)

2.15 Cutting, fill and compact new earth channel canal lining. m 510

2.16 Excavate to profile, spoil removal to the cutting new earth Cm 2520
channel canal lining,
Location W – Z
2.17 Import material, place, compact per specification Cm 8082
2.18 Excavate to profile, construct canal on grade as indicated m 862
in drawings.
2.19 Construct concrete lined canvas. Chamfer joint to m 968
drainage line as per drawing.
Location X
2.20 Construct off take box as per drawing(Reinforced No. 1
concrete Class A to walls, diaphragm wall,deck slab &
base )
Location Y
2.21 Construct off take box as per drawing (Reinforced No. 1
concrete Class A to intake walls, diaphragm wall,deck
slab & base )

2.22 Stone masonry to division box of random rabble less than Cm 188
250mm thick in 1:3 cement sand mortar
SUB-TOTAL CARRIED OVER TO GRAND SUMMARY
BILL NO: 3 NIGHT STORAGE RESEIVOIR
3.1 Excavation for the cutoff trench Cm 1,920
3.2 Formation of homogeneous embankment and core from Cm 12,800
selected fill material and compacted to 95% proctor from
material within 2km
3.3 Importation of material to embankment, placement and Cm.km 4,200
compaction material beyond 2 km.
3.4 Earth fill to the spillway guide bund Cm 600
3.5 Excavation of spillway Cm 780
3.6 Provide earth fill to the cutoff trench including compaction Cm 1,640

3.7 Provide mass concrete 1:3:6 to spillway gauge Cm 18


3.8 Plum concrete to spillway Cm 82
3.9 Install as per drawing the inlet works(provide 1:2:4 No 1
concrete to inlet chamber and its collar)
3.10 Supply and Install as per drawing the outlet m 80
works(600mm steel pipe including all fittings)

SUB-TOTAL CARRIED OVER TO GRAND SUMMARY

BILL NO: 4 Secondary Canal downstream of NSR from location A


to Location E

4.1 Excavate to profile and gradient, fill and compact where m 796
required, as per information on drawings.
4.2 Construct concrete canvas with 75mm thick concrete as m 796
per information on drawings.
4.3 Construct drop falls to maintain design gradient as m 72
required.
4.4 Construct off take boxes at locations B, C, D and E as per m 14
drawings
Tertiary Canals
4.5 Excavate in material placed by other contractor, feeder m 9500
canals to shape indicated in drawings. Where required
place drop falls to maintain gradient as specified on
drawings

SUB-TOTAL CARRIED OVER TO GRAND SUMMARY


BILL NO: 5 Roads

5.1 Clearing, grubbing and removal of top soil Sq 58,500.00


5.2 Common excavation to spoil including transportation of Cm 5,000
the same within a km from the the site
5.3 Heavy reshaping (6m wide road) km 6.5
5.4 Excavate, load, haul, spread water and compact fill Cm 1,000
materials (G15)
5.5 Excavate, load, haul, spread water and compact gravel Cm 5,500
materials (G25)
5.6 Excavate for culverts to a depth not exceeding 1.5m Cm 200
5.7 Concrete in drainage structures (Class 15) Cm 8
5.8 Concrete in drainage structures (Class 20) Cm 200
5.9 Concrete in drainage structures (Class 25) Cm 24
5.10 Supply and install pipe culverts (900mm dia.) m 100
5.11 Supply and install pipe culverts (600mm dia.) m Rate only -
5.12 Excavate, load, haul, spread water and compact fill Cm 100
materials (G15) around the culverts
5.13 Excavate inlet and outlet drains Cm 75
5.14 Excavate Catchwater drains m 200
5.15 Stone masonry Wall Cm 50

SUB-TOTAL CARRIED OVER TO GRAND SUMMARY

BILL NO: 6 Drains


6.1 Excavate to grade as indicated on drawings to various Cm 9800
depths to be given on site, but not exceeding 2.0m.

6.2 Transport and dispose excavated material in specified Cm 4800


dump location within 2.0km
6.3 Transport and dispose excavated material in specified Cm Rate only
dump site up to 10km
Sub-total Drains

SUB-TOTAL CARRIED OVER TO GRAND SUMMARY