SUI NORTHERN GAS PIPELINES LIMITED QA DEPARTMENT

DAILY PROGRESS REPORT – QA PROJECTS QA-FM-01 / 02 / 02-01-06

FROM: EXEC.ENGINEER TO: GENERAL MANAGER


(QUALITY ASSURANCE) (QUALITY ASSURANCE)
REF: QA / PHN / 16/07/01 DATE: 04-07-2016
PROJECT / LINE: LNG II LOOP LINE , PHOOL NAGAR TO MP 59.9
MP FROM: TO:
CHAINAGE FROM (CH): TO:
TOTAL LENGTH: 63.5 KMS REPORT FOR DATE: 01-07-2016 TO 03-07-2016
SR.
ACTIVITY TODAY TO DATE % AGE
# COMPLETED
1. ROW CLEANING (FT.) 0 196524 94%
2. PIPE STRINGING (NOS. + FT.) ()(0) (5004)(200942.64) 96%
3. MAIN LINE (10)(396.88) (4775)(192381.84) 92%
I. JOINTS & PIPE WELDED (JOINT NOS. + FT.)
II. RADIOGRAPHED (NOS.)
III. REPAIRS (NOS.)
IV. REPAIRS RECTIFIED (NOS.)
4. TIE INS
I. JOINTS (NOS.)
II. RADIOGRAPHED (NOS.)
III. REPAIRS (NOS.)
IV. REPAIRS RECTIFIED (NOS.)
5. FABRICATION
I. JOINTS (NOS.)
II. RADIOGRAPHED (NOS.)
III. REPAIRS (NOS.)
IV. REPAIRS RECTIFIED (NOS.)
6. AIR TESTING (FT.)
7. SLEEVING – JOINTS SLEEVED (NOS.) 43 4740
8. TRENCHING (FT.) 2654 177710 85%
9. LOWERING – IN (FT.) 1394 175309 84%
10. BACKFILLING (FT.) 2654 145983 70%
11. YO YO TEST
12. HYDROSTATIC TESTING
13. TRENCHING WT. PRECASTED (NOS.)
14. RCC SLABS PRECASTED (NOS.)
REMARKS: ROW IS IN PROGRESS

COMPUTER, SCANNER, PRINTER REQUIRED

_________________________________
EXEC. ENGINEER (QA) MOR KHUNDA CAMP