Commissioning Check List E

Restricted
ANSI 46
CL-E127 Unbalanced Load
Protection
Primary Injection Tests
Panama Colon PP BB001062
Power Plant Plant Code

System: Protection/ Synchronization and Metering (Generator)

Component: CHA10-U08-F01 – generator protection

Page: 1 of 2 Appendices:

No. Activity (Items not applicable to be marked N/A) Remarks Confirmed

1. Technical data: See device coversheet

Secondary injection checklist CL-E227 available 

2. Primary tests (carried out on two phase short circuit)


- 2 phase short circuit on generator terminals.
- All other current measuring protection is blocked in DIGSI.
- Block the Generator Circuit Breaker for ON command.
- The Generator is in service with manual excitation.
- Increase the excitation to approximately 3 x Istart.
- Verify the Trip Time (t=3x (Ib / Isc)² K).
Ib = nominal current 7831 A
Isc = actual short circuit current 1880 A
Trip current ………..A 1880 A
Trip time …………s 124 s

Primary tests (carried out on load)

Rated Current IN[A]


Phase Current L1 Ipri[A]
Phase Current L2 Ipri[A]
Phase Current L3 Ipri[A]
Negative sequence current I2[A]
Unbalanced load I2/IN

3. Evaluation

- No measurement monitoring functions respond 

- Unbalanced load negligible 

Transmittal, reproduction, dissemination and/or editing of this document as well as utilization


of its content and communication thereof to others without express authorization are prohibited.
Project Site Execution Offenders will be held liable for payment of damages. All rights created by patent grant or
registration of a utility model or design patent are reserved.
Power Plant: Panama Colon E27 Unbalanced load protection

Commissioning Checklist E System:


Component:

Page: 2 of 2

No. Activity (all activities are part of electrical commissioning and start-up) Remarks Confirmed

4. Remarks:

.......................................................................................................................................................................................... 1

......................................................................................................................................................................................... 2

Department: ........................................................ Name: .......................................................................

Date:. ...................................................................... Signature: .............................................................

Siemens AG . Power Generation (PG) Construction and Commissioning


This document is subject to the handling restrictions set forth on the title page.

Potrebbero piacerti anche