Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
PILE CAP
Cross-sectional Area: (actual calculation)
(0.50m x 0.6m) + (1.00m x 0.2m) + (0.5m x 0.2m x 0.2m) = 0.52 sq.m.
Total volume:
0.52m² x 354.0 m = 184.08m³, say 185 m³
Materials:
Cement: Use 40kg. bag, class A (1:2:4)
185 cu. m. x 9.0 = 1665 bags
Sand: 185 cu. m. x 0.5 = 92.5 cu. m.
Gravel: 185 cu. m. x 1.0 = 185 cu. m.
Ties:
For 10mm diameter vertical bars:
2 x (364)
2 x (464)
364 mm
2 x 933
66
2 x 85
538
329
100
148
2 x 100
2 x (28) ------------- bending allowance
2 x (42) ------------- bending allowance
3557 mm, say 3.6 m
Using 7.5m bar,
1pc. 7.5m bar= 2pcs. 3.75m
@ 354.0m total length with ties 0.3m spaced O.C.,
354.0m/ 0.3m= 1180pcs. + 1= 1181pcs.
1181pcs/ 2 = 590.5pcs = 591pcs 7.5m, 12mm dia. Bar
Tie wires:
Cement:
392.15 cu.m x 7.5 = 2941.125, say 2942 bags
Sand:
392.15 cu.m x 0.5 = 196.07 cu.m., say 197 cu.m.
Gravel:
392.15 cu.m x 1.0 = 392.15 cu.m, say 393 cu.m.