IV BTECH I SEM I MID EXAMINATION SET-1
SUBJECT: Estimating & Costing (A70138) MAX.MARKS:10
BRANCH: CIVIL DATE: 14.09.2017 (F.N) DURATION: 1Hr
Note: Answer any 2 questions 2X5M=10M
1. Answer the following
a. What is meant by estimating and costing and state its need? (1.5M)
b. Estimate the cost of earthwork for a portion of road for 400m length from the
following data: (3.5M)
Formation width of the road is 10m. Side Slopes are 2:1 in banking , 1.5:1 in Cutting.
Station Distance (m) R.L of Ground R.L of Formation
25 1000 51.00 52.00
26 1040 50.90
27 1080 50.50
28 1120 50.80
29 1160 50.60 Downward Gradient
30 1200 50.70
of 1 in 200
31 1240 51.20
32 1280 51.40
33 1320 51.30
34 1360 51.00
35 1400 50.60
2. Answer the following
a. Distinguish lead and lif (2.0M)
b. Estimate the Cost of 1000 Sqm of 16mm thk Plastering using cement mortar 1:4
(Fine Sand) (3.0M)