Sei sulla pagina 1di 17

ARCHITECT ROLE - AS PER ‘ NBC’ GENERAL ARCHITECT ROLE

SPECIFIC ARCHITECT LIABILITIES

TEAM APPROACH OTHER DICIPLINARIES

m) Interior designer,
A land development / building project comprises the
following major stages: n) Quantity surveyor,
a) Location/siting, o) Project/construction manager,
b) Conceptualization and planning, P Other subject specialist(s).
c) Designing and detailing,
d) Construction/execution, and
e) Maintenance and repair. 4.2 Project Management Construction Management Teams
Each stage necessarily requires professional Appropriate multi- The objective of project management or construction
disciplinary teams need to be constituted to successfully meet the management is primarily to achieve accomplishment
requirements of different stages. Each team may comprise need of project in accordance with the designs and specifications in a
based professionals out of the following depending upon the nature, stipulated time and cost frame work, with a degree of assurance
magnitude and complexity of the project: prior to commencement and satisfaction on accomplishment. For
large projects, separate teams of experienced professionals from the
required disciplines may be constituted for project management and
a) Architect, for construction management depending upon the complexities of
b) Civil engineer the project.
c) Structural engineer,
d) Electrical engineer,
e) Plumbing engineer, 5 PLANNING, DESIGNING AND DEVELOPMENT
f) Fire protection engineer, 5.1 The main functions of design team (see 4.1) constituted for the
g) HVAC engineer, planning, designing and development, are as under
h) Environment specialist,
i) Town planner, a) Formalization of design brief in consultation with the
j) Urban designer, owner.
k) Landscape architect, b) Site investigation survey.
l) Security system specialist, c) Preparation of alternative concept designs.
d) Selection of a concept in consultation with and with the b) Inclusion of the concept of team of building officials;
consent of owner. c) Inclusion of provision of single window approach for permit for
e) Sizing the system. all services;
Development of design, covering : d) Inclusion of provisions regarding computerization of approval
1) Integration of architecture, structure and services, processes for building permits;
2) Synthesis of requirements of each discipline, and e) Inclusion of provision to certify safety of buildings against
3) Interacticm with each other and with the owner. natural disaster by engineer/structural engineer and owner;
f) Preparation of preliminary designs and drawings and f) Inclusion of provision of two stage permit for high rise
obtaining owner’s approval, residential buildings and special buildings;
g) Preparation of preliminary cost estimates for approval of owner, g) Provisions regarding inspection of completed and occupied
h) Preparation of work-breakdown structure and programme for building by the Authority from safety point of view have been made
pre-construction activities. comprehensive;
i) Assisting client to obtain approvals of the Authority. h) Inclusion of provision empowering engineers/architects for
J) Preparation of detailed specification and construction working sanctioning plans of residential buildings
drawings with integration of engineering inputs of all concerned up to 500 sq. m;
disciplines. j) Provisions for architectural control to effectively take care of the
k) Preparation of detailed design of each discipline for various urban aesthetics, have been modified; and
services. k) Inclusion of landscape architect and urban designer among the
l) Peer review proof checking of the drawingsl/designs in case of registered professionals for the concerned applicable works.
important projects,depending upon their complexity and sensitivity.
m) Preparation of detailed cost estimate.
n) Obtaining final approval of client. 2.17 Registered Architect, Engineer, Structural
o) Preparation of bill of quantities, specifications and tender Engineer, Supervisor, Town Planner, Landscape
documents. Architect, Urban Designer — A qualified architect,
engineer, structural engineer, supervisor, town
In NBC Second version of context, structural design of buildings in planner, landscape architect or urban designer who
accordance with the provisions of the Code and construction and has been registered by the Authority or by the body
supervision thereof by competent professionals to ensure structural governing such profession and constituted under a
safety have been given due importance in this revision. Other statute, as may be applicable. The registration
significant requirements of these professionals shall be as given
modifications incorporated include: in Annex A.
a) Modifications in the definitions of certain terms; NOTES
1) Unless specified otherwise, the word ‘engineer’ shall mean above empowerment of professionals, the Authority may extend
“civil engineer’ or ‘architectural engineer’. such provision for larger areas and other building
2) The word ‘licencing/licensed, etc’ if used by the Authority occupancies.
in the above context shall be deemed to mean ‘registration/
registered’, etc. 12.2.7 Specifications
Specifications, both general and detailed, giving type and grade of
9 VIOLATIONS AND PENALTIES materials to be used, duly signed by the registered architect,
engineer, structural engineer or supervisor shall accompany the
9.1.3 The registered architect, engineer, structural notice (see Annex B).
engineer, supervisor, town planner, landscape architect, urban
designer and utility service engineer (see Annex A) responsible for 12.2.8 Structural Suflciency Certljlcate
the services rendered for supervision of the construction The plans shall be accompanied by structural sufficiency certificate
development and for the completion certificate; in the event of in the prescribed form (see Annex C) signed by the
violation of the provisions of the Code, shall be liable to penalties as engineer/structural engineer (see Annex A) and the owner jointly to
prescribed by the Authority including cancellation of registration the effect that the building is safe against various loads, forces and
done by it or make such recommendation to the statutory body effects including due to natural disasters, such as, earthquake,
governing such profession. landslides, cyclones, floods, etc as per Part 6 ‘Structural Design’ and
other relevant Codes. The engineer/structural engineer shall also
have the details to substantiate his design.
11.1.4 The Authority shall permit a registered 12.2.9 Supervision
Architect/engineer to approve the building proposals The notice shall be further accompanied by a certificate in the
including plans, and certify completion of building for prescribed form (see Annex D) by the registered
issue of related regulatory building permits and architect/engineer/structural engineer/supervisor/town planner (see
occupancy certificate for residential buildings designed Annex A) undertaking the supervision (see 9.3).
by self or otherwise, on plot size up to 500 m2. The
responsibility of compliance with respect to provisions 12.3 Preparation and Signing of Plans
of Code shall rest with the registered architect/engineer. The registered architect/engineer/supervisor/town planner/landscape
However, the plans shall be required to be submitted architect/urban designer/utility service engineer shall prepare and
to the Authority for information and record. duly sign the plans as per their competence (see Annex A) and shall
NOTE—Where the experience clearly shows that satisfactory indicate his/her name, address, qualification and registration number
building permit activities are being carried out through the as allotted by the Authority or the body governing such profession.
The structural plans and details shall also be prepared and duly
signed by the competent professionals like registered engineer/ notice of the Authority (with relevant documents). The team of
structural engineer (see Annex A). The plans shall also be duly building officials or its duly authorized representative shall then visit
signed by the own. indicating his address. The type and volume of the site and occupancy certificate shall be given in one instance.
buildings/development work to be undertaken by the registered
professionals may generally be as in Annex A. 18 ARCHITECTURAL CONTROL
18.1 Compliance with the provisions of the Code is adequate for
12.9 Qualifications of Structural Engineers/Landscape Architect normal buildings. But for major public building complexes or
urban Architects/Engineers/Designer/Supervisors/Town buildings coming up in an important area near historic/monumental
Planners/Services Personnel buildings and areas of heritage, the aesthetics of the whole scheme
Architects, engineers, structural engineers, landscape architect, may also have to be examined, vis-a-vis existing structures. In
urban designer, supervisors and town planners wherever referred in addition, any development which may mar the general
the Code, shall be registered by the Authority or the body governing characteristics and environment of historical, architectural or other
such profession constituted under a statute, as competent to do the monuments should also be subject to the provisions of this clause.
work for which they are employed. A guide for the equivalent This clause is intended to cover very few structures to come up in
technical qualifications and professional experience required for the vicinity of other declared historically important structures, and
such registration with the Authority is given in Annex A. In case of the scrutiny shall be limited to the external architectural features
building and plumbing services, qualifications for engineers for only so as to ensure an aesthetic continuance of the existing
utility services shall be as given in A-2.8. structures with the new. The scrutiny shall not deal with the routine
12.1 .9 In case the registered professional associated with the building plan scrutiny from other requirements of Code from the
preparation and signing of plans or for supervision, is being changed point of view of structural safety and
during any stage of building/land development process, the functional requirements.
professional shall intimate the Authority in writing about the further
non-association with the project. A-2 REQUIREMENTS FOR REGISTRATION
AND COMPETENCE OF PROFESSIONALS

14 INSPECTION, OCCUPANCY PERMIT AND A-2.1 Architect


POST-OCCUPANCY INSPECTION The minimum qualifications for an architect shall be the
qualifications as provided for in the Architects Act, 1972 for
14.2.1 The owner/concerned registered architect/engineer/structural registration with the Council of Architecture.
engineer/town planner will serve a notice/completion certificate to A-2.1.1 Competence
the Authority that the building has been completed in all respects as The registered architect shall be competent to carryout the work
per the approved plans. The deviations shall also be brought to the related to the building/development permit as given below:
a) All plans and information connected with building permit except with minimum 3 years experience in structural engineering practice
engineering services of multistoreyed/special buildings given with designing and field work.
in 12.2.5.1. NOTE—The 3 years experience shall be relaxed to 2 years in the
b) Issuing certificate of supervision and completion of all buildings case of post-graduate degree of recognized Indian or foreign
pertaining to architectural aspects. university in the branch of structural engineering .In case of
c) Preparation of sub-divisionl layout plans and related information doctorate in structural engineering, the experience required
connected with development permit of area up to 1 hectare for would be one year.
metro-cities and 2 hectare for other places. A-2.3.1 Competence
d) Issuing certificate of supervision for development of land of area The registered structural engineer shall be competent to prepare the
up to 1 hectare for metro-cities and 2 hectare for other places.` structural design, calculations and details for all buildings and
supervision.
A-2.2 Engineer A-2.3.1.1 In case of buildings having special structural features, as
The minimum qualifications for an engineer shall be graduate in decided by the Authority, which are within the horizontal areas and
civil engineering/architectural engineering of recognized Indian or vertical limits specified in A-2.2 .l(b) and A-2.4.l(a) shall be
foreign university, or the Member of Civil Engineering designed only by structural engineers.
Division/Architectural Engineering Division of the Institution of A-2.4 Supervisor
Engineers (India) or the statutory body governing such profession, The minimum qualifications for a supervisor shall be diploma in
as and when established. civil engineering or architectural assistantship, or the qualification in
A-2.2.1 Competence architecture or engineering equivalent to the minimum qualification
The registered engineer shall be competent to carryout the work prescribed for recruitment to non-gazetted service by the
related to the building/development permit as given below: Government of India plus 5 years experience in building design,
All plans and information connected with building permit; construction and supervision.
Structural details and calculations of buildings on plot up to 500 m2 A-2.4.1 Competence
and up to 5 storeys or 16 m in height; Issuing certificate of The registered supervisor shall be competent to carryout
supervision and completion for all buildings; Preparation of all the work related to the building permit as given below:
service plans and related information connected with development a) All plans and related information connected with building permit
Permit; and Issuing certificate of supervision for development of for residential buildings on plot up to 100 m2 and up to two storeys
land for all area. or 7.5 m in height; and
A-2.3 Structural Engineer The minimum qualifications for a b) Issuing certificate of supervision for buildings as per (a).
structural engineer shall be graduate in civil engineering of A-2.5 Town Planner
recognized Indian or foreign university, or Corporate Member of The minimum qualification for a town planner shall
Civil Engineering Division of Institution of Engineers (India), and be the Associate Membership of the Institute of Town
Planners or graduate or post-graduate degree in town and country The registered urban designer shall be competent to carryout the
planning. work related to the building permit for urban design for land areas
A-2,5.1 Competence more than 5 hectares and campus area more than 2 hectares. He /She
The registered town planner shall be competent to carry out the shall also be competent to carryout the work of urban renewal for all
work related to the development permit as given below: areas.
a) Preparation of plans for land sub-division/ layout and related NOTE— For smaller areas below the limits indicated above,
information connected with development permit for all areas. Association of urban designer may be considered from the point
b) Issuing of certificate of supervision for development of land of of view of desired urban design.
all areas. A-2.8 Engineers for Utility Services
NOTE— However ,for land layouts for development permit above 5 For buildings identified in 12.2.5.1, the work of building and
hectare in area, landscape architect shall also be associated, and for plumbing services shall be executed under the planning, design and
land development infrastructural services for roads, water supplies, supervision of competent personnel. The qualification for registered
sewerage/ drainage, electrification, etc. the registered engineers for mechanical engineer (including HVAC), electrical engineer and
utility services shall be associated. plumbing engineers for carrying out the work of Air conditioning,
A-2.6 Landscape Architect Heating and Mechanical Ventilation, Electrical Installations, Lifts
The minimum qualification for a landscape architect shall be the and Escalators and Water Supply, Drainage, Sanitation and Gas
bachelor or master’s degree in landscape architecture or equivalent Supply installations respectively shall be as given in Part 8
from recognized Indian or foreign university. ‘Building Services’ and Part 9 ‘Plumbing Services’ or as decided by
A-2.6.1 Competence the Authority taking into account practices of the National
The registered landscape architect shall be competent to carrv out professional bodies dealing with the specialist engineering services.
the work related to landscape design for building/development A-3 BUILDER CONSTRUCTOR ENTITY
permit for land areas 5 hectares and above. In case of metro-cities, The minimum qualification and competence for the
this limit of land area shall be 2 hectares and above. builder/constructor entity for various categories of building and
NOTE— For smaller areas below the limits indicated above, infrastructural development shall be as decided by the Authority to
Association of landscape architect may also be considered from ensure compliance of quality, safety and construction practices as
the point of view of desired landscaped development. required under the Code.
A-2.7 Urban Designer ANNEX D
The minimum qualification for art urban designer shall be the PROTECTION AGAINST TERMITE ATTACK
master’s degree in urban design or equivalent from recognized IN BUILDINGS
Indian or foreign university.
A-2.7.1 Competence 19.2 Chemical Methods Termites live in soil in large colonies
and damage the wooden structure in the buildings by eating up the
wood or building nests in the wood. Poisoning the soil under and c) continuous floor slabs, apron floors and termite grooves on
around the building is a normal recommended practice. Spraying of periphery of buildings.
chemical solution in the trenches of foundations in and around walls,
areas under floors before and after filling of earth, etc. In already 4 MODULAR CO-ORDINATION,
constructed building the treatment can be given by digging trenches ARCHITECTURAL TREATMENT AND
all around the building and then giving a liberal dose of chemicals FINISHES
and then closing the trenches.
19.3 Wood Preservatives 7.3 Systems for Mixed/Composite Construction The system of
Natural resistance against organisms of quite a few wood species mixed/composite construction depends on the extent of the use of
provides durability of timber without special protection measure. It prefabricated components, their materials, sizes and the technique
is a property of heartwood while sapwood is normally always adopted for their manufacture and use in building.
susceptible to attack by organisms. Preservatives should be well 7.3.1 Combinations of System Components for Mix &
applied with sufficient penetration into timber. For engineers, Composite Construction
architects and builders, the following are prime considerations for The following combinations may be used in mixed/ composite
choice of preservatives: constriction:
a) Inflammability of treated timber is not increased and mechanical a) Structural steel work and timber roofs on precast frames.
properties are not decreased; b) Precast floors onto steel and concrete beams, and masonry walls.
b) Compatibility with the glue in laminated wood, plywood and c) Profiled metal decking on precast beams.
board material; d) Precast frames onto cast in-situ foundations, retaining walls, etc.
c) Water repellent effect is preferred; e) Precast frames stabilized by masonry walls, steel bracing, etc.
d) Possible suitability for priming coat; f) Precast cladding in steel or cast in-situ frames and vice versa.
e) Possibility of painting and other finishes; g) Glass curtain walling, stone cladding or metal sheeting onto
f) Non-corrosive nature fasteners; and precast concrete frames, etc.
g) Influence on plastics, in case of metal rubber, tiles and concrete. h) Reinforced concrete and structural steel as
19.4 Constructional Method composite columns and beams.
Protection against potential problem of termite attack can simply be 7.3.1.1 Precast concrete may be combined with cast in-situ concrete,
carried out by ordinary good construction which prevents a colony often termed hybrid construction. Cast in-situ is mostly used to form
from gaining access by: homogeneous connections between precast elements and provide a
a) periodic visual observations on termite galleries to be broken structural topping for horizontal diaphragm action. In other cases
off it is used to form the foundations and sub-structure to the building.
b) specially formed and properly installed metal
shield at plinth level; and
7.3.1.2 Structural steelwork is largely used in long span pre stressed grouted joints need a few days of temporary propping unless
concrete floors supported on rolled and prefabricated steel beams combined mechanical connections are also used.
and also as steel roof trusses supported on concrete columns. c) As a consequence of the above, the need to design some of the
7.3.1.3 Timber may be used as long span glue laminated beams and key components to achieve temporary stability.
rafters, with precast concrete .Precast floors may be used in timber d) The availability and or positioning of equipments to transport
frame construction. Similarly, timber frames with precast and erect components — The size and weight of the various
elements shall be used as a building system. components shall be organized to make optimum use of crane
7.3.1.4 Brick and block masonry may be combined with precast capacity, for example, the lightest units farthest from the operating
concrete structures and floors. The’ most common combinations is zone.
to use pre stressed floors on load bearing walls. e ) Erection safety and speed of construction,
7.4 Design’ Considerations with attention to cast in-situ concreting
The mixed/composite structures shall be analyzed appropriately and sequences — This is particularly important where fixing gangs are
the joints in them designed to take the forces of an equivalent unaccustomed to working with different materials.
discrete system. Resistance to horizontal loading shall be provided f) Tolerances for economical construction —This is particularly
by placing beams, walls and bracings in two directions at right important where different manufacturers are producing components
angles or otherwise. The individual components shall be designed, in different materials.
taking into consideration appropriate end conditions and loads at
various stages of construction. The components of the structure shall
be designed for loads in accordance with Part 6 ‘Structural Design, 26.3.4 Maintenance Work Programmed
Section / Loads, Forces and Effects’. In addition, members shall be The programming of maintenance work can affect an owner or his
designed for handling, erection and impact loads that may be activities in the following ways:
expected during handling and erection. a) maintenance work should be carried out at such times as are
7.4.1 For mixed and composite construction the following points likely to minimize any adverse effect on output or function.
shall be considered: b) programme should be planned to obviate as far as possible any
abortive work.
a )Positions of stability cores, walls, bracing,etc. — In high rise This may arise if upgrading or conversion
buildings the most popular method is a cast in-situ core constructed work is carried out after maintenance work has been completed or if
several storeys ahead of the framework. In medium height buildings work such as rewiring is carried out after redecoration. any delay in
this may be precast concrete or brick infill, steel cross bracing or rectifying a defect should be kept to a minimum only if such delay is
precast concrete diagonal bracing. likely to affect output or function. The cost of maintenance increases
b)Maturity of connections — This may be decisive for or alter with shortening response times. maintenance work, completed or
planned site progress unless it is properly managed. Cast in-situ
being carried out should comply with all statutory and other legal benefit of the building industry as a whole. There should be frank
requirements. and recorded dialogue on an on-going basis between those who
26.3.5 Maintenance Guides occupy and care for buildings and those who design and construct
An owner responsible for a large number of buildings may have them.
established procedures for maintenance. When an owner is 26.3.7.2 Feed back should aim at the following:
responsible for the maintenance of only one building or a small a) User satisfaction,
number of buildings, the preparation of a guide tailored to suit each b) Continuous improvement, and
particular building, can offer significant advantages. Such a guide c) Participation by all.
should take into account the following: 26.3.7.3 Source of information
a) type of construction and residual life of the building, and The information on feed back can be obtained from
b) environment and intensity of use (see 26.3.2). The guide may the following:
form part of a wider manual covering operational matters. a) Occupants,
26.3.6 Planning of Maintenance Work b) Inspections,
Work should take account of the likely maintenance cycle of each c) Records, and
building element and be planned logically, with inspections being d) Discussions.
made at regular intervals. Annual plans should take into account 26.3.8 Means of Effecting Maintenance
subsequent years’ programmed to incorporate items and to prevent 26.3.8.1 Responsibility
additional costs. It should be stressed that the design of some Some maintenance work will be carried out by the occupier of a
buildings can lead to high indirect costs in maintenance contracts building or by the occupier’s representative. In the case of leasehold
and therefore, careful planning can bring financial benefits. or similar occupation not all maintenance may be the responsibility
Decisions to repair or replace should be taken after due of occupier. Responsibility of common areas may be clearly defined.
consideration. 26.3.8.2 Maintenance work sub-divided into major repair,
26.3.7 Feed Back restoration, periodical and routine or day-to-day operations will be
26.3.7.1 Feed back is normally regarded as an important procedure undertaken by one of the following:
of providing information about the behaviour of materials and a) Directly employed labour,
detailing for the benefit of the architect/engineer designing new b) Contractors, and
buildings, which will result in lessening maintenance costs. It is c) Specialist contractors under service agreement
an equally valuable source of information for the persons or otherwise.
responsible for maintenance. Every maintenance organization 26.3.8.3 The merits of each category for typical maintenance work
should develop a sample way of communicating its know how, must be considered because optimum use of resources appropriate to
firstly for benefit of others in the organization and secondly for the tasks in a given situation is an important element of policy.
26.3.8.4 The success of contracting out depends on the nature of the glass panes;
services, conditions in which contracting is undertaken (the c) Checking and repairing electric conduits/ wiring;
tendering process), how the contract is formulated and subsequent d) Checking and repairing gas pipes, water pipes and plumbing
monitoring of service quality. The important consideration in the services;
decision to contract out is whether a contractor can ensure a socially e) Re-building non-structural walls, smoke chimneys, parapet walls,
desirable quantity and quality of service provision at, a reasonable etc;
cost to the consumers. f) Re-plastering of walls as required;
26.4 Access g) Rearranging disturbed roofing tiles;
26.4.1 General h) Relaying cracked flooring at ground level; and
All maintenance activities including any preliminary survey and i) Redecoration — whitewashing, painting, etc.
inspection work require safe access and in some situations this will The architectural repairs as stated above do not restore the original
have to be specially designed. Maintenance policy, and maintenance structural strength of structural components in the building and any
costs, will be much influenced by ready or difficult access to the attempt to carry out only repairs to architectural/non-structural
fabric and to building services. Special precautions and access elements neglecting the required structural repairs may have serious
provisions may also need to be taken for roof implications on the safety of the building. The damage would be
more severe in the event of the building being shaken by the similar
28 REPAIRS AND SEISMIC STRENGTHENING OF shock because original energy absorption capacity of the building
BUILDINGS would have been reduced.
28.1 General Principles and Concepts 28.1.2 Structural Repairs
28.1.1 Non-structural/Architectural Repairs 28.1.2.1 Prior to taking up of the structural repairs and strengthening
28.1.1.1 The buildings affected by earthquake may suffer both non- measures, it is necessary to conduct detailed damage assessment to
structural and structural damages. Nonstructural repairs may cover determine:
the damages to civil and electrical items including the services in the a) the structural condition of the building to decide whether a
building. Repairs to non-structural components need to be taken up structure is amendable for repair; whether continued occupation is
after the structural repairs are carried out. Care should be taken permitted; to decide the structure as a whole or a part require
about the connection details of architectural components to the main demolition, if considered dangerous;
structural components to ensure their stability, b) if the structure is considered amendable for repair then detailed
28.1.1.2 Non-structural and architectural components get easily damage assessment of the individual structural components
affected/dislocated during the earthquake. These repairs involve one (mapping of the crack pattern, distress location; crushed concrete,
or more of the following: reinforcement bending/yielding, etc). Non-destructive testing
a) Patching up of defects such as cracks and fall of plaster; techniques could be employed to determine the residual strength of
b) Repairing doors, windows, replacement of the members; and
c) to work out the details of temporary supporting arrangement of c) Eliminating features that are sources of weakness or that produce
the distressed member so that they do not undergo further distress concentration of stresses in some members. Asymmetrical plan
due to gravity loads. distribution of resisting members, abrupt changes of stiffness from
28.1.2.2 After the assessment of the damage of individual structural one floor to the other, concentration of large masses and large
elements, appropriate repair methods are to be carried out openings in walls without a proper peripheral reinforcement are
component wise depending upon the extent of damage. The repair examples of defects of this kind.
may consist of the following: d) Avoiding the possibility of brittle modes of failure by proper
a) Removal of portions of cracked masonry walls and piers and reinforcement and connection of resisting members.
rebuilding them in richer mortar. Use of non-shrinking mortar will
be preferable.
b) Addition of reinforcing mesh on both faces ANNEX A
of the cracked wall, holding it to the wall through spikes or bolts and (Clause 2.1.2)
then covering it, suitably, with cement mortar or micro concrete. PROGRAMME EVALUATION AND REVIEW TECHNIQUE,
c) Injecting cement or epoxy like material which is strong in tension, AND CRITICAL PATH METHOD
into he cracks in walls. A-O INTRODUCTION
d) The cracked reinforced cement elements may be repaired by A-O.1 Programme Evaluation and Review Technique (PERT) and
epoxy grouting and could be strengthened by epoxy or polymer Critical Path Method (CPM) are modern management tools or
mortar application like shotcreting, jecketting, etc. devices, which have made it possible to achieve considerable
28.1.3 Seismic Strengthening savings in cost and time of construction. They can be used with
The main purpose of the seismic strengthening is to upgrade the advantage for demolition, constructional safety and fire protection
seismic resistance of a damaged building while repairing so that it measures, by including them in the list of activities (also called
becomes safer under future earthquake occurrences. This work may events) along-side with other ‘events’ of the project.
involve some of the following actions: A-O.2 Advance Planning
a) Increasing the lateral strength in one or both directions by A-O.2.1 PERT and CPM enable us to achieve judicious employment
increasing column and wall areas or the number of walls and and utilization of resources, such as labour, materials, and
columns. equipment by pre-determining the various stages, listing out the
b) Giving unity to the structure, by providing a proper connection various activities and drawing out ‘Arrow Network Diagram’.
between its resisting elements, in such a way that inertia forces A-O.3 Synchronization of Sub-Projects
generated by the vibration of the building can be transmitted to the A-O.3.1 Another extremely important advantage of CPM is that
members that have the ability to resist them. Typical important various factors influencing completion of a project can be
aspects are the connections between roofs or floors and walls, scientifically planned to be coordinated such that the completion of
between intersecting walls and between walls and foundations.
various sub-projects and services, such as furniture, sewage, Electricitricity Rules, 1956 framed there under and also the
electricity and water supply synchronises. relevant regulations of the Electric Supply Authority concerned as
A-1 PREPARATION OF CPM CHART (LISTING amended from time to time. Extracts from the Indian Electricity
OUT THE ACTIVITIES) Rules, 1956, referred to in this section, are given in Annex B.
A-1.l The most important step in preparation of CPM NOTE — Indian Electricity Rules which are being revised would
network is to list out the activities involved to the minutest details. become applicable on their notification.
For example, a few activities in case of a building project are given
below: 4.1.3 Co-ordination
a) Planning and designing of building by architect, engineer and Proper co-ordination and collaboration between the architect, civil
approved of plans by the Authority. engineer and the electrical and mechanical engineer shall be effected
b) Making the land available. from the planning stage of the installation. The provisions that will
c) Outlining detailed specifications. be needed for the accommodation of substation, transformer,
d) Procurement of materials, such as sand, cement, stone and timber switchrooms, service cable ducts, rising mains and distribution
and plants, such as concrete mixer, vibrators, water pump for curing. cables, sub-distribution boards, openings and chases in floors and
e) Soil explorations and trial pits. walls for all required electrical installations, etc, shall be specified in
f) Excavation in foundations, including demolition, if needed. advance.
g) Construction safety aspects specially in case of pile foundations. 4.1.4 Before starting wiring and installation of fittings and
h) Blasting if required (for deep foundations). accessories, information should be exchanged between the owner of
j) Fire protection measures. the building/architect/electrical contractor and the local supply
authority in respect of tariffs applicable, types of apparatus that may
2.2 Conventional Symbols be connected under each tariff, requirement of space for installing
The architectural symbols that are to be used in all drawings, wiring meters, switches, etc, and for total load requirements of lights, fans
plans, etc, for electrical installations in buildings shall be as given in and power.
Annex A. 4.1.5 While planning an installation, consideration should be taken
For other graphical symbols used in electrotechnology, reference of the anticipated increase in the use of electricity for lighting,
may be made to good practice [8-2(1)]. general purpose socket outlet, kitchen heating, etc. It is essential that
adequate provision should be made for all the services which may
3.1 Conformity with Electricity Act 2003 and Rules be.required immediately and during the intended useful life of the
Amended Up-to-date building, for the householder may otherwise be tempted to carry
The installation shall generally be carried out in conformity with the out extension of the installation himself or to rely upon use of
requirements of The Electricity Act, 2003 as amended up-to-date multiplug adopters and long flexible cords, both of which are not
and the Indian recommended.
11.1 Basic Considerations for Lightning Protection a) Ensure a
10 TELECOMMUNICATION AND OTHER close liaison between the architect, the builder, the lightning
MISCELLANEOUS SERVICES protective system engineer, and the appropriate authorities
10.1 Telecommunication Service throughout the design stages.
10.1.1 House wiring of telephone subscribers offices in small b) Agree the procedures for testing, commissioning and future
buildings is normally undertaken by the Telephone Department on maintenance.
the surface of walls. But in large multi- storeyed buildings intended
for commercial, business and office use as well as for Installation of Lifts and Escalators
residential purposes, wiring for telephone connections is generally
done in a concealed manner through conduits. 1.2 This Section gives information that should be exchanged
10.1.2 The requirements of telecommunication facilities like among the architect, the consulting engineer and the liftiescalator
Telephone connections, Private Branch Exchange, manufacturer from the stage of planning to installation including
Intercommunication facilities, Telex and Telegraph lines are to be maintenance.
planned well in advance so that suitable provisions are made in the 3 GENERAL
building plan in such a way that the demand for telecommunication 3.1 The appropriate aspect of lift and escalator installation shall be
services in any part of the building at any floor are met at any time discussed during the preliminary planning of the building with all
during the life of the building. the concerned parties, namely, client, architect, consulting engineer
10.1.3 Layout arrangements, methods for internal block wiring and and/or lift/escalator manufacturer. This enables the lift/escalator
other requirements regarding provisions of space, etc, may be manufacturer to furnish the architect and/or consulting engineer with
decided defending as the number of phone outlets and other details the proposed layout on vice-versa.
in consultation with Engineer/Architect and user. 3.2 Exchange of Information
3.2.1 If the proposed installation is within the scope of 6, the
10.3.2 Master antenna is generally provided at the top guidelines laid down together with Fig. 1 will enable the preliminary
most convenient point in any building and a suitable room on the top scheme for the installation to be established. Figure 1 shows only
most floor or terrace for housing the amplifier unit, etc, may also be some of the typical arrangements and variations are possible with
provided in consultation with the architect/engineer. respect to number of lifts and the layout,
10.3.3 From the amplifier rooms, conduits are laid in recess to Although the recommended outline for the various classes of lifts
facilitate drawing co-axial cable to individual flats. Suitable ‘Tap given in 6 enables the general planning details to be determined by
Off’ boxes may be provided in every room/flat as required. the architect, these should be finally settled at the earliest possible
stage by detailed investigation with the purchaser’s representative
reaching agreement with the lift maker where necessary before an c) Size, position, number and type of landing doors;
order is finally placed. This will enable a check to be made and d) Number of floors served by the lift;
information to be exchanged on such vital matters as: e) Height between floor levels;
a) the number, capacity, speed and disposition of the lifts necessary f) Number of entrances;
to give adequate lift service in the proposed building. g) Total headroom;
b) the provision of adequate access to the machine room. h) Provision of access to machine room;
c) The loads which the lift will impose on the building structure, and i) Provision of ventilation and, if possible, natural lighting of
the holes to be left in the machine room floor and cut-outs for wall machine room;
boxes for push-buttons and signals; j) Height of machine room;
d) The necessity for and type of insulation to minimize the k) Depth of lift pit;
transmission of vibration and noise to other parts of the building; l) Position of lift machine, above or below lift well;
e) The special requirements of local authorities and other m) Size and position of any trimmer joists or stanchions adjacent to
requirements set out in the ‘planning permit’; the lift well at each floor;
f) The need for the builder to maintain accuracy of building as to n) Size and position or supporting steel work at roof levels;
dimensions and in plumb; o) Size and position of any footings or grillage foundations, if these
g) The periods of time required for preparation and approval of are adjacent to the lift pit; and
relevant drawings for manufacturing and the installation of the lift p) In the case of passenger lifts whether the lift cage is required to
equipment; carry household luggage, such as refrigerator, steel almirah, etc.
h) The requirements for fixing guide brackets to the building
structure; 3.2.2.2 The architect/engineer should advise the lift manufacturer, if
i) The time at which electric power will be required before the Authority has any special requirements regarding lifts in
completion to allow for testing; buildings in the administrative area concerned.
j) requirements for electrical supply feeders, etc; 3.2.2.4 The architect/engineer should inform the lift/ escalator
k) The requirements for scaffolding in the lift well and protection of manufacturer of the dates when the erection of the lift/escalator may
the lift well prior to and during installation of equipment; and be commenced and is to be completed so that sufficient time is
l) Delivery and storage of equipment. allowed for the manufacture and erection of the lift/escalator.
3.2.2 Information to be Provided by Architect or
Engineer 3.2.2.5 When submitting application for a building permit to the
As a result of preliminary discussion (see also 6), the drawings of local Authority, the building plans shall include the details of lifts
the building should give the following particulars and finished sizes: (number of lifts duly numbered, location, type, type of doors,
a) Number, type and size of lifts and position of lift well; passenger capacity and speed).
b) Particulars of lift well enclosure;
3.2.3 Working Drawings to be Prepared by the Lift/Escalator electric lifts shall be carried out in accordance with the provisions of
Manufacturer The Indian Electricity Act, 2003 and the provisions framed there
The lift/escalator manufacturer requires sufficient information for under as amended from time to time, and shall also comply with the
the preparation of working drawings and is usually obtained from other provisions of Part 8 ‘Building Services, Section 2
architect’s drawings supplemented by any information obtained Electrical and Allied Installations’.
from the site and by collaboration with tie other contractors.
3.2.3.1 Working drawings showing the layout of lift/escalator duly 4.3 Conformity with Indian Standards
numbered, details of builders work, for example, holes in walls for 4.3.1 All materials, fittings, appliances etc used in electrical
guide fixing, holes in machine room floor for ropes and conduits, installation shall conform Indian Standard specifications wherever
recesses for landing sills, supports for lift/escalator machine and these exist. In case of materials for which Indian Standard
loads imposed on the building should be submitted by the specifications do not exist, the materials shall be approved by the
liftiescalator manufacturer to the architect/engineer for written competent authority. For detailed specification for lifts, reference
approval. shall be made to accepted standards [8-5(2)].
3.3 Electrical Requirement
For information of the electrical engineer, the lift/escalator 4.9 Planning for Dimensions
manufacturer should advise the architect engineer of his electrical 4.9.1 General
requirements. This information should be available early in the The dimensions of lift well have been chosen to accommodate the
planning stage so that the electrical supply requirements of the doors inside the well which is the normal practice. In special cases,
lift(s)/escalator(s) may be included in the electrical provisions of the the door may be accommodated in a recess in the front wall, for
building and that suitable cables and switchgear may be provided. which prior consultation shall be made with the lift manufacturer.
3.4 The requirements given under 4 to 13 deal with installation of 4.9.2 Plan Dimensions
lifts and 14 deal with the installation of escalators. 4.9.2.1 All Plan dimensions of lift well are the minimum clear
4 ESSENTIAL REQUIREMENTS plumb sizes. The architect/engineer, in conjunction with the builder,
4.1 Conformity with Lifts Act and Rules shall ensure that adequate tolerances are included in the building
The installation shall be generally carried out in conformity with design so that the specified minimum clear plumb dimensions are
Lifts Act and Rules there under, wherever they are in force. obtained in the finished work.
4.1.1 It is the responsibility of the owner of the premises where the NOTE — The words ‘clear plumb dimensions’ should be noted
lift will be installed, to obtain necessary permission from the particularly in case of high rise buildings.
Authority before and after the erection of lifts and for subsequent
operation of lift(s). 3 PERMIT
4.2 Conformity with Indian Electricity Act and 3.1 Application for Licence or Permit and Required
Rules All electrical work in connection with installation of Drawings Any development project for which a permit or Iicence
signage etc.
is required, shall make application to the Authority on the prescribed j) Drainage system, proposed finish ground elevations and finish
form containing such particulars as the Authority may require. The grades.
form shall be signed by the owner and shall include the information l) Location of proposed fire hydrant points.
given in 3.2 to 3.4. For various aspects of obtaining the permit, etc m) Location and dimension of fire lanes.
reference shall be made to Part 2 ‘Administration’. n) Proposed lighting layout.
3.2 Site Plan Contents and Specifications o) Landscape irrigation points and source of water.
3.2.1 Site Plan p) Fences, walls, or vegetation for screening by type, material,
The site plan to be submitted with the application for permit shall height, location, and spacing.
be drawn to a scale of not less than 1 in 500 for a site up to one q) Location of proposed street furniture.
hectare and not less than 1 in 1000 for site more than 10 hectare. t) Refuse container location, size, and access.
The following information shall be provided in addition to u) Landscape paving materials with location.
requirements for Site Plan as stated in, part 2 ‘Administration’: v) Location, type, size, and height of existing and proposed signage.
a) Existing and proposed topographic contours at interval not w) List of existing trees with botanical and common names and
exceeding 50, cm and/or spot elevations as pertinent and Bench height of the tree (see 4.1.2 for plant material schedule).
Mark of site with reference to the City Datum relative to the Mean x) Prior approvals.
Sea Level.
b) Limits of the 100 year flood plain and water surface elevation 4.1.1 Timing of Construction
(when applicable). Construction work and erosion control applications shall be
c) Location of existing major physical features, such as railway scheduled and sequenced during dry weather periods when the
track, drainage ways etc. potential for erosion is the lowest. Slope protection techniques to
d) Location of service utilities adjacent to the project with relevant control erosion shall be used when construction during wet season is
top and invert levels clearly indicated. unavoidable. Sedimentation collection systems, drainage systems,
e) Point of egress and ingress including locations and width of road. and runoff diversion devices shall be installed before construction
f) Fully dimensioned loading spaces and maneuvering areas. activity. The Landscape Architect/Architect/Engineer-in-charge
g) Parking including, location, parking spaces, size and number, and shall monitor the site conditions and progress of work and schedule
typical parking space details for both handicapped and standard appropriate timing and sequencing of construction
spaces.
h) Vehicular, bicycle, pedestrian and handicapped circulation clearly Existing drainage patterns through or into any preservation area
identified. shall not be modified unless specifically directed by the Landscape
i) Detail for parking areas including type of lighting, material for Architect/Architect/Engineer-in-charge.
paving, and security rooms, rest rooms; and type of directional
Existing grades shall be maintained around existing vegetation and 8.2.1 Fine Grading Grades will be smooth and even on a uniform
lowering or raising the levels around the vegetation is not allowed plane without abrupt changes or pockets and slope away from the
unless specifically directed by the Landscape buildings. The nominated landscape contractor will
Architect/Architect/Engineer-in-charge. Maintenance activities shall verify the surface drainage of plating areas and notify the landscape
be performed as needed to ensure that the vegetation remains architect of any discrepancies, obstructions or other conditions
healthy. considered detrimental to proper execution of the work and plant
growth
The preserved vegetated area shall be inspected by the Landscape
Architect/ Architect/Engineer-in-charge at regular intervals so that 8.6.7 Clean-Up Works -There shall be areas designated by
they remain undisturbed. The date of inspection, type of landscape architect for the contractor to carry out clean-up works.
maintenance or restorative action followed shall be recorded in the These shall include the following:
logbook. a) Removal of dead and/or overhanging branches of existing trees,
palms, shrubs and groundcovers.
LAND SCAPE b) Removal of any garbage and unsightly foreign materials.
c) Removal of dead vines and plant materials.
8 SPECIFICATIONS FOR PLANTING WORKS The contractor shall prevent damages to the existing plant materials,
The requirements relating to plant materials and other identified to be conserved. The plant materials that are to be
materials; execution of work of tree planting, shrub planting conserved if damaged beyond use during the clean-up operations,
and grassing; maintenance; etc shall be as given in 8.1 to 8.6. the contractor shall be liable to replace the plant materials at their
The contractor shall furnish all materials, labour and related own expense.
items necessary to complete the work indicated on drawing and 3.2.4 Temporary Signs
specified herein and shall carry out maintenance of the premises 3.2.4.1 Construction site signs
for 12 months after completion of the work or as specified by the Construction signs, engineers’ and architects’ signs and other
landscape architect. similar signs which may be authorized by the Authority in
connection with construction operations.
All plant material shall be protected from sun and adverse weather
until planted. Nursery stock shall be inspected and approved by the
landscape architect and the horticulturist Botanist shall do the
botanical authenticity of the selected species.

8.2 Execution

Potrebbero piacerti anche