01 Execution Plan
PT PRIMA DISTRIBUSI ELEKTRIKA 1 of 1

PROJECT EXECUTION PLAN

Project : Exhaust Elbow Piping


Tanggal : 7/1/2014
Client : PT Hasta Energy

No Description Estimate
1 PO 1 day
- Mengecek dan memeriksa isi PO

2 Engineering drawing 5 days


- Design dan preparation drawing

3 Submission drawing 2 days


- Submit dokumen ke client
- Memastikan dokumen tersebut sudah
sampai ke client

4 Material Procurement 5 days


- Pipa
- Elbow
- Flange

5 Approval drawing 1 days


- Menerima approval dokumen client baik
berupa softcopy maupun hardcopy dimana
6 Fabrication 5 days
- Exhaust elbow piping

7 Dimensional check 1 days

8 Blasting Painting 1 days

9 Packing 1 days

10 Delivery 1 days
FK.PRJ.008.01 Execution Plan
PT PRIMA DISTRIBUSI ELEKTRIKA 2 of 1

PROJECT EXECUTION PLAN

Exhaust Elbow Piping

PT Hasta Energy

Notes
FK.PRJ.008.01 Execution Plan
PT PRIMA DISTRIBUSI ELEKTRIKA 3 of 1

PROJECT EXECUTION PLAN

Project : Penyediaan Generator Set 500 KVA


No. Project : GMS-1309/03/LLG
Tanggal : 5/12/2013
Client : KSO Pertamina EP - Geo Minergy

No Description Estimate
1 PO 1 day
- Mengecek dan memeriksa isi PO

2 Engineering drawing 30 days


- Design dan preparation drawing
- Calculation Setting Line Differential Relay

3 Submission drawing 2 days


- Submit dokumen ke client
- Memastikan dokumen tersebut sudah
sampai ke client

4 Material Procurement 15 days


- Genset
- Panel Synchrone
- Cable

5 Approval drawing 2 days


- Menerima approval dokumen client baik
berupa softcopy maupun hardcopy dimana
- Revised dokumen yang di proposed oleh
client jika perlu

6 Delivery 3 days

7 Installation 13 days
- Genset
- Panel Synchrone
- Cable

8 Termination 1 days

9 Testing 2 days

10 Pre-Comm & Comm 3 days


FK.PRJ.008.01 Execution Plan
PT PRIMA DISTRIBUSI ELEKTRIKA 4 of 1

11 On Hire 1 days
FK.PRJ.008.01 Execution Plan
PT PRIMA DISTRIBUSI ELEKTRIKA 5 of 1

PROJECT EXECUTION PLAN

Penyediaan Generator Set 500 KVA & Maintenance


GMS-1309/03/LLG

KSO Pertamina EP - Geo Minergy

Notes
FK.PRJ.008.01 Execution Plan
PT PRIMA DISTRIBUSI ELEKTRIKA 6 of 1
FK.PRJ.008.01 Execution Plan
PT PRIMA DISTRIBUSI ELEKTRIKA 7 of 1

PROJECT EXECUTION PLAN

Project :
No. Project :
Tanggal :
Client :

No Description Estimate
FK.PRJ.008.01 Execution Plan
PT PRIMA DISTRIBUSI ELEKTRIKA 8 of 1

PROJECT EXECUTION PLAN

Notes
FK.PRJ.003.001 Form Daftar Peralatan
9 of 1

DAFTAR PERALATAN

No Nama Alat Merek/ Type Jumlah


Name of Equipment Brand/ Type Qty
FORM PEMINJAMAN PERALATAN

Form Peminjaman Peralatan


FK.PRJ.003.02

Project :
No. Project :

No Nama Alat Ukur Merk/Type Tanggal Pinjam Tanggal Kembali Lokasi Keterangan

Tanggal Pinjam : Tanggal Kembali :


Nama Peminjam : Nama Penerima :
Paraf : Paraf :
PT. Prima Distribusi Elektrika
Kepuasan Pelanggan
FK.PRJ.006.01

Costumer Company Detail


Costumer Name :
Address :
Person Responsible :
Date Submission :

1. Product Performance

Score : 1 2 3 4 5

2. Delivery Performance

Score : 1 2 3 4 5

3. Response and Service Communication

Score : 1 2 3 4 5

4. Price Performance

Score : 1 2 3 4 5

Note : 1= Very Good


2= Good
3= Good Enough
4= Poor
5= Very Poor
FK.PRJ.007.01 Form Daftar Alat Ukur
12 of 1

DAFTAR ALAT UKUR

No Nama Alat Merek/ Type Jumlah


Name of Equipment Brand/ Type Qty

5
JADWAL KALIBRASI ALAT UKUR

Form Jadwal Kalibrasi


FK.PRJ.007.02

Kalibrasi Periode Tanggal Tanggal


No Nama Alat Ukur Merk/Type Tempat Kalibrasi Keterangan
Internal/Eksternal Kalibrasi Kalibrasi Kembali

Date Prep'd
AL KALIBRASI ALAT UKUR

Paraf

App'd

Potrebbero piacerti anche