1.1 Allow a sum for surety, insurance, workmen`s compensation L/S 1.0
etc as required by the general and special conditions for civil
engineering
1.3 Allow for provisional sum for sign Boards L/S 1.0
1.4 One water point will be made available on site. Allow for any
additional services not included in the site reticulation
1.5 Allow provisional sum for the alteration to existing service L/S 1.0
Total $16,523.48
1 Clearing
1.1 Clear the road areas of all bush and
small trees (girth less than 1m
measured 1m above ground)
including grubbing, stumps and
root system disposal. m2 16500 1.00 16,500.00
1.2 Removal of trees, girth exceeding
1m No rate only 75.00
2 Earthworks
2.1 Remove topsoil up to 300mm thick
from all road formation including all
grass and roots and spread within
1km radius of site, excludes drain
areas m2 16500 4.00 70,000.00
2.2 Cut to waste of unsuitable materials
or expansive sections m3 1800 6.00 12,800.00
2.3 Shaping of road formation by
cutting and filling and compacting to
93% Mod. AASHTO in 150mm m2 9000 2.50 25,000.00
layers.
2.6 Anthill excavation to waste including
treatment of affected areas. No.
2.7 Borrow to fill. Rate to include win from borrow, load ,
haul and dump. To be measured after
compaction m3 1700 28.00 47,600.00
3 SURFACING
Sweep base course and supply all materials and apply TP7 or MC30 as a
3.1 m2 8,800.00 1.80 15,840.00
prime at a rate of 0.8 litres/surface
Supply all materials and apply double seal spray and chip surfacing to all
3.2
road surfaces using the following - including testing:
3.4 Supply all materials and paint kerbing in alternating black and white paint m2
3.7 Supply and erect a stop sign at intersection no 2.00 250.00 1,000.00
Total $411,563.48
SUB TOTAL