RECOVERY PLAN (BASED ON CURRENT TEAM) MONTH / DAY

SCHEDULE SCHEDULE ACTUAL ACTUAL Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18
NO ACTIVITY/TASK DURATION
START FINISH START FINISH 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
CIVIL, STRUCTURE & BUILDING WORKS 290 4-Feb-18 29-Aug-18
A Wash Water Collection & Sludge Balancing Tank 103 4-Feb-18 16-May-18
1 Slab for All exluding Dry Well 20 4-Feb-18 22-Feb-18
i Erect formwork, install reinforcement, kicker & waterstop 16 4-Feb-18 18-Feb-18
ii Inspection 1 19-Feb-18 19-Feb-18
iii Concreting work (volume = 147m3) 2 20-Feb-18 21-Feb-18
iv Dismantle formwork 1 22-Feb-18 22-Feb-18
2 Slab for Dry Well 10 23-Feb-18 4-Mar-18
i To excavate, level & compact 1 23-Feb-18 23-Feb-18
ii Lay of 75mm thick lean concrete 2 24-Feb-18 25-Feb-18
iii Erect formwork, install reinforcement, kicker & waterstop 3 26-Feb-18 28-Feb-18
iv Inspection 1 1-Mar-18 1-Mar-18
v Concreting work (volume = ) 2 2-Mar-18 3-Mar-18
vi Dismantle formwork 1 4-Mar-18 4-Mar-18
3 WALL 1 - First 2.4m Height 13 5-Mar-18 17-Mar-18
i Erect scaffold 1 5-Mar-18 5-Mar-18
ii Erect formwork, install reinforcement, kicker & waterstop 4 6-Mar-18 9-Mar-18
iii Install 4 units of 100mm dia. Pipes 2 10-Mar-18 11-Mar-18
iv Inspection 1 12-Mar-18 12-Mar-18
v Concreting work (volume = 83m3) 1 13-Mar-18 13-Mar-18
vi Curing (spraying water to prevent cracks on new concrete) 3 14-Mar-18 16-Mar-18
vii Dismantle formwork & scaffold 1 17-Mar-18 17-Mar-18
4 WALL 2 - First 2.4m Height 13 18-Mar-18 30-Mar-18
i Erect scaffold 1 18-Mar-18 18-Mar-18
ii Erect formwork, install reinforcement, kicker & waterstop 4 19-Mar-18 22-Mar-18
iii Install 2 units of 200mm & 300mm dia. Pipes 2 23-Mar-18 24-Mar-18
iv Inspection 1 25-Mar-18 25-Mar-18
v Concreting work (volume = 83m3) 1 26-Mar-18 26-Mar-18
vi Curing (spraying water to prevent cracks on new concrete) 3 27-Mar-18 29-Mar-18
vii Dismantle formwork & scaffold 1 30-Mar-18 30-Mar-18
5 WALL 1 - Second 2.4m Height 12 31-Mar-18 11-Apr-18
i Erect scaffold 1 31-Mar-18 31-Mar-18
ii Erect formwork, install reinforcement 4 1-Apr-18 4-Apr-18
iii Install 2 units of 300mm dia. of pipes (level - 22.50) 1 5-Apr-18 5-Apr-18
iv Inspection 1 6-Apr-18 6-Apr-18
v Concreting work (volume = ) 1 7-Apr-18 7-Apr-18
vi Curing (spraying water to prevent cracks on new concrete) 3 8-Apr-18 10-Apr-18
vii Dismantle formwork & scaffold 1 11-Apr-18 11-Apr-18
6 WALL 2 - Second 2.4m Height 12 12-Apr-18 23-Apr-18
i Erect scaffold 1 12-Apr-18 12-Apr-18
ii Erect formwork, install reinforcement 4 13-Apr-18 16-Apr-18
iii Install 2 units of 300mm dia. of pipes (level - 22.50) 1 17-Apr-18 17-Apr-18
iv Inspection 1 18-Apr-18 18-Apr-18
v Concreting work (volume = ) 1 19-Apr-18 19-Apr-18
vi Curing (spraying water to prevent cracks on new concrete) 3 20-Apr-18 22-Apr-18
vii Dismantle formwork & scaffold 1 23-Apr-18 23-Apr-18
7 Top Slab 11 24-Apr-18 4-May-18
i Erect scaffold 1 24-Apr-18 24-Apr-18
ii Erect & install formwork, t-prop, soffit and reinforcement 4 25-Apr-18 28-Apr-18
iii Inspection 1 29-Apr-18 29-Apr-18
iv Concreting work (volume = ) 1 30-Apr-18 30-Apr-18
v Curing (spraying water to prevent cracks on new concrete) 3 1-May-18 3-May-18
vi Dismantle formwork & scaffold 1 4-May-18 4-May-18
8 Housekeeping 1 5-May-18 5-May-18
To clean up site condition 1 5-May-18 5-May-18
9 Water Tighness Testing 4 6-May-18 9-May-18
i To fill up WWCT & SBT with water 1 6-May-18 6-May-18
ii Monitoring 3 7-May-18 9-May-18
10 Backfilling & Compaction 7 10-May-18 16-May-18
i To backfill & compact outer perimeter of WWCT & SBT 7 10-May-18 16-May-18
B Polymer Building 129 23-Apr-18 29-Aug-18
1 Excavation, Levelling, Compaction for Foundation 2 23-Apr-18 24-Apr-18
i To excavate, level & compact ground to receive foundation 2 23-Apr-18 24-Apr-18
2 Footing 9 25-Apr-18 3-May-18
i Lay of 50mm thick lean concrete 1 25-Apr-18 25-Apr-18
ii Erect formwork, install reinforcement 2 26-Apr-18 27-Apr-18
iii Inspection 1 28-Apr-18 28-Apr-18
iv Concreting work (volume = ) 1 29-Apr-18 29-Apr-18
v Curing (spraying water to prevent cracks on new concrete) 2 30-Apr-18 1-May-18
vi Dismantle formwork & backfilling 2 2-May-18 3-May-18
3 Stump & Ground Beam 11 4-May-18 14-May-18
i Lay of 50mm thick lean concrete 2 4-May-18 5-May-18
ii Erect formwork, install reinforcement 4 6-May-18 9-May-18
iii Inspection 1 10-May-18 10-May-18
iv Concreting work (volume = ) 1 11-May-18 11-May-18
v Curing (spraying water to prevent cracks on new concrete) 2 12-May-18 13-May-18
vi Dismantle formwork 1 14-May-18 14-May-18
4 Ground Slab 10 15-May-18 24-May-18
i Backfilling work 1 15-May-18 15-May-18
ii Lay of 50mm thick lean concrete 2 16-May-18 17-May-18
iii Erect formwork, install reinforcement 2 18-May-18 19-May-18
iv Inspection 1 20-May-18 20-May-18
v Concreting work (volume = ) 2 21-May-18 22-May-18
vi Curing 1 23-May-18 23-May-18
vii Dismantle formwork 1 24-May-18 24-May-18
5 Column - First 2.4m Height 10 25-May-18 3-Jun-18
i Erect scaffold 1 25-May-18 25-May-18
ii Erect formwork, install reinforcement 3 26-May-18 28-May-18
iii Inspection 1 29-May-18 29-May-18
iv Concreting work (volume = ) 1 30-May-18 30-May-18
v Curing (spraying water to prevent cracks on new concrete) 3 31-May-18 2-Jun-18
vi Dismantle formwork & scaffold 1 3-Jun-18 3-Jun-18
6 Intermediate Beam & Column 1.6m Height 13 4-Jun-18 16-Jun-18
i Erect scaffold 2 4-Jun-18 5-Jun-18
ii Erect & install formwork, t-prop, soffit and reinforcement 5 6-Jun-18 10-Jun-18
iii Inspection 1 11-Jun-18 11-Jun-18
iv Concreting work (volume = ) 1 12-Jun-18 12-Jun-18
v Curing (spraying water to prevent cracks on new concrete) 3 13-Jun-18 15-Jun-18
vi Dismantle formwork & scaffold 1 16-Jun-18 16-Jun-18
7 Roof Beam + Column 0.5m Height 14 17-Jun-18 30-Jun-18
i Erect scaffold 2 17-Jun-18 18-Jun-18
ii Erect & install formwork, t-prop, soffit and reinforcement 6 19-Jun-18 24-Jun-18
iii Inspection 1 25-Jun-18 25-Jun-18
iv Concreting work (volume = ) 1 26-Jun-18 26-Jun-18
v Curing (spraying water to prevent cracks on new concrete) 3 27-Jun-18 29-Jun-18
vi Dismantle formwork & scaffold 1 30-Jun-18 30-Jun-18
8 Roof Truss & Covering 9 1-Jul-18 14-Jul-18
i Install prefabricated light gauge MS roof truss 2 1-Jul-18 2-Jul-18
ii Inspection 6 3-Jul-18 8-Jul-18
iii Install concrete roof tiles, ridge cap, gutter, UPVC downpipe 1 9-Jul-18 9-Jul-18
9 Floor, Wall, Ceiling & Accessories 42 10-Jul-18 20-Aug-18
i Install 225mm thk. brickwall, tie with mortar 5 10-Jul-18 14-Jul-18
ii Install roller shutter & frame for door and window 3 15-Jul-18 17-Jul-18
iii Electrical wiring works - carry out by specialist team 5 18-Jul-18 22-Jul-18
iv External plastering 3 23-Jul-18 25-Jul-18
v Internal plastering 3 26-Jul-18 28-Jul-18
vi Install frame & ceiling (external) 3 29-Jul-18 31-Jul-18
vii Install frame & ceiling (internal) 3 1-Aug-18 3-Aug-18
viii Rendering of floor, install tiles & skirting 6 4-Aug-18 9-Aug-18
ix Painting of wall (external & internal) and ceiling - undercoat 4 10-Aug-18 13-Aug-18
x Painting of wall (external & internal) and ceiling - finish coat 4 14-Aug-18 17-Aug-18
xi Install door & windows 1 18-Aug-18 18-Aug-18
xii Install GI tray / condiut 2 19-Aug-18 20-Aug-18
10 Apron, Ramp & Drain 9 21-Aug-18 29-Aug-18
i Backfilling, levelling & compaction works 2 21-Aug-18 22-Aug-18
ii Erect formwork, install reinforcement 3 23-Aug-18 25-Aug-18
iii Inspection 1 26-Aug-18 26-Aug-18
iv Concreting work 1 27-Aug-18 27-Aug-18
v Dismantle formwork & housekeeping 2 28-Aug-18 29-Aug-18
C Geotube Platform 58 4-May-18 30-Jun-18
1 Excavation, Levelling & Compaction for Slab, Drain & Ramp 3 4-May-18 6-May-18
i To excavate, level & compact ground 3 4-May-18 6-May-18
2 Hardcore 2 7-May-18 8-May-18
i To lay, spread & compact Crusher-run 2 7-May-18 8-May-18
3 Drain (Base) 12 9-May-18 20-May-18
i Lay of 50mm thick lean concrete 2 9-May-18 10-May-18
ii Erect formwork, install reinforcement 5 11-May-18 15-May-18
iii Inspection 1 16-May-18 16-May-18
iv Concreting work 2 17-May-18 18-May-18
v Curing 1 19-May-18 19-May-18
vi Dismantle formwork 1 20-May-18 20-May-18
4 Drain (Wall - 2 sides) 13 21-May-18 2-Jun-18
i Erect formwork, install reinforcement 7 21-May-18 27-May-18
ii Inspection 1 28-May-18 28-May-18
iii Concreting work 2 29-May-18 30-May-18
iv Curing 1 31-May-18 31-May-18
v Dismantle formwork & backfilling 2 1-Jun-18 2-Jun-18
5 Slab 14 3-Jun-18 16-Jun-18
i Lay of 50mm thick lean concrete 2 3-Jun-18 4-Jun-18
ii Erect formwork, install reinforcement 7 5-Jun-18 11-Jun-18
iii Inspection 1 12-Jun-18 12-Jun-18
iv Concreting work 2 13-Jun-18 14-Jun-18
v Curing 1 15-Jun-18 15-Jun-18
vi Dismantle formwork 1 16-Jun-18 16-Jun-18
6 Ramp 14 17-Jun-18 30-Jun-18
i Lay of 50mm thick lean concrete 2 17-Jun-18 18-Jun-18
ii Erect formwork, install reinforcement 4 19-Jun-18 22-Jun-18
iii Inspection 1 23-Jun-18 23-Jun-18
iv Concreting work 2 24-Jun-18 25-Jun-18
v Curing 1 26-Jun-18 26-Jun-18
vi Dismantle formwork 1 27-Jun-18 27-Jun-18
vii Install cheuque plate covers 1 28-Jun-18 28-Jun-18
viii To clean up site condition including levelling & compaction 2 29-Jun-18 30-Jun-18