Purpose
Use this procedure to review and approve outline agreements.

Trigger
Perform this procedure when an outline agreement is ready for your release (approval), either because
you are the responsible Contract Administrator (CA release code) or you have a City Signatory role for
this outline agreement.

Prerequisites
There is an outline agreement awaiting your approval.

You know the outline agreement number you wish to approve.

You know your City Signatory role (release code).

Transaction Code: ME35K

Helpful Hints
R/O/C column in tables represents Required, Optional, or Conditional entry.

If you don't know your Release Code, use the Matchcode button (identified below) to locate all codes
available. For Contract Administrators, the code is CA.

NOTE: The term “Outline Agreement” is used when referencing what is done in SAP while the
term, “Contract” is used when referencing the legal (paper) document.

Procedure

1. Enter transaction code ME35K in the Command Field (circled below) and click the Enter button
(the green check mark icon). The Release (Approve) Purchasing Documents screen displays.

Release (Approve) Purchasing Documents

ME35K Approve Outline Agreement Page 1 of 11


2. As required, complete/review the following fields:
Field R/O/C Description
Release Code R A release code represents the level of authorization required.
Enter the code for which you are authorized to release outline
agreements.

Example: CA for Contract Administrators

Set Release R Check mark is present.

Release Prerequisite R Check mark is present.


Fulfilled

Scope of List R Must leave with the defaulted code “ALV”.

Purchasing R Must leave with the defaulted code “K”.


Document Category

Document Number R Enter the outline agreement number you wish to access and
release.

Example: 30000841

3. Click the Execute button (the clock with green check mark icon). The Release Purchasing
Documents with Release Code XX screen displays.

Release Purchasing Documents with Release Code XX

4. Select the desired row you wish to review by clicking the outline agreement number on the left
hand side of the screen.

ME35K Approve Outline Agreement Page 2 of 11


5. Click the Details button (the magnifying glass icon). The Display Contract: Item XXXXX screen
displays.

Display Contract: Item XXXXX

6. Click the left side of the Services for Object button (circled above). The Purchase contract
00XXXXXXXX menu displays.

Purchase contract 00XXXXXXXX

7. Click the Attachment list button (circled above). The Service: Attachment list dialog box displays.
Review all attachments to ensure this contract meets all City regulations and procedures.

ME35K Approve Outline Agreement Page 3 of 11


Service: Attachment list

8. To review an attachment, select the desired attachment by clicking on the row (line).Click the
Display button (the eyeglasses icon circled above) to open for review. The attachment
displays.

Adobe Acrobat Professional file

ME35K Approve Outline Agreement Page 4 of 11


9. Click the Close button (the X in the upper right hand corner) to exit the document. Continue to
review each attachment for compliance.

10. Click the Continue button (green check mark icon) to close the Service: Attachment list screen
when done with your review of attached documents. The Purchase contract 00XXXXXXXX menu
displays.

Service: Attachment list

11. Click the Close button (the X) of the Purchase contract 00XXXXXXXX menu to return to the
Display Contract: Item XXXXX screen.

Display Contract: Item XXXXX

ME35K Approve Outline Agreement Page 5 of 11


12. Click the Overview button (circled above). The Display Contract: Item Overview screen
displays.

Display Contract: Item Overview

13. Review the following fields in the Display Contract: Item Overview screen to make sure the outline
agreement is setup correctly:

Field R/O/C Description


Item Category R Must be BLANK.
Account Assignment R The code entered should be “U”.
Category
Material C If applicable, review the uniquely identified material number
assigned to the item for which you will purchase under this
contract.
Short Text R Review the description of what is to be purchased under this
contract and to ensure the description is clear.

Examples: Mental Health Provider


Pipe, PVC, 3” Diameter Elbow Bend
Nob Hill Sewer Replacement Project

Target Quantity R Make sure this field is left BLANK or “0” (zero), as the value in
the contract is derived from the Target Value in the Header Data
screen.

Order Unit of R Review how the item or service under this contract will be
Measure purchased; the unit of measure in which the material is ordered.

For Price Agreement, review the unit of measure to be


purchased. Example: EA for each or BX for box

ME35K Approve Outline Agreement Page 6 of 11


For Value Contract, only “USD” for U.S. Dollar should be used.

Net Price R Identifies the per unit price.

For Price Agreement, review the price per unit specified in the
previous field. Example: Net Price Per EACH or BOX.

For Value Contract, only “1” should be used.

Per R Indentifies the number of units of the Order Price Unit for which
the Net Price is valid. Typically, you should see “1” in this field.

NOTE: For certain orders where a conversion factor is used, the


data enter in this field will not be “1.” This is rare.

Order Price per Unit R Indicates the unit of measure for the order unit price.

For Price Agreement, you should see the unit of measure used in
the Order Unit of Measure field. Example: EA for each or BX for
box

For Value Contract, you should see only “USD” for U.S. Dollar
used.

Material Group R You should see the five-digit code for what is purchased under
this contract. A Material Group is a collection of goods or
services that share common characteristics. For example, Office
Supplies would be used if your contract is for pens, papers,
staplers, etc.

Example: 96100 for Miscellaneous Professional Services

Plant C This is the bureau or office organization unit number. If this is a


citywide contract, it should be BLANK. Otherwise you should
see the Plant Code for the bureau or office who owns this
contract.

Example: PK00

SLoc (Storage C Not Common. You should see a BLANK field unless there is a
Location) unique number to identify the specific storage location at which
the material is stored. A plant may contain one or more storage
locations.

ME35K Approve Outline Agreement Page 7 of 11


14. Click the Header Details button (the top hat icon) if all fields are correctly done. The Display
Contract: Header Data screen displays.

Display Contract: Header Data

15. Review the following fields in the Display Contract: Header Data screen to make sure the outline
agreement is setup correctly, data should match to what is in the contract and contracting
documents:

Administrative Fields area:


Field R/O/C Description
Validity Start R You should see the contract start date - mmddyy. SAP will
default this field to the date the contract was created into SAP.
Make sure this date matches the actual contract start date.

Example: 01/01/2010

Validity End R You should see the contract expiration date - mmddyy. Make
sure this date matches the actual contract end date.

Example: 12/31/2010

ME35K Approve Outline Agreement Page 8 of 11


Terms of Delivery and Payment area
Field R/O/C Description
Target Value R You should see the contract value. The total value of all
materials or services to be released against the outline
agreement (contract). The value in this field will change when
compensation is increased or decreased with executed
amendments or change orders (for construction).

Example: 150,000.00

Reference Data area

NOTE: You don’t need to review this area, but do know that there may be contents in these fields.

Field R/O/C Description


Quotation Date O Vendor offer date

Your Reference R You should see the solicitation number in this field.

Also, could be used to enter an Old outline agreement (contract)


number if this new outline agreement is created due to a
reassignment or the vendor had to have a new City Vendor ID
number for any number of reasons.

Our Reference C  City ordinance number, if one exists

Quotation O  Vendor offer number, if any.

Salesperson O  Vendor contact person’s name.

Telephone O  Vendor contact person’s phone number.

Invoicing Party O The Vendor ID number to whom the City is sending payments.

Information area
Field R/O/C Description
Description R  You should see a short description of the contract.

Example: Citywide Office Supplies Contract

Project Manager R  You should see the name of the City Project Manager
responsible for this contract.

Example: Jane Buyer

Sole Source C  You should see a “Y” if this is sole source contract, an “N” if not,
or just a BLANK field.

On-Call(PTE) C  You should see a “Y” if this is a PTE On-Call Contract or just a
BLANK field.

ME35K Approve Outline Agreement Page 9 of 11


Owner Cost Center R  You should see the cost center of the Project Manager (PM). No
charges or encumbrances will result from this.

Example: MFPU000001 for a PM within Procurement Services

Bureau R  You should see the Plant code or the owner’s four-character
alpha code.

Example: MFPU for OMF Procurement Services

Original Contract R You should see the original contract amount. The value in this
Amount field is the same as the value in the Target Value when this is a
new contract. The value in this field will never change.

Example: 150,000.00

Bureau Project No. O You should see the bureau specific project number, if applicable.

Auto Renewal O This should be left BLANK. You should see a “Y” only if there is
a clause in the contract that states the contract automatically
renews itself unless there is a written amendment to terminate
the contract.

No. of Renewals O You should see the number of renewals allowed, based on the
renewal interval stated below.

Renewal Interval O You should see the renewal interval per the No. of Renewals
above.

Workers Comp. O You should see the expiration date – mmddyy.


Insurance Expiration

General Liability O You should see the expiration date – mmddyy.


Insurance Expiration

Auto Insurance O You should see the expiration date – mmddyy.


Expiration

Professional Liability O You should see the expiration date – mmddyy.


Insurance Expiration

ME35K Approve Outline Agreement Page 10 of 11


16. Click Back button (the green arrow icon indicated below). The Release Purchasing Documents
with Release Code XX screen displays.

NOTE: If you are rejecting this outline agreement for any reason, you will need to stop
here and use the “ME32K Reject an OA” procedures.

Release Purchasing Documents with Release Code XX

17. Click Release possible button (circled above) to approve. The button will change from a check
mark and pencil icon to a green check mark icon.

18. Click the Exit button (yellow arrow up icon).

Result
You have approved an outline agreement.

 
Next Steps

You are done, unless you need to reject this outline agreement. If so, you will need to use the
“ME32K_Reject an OA” procedures.

ME35K Approve Outline Agreement Page 11 of 11