Installation Instruction
EPP-0778-11/02
Terminations for
Screened Single Core
Polymeric Insulated
Cables up to 24 kV
without Armour
Refer to the kit label and the title of the installation instruction.
Components or working steps may have been improved since you last installed this
product.
General Instructions
Use a propane (preferred) or butane gas torch.
Adjust the torch to obtain a soft blue flame with a yellow tip.
Keep the torch aimed in the shrink direction to preheat the material.
Clean and degrease all parts that will come into contact with adhesive.
Tubing should be cut smoothly with a sharp knife leaving no jagged edges.
Ensure that the tubing is shrunk smoothly all around before continuing along the cable.
Tubing should be smooth and wrinkle free with inner components clearly defined.
The Information contained in these installation instructions is for use only by installers trained to
make electrical power installations and is intended to describe the correct method of installation
for this product. However, Tyco Electronics has no control over the field conditions which influence
product installation.
It is the user's responsibility to determine the suitability of the installation method in the user's field
conditions. Tyco Electronics' only obligations are those in Tyco Electronics' standard Conditions of
Sale for this product and in no case will Tyco Electronics be liable for any other incidental, indirect
or consequential damages arising from the use or misuse of the products.
Raychem is a trade mark.
Table 1
L
A1 A2
Cut the cable to the required length. Bend the shielding wires back onto
Remove the oversheath according to the oversheath. Avoid crossing the
dimension L (see Table 1). individual wires.
Degrease and clean the end of the Fix the shielding wires with a wire
oversheath for about 100 mm. binder 60 mm from the end of the
Wrap the red sealant tape around oversheath.
the end of the oversheath. Gather the shielding wires together
to form an earth lead.
Thoroughly remove the core screen Cut back the insulation according to Remove the release paper and wrap
to within 40 mm of the oversheath dimension K = depth of cable lug the void filling strip (yellow) around
cut. The surface of the insulation barrel hole + 5 mm. the end of the core screen.
should be free from all traces of Install the cable lug. Stretch the strip to half of its original
conductive material. Degrease and clean the core insulation width to achieve a fine, thin edge
Smooth out any irregularities. and the lug. onto the insulation.
Note: Do not nick the insulation. Note: Do not use cable lugs with barrel Cover 20 mm of the core screen and
holes deeper than max. 110 mm. continue onto the insulation for
10 mm.
A3 A4 A5
insulation
10
20
max.
110 K
core screen
40
void filler
(yellow)
Thoroughly remove the core screen Cut back the insulation according to Remove the release paper and wrap
to within 50 mm of the oversheath dimension K = depth of cable lug the void filling strip (yellow) around the
cut. The surface of the insulation barrel hole + 5 mm. end of the tape shield.
should be free from all traces of Install the cable lug. Stretch the strip to half of its original
conductive material. Degrease and clean the core width to achieve a fine, thin edge onto
Smooth out any irregularities. insulation and the lug. the insulation.
Note: Do not nick the insulation. Note: Do not use cable lugs with barrel Cover 5 mm of the tape shield and
holes deeper than max. 110 mm. continue along the core screen onto
the insulation for 10 mm.
B3 B4 B5 10
30
5
insulation
max.
110 K
core screen
50
void filler
(yellow)
6 7 8
Shim the cable lug barrel: Preheat the cable lug slightly before Shrink the tubing down starting at the
Use additional red sealant tape to placing the tubing over the core. screen cut using a soft yellow
shim the cable lug barrel for the The bottom end of the tubing should flame. Heat the area well but avoid
following voltage levels and cross be level with the wire binder. scorching of surface. Continue
sections. shrinking towards the cable lug.
12 kV: 10 to 25 mm2 Finally shrink down the bottom end of
17,5 kV: 16 to 25 mm2 the tubing.
24 kV: 25 mm² The numbers in the drawing indicate
the shrink sequence.
Note: After installation the termination Shrink the skirts into place at the
must be post-heated as well as the position shown in the drawings on
palm of the cable lug until a bead of the back page. Start with the first
sealant (green) appears around the skirt on the lowest position.
top of the tubing.
Allow the termination to cool before
applying any mechanical strain.
9 10
60 60
60
60
60
180
a
r
min
45°
D