CONTRACT BILL
Contract Identification Number: DROBTD/3373354/071/72/71
Name of The Project: Roadway Excavation and Structure Works in Paribagar -Khandeshori Road, Darchula
Original Contract Upto Previous IPC Current IPC Work Completed Till Date Balance
S.N. Description of Works Unit Phy. Fin. Item Phy. Fin. Remarks
Quantity Rate Amount Quantity Amount Quantity Amount Quantity Amount Quantity %
Wtge. Wtge. Progress Progress Progress
1 2 3 4 5 6=4*5 7 8 9=8*5 10 11=10*5 12 13 14=12/4 14 15 16=4-12 17
Insurance of work, workmen and Contractor's
Equipment, Third party insurance including personal
1 LS 1.00 50,000.00 50,000.00 0.60% 0.64% - - - - - 0.00% 0.00% 0.00% 1.00 100.00%
injury or death as per condition of contract and
contract data .
Roadway excavation(Back/Grade/Fresh Cutting) in
all type of soil at various chainages including disposal
2 m3 25,500.00 227.00 5,788,500.00 69.54% 74.54% 7,660.80 1,739,001.60 16,400.00 3,722,800.00 24,060.80 5,461,801.60 94.36% 65.62% 70.33% 1,439.20 5.64%
to nearest suitable location all complete as per
specification and as directed by Engineer.[SS 905]
Excavation for foundation through all types of soil
3 including relevant lift and disposal all complete [907 m3 210.00 888.00 186,480.00 1.13% 2.40% 98.10 87,112.80 - - 98.10 87,112.80 46.71% 0.53% 1.12% 111.90 53.29%
]
Backfilling in layers in foundation pits,trenches with
common excavated material etc including
4 m3 105.00 506.00 53,130.00 0.64% 0.68% 40.25 20,366.50 68.00 34,408.00 108.25 54,774.50 103.10% 0.66% 0.71% (3.25) -3.10%
compaction and watering etc complete for depth of
foundation upto 1.5m . [908 ]
Providing,laying and levelling of dry stone soling
5 m3 10.50 2,250.00 23,625.00 0.29% 0.30% - - - - - - 0.00% 0.00% 0.00% 10.50 100.00%
works in foundation all complete.[2602,2603]
Providing and placing machine mixed M15/40
cement concrete for drain and slab including
6 m3 7.00 10,800.00 75,600.00 0.82% 0.97% - - - - - - 0.00% 0.00% 0.00% 7.00 100.00%
compaction, curing, testing etc. all complete as per
specification and drawing. [2000 ]
Providing and laying Random rubble stone masonry
in cement mortar [ cement(1) : sand(4)] including
7 scaffolding, curing, preparation of mortar etc. m3 131.25 1,700.00 223,125.00 12.75% 2.87% 37.65 64,005.00 - - 37.65 64,005.00 28.69% 3.66% 0.82% 93.60 71.31%
complete, masoned height 0-5m, lead 30m (manual
mixing), mortar 35% [2607 ]
Page 1 of 2
CONTRACT BILL
Contract Identification Number: DROBTD/3373354/071/72/71
Name of The Project: Roadway Excavation and Structure Works in Paribagar -Khandeshori Road, Darchula
Original Contract Upto Previous IPC Current IPC Work Completed Till Date Balance
S.N. Description of Works Unit Phy. Fin. Item Phy. Fin. Remarks
Quantity Rate Amount Quantity Amount Quantity Amount Quantity Amount Quantity %
Wtge. Wtge. Progress Progress Progress
1 2 3 4 5 6=4*5 7 8 9=8*5 10 11=10*5 12 13 14=12/4 14 15 16=4-12 17
Grand Total Including VAT and PS (K)=(J+I) 5,903,730.37 2,164,078.63 2,933,546.21 5,097,624.84