LIST OF ACTIVITIES FROM OCTOBER 2018 - APRIL 2018

NO DESCRIPTION DATE START DATE FINISH


1 Project start 10/2/2017 -
2 Contractor enter site 11/15/2018 -
3 No activity due to no workers enter site yet 11/16/2018 11/20/2018
4 Workers enter site 11/21/2018 -
5 Prepare & repair existing site office 11/22/2018 12/14/2018
6 No activity due to no materials at site 11/29/2018 11/30/2018
7 Install hording 12/1/2018 12/15/2018
8 Deliver & erect formwork for WWCT & SBT 12/5/2018
9 Install project signboard 12/7/2018
10 Site clearing & divert existing drain 12/11/2018
11 Setting up of site (marking & checking grid line) 12/14/2018
12 Deliver & fabricate rebar 12/18/2018
13 Relocate service utilities 12/20/2018
14 Trial mix for G30N & G35A – Hanson Plant 12/21/2018
15 Excavation works for WWCT & SBT 12/27/2018 1/31/2018
16 Repair collapsed slope & protect with canvas 1/25/2018
17 Construction of main slab for WWCT & SBT 2/1/2018 2/22/2018
18 Construction of Wall ‘1’ – 1st Lift (WWCT & SBT) 2/22/2018 3/27/2018
19 Construction of Wall ‘2’ – 1st Lift (WWCT & SBT) 2/27/2018 4/6/2018
20 Construction of slab for Drywell WWCT & SBT 3/3/2018 3/12/2018
21 Construction of Wall ‘1’ – 2nd Lift (WWCT & SBT) 3/1/2018 4/13/2018
22 Construction of Wall ‘2’ – 2nd Lift (WWCT & SBT) 3/5/2018 4/26/2018
Delivery of pipes (200mm & 300mm), DF Sluice Valves (100mm & 300mm), DF Sluice
23 Valve C/W Head Stock & Extension Spindle (100mm & 300mm), MSCL Collar, 45° & 3/29/2018 -
90° MSCL Bend for Pipeworks
Delivery of submersible supernatant pump, sludge pump, mixer, portable pump,
24 portable water jet, DF Non Slam Non Return Valves (100mm, 150mm, 200mm, 3/30/2018 -
300mm) & Non Rising Stem Sluice Valves
25 Construction of Overflow & Walkway Slab 4/4/2018 4/27/2018
26 Partial backfilling works for WWCT & SBT 4/18/2018
27 Repair of Cold Joints, Waterproofing & Painting 4/18/2018
28 Site measurement & marking for Geotube & Polymer building 4/24/2018
29 Delivery of geotube – 30 units 4/24/2018
30 Delivery of Submain Cabling Works for MMC-SDP-Palong 4/24/2018
31 Installation of pipes (200mm & 300mm) 4/25/2018
32 Construction of footing & stump for Polymer Building 4/28/2018 5/5/2018
33 Delivery of Pipes for Mechanical Works ?
Delivery Air Compressor Set, Gasoline Engine for Submersible Pump & Horizontal
34 ?
Screw Pump
Fabrication of Polymer Plant (Mixing & Service Tank, Hopper; Feeder & Pump Skid;
35 ?
Local Control Panel; Booster Pump)
36 Delivery of Fittings, Valves & Penstocks ?
37 Delivery of Fabricated Polymer Plant ?
38 Delivery of Crane / Lifting Equipment, High Pressure Rubber Hose (WWCT & SBT) ?
39 Delivery of Balustrading & Handrail ?