Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Manual
Document1 1
Section 1 ........................................................................................................................ 4
Procurement Objectives and Governance ................................................................. 4
Important General Issues ................................................................................ 4
Expertise and Probity ..................................................................................... 4
Casual Purchases. ........................................................................................... 4
Pilot Projects .................................................................................................. 4
Sole Suppliers ................................................................................................ 4
Conflict of Interest ......................................................................................... 5
Statutory Provisions ....................................................................................... 5
Collusive Tendering ....................................................................................... 5
Criminal Convictions ..................................................................................... 5
Procurement and Accessibility ...................................................................... 5
Section 2 ........................................................................................................................ 6
Procurement Process ................................................................................................... 6
Competitive Process below EU threshold values .......................................... 6
Procedures available Nationally ..................................................................... 6
a) Open Procedure .......................................................................................... 6
b) Restricted Procedure. ................................................................................. 7
Awarding a contract without a competitive process ..................................... 7
Direct Invitation (without Advertising) ......................................................... 8
Section 3 ........................................................................................................................ 9
Authorisation (Thresholds) and Responsibilities ...................................................... 9
Certifying and Authorising invoices............................................................... 9
Framework Agreements .................................................................................. 9
Operation of Panels/Lists .............................................................................. 10
Section 4 ...................................................................................................................... 11
Quotation/Tendering Procedures ............................................................................. 11
A. Low Value Procedure (less than €5,000) .............................................. 11
B. Medium Value Procedure (between €5,000 and €50,000) .................. 11
D. EU Procedure, (greater than EU Threshold) ...................................... 12
Formal Tendering Process ........................................................................................ 12
a. Budget approval ..................................................................................... 12
b. Specification of requirements ............................................................... 12
c. Terms of Reference ................................................................................ 13
d. Selection of potential suppliers ............................................................. 13
e. Pre tender clarification requests........................................................... 13
f. Developing evaluation selection/award criteria .................................. 14
Sample of Award Criteria for a Service Contract .................................................. 14
Sample of Award Criteria for a Supply Contract .................................................. 14
Evaluating Selection Criteria ............................................................... 15
Evaluating Award Criteria ................................................................... 15
g. Delivery and opening tenders ............................................................... 15
h. Evaluation of tenders and contract award .......................................... 15
Scoring Cost................................................................................................................ 16
i. De-briefing unsuccessful suppliers ....................................................... 17
j. Contract Management, .......................................................................... 18
k. Filing and storage of tender documentation ........................................ 18
Document1 2
l. Risk Management .................................................................................. 18
Section 5 ...................................................................................................................... 20
Engagement of Consultants and other External Support .......................... 20
Engaging external support ................................................................................... 20
Services comprising a significant element of direct service to office holder ...... 21
Ethics in Public Office Act 1995 ......................................................................... 21
Engagement of external support by Body to undertake work in another ............ 22
Documenting the decision to acquire external support ........................................ 22
Accounting for consultancy, contracting and external services ........................... 22
Where to charge Contractors and External Service Providers expenditure ......... 23
Establishing the Business Case for Consultancy services ................................... 23
Whole Life Costings ............................................................................................ 24
Cost benefit analysis ............................................................................................ 25
Risk Assessment and Management ...................................................................... 25
Approval of the Business Case ............................................................................ 25
Absence of a business case. ................................................................................. 26
Project Organisation............................................................................................. 26
Re-Tendering ....................................................................................................... 26
Reporting on Contracts ........................................................................................ 27
Appendices/Templates .................................................................................................. 28
Appendix 1 - Thresholds ..................................................................................... 28
Appendix 2 - Project File .................................................................................... 29
Appendix 3 - Glossary of Terms .......................................................................... 30
Appendix 4 - Guide to etenders website ............................................................... 32
Appendix 5 - Summary Overview of Procedures and Timescales ........................... 35
Template 1 - Certificate of Tender Received......................................................... 37
Template 2 - Open Procedure Tender Evaluation .................................................. 39
Template 3 - Score sheet for Evaluation of Tenders .............................................. 41
Template 4 - Score Sheet for Evaluation of Tenders – (Multiplier Method) ............ 42
Template 5 - Tender Evaluation – Checklist ......................................................... 43
Template 6 - Request for Tender (RFT) Letter ...................................................... 44
Template 7 - Acknowledgement Slip ................................................................... 45
Template 8 - Tender Documents – Checklist ........................................................ 46
Template 9 - Sample RFT ................................................................................... 47
Document1 3
Section 1
It is very important that the public procurement function is discharged honestly, fairly
and in a manner that secures best value for public money. This Department must be
cost effective and efficient in the use of resources while upholding the highest
standards of probity and integrity.
Casual Purchases.
Divisions should examine purchasing profiles to minimise casual or “once off”
purchases. An appropriate contracting arrangement should be put in place for efficient
and cost effective delivery of recurring supplies and services.
Pilot Projects
Where a procurement process involves a pilot stage, the pilot should be conducted in
a manner that allows and encourages the identification of a range of acceptable
options.
Sole Suppliers
Where it is necessary to deal with a sole supplier, service provider or contractor,
arrangements, which provide best value for money, should be negotiated. Divisions
Document1 4
should take care when they face such a scenario. Open-ended arrangements with these
distributors should be avoided where possible.
Conflict of Interest
Divisions should be aware of potential conflicts of interest in the tendering process
and should take appropriate steps to avoid them.
Statutory Provisions
Before awarding a contract, Divisions should ensure that tenderers have regard to
statutory provisions relating to minimum pay, legally binding industrial or sectoral
agreements and relevant health and safety issues, when preparing tenders.
Collusive Tendering
Divisions should watch for anti-competitive practices such as collusive tendering.
Criminal Convictions
Candidates or tenderers who have been convicted of involvement in organised crime,
fraud, corruption or money laundering must be excluded from performing a public
contract.
Document1 5
Section 2
Procurement Process
For contracts below the EU threshold values (€125,000) the procedures set out below
should be followed:
Supplies or services less than €5,000 in value might be purchased on the basis of
verbal quotes from one or more competitive suppliers;
Supplies or services contracts between €5,000 and to €25,000 in value might be
awarded on the basis of responses to specifications sent by fax or e-mail to at least
three suppliers
Contracts above €25,000 and up to the value of the EU thresholds should
normally be as part of a formal tendering process. Publication on the
etenders.gov.ie website generally meets national advertising and publicity
requirements and significantly reduces the need for expenditure on advertising.
While Divisions are not required to advertise on the national public procurement
website etenders.gov.ie for requirements below €25,000 they are encouraged to do so
if the anticipated response would not be disproportionate, having regard to the value
of the requirement.
The main requirement in relation to contracts entered in to for supplies and services is
for “Competitive Tendering” with Divisions/Units being widely encouraged to use
the e-Tenders website as a standard means for awarding their contracts.
a) Open Procedure
Divisions/Units may use the open procedure for below threshold contracts whereby
tender documents are made available to all. This can be augmented by issuing tender
documents to known suppliers. Tender documents should test the financial and
technical capacity of supplier in addition to assessing their responsiveness to any
specific requirements.
While the Department of Finance guidelines do not set down any timescales for the
receipt of tenders/quotes it is the policy of the Department of Transport that a
minimum of 21 days be given.
Document1 6
b) Restricted Procedure.
This is a two-phase procedure. Phase 1 being the request for expressions of interest
(EOI) based on financial and technical capacity. As an alternative Divisions/Units
may issue a questionnaire as a means of standardising responses. Phase 2 being the
invitation to tender phase.
As with the open procedure it the policy of the Department of Transport that a
minimum of 21 days be given to tenderers to respond to both phases i.e. 21 days to
respond to requests for expressions of interest and 21 days for suppliers to submit
tenders. It should be the practice where at all possible to invite at least 5 competent
entities to tender.
When awarding a contract, care should be taken to avoid entering into open-ended
arrangements, for administrative convenience, that reduces or hinders competition.
Market testing should be undertaken at appropriate intervals to ensure that market
openness and competition is maintained. It may be even appropriate to advertise in the
OJEU to establish if there are international suppliers capable of meeting your needs.
However should the situation arise at a minimum a Division/Unit should negotiate the
terms of the contract with the company to ensure value for money.
If for any reason it is proposed to procure any good/service above €25,000 without a
competitive process, it should be noted that these procurements are subject to prior
review by the Department’s Procurement Officer/ Internal Audit. Such instances
where a competitive process is not used are subject to reporting to the Comptroller
and Auditor General and the Department of Finance by the Secretary General.
Document1 7
Direct Invitation (without Advertising)
Alternatively a process of direct invitation to tender may be used. This may involve:
invitation to firms deemed appropriately qualified for a particular project (this
maybe be appropriate for specialised requirements in markets where there is a
limited number of suppliers or service providers);
invitation to tender to firms on a list established on an open and objective basis
(normally used when there is a frequent or recurring requirement or to maintain a
well organised ongoing procurement system).
Where direct invitations are issued, firms from which tenders are sought should be a
good representative sample of all potential bidders in the market concerned. The
number must be sufficient to ensure adequate competition, and should not be
restricted for reasons of administrative convenience. At least five firms should
normally be invited to submit tenders.
In keeping a list of firms from which they invite tenders a Division should advertise at
appropriate intervals (normally on an annual basis) for the admission of interested
parties and should ensure that the lists are open to suitably qualified entrants at all
times. Care should be taken to ensure that such lists are used in an open and non -
discriminatory manner and ensuring that recently established firms, or firms with no
previous experience of public contracts, are not excluded from invitations to tender.
Document1 8
Section 3
HEO up to €50,000
AP up to €200,000
PO No limit.
To authorise an invoice for a particular cost centre, you must be listed on the
authorising officers form for that cost centre currently held by Finance Division.
Blank Authorising Officers forms can be found on the Finance Division forms page
on Staffnet. Original completed copies of these forms should be submitted to Finance
Division and must be updated whenever there is a change to the authorising officers
for any cost centre. Finance Division will request updates on these forms annually
however it is the Division’s responsibility to ensure that invoices are being authorised
only by officers listed on the authorising officers form for that cost centre.
Framework Agreements
Framework Agreements/Panels
The revised public sector Directive provides for “framework agreements” under
which contracting authorities enter into arrangements with suppliers or service
providers to supply goods or services under agreed conditions for a period of time,
normally not more than four years. Under these agreements, some elements of the
requirement, for example quantity, price, precise product specification, will generally
not be fully established at the start of the agreement. Advertising for framework
agreements should set out the precise nature of the proposed procurements to the
highest degree possible.
Document1 9
The fundamental requirement is that non – discriminatory and transparent competition
prevails in establishing framework agreements and in awarding contracts on the basis
of such arrangements. The provisions of the revised Directive (Article 32) are
designed to ensure this.
Operation of Panels/Lists
Lists of companies can be established from which future tenders may be sought for
ongoing regular requirements. The existence of such a list from which tenders will be
requested as and when requirements arise must be advertised.
Document1 10
Section 4
Quotation/Tendering Procedures
This procedure must be used for purchases with an estimated value of less than
€5,000.
One or more quotations from competitive suppliers,
Market testing should be carried out periodically,
For purchases of less than €1,000 the use of a low value purchase card should be
considered, otherwise a Purchase Order must be raised,
Relevant backing documentation filed (See reference to documentation).
This procedure must be used for purchases with an estimated value greater than
€5,000 and less than €25,000.
Allocation (budget) must be in place before proceeding with purchase,
Expenditure approval of budget holder required,
Minimum of three competitive quotations based on specification,
Advertising on e-tenders is recommended,
All contract award procedures should include a verifiable audit trail,
Purchase Order must be raised,
Relevant backing documentation filed (See section on documentation).
This procedure must be used for purchases with an estimated value greater than
€25,000 and less than €125,000 (current EU threshold).
Allocation (budget) must be in place before proceeding with purchase,
Expenditure approval of budget holder required,
Formal tendering must be used,
Specification is required,
Minimum of 3 weeks response time for suppliers,
Advertise on e-tenders unless exceptional circumstance,
Sealed bids before a prescribed date,
Formal purchase approval supported by technical/commercial recommendations
where appropriate,
All contract award procedures should include a verifiable audit trail,
Purchase Order must be raised,
Relevant backing documentation filed (See section on documentation).
Document1 11
D. EU Procedure, (greater than EU Threshold)
This procedure must be used for purchases, which exceed the EU threshold.
(Currently €125,000 for supplies and services)
Prior Information Notice should be used if practical,
Allocation (budget) must be in place before proceeding with purchase,
Expenditure approval of budget holder required,
Formal tendering must be used,
Call for competition (outlining OJEU award criteria),
OJEN contract award notice,
All contract award procedures should include a verifiable audit trail,
Purchase Order must be raised,
Relevant backing documentation filed (See section on documentation.
a. Budget approval
A realistic estimate of all phases of the service or product is essential, as this will
influence the procurement procedure to be followed and is important for budgeting
purposes. Establish whether sufficient funds are available to meet the purchase. If
there is an on-going commitment into a subsequent year, the funding for this
eventuality must be factored in. It is important at this stage to determine whether the
estimate (exclusive of VAT) is over the relevant EU procurement threshold (see
Appendix 1)
Once a realistic estimate of cost is available the relevant budget holder (Principal
Officer) should be requested to approve the expenditure. This should be done a timely
fashion. The senior management (i.e. Principal Officer level for projects with a cost
estimate less than €500,000; Assistant Secretary level for projects at or above this
level; and Accounting Officer level for all projects with a cost estimate equal to or in
excess of €30 million) review of the business case must, at a minimum, assess and
approve the business justification for the project on presentation of the full business
case; the decision to hire external support; and the procurement strategy proposed.
If no funding is available it will be necessary to make a business case to the Finance
Division to establish if funding can be made. Under no circumstances must a
commitment be made to initiate any procurement process in the absence of a
sufficient budget sanctioned by the Finance Division and should a procurement
process be initiated in the absence of such funding a Division may find that its future
budget might be reduced accordingly.
b. Specification of requirements
Document1 12
services required and must set out the criteria for the selection of the successful
tenderer.
It is very important that the specification does not make reference to trade
names/patents or individual companies. In exceptional circumstances where there is
no alternative it is essential that the words “or equivalent” are included.
c. Terms of Reference
Terms of reference are essentially the specification for consultancy services. Standard
terms of reference include:
Brief background on the Department including scale and number of staff etc;
Details and background of the proposed assignment;
Required deliverables from consultant;
Timeline including proposed starting date;
Outline resources to be provided by the Department/Division if relevant;
Reporting & contact details;
Selection details including contract award criteria;
If required, notification that presentation to selection panel must be made;
Request for reference details and CV’s of proposed project team.
It is important to put serious thought and consideration into the selection of potential
suppliers. One established way is to establish a list of firms from which tenders for
different requirements can be sought. The existence of such list(s) should be
advertised annually and the admission to the list must be open to suitably qualified
entrants at all time. It is very important that the use of lists is done so in an open,
transparent and non-discriminatory way.
Following the issue of tender documents, any further correspondence with the
tenderers prior to the closing date of the competition, must be verifiable, e.g. copy of
fax, email or registered post. It is recommended that any bidders seeking clarification
or additional information do so to a specified email address rather than by phone. Any
response to verbal queries should be confirmed in writing /email.
Document1 13
It may arise where tenderers do not have sufficient time to prepare a complete tender
and they request an extension to the bidding period. Only in very exceptional
circumstances should a request for an extension be granted and normally this will
only occur if a substantial number of interested parties submit similar requests. Under
no circumstances should an extension be given if the request is received within seven
days of the closing date.
In the event that bidders are invited to visit a site/office to fully assess a proposed
contract before submitting a formal tender, all companies/individuals on the tender list
must be invited so that each has the same opportunity to tender effectively. Site visits
must be carefully arranged and supervised by a nominated person and due care must
be taken to ensure that all bidders are given the same information and access.
All tendering procedures can be divided into two separate assessment operation:
Selection Criteria – These criteria are concerned with the qualities of the supplier
as such in terms of their financial, economic and technical resources at their
disposal.
Contract Award Criteria – The award criteria relate to the qualities and cost of the
products or services which the supplier proposes to provide if successful in
winning the contract.
In short, contracts are awarded after applying the award criteria, but only after the
suitability of those excluded have been checked under the suitability criteria.
Document1 14
Evaluating Selection Criteria
When information is sought from suppliers to test their financial and technical
competence as part of the expression of interest under the restricted procedure or as
part of the tender under the open procedure, all the information received must be
assessed
In the open procedure it is a process of verifying that tenderers meet the minimum
levels set (a yes/no process, whereby they must meet the minimum levels). In the
open procedure a large number of tenders may be received. The evaluation process
involves firstly confirming that the tenderers meet the minimum levels of
financial/technical competence; secondly confirming that they comply with the
specification and lastly they are evaluated against the award criteria.
When tenders have been received they should be evaluated on the basis of the
specification issued and the award criteria and weightings indicated and by the same
team appointed before the invitation to tender has issued. In relation to award criteria
it is a requirement to include the weightings for each criterion in the tender documents
(for EU procurements). Tenders must be evaluated against the stated criteria. No new
criteria can be introduced once the tenders have been received. The tenderer with the
highest score, meeting all the criteria is the winning tender.
All tenders should be opened together and as soon as possible after the designated
time and date of receipt. They must be opened in the presence of two officials to
ensure in the case of a dispute there is a clear and formal vouched report of the
tenders received. They should be signed and date stamped as should the Form of
Tender and other tender pages, which contain prices, rates etc. Tenders received after
prescribed deadline should be returned unopened.
After tenders have been opened, information relating to tenders should not be
disclosed to any of the tenderers or to any staff not officially concerned in the
tendering process.
Document1 15
Only tenders that comply with the specifications and general requirements of
the tender documentation will be considered
A tender that does not meet these needs cannot be accepted and must be
treated as invalid
The pre-published award criteria may not be altered in carrying out the
evaluation process
Tenders which fall into the following categories may be rejected:
Irregular tenders which fail to meet the specification;
Unacceptable tenders which fail to meet the suitability criteria, or
late;
“unsuitable" tenders which fail properly to address the
requirements to any reasonable degree.
The result shows that Tender B is the winner even though priced at 33% higher than
the lowest cost.
Scoring Cost
Cost scoring may be carried out using a variety of different formulae. The two most
commonly used methods include:
Document1 16
Maximum Score Tender A Tender B Tender C
3500 points (Representing cost at 35% €150,000 (lowest €200,000 (33% €250,000 (66%
weighting) cost) higher) higher)
Formula using Graduated Scale 150,000x 3500 150,000x 3500 150,000x 3500
150,000 200,000 250,000
Score using Graduated Scale 3,500 2,625 2,100
Score using Sudden Death 3,500 2,333 (33% lower) 1,166 (66% lower)
Tenderers should be informed as to which methodology has been chosen for the evaluation and scoring of cost .
Evaluation Report
Apart from observing the legal obligations where the provisions of the procurement
Directives apply, where contracts are awarded on the basis of the most economically
advantageous it is good practice to adopt a voluntary constructive policy on de-
briefing unsuccessful candidates. Unsuccessful tenderers should be given an
objective assessment of the comparative strengths and weaknesses of their tenders
having due regard of the need to avoid compromising the competitive situation of
tenderers and for commercial sensitivity.
Document1 17
j. Contract Management,
Once a contract has been signed or purchase order has been raised, it is incumbent on
the Department of Transport that the supplies, works or services are delivered in
accordance with the terms of the tender and the prices quoted. If companies fail to
meet these requirements they should be contacted immediately and a management
process of improvement put in place. A full written record of all correspondence
with/from the supplier should be maintained.
A Division must maintain complete records of each stage of the procurement process.
The records must detail all decisions made in relation to the contract and must be kept
for a period of at least seven (7) years.
The file should be clearly labelled, with contract description and reference number
and should be divided into the following sub-sections:
A copy of every contract entered into should be forwarded to the Procurement Unit of
the Finance Division.
l. Risk Management
The Report of the Working Group on the Accountability of Secretaries General and
Accounting Officers (the Mullarkey Report) recommended, inter alia, that all
Government Departments and offices should introduce a formal risk management
system and should make risk management part of the business planning process. The
process of risk management involves a cycle of identifying risks, evaluating their
potential consequences and determining the most effective methods of responding to
them. This means reducing the chances of their occurrence and reducing their impact
if they do occur.
Divisions should ensure that appropriate procedures are in place to identify and assess
Document1 18
all relevant risks throughout the procurement cycle. As a general principle, risks
should be borne by the party best placed to manage them and a body should not
accept risks, which another party is better placed to manage.
While a detailed exposition of risk assessment and management is beyond the scope
of these guidelines, Division’s should note that, typically, risk will impact the project
at different stages and it should be addressed appropriately as follows:
Project risk. This encompasses risk to the project from the inadequate definition or
assessment of the need, scope, scale and financing of the project. These should be
addressed in the business case;
Process risk. This is risk resulting from an inadequate knowledge of national and
EU procurement policy and law and from incorrectly or inadequately carrying out
a public procurement procedure. Process risk is addressed by adhering to these
guidelines and to the other documents referenced herein;
Relationship risk. This is risk resulting from inadequate relationships with the
contract holder and the implementation of the project. It is addressed by the
contract, the project management plan, project management procedures and by
review procedures (e.g. mid-term review, independent peer review, etc.);
Termination risk. This is risk resulting from inadequate definition of project
boundaries, of ‘project creep’, incrementalism, etc. It is addressed by having a
business case that specifies the scope of the project; a contract that states how and
when project change can occur; by change management procedures; and by the
final report.
Document1 19
Section 5
External Service Providers are organisations that provide the services or the
human/physical resources to meet the ICT and other service requirements of a
Department. These requirements could include software development; network
installation and management; infrastructure management; data centre hosting;
managed services; shared services, etc. External service provision involves the
transfer of actions for delivering business functions or services to an external service
provider but does not include the use of contractors (i.e. external support under the
day-to-day direction of the contracting authority) or the cost of purchasing packaged
software.
Before a Department considers hiring external support, it must first determine that the
project cannot be delivered in-house. If adequate internal resources are not available
Document1 20
or if an external review is mandated, it is only at this stage that hiring of external
support should be considered.
In line with stated Government policy, all public bodies must use a competitive
process for the purchase of goods and services, whatever the value. Consultants,
contractors and outside service providers, therefore, must be engaged following such
a process. Awarding a contract without a competitive process can be considered only
in the situations specified in section 2 (Direct Invitation without Advertising). If the
value of the contract is equal to or above the EU threshold, the provisions of Article
31 of Directive 2004/18/EC must be complied with where a contract notice has not
been published or Article 30, where such notice has been published.
Employed under a contract for services by an office holder, having been selected
for the award of the contract by an office holder personally otherwise than by
means of a competitive process; and
Whose function or principal function as such a person was or is to provide advice
or other assistance to or for the office holder.
Therefore, if a person is: (a) selected by the office holder personally; (b) employed
under a contract for services that was awarded without a competitive process; and (c)
whose function or principal function is to provide advice or other assistance to or for
the office holder, the person is a special adviser, as provided for by section 19(1)(b)
the 1995 Ethics Act and, where this is the case, there must be compliance by both the
office holder concerned and the special adviser with their respective obligations (e.g.
laying the contract before the Houses of the Oireachtas, preparing and furnishing
statements of interests, etc.) as required by the Ethics legislation.
Note that special advisors can also be appointed under the provisions of section
19(1)(a) of the Ethics in Public Office Act 1995 (i.e. where an excluding order is
Document1 21
obtained) and under the provisions of section 11(1) of the Public Services
Management Act 1997 (i.e. by Government order).
Document1 22
Where to charge Contractors and External Service Providers expenditure
As engaging external support is a cost on the public purse, a business case for the
project, linked to this Department’s business strategy, must be produced and must
provide financial justification for the project based on its whole life cost. In essence,
the business case must justify the project in business terms; say what business benefits
can be expected by implementing it; and must show why the project cannot be
developed in-house and why external support is required. The business case must
demonstrate in clear concise terms understandable to senior management that the
envisaged solution is the optimum combination of fitness for purpose and whole life
cost that meets the Department’s policy objectives for the project. That is to say, when
implemented, it will achieve Value for Money.
The relevant Division must determine the set of outputs that, if delivered to its quality
standards and if implemented on schedule and on budget, will be the most effective in
achieving the Department’s policy objectives for the project. The business case,
therefore, must present the deliverables, whether goods or services that the contract
holder will be required to produce or provide. It must show how these deliverables
will meet this Department’s policy objectives for the project and that its goals are
expressed and quantified in terms of impact on this Department’s business objectives.
This is a key requirement, and if the proposed deliverables cannot meet this
Department’s policy objectives for the project, serious consideration should be given
to cancellation of the project or to carry out a review of its justification. The use of
whole life costing will help determine the total cost of achieving the policy objectives
in the way envisaged by this Department.
For contracts below the EU threshold, all Divisions should develop a business case, at
a level of detail proportional to the value of the contract, prior to obtaining external
support. For simple and low price contracts for services (e.g. hiring computer
programmers to carry out specific tasks) whole life costing may well be excessive and
Department, in such situations, should develop Requests for Tender with clearly
defined technical specifications and requirements for contractors or external service
providers to perform specific tasks at the lowest cost or that are the most
economically advantageous.
Document1 23
For framework agreements, it should not be necessary to set out a detailed business
case for every individual contract to be drawn down under the agreement, as the
initial business case would have justified the decision to set up the framework
agreement and addressed the type of contracts it was envisaged to establish under the
framework. In all cases, the business case must be approved at the appropriate
management level before engaging external support.
In establishing the business case, it is good practice for the contracting authority to
consult with other public sector Department that have carried out similar projects
involving external support. The objective is to build on the success of these projects
and not to repeat problems.
Whole life costing assesses the total cost of an asset or service over its whole life: it
takes into account the initial purchase cost and additional related costs, (e.g. ongoing
maintenance and operational costs, disposal costs (if relevant), and other costs (be
they staffing, supervisory, health and safety, etc.) specific to the solution that the
contracting authority otherwise would have not incurred if it had not acquired the
asset or service. If whole life costing is not carried out it is unlikely that VFM can be
achieved.
Department/Division must decide the pricing model that will allow the award of a
contract on a basis that complies with public procurement policy and that will also
obtain VFM over the life of the project. This can be achieved by developing a pricing
model or cost breakdown structure that will evaluate the fixed (and variable, if any)
prices proposed by tenderers over the whole life of the project. In particular, a
tenderers cost proposal must be evaluated to see if it changes the contracting
authority’s costs, and what impact such changes would have on the whole life cost of
the project.
In ‘design and build’ or ‘advise and execute’ projects, it is often only when the design
or advice is presented that the future (i.e. staffing/operating) costs of a project become
clear (i.e. it may not be possible to estimate whole life costs accurately until the initial
phases of the project are completed).
Document1 24
review phase to reject a design and / or policy proposal or to terminate any subsequent
phase of the contract, because of future costs and / or negative policy implications.
For all projects with an estimated cost in excess of €30 million a cost benefit analysis
must be carried out. The cost benefit analysis must identify costs on as wide a basis as
possible, be maintained and reassessed throughout the project and be used to set out
targets and plans to achieve the identified benefits. It must be annexed to the business
case and lodged in the project file.
The Report of the Working Group on the Accountability of Secretaries General and
Accounting Officers (the Mullarkey Report) recommended, inter alia, that all
Government Departments and offices should introduce a formal risk management
system and should make risk management part of the business planning process. The
process of risk management involves a cycle of identifying risks, evaluating their
potential consequences and determining the most effective methods of responding to
them. This means reducing the chances of their occurrence and reducing their impact
if they do occur.
The senior management (i.e. Principal Officer level for projects with a cost estimate
less than €500,000; Assistant Secretary level for projects at or above this level; and
Accounting Officer level for all projects with a cost estimate equal to or in excess of
€30 million) review of the business case must, at a minimum, assess and approve the
business justification for the project on presentation of the full business case; the
decision to hire external support; and the procurement strategy proposed.
Senior management should also confirm that the project is well planned and will
achieve policy objectives of sufficient importance to the contracting authority relative
to the whole life costs, in terms of the resources, both financial and personnel, which
they are prepared to commit to the implementation of the project and thereafter; that
the business case is comprehensive, has been properly prepared and is justified; and,
that, on implementation, the project will achieve the contracting authority’s policy
objectives and VFM.
The approved business case must be lodged in the project file. As this Department is
operating under an Administrative Budget Agreement, the provisions of that
agreement in relation to delegated sanction for engaging consultants and other
external support must be followed. Even if the estimated cost is within the overall
Document1 25
level delegated to this Department, the Department of Finance / CMOD may wish to
view the business case and / or the Request for Tenders (RFT), e.g. if a purchase
within the delegated limit could significantly affect future spending decisions or could
impact on civil service numbers policy.
There may be occasions when this Department needs to engage external support at
short notice to deal with matters of public urgency. In these cases there may be no
time to prepare a business case. If this happens the project manager must ensure that
there is compliance with all key elements of these guidelines (and both national and
EU public procurement law, as appropriate); the reasons for the departure from
normal practice are recorded in the project file and that the decision to proceed
without a business case is approved and signed off at the appropriate level.
The decision to proceed without a full business case must be documented, approved at
the appropriate level and the decision recorded in the project file.
Project Organisation
Projects must not take place without clearly defined lines of authority, responsibility
and accountability and a means of ensuring they are observed in practice. The project
organisation (i.e. the Department’s intended management structure for the project and
the envisaged allocation of staff to the project) must be defined in the business case.
Typically, for all but the smallest projects, this will involve a steering committee
chaired at senior level to oversee the project, the appointment of a staff member as
project manager and the assignment of appropriate business, technical and user co-
ordinators. For all major ICT and capital projects within the public sector an
individual civil/public servant must be assigned as project manager with responsibility
for the project.
The project manager is responsible for managing the external support to achieve
project targets and for reporting progress to the project board and to the Management
Board. A checklist on the responsibilities of a project manager in relation to the
management of a contract is in the ‘Quigley Report – Guidelines (appendix B -
Managing Consultancy Contract (Checklist for Departments)’, available on the e-
Tenders web site under ‘General Procurement Guidance’.
In addition, as part of the delegated sanction arrangements for ICT Projects (i.e. the
regime established by circular 16/97) Departments and Offices are required to
maintain a progress report for all such projects. Copies of the circular 16/97 progress
reports must be retained in the project file. The template for such reports is available
from IT Control Section, CMOD, Department of Finance.
Re-Tendering
The RFT must state clearly that open ended contracts cannot be awarded and that, in
all cases there cannot be an extension of a contract for services without re-tendering,
if the cost of the extension is more than 50% of the original contract price or exceeds
€250,000 whichever is the lower. Where future phases of a project are envisaged,
Document1 26
RFT’s must make it clear that being awarded a contract for any particular phase does
not give to the contract holder any entitlement to be engaged for any other or
subsequent phase.
Reporting on Contracts
For all capital projects with a cost in excess of €30 million and for all ICT,
consultancy and other projects with a cost in excess of €5 million, the relevant must
furnish a separate progress report, on a quarterly basis, to the Departments
Management Board for departmental projects and then to the Minister. These reports
may be subject to inspection by the Department of Finance.
As part of the annual capital envelope this Department must furnish a report in
relation to capital projects with a cost in excess of €30 million in a format that shows,
for these projects, the outputs against contract timescales and budgets to the
Department of Finance and in the Annual Report on the Statement of Strategy.
This Department must furnish annually to the Department of Finance a report on the
ICT projects in our ICT strategy statement and must publish progress on peer reviews
of major ICT projects on a Department of Finance website.
Document1 27
Appendices/Templates
Appendix 1 - Thresholds
The main advertising thresholds with effect from 1 January 2010 to 31 December 2011 are as
follows:
Works
Contract Notice €4,845,000 Threshold applies to Government Departments and
Offices, Local and Regional Authorities and other public
bodies.
Contract Notice €193,000 Threshold applies to Local and Regional Authorities and
public bodies outside the Utilities sector.
Utilities
Works Contracts / Prior €4,845,000 For entities in Utilities sectors covered by GPA
Indicative Notice
Supplies and Services € 387,000 For entities in Utilities sectors covered by GPA
1
Thresholds are revised every two years. Full and up to date thresholds can be checked on the EU public procurement
website http://simap.eu.int .
Document1 28
Appendix 2 - Project File
a record of the meeting at which it was decided to engage external support and the
reasons justifying this decision;
the business case;
the cost benefit analysis (if performed);
all correspondence wit the Department of Finance
the contract notice;
all advertising related to the tender;
the Requests for Tender;
all clarifications sent to those who requested the tenders;
the report of the opening of the tenders;
the successful tender. (Unsuccessful tenders should be archived together with a copy of
the RFT, the contract notice and the evaluation report);
the evaluation report;
the acceptance by management of the evaluation team’s report
the acceptance letter to the successful tender informing of the result of the tender
competition;
the letters to the unsuccessful tenders;
the contract award notices;
the contract;
the project management plan (including the risk assessment);
the minutes of all project management meetings (including the project inception
meeting);
all orders to the contract holder for work-packages/services;
all requests/responses for project changes;
for framework agreements all correspondence, including orders, relating to individual
contracts/draw downs;
all requests for payment by the contract holder;
all requests for expenses, supporting documentation and vouched expense claims from the
contract holder;
all acceptance notes for deliverables and services;
all acceptance notes for expenses
all correspondence with contract holder, including emails;
all progress reports;
the reports of any mid-term or perm reviews;
the final report
the post-implementation review or review/reports by third parties.
Document1 29
Appendix 3 - Glossary of Terms
Call for Competition The means by which public bodies advertise their requirements –
published in the Official Journal of the European Communities
EU European Union
Irregular Tender A tender that fails to comply in all material respects with the
specification
Negotiated Procedure A purchasing procedure that involves negotiating with a small number
of companies (approx 3). It is widely used by utilities but can only be
used by the public sector in limited circumstances.
OJEU Official Journal of the European Union where all above threshold
advertisements are published.
Open Procedure This is a commonly used purchasing procedure whereby all those
companies who apply for tender documents will be allowed to tender.
Document1 30
RFT Request for Tender
Document1 31
Appendix 4 - Guide to etenders website
The Irish Government has established a common procurement portal www.etenders.gov.ie for
use by all public bodies or bodies in receipt of state funding. It is a one-stop-shop for public
bodies to publish contract opportunities and for the market to identify opportunities. It is a
free service for all users
The site can be used to issue National or European Notices. The options are to create:
A Site Notice - for National advertising – notices appear immediately on etenders only,
An OJEU Notice – for contracts subject to European rules – notices appear on etenders
and are sent automatically to the European Journal and published in approximately 3-5
days. (It is advisable to check when they have been published and to copy to file with
publication date and reference number). One can log on to OJEU website as follows:
ted.europa.eu
The Department of Transport is a registered buyer on etenders and it this Department’s policy
to utilise this portal to the fullest possible extent.
1. Registration
If you have not already done so go to www.etenders.gov.ie and click the register link on the
top menu and enter your details. Your registration will be checked and approved within a
short period and you will be granted full access to the site.
If you have already registered, go to www.etenders.gov.ie select the sign in link from the top
menu, and enter your username and password. If you have forgotten your password use the
‘Forgot your password’ link on the sign in page and it will be emailed to you. After signing in
you will be taken to the ‘Supplier Home Page’ and from there you can view and update your
registration details and check on tenders that you have previously registered an interest in.
One can search for notices published by various awarding authorities by selecting the
‘Notices Search’ from the top menu and entering your search criteria. By default all the
current notices will be selected and you can page through them by using the ‘video recorder’
type controls and the top of the list. To filter the number of tenders, select a category and/or
enter a keyword and click the search button.
4. Viewing a Notice
Click on the title of the tender to view the full notice and optionally register your interest in
the notice. When you register an interest you will be sent any additional documents when they
become available.
Document1 32
Document1 33
Document1 34
Appendix 5 - Summary Overview of Procedures and Timescales
Note: When deciding the appropriate process on should work on the basis of 10-15%
less than threshold to ensure appropriate coverage
Document1 35
Procedure Receipt of expressions Receipt of tenders
of interest
National [Recommended]
European [Mandatory]
Restricted - with PIN and using eTenders for 30 days 17-31 days
Notice
Document1 36
Template 1 - Certificate of Tender Received
37
Template 2 - Open Procedure Tender Evaluation
First Stage – Examine if tenderers meet the minimum standards specified in the tender documents/notice, in terms of technical and financial capacity and
expertise
Outcome of Assessment:
Companies A, C, E and G meet the minimum standard and are therefore eligible to have their tenders evaluated.
The remaining companies do not meet the minimum standard and are ruled out of further consideration (i.e. their tenders will not be
evaluated).
39
Template 3 - Score sheet for Evaluation of Tenders
Award Criteria Quality of Relevant Ultimate Cost Company access Proposed Timeframe for Total marks
proposal in knowledge, (inc expenses) to relevant methodology delivery awarded
addressing skills and international
requirements of expertise of information
project personnel
assigned to
project
Total Points 25 25 25 10 10 5 100
available
Company A 20 20 22 8 5 5 80
Company B 22 18 15 6 5 5 71
Company C 20 15 10 5 8 5 63
Outcome: - Company ‘A’ received the highest number of points and is recommended for the contract
41
Template 4 - Score Sheet for Evaluation of Tenders – (Multiplier Method)
Award Criteria Technical After Sales Accommodation Ultimate Cost Emissions Total Score
Characteristics Services Capacity
Multipliers UC Maximum Points x Lowest UC responsive valid tender = Tender ‘n’ score under ‘UC’
UC of tender ‘n’
42
Template 5 - Tender Evaluation – Checklist
43
Template 6 - Request for Tender (RFT) Letter
Dear Sir/Madam
You are invited to submit a tender for the above contract/competition in accordance
with the enclosed tender documents, which comprise the following:
Technical Specifications
Conditions of Contract
Schedule of requirements
Instructions to tenderers
Drawings & Tables (if appropriate)
Certificate of bona fide tender
Yours faithfully
__________________
<name>
<Division>
Department of Transport
44
Template 7 - Acknowledgement Slip
Dear Sir/Madam
We hereby acknowledge receipt of the tender documents for the above contract. We confirm
that we will/will not* submit a completed tender by the closing date.
*(Delete as appropriate)
Signed…………………………………..
N.B. This acknowledgement slip must be returned by Fax, within 7 days of the date of
issue of the tender documents.
45
Template 8 - Tender Documents – Checklist
Comments
Signed:………………………… Date………………………..
46
Template 9 - Sample RFT
for
Open Procedure
[Contracting Authority]
[Date]
This sample document is intended for general guidance. It is not definitive or exhaustive
on all the considerations that arise in preparing a Request for Tenders [RFT]. The
sample is based on an open tendering procedure under EU procurement rules but the
same principles should apply to a non-EU procedure. It follows a format and structure
commonly used and may be of assistance in assembling tender documentation.
Contents
1. Introduction
2. Specification of Requirements
3. Format of Tender
Generally sets out conditions relating to such matters as need for tax
compliance, freedom of information and data protection provisions, conflict of
interest, intellectual property, latest time for submission of tenders etc.
5. Appendices
47
1. Introduction
The Irish Government Public Sector Procurement Website ......... has been live since March
2001, and all public sector (Central Government, Health Sector, Local Government,
Education Sector, etc) procurement opportunities are published on the site.
The [contracting authority] now invites tenders for the management, maintenance and
continuing development of this website. The services to be provided are:
It is proposed to place a contract for a period of two years with an option for renewal for up to
a further two years.
Payment for services covered by this invitation to tender will be on foot of appropriate
invoices, which will be based on agreed deliverables. Invoicing arrangements will be agreed
with the successful service provider, following the award of contract. A contract entered into
on foot of this Request for Tender is subject to the Prompt Payments of Accounts Act.
Every effort has been made to ensure that this documentation contains all the necessary
information for completion of tenders. However, in the interests of equity, requests for
additional information, clarification on the content of this document and all other queries of
substance (other than in relation to purely factual or procedural matters) must be made in
writing or by email. Any additional information elicited will be made available to all potential
tenderers who have obtained a copy of this document via the etenders website or directly from
[contracting authority].
Any queries should be submitted by email or in writing only, not later than [local time] on
[day and date] addressed to:
Name : Address :
Fax : E-mail :
1.4 Timetable
48
2. Specification of Requirements
Potential service providers should be familiar with the ....... website and the facilities and
functionality currently available to users.
The Site is a built as a Lotus Notes Application and the data is stored in several Notes
Databases. Information on the technical specification of the site is set out in .?(Appendix ...
?).
The initial requirement is to ensure that the facilities and functionality currently available on
the site continue to be available, without any break in the availability of these services. The
following are the processes and functions available to users.
More details on these elements are included in points 2.1.1 to 2.1.3 below.
(a) All Public Procurement advertisements from the European Journal (OJEU) including
Contract, Prior Information and Contract Award Notices are published. Any associated
notices, which appear in the OJEU are also published.
(b) All additional public sector tender opportunities advertised in national and local
newspapers and other relevant publications (e.g., provincial newspapers) where public sector
tenders commonly appear are also replicated on the site.
(c) Tenders are also entered directly by Awarding Authority Users onto the site. At present
between 30- 40% of users are uploading their notices directly onto the site via the online
notice publication facility. The rest of the notices are being sourced as in a) and b) above.
Organisation of Content
Advertisements, notices and awards appear initially under the categories Works, Supplies
49
and Services. Sub categories used refer to type of service/supply (e.g., computers &
electronic, stationery & printing, etc). They are also categorised under Publication Date,
Competition Closing Date and Awarding Authority.
(b) Full responsibility for ongoing maintenance and support of the site will rest with the
selected service provider. ........................
(c) The successful tenderer should provide corrective maintenance on the server and the
application. ............
(d) The service provider must also continue to maintain a test environment for the
etenders site at..........
(b) The selected service provider will be expected to have a process in place to ensure
that the site is populated on an ongoing basis as defined at 2.1. Details of this process
should be included in the service provider’s proposals in reply to this RFT.
(c) While Awarding Authorities will continue to be able to upload documents to the site,
it will be the responsibility of the selected service provider to check and verify the
authenticity of the documents and to ensure that correct categorisation principles have
been applied.
(d) The successful service provider will be expected to meet with the [contracting
authority] on a regular basis, at a minimum on a quarterly basis, during the lifetime of
the contract. These meetings will take place in [Dublin ?].
(e) The successful tenderer will be facilitated with site familiarisation (in terms of
existing program code, etc.) and will be expected to participate in a handover process
with the current service provider.
50
2.5 Minor Additions / Changes required for Improved Usability:
a) .......................................
b) .........................
c) .......................................
The [contracting authority] intends that additional functionality would be added to the
existing etenders website. The ultimate objective is, in the long term, to transform the
etenders site into a National Tender Management Facility(see 1.2 above). Below is a brief
outline of some of the proposed enhancements. It should be noted that there is no
commitment on behalf of the [contracting authority] that any of these items will be
implemented. Requirements for other functionality may be identified by the [contracting
authority] and this will be addressed by way of Change Control.
Tenderers must confirm their ability to provide enhanced functionality, and must quote
separately for each of the enhancements listed below, stating any assumptions and/or
prerequisites.
Tenderers must state how they propose to implement the functionality below and must
state whether they are proposing bespoke development OR an off-the-shelf solution OR
an ASP type offering. The estimated development or lead-time for each function must be
indicated.
Arrangements for acceptance testing and piloting of any enhanced functionality, and
related arrangements for payment based upon successful completion of agreed
deliverables, will be agreed between the [contracting authority] and the successful
tenderer.
51
2.7.4 Notice Completion Facility or Wizard
There is a requirement to provide Awarding Authority users with a facility to enable them to
prepare, online, the complete range of standard OJEU notices i.e. PIN, Contract and Contract
Award notices. (Please see www.simap.eu.int/EN/pub/src/welcome.htm for format of OJEU
forms).
A further requirement is to maintain the facility in line with changes in policy and directives
set out by the [contracting authority] or EU in relation to procurement. Full details of the
arrangements for updating the facility i.e. revised thresholds or timeframes, should be
provided.
52
said services, including the measures in operation for ensuring that a quality service
will be delivered.
53
3. Format of Tender
Tenders must address all the requirements and must be in the format requested below.
Tenders not in this format will not be considered.
(a) Name, address, telephone number, e-mail address and fax number of tenderer.
(b) Name, address, telephone number and e-mail address of any third parties involved
in tender.
(c) Confirmation of acceptance by the tenderer and any third parties of the conditions
of tender described in Section 5 of the invitation to tender.
(d) Details of previous experience of staff being assigned to this task in implementing the
type of project specified at 2.
(e) Details of relevant reference sites [must be at least at least one] where similar work
has been carried out. ....................................
(f) An appropriate financial profile for the last three years must be provided including, in
the case of corporate entities, independently audited accounts. Where a tenderer is
trading for less than three years accounts for each year of trading must be provided.
3.2 Proposals
3.2.2 Such response to include a statement of the number of elapsed days (lead time)
required for the initial implementation of all additional services i.e. launch, pilot phase (if
applicable) and initial full commissioning of site.
3.3.1 Tenderers must confirm that the level, extent and nature of the maintenance and
support requirements including any associated warranties described in Section 2 of this
document will be fully met. Where this support would be provided by a third party, the
name, address and telephone number of such party must be disclosed.
3.4 Schedule of Costs
All costs must be quoted in euro (€), exclusive of VAT and the schedule must take the
following format:
3.4.1 Individual cost figures should be provided for each of the following
Cost of provision of service for site management and maintenance for 2 years
Cost of familiarisation period and handover from current service providers
Cost of redevelopment work required on existing site at 2.6 together with any
additional ongoing maintenance costs
The total cost of the tender
54
3.4.2 Tenderers should provide daily rates for the following:
Project Management
Business Analysis
Software Development
Training/documentation
These will be the maximum rates to be charged for any additional work, including change
control, which arises during the initial contract. The [contracting authority] reserves the
right to seek to negotiate lower rates for any such additional work.
3.4.3 Confirm that the tender holds good for 90 days after the closing date for receipt of
tenders.
3.4.4 Indicate the applicable rate of VAT in respect of each of the services being
proposed.
3.4.5 Give details of any other costs, taxes or duties, which may be incurred. Any
licensing costs associated with any part of the proposal should be clearly identified.
Proposals should clearly indicate any discounts to which the [contracting authority]
would be entitled, including public sector discounts, early payment discounts, forward
contract discounts and any other discounts.
3.5 Contract
A contract will be concluded with the tenderer whose tender is deemed to be the most
economically advantageous subject to agreement on conditions of contract. [The contract
will not be concluded / take effect until 14 days after unsuccessful tenderers have
been notified of the result of this tendering procedure 2].
2
This time delay in signing a contract is mandatory for contracts covered by EU procurement
Directives in order to observe a recent judgment of the European Court of Justice [Alcatel: Case
C-81/98]. The Court ruled that unsuccessful tenderers must be notified of the result of a tender
competition and, if aggrieved or feel rules have not been observed, given a reasonable
opportunity to request a review of the decision before a contract is put in place.
55
4 Examination and Evaluation of Tenders [for Open Procedure] 3
b) Stated ability of the tenderer to meet all the requirements specified in Section 2 of this
document;
c) Statement that none of the circumstances listed in Regulation 53 of S.I. 329 of 2006
apply to the tenderer (Regulation may be appended to RFT – Appendix A);
Only those tenders who satisfy conditions in relation to the above will be eligible for
inclusion in the award process.
The contract will be awarded to the most economically advantageous tender of those
meeting the specifications set out in Section 2, and not otherwise validly excluded, on the
basis of the following award criteria [scored from 200 marks weighted as indicated]:
Quality and technical merit of proposals for providing service detailed in Section 2 of
this RFT (70 marks)
The management and service structure proposed (30 marks)
Expertise and skills of assigned personnel in providing the type of services described
in Section 2 [including experience of at least one relevant reference site] (30 marks)
Time frame for delivery of service (20 marks)
Proposed cost of providing service [including ongoing site maintenance as detailed at
2.1-2.5 above, redevelopment work required on existing site at 2.6 above and cost of
providing the enhanced functionality at 2.7 above] (50 marks).
4.3 During the evaluation period clarification may be sought in writing from tenderers.
Responses to requests for clarification may not materially change any of the elements
of the tenders submitted. No unsolicited communications from tenderers will be
entertained during the evaluation period. A number of the most competitive tenderers
may be invited to make presentations on their proposals for the purpose of
elaboration, clarification and / or aiding mutual understanding. Invited tenderers must
3
In an Open Procedure all interested are invited to submit tenders. However, a contracting authority
may request information relating to technical and financial capacity, experience etc. and only evaluate
tenders from those who possess the minimum capacity required.
In a’ Restricted Procedure’ interested parties will have been invited to submit expressions of interest.
They will have been requested to provide details of professional, technical, economic, financial etc.
capacity and expertise. Only those that meet minimum requirements, i.e. those that the contracting
authority is satisfied has the capability and expertise to carry out its contract, will be supplied with the
full tender documents [RFT]and invited to submit tenders. [See Section 6.13 of the Competitive
Process Guidelines on this section of the website and Articles 45 to 50 of Directive2004/18/EC].
56
be in a position to make such a presentation around [date]. Any proposed
subcontractors may be required to participate in the presentation.
Tenders should be prepared in English or Irish and are subject to the following:
5. 1 This Request for Tender shall form part of the contract documents 4. The contract
will not be concluded / take effect until 14 days after unsuccessful tenderers have been
notified of the result of this tendering procedure [as per paragraph 3.5 and footnote 1].
5. 2 The [contracting authority] will use its best efforts to hold confidential any
information provided by tenderers subject to their obligation under law, including the
Freedom of Information Act which came into force on 21 April, 1998. Tenderers should
indicate, when tendering, what parts of their tenders are commercially sensitive and which
they consider should be kept confidential should an FOI request be received. The
[contracting authority] will consult with tenderers about any such sensitive information
before making a decision on any FOI request received. Similarly, the [contracting
authority] requires that all information provided pursuant to this invitation to tender will be
treated in strict confidence by tenderers.
5. 3 Tenderers should be aware that national legislation applies in other matters such as
Official Secrets, Data Protection and Health and Safety.
5. 4 Tenderers must have regard to statutory terms relating to minimum pay and to
legally binding industrial or sectoral agreements in preparing tenders.
Any registerable interest involving the tenderer and the [contracting authority], members of
the Government, members of the Oireachtas or their relatives must be fully disclosed in the
response to this RFT, or should be communicated to the [contracting authority] immediately
upon such information becoming known to the tenderer, in the event of this information only
coming to their notice after the submission of a bid and prior to the award of the contract.
The terms 'registerable interest' and 'relative' shall be interpreted as per section 2 of the Ethics
in Public Office Act, 1994.
5. 7 Before a contract is awarded the successful tenderer (and agent, where appropriate)
will be required to promptly produce a Tax Clearance Certificate, or in the case of a non-
resident tenderer, a statement from the Revenue Commissioners confirming suitability on
tax grounds. Non-residents should contact the Office of the Revenue Commissioners,
Revenue Residence Section, Government Offices, Nenagh, Co. Tipperary. In addition,
contractors must retain records of tax reference numbers for any subcontractors where
payments exceed €650 (incl. VAT).
Tenderers should note that the provisions of Department of Finance Circular 43/2006 apply
and the [contracting authority] may require sight of Tax Clearance Certificates for any
4
It is recommended that a draft contract document be issued with the tender documentation .
57
subcontractor where payments exceed €2,600. Forms are attainable from the following
address: Office of the Revenue Commissioners, Sarsfield House, Limerick. Where a Tax
Clearance Certificate expires within the course of the contract, the [contracting authority]
reserves the right to seek a renewed certificate. All payments under the contract will be
conditional on the contractor(s) being in possession of a valid certificate at all times.
(a) The successful tenderer shall be responsible for the delivery of all services provided for
within the contract on the basis of a fixed price agreement set at the beginning of the
contract. Prices quoted in the tender cannot be increased during the currency of the tender.
Similarly, terms and conditions cannot be altered.
(b)The [contracting authority] retains the right to withhold payment where a contractor has
failed to meet his/her contractual obligations in relation to the delivery of services to an
acceptable level of quality.
5. 9 The [contracting authority] will not be liable in respect of any costs incurred by
tenderers in the preparation of tenders or any associated work effort.
5. 10 Responses to this RFT will be evaluated in their own right. No recognition will be
given to information previously submitted.
5. 11 The [contracting authority] is not bound to accept the lowest or any tender
submitted.
5. 12 The [contracting authority] will have copyright ownership of any graphics used on
the proposed site.
5. 14 Three (3) copies of the tender in a sealed envelope, marked “Tender for ........”
and addressed to:
Name ...................
Address ...................
should be delivered to the above address not later than [local time] on [day and date].
58
Appendix A
Exclusion of certain persons from being considered for awards of public contracts
b) corruption, or
c) fraud, or
d) money laundering.
3. who has committed grave professional misconduct provable by means that the
authority can demonstrate, or
5. who has not fulfilled an obligation to pay a tax or levy imposed by or under a law
59
of the country or territory―
c) the person’s affairs are being administered by a court, or the person is the subject
of proceedings in which it is sought to have the person’s affairs so administered, or
f) the person is, in the opinion of the contracting authority concerned, in any
situation analogous to any of those mentioned in subparagraphs (a) to (e) under a
law of the State, another Member State or a third country relating to bankruptcy
or insolvency.
6. A contracting authority shall accept as sufficient evidence that a person is not liable to
be excluded under paragraph (1) or under subparagraph (a), (b), (d) or (e) of paragraph (4)―
b) although it issues documents of that kind, they do not cover the case in question,
60
the contracting authority concerned shall accept instead a declaration made by the
person on oath or, in the case of a Member State where there is no provision for
making a declaration on oath, a solemn declaration made by the person before a
person authorised for the purpose under a law of that Member State.
9. The following are authorised authorities for the purposes of paragraph (8):
61