Material Request status as at 5th of July, 2018

Materials to be  Materials to be 
July & August  Stock as at 5th  Less availble 
S/N Material Desceription Unit supplied for this  supplied for this  Remarks
2018 Budget      July , 2018 stock
month (July) month (August)
1 3/4" Tons 1334.61 142.57 1192.04                       700                      500
2 1/2" Tons 2700.64 348.32 2811.06                   1,500                  1,220
3 3/8" Tons 458.74 0 0                        ‐                       ‐ Converted to 1/2"
4 Dust Tons 3330.43 851.41 2479.02                   1,200                  1,280
5 Cement Tons 412.69 44.54 368.15                       200                      170
6 Bitumen Tons 317.67 26.05 291.62                       180                      120
7 Diesel AGO Literes 72848.11 5138 67710.11                 33,000                33,000
8 Kerosene Literes 5128.56 0 5128.56                   5,200                       ‐
9 BRC Roll 423.52 162 261.52                       150                      120
10 Binding Wire Roll 100 12 88                         50                        40

Note:
List of Asphalt and Lined drains Works  budgeted for July and August, 2018
s/n Work Item Chainage Legth Total
1 MC1 Priming on carriageway CH16+000 ‐ CH6+525 525m 525m
2 Asphaltic concrete binder course, 60mm thick. CH16+000 ‐ CH6+525 525m 525m
3 Bituminous Tack coat  CH4+700 ‐ CH6+950 2,250m
CH9+350 ‐ CH13+025 3,675m 5,925m
4 Wearing Course, 40mm thick CH4+700 ‐ CH6+950 2,250m
CH9+350 ‐ CH13+025 3,675m 5,925m
5 First coat surface dressing with 18mm thick aggregate on shoulders. CH10+450 ‐ CH10+950(LHS/RHS) 500m 500m
6 Second coat surface dressing with 12mm thick aggregate on shoulders. CH9+375 ‐ CH10+950(LHS/RHS) 1,575m
CH12+400 ‐ CH13+025(LHS/RHS) 625m 2200m
7 Side Trapezoidal Lined drain CH4+700 ‐ CH 6+950 2,250m
CH 11+600 ‐ CH 12+950 1,350m 3,600m