Commissioning Check List E

Restricted
ANSI 21
CL-E128 Impedance Protection
Primary Injection Tests
Panama Colon PP BB001062
Power Plant Plant Code

System: Protection/ Synchronization and Metering (Generator)

Component: CHA10-U08-F01 – generator protection

Page: 1 of 1 Appendices:

No. Activity (Items not applicable to be marked N/A) Remarks Confirmed

1. Technical data: See device coversheet

Secondary injection checklist CL-E228 available 

2. Primary tests

Direction check (min. 30 % of rated current of relay)

Phase Current L1 Ipri[A]


Phase Current L2 Ipri[A]
Phase Current L3 Ipri[A]
Voltage U1-N [kV]
Voltage U2-N [kV]
Voltage U3-N [kV]
Active Power P [MW]
Reactive Power Q [MVAr] (oe)
Resistance R[]
Reactance X[]

3. Evaluation

- Measurement plausible 

- Tests carried out with on load 

4. Remarks:
.......................................................................................................................................................................................... 1

......................................................................................................................................................................................... 2

Department:......................................................... Name: .........................................................................


Date:......................................................................... Signature: ............................................................

Transmittal, reproduction, dissemination and/or editing of this document as well as utilization


of its content and communication thereof to others without express authorization are prohibited.
Project Site Execution Offenders will be held liable for payment of damages. All rights created by patent grant or
registration of a utility model or design patent are reserved.