Prepared By Engr.

:
WALEEDCOURSE
PMP PREPARATION ELBASYOUNI
Planning
BY PROCESS
®
& GROUPS
Project Control Engineer
Based On PMBOK Guide Sixth Edition
PMP®, PMI-RMP®, TOT®, MSc (Cand.)

Prepared By Engr. : PMI Member PMP PMI-RMP


June.2015 Sep.2016 Dec.2017

WALEED ELBASYOUNI
Planning & Project Control Engineer
PMP®, PMI-RMP®, TOT®, MSc (Cand.)
About Instructor
Engr. WALEED ELBASYOUNI, BSc, PMP, PMI-RMP, TOT
• Senior Project Control and Project Management Engineer With More Than 10 Years Experience In Construction

Prepared By Engr. :
Industry At Mega Projects In Egypt And Saudi Arabia.
• BSc. of Architectural Engineering, Cairo‐Egypt .

WALEED ELBASYOUNI
• Project Management Professional (PMP®) Certified By The Project Management Institute (PMI®),  USA.
• Strategic Planning Diploma from NSP, Arab Center for Strategic Planning Studies.

Planning & Project Control Engineer


• Risk Management Professional (PMI‐RMP®) Certified By (PMI®), USA,.
• MSc Researcher in Projects Management in Establishing Project Management Office (PMO).

PMP®, PMI-RMP®, TOT®, MSc (Cand.)


• Training of Trainers (TOT®) By American Institute for Applied Education (AIAE®), USA.
• Project Management, Project Control and Strategic Planning Instructor.
• Founder & CEO of Ana Memarey Magazine, Cairo ‐ Egypt, from 2010 to Present.
• Speaker volunteer involvement in Planning and Project Management Conference, from 2015 to Present.
• Member of the Training Board in Human Energy Academy, Malmo, Sweden.
• Member of the Training Board in Management Academy, Istanbul, turkey.
• Member in Project Management Institute PMI® From 2015 To Present .
• Member in Saudi Council Of Engineers From 2010 To Present .
@Waleed Elbasyouni
• Member in Egyptian Syndicate Of Engineers From 2007 To Present .
Prepared By Engr. :
INTROUDACTION
WALEED ELBASYOUNI
Planning & Project Control Engineer
PMP®, PMI-RMP®, TOT®, MSc (Cand.)
1.
Prepared By Engr. :
Course And Exam Requirements?

2. WALEED
What is the Best Manner Of Study in thisELBASYOUNI
Course?

3. Planning
Who Is The & Project Control Engineer
Target Audience?

4. PMP®,
Why We Need StudyPMI-RMP®, TOT®,
PMP® By Process Groups ? MSc (Cand.)
5. After We Completed This Course, What Will We Learn?

6. What`s New In PMBOK Guide Sixth Edition ?

7. Course Contents
Prepared By Engr. :
WALEED ELBASYOUNI
Planning & Project Control Engineer
PMP®, PMI-RMP®, TOT®, MSc (Cand.)
Course & Exam Requirements?
Course and Exam requirements?

• To be familiar with this Course all Students should be working in a Project environment organization.

Prepared By Engr. :
WALEED ELBASYOUNI
PMP Certification Eligibility Criteria

Planning & Project


Eligibility Requirement Control
Four‐Year Degree Engineer
Secondary Degree

PMP®, PMI-RMP®,
Years of Project 
Management Experience
TOT®,
3 Years (36 Months) MSc (Cand.)
5 Years (60 Months)

Hours Leading & 
4,500 Hours 7,500 Hours
Directing Projects

• Hard or soft copy of the "A Project Management Body of Knowledge (PMBOK® Guide, Sixth Edition)" would

make also a good reference to use throughout the course.


The Best Manner of Study in this Course
• This Course Based On PMBOK® Guide Sixth Edition authored by PMI®, 2017.

• This Course use the vertical way Method to study PMP® preparation Course, Presented by Process Groups.
Prepared By Engr. :
WALEED ELBASYOUNI
We will Follow the smart study way to gait a maximum benefits 

Planning & Project Control Engineer


from this course:‐
Listening well to each lecture in this course with high concentration.
PMP®, PMI-RMP®,
 Reading well the TOT®, MSc
same content from PMBOK (Cand.)
6 guide. th

 Record your Comments To Facilitate your review before your exam.

 Mack a practical application and Solving Questions at the end of Every


Sessions.

 To be different make your own success story as much as possible.


Prepared By Engr. :
WALEED ELBASYOUNI
Who is the
Planning & Project Control Engineer
Target Audience?
PMP®, PMI-RMP®, TOT®, MSc (Cand.)
Who is the target audience?

Anyone who wishes to learn about Project Management according to PMI® Methodology.

Prepared •
By Engr. :
Project Managers, Project Sponsors, Project Management Office (PMO) team, Business
owners, Engineers, Project management field Start-ups, Management Consultants.
WALEED
• Anyone who wishes ELBASYOUNI
to improve his management skills of high complexity projects, in

Planning & Project Control Engineer


order to improve the success ratio in Small and Mega projects.

• Anyone who wishes to shift his career to Project Management field, with Professional
PMP®, PMI-RMP®,
study. TOT®, MSc (Cand.)
• Fresh graduate Individuals who are willing to start a profession in the field of project
planning and management.

• Company directors seeking to increase the efficiency decision making in projects.

• Anyone wanting to gain knowledge in Project Management techniques.

• Anyone who wishes to obtain the PMP® certificate.


Prepared By Engr. :
Why PMP® By
WALEED ELBASYOUNI
Process
Planning & Project Groups?
Control Engineer
PMP®, PMI-RMP®, TOT®, MSc (Cand.)
Why we need Study PMP® by Process Groups ?

• Because it`s The real and logical sequence of any project.

Prepared

By Engr. :
To understand how to implement the project management
Knowledge with more reality.
WALEED • ELBASYOUNI
Because the PMP® Exam designed by process groups Domains

Planning & Project Control Engineer


and the exam results coming by P G`s not by Knowledge areas.

PMP®, PMI-RMP®, TOT®, MSc (Cand.)


Prepared By Engr. :
WALEED ELBASYOUNI
After we Completed this Course
Planning & Project Control Engineer
what will we Learn?
PMP®, PMI-RMP®, TOT®, MSc (Cand.)
After we completed this Course what will we Learn?

• Describe  and  understand  all  Project  Management  processes,  as  outlined  in  the  PMI®  PMBOK®  Guide 
6th Edition. Prepared By Engr. :
• WALEED
Gain  the  all  must  necessary  information  to ELBASYOUNI
prepare  for  the  Project 

Planning & Project Control Engineer


Management Professional (PMP®) Certification Exam.
• Describe  Project  Management  Principles  and  Techniques  and  how  they 
apply PMP®, PMI-RMP®,
to  the  day‐to‐day  TOT®,
in  the  real  and  logical  sequence  of  any MSc
project  (Cand.)
management of projects and operations.
• Understand  the  Eligibility  Requirements  and  the  nature  of  the  PMP® 
exam.
• Understand the Exam Strategies and Know where to Focus while Preparing 
for the Exam and how to collect some tricks on the exam.
Prepared By Engr. :
WALEED ELBASYOUNI
Planning & Project Control Engineer
What`s New
PMP®, PMI-RMP®, TOT®, MScin (Cand.)
PMBOK Guide Sixth Edition
What`s New in PMBOK Guide Sixth Edition

If you’re not familiar with the PMI, or the PMBOK:



Prepared By Engr. :
The PMBOK 6th Edition is the PMI’s primary standard document. It is accredited by the
American National Standards Institute (ANSI) and must be updated every 4 to 5 years.

• The Project Management WALEED ELBASYOUNI


Science is an Evolves knowledge, should be update

Planning & Project Control Engineer


continuously as much as possible.

PMP®, PMI-RMP®, TOT®, MSc (Cand.)


What`s New in PMBOK Guide Sixth Edition

1. New Methodology

Prepared By Engr. :
• Change Management  Methodology,  Terminologies  and  all  most    information 
Narrative  Transferred  from  waterfall  Management  to  agile  management 
WALEED
Methodology. ELBASYOUNI
Planning

& Project Control Engineer
From (systematic, linear, and traditional Method ) to (shortest time possible, more 
flexibility)
PMP®, PMI-RMP®, TOT®, MSc (Cand.)
What`s New in PMBOK Guide Sixth Edition

Waterfall

Prepared By Engr. :
It Is The More Traditional Project Management Methodology, 

WALEED ELBASYOUNI
In  Which  Every  Phase  Of  The  Project  Must  Be  Fully 

Completed  and  Signed  Off  Before  Moving  Forward  To  The 


Planning & Project Control Engineer
Next Stage (step to step).

PMP®, PMI-RMP®, TOT®, MSc (Cand.)


Agile

It  Is  Ongoing,  iterative and  more  flexibility  Based  On  Principles  Of  Interaction  And 

Collaboration  Among  Team  Members,  Where  Tasks  Are  Executed  Quickly  And  In  An 

Adaptive Manner, This Helps To Improve The Overall Output With Every Iteration.
What`s New in PMBOK Guide Sixth Edition

The New PMBOK 6th Called


Prepared By Engr.Informed
Research : Standard
WALEED ELBASYOUNI
Planning & Project Control Engineer
PMP®, PMI-RMP®, TOT®, MSc (Cand.)
What`s New in PMBOK Guide Sixth Edition

2. Information Narrative

Prepared By Engr. :
• Add 4 new sections in each Chapter (Knowledge area).
KEY CONCEPTS
• Focus on Strategic and Business Knowledge and it`s
WALEED
relation with Project Management . ELBASYOUNI

Planning & Project Control Engineer


PMP®, PMI-RMP®, CONSIDERATIONS FOR TOT®, New 
MSc (Cand.)TRENDS AND 
AGILE/ADAPTIVE ENVIRONMENTS Sections EMERGING PRACTICES

TAILORING CONSIDERATIONS
What`s New in PMBOK Guide Sixth Edition

3. Structure

Prepared By Engr. :
• Added New Chapter On THE ROLE OF THE PROJECT MANAGER

WALEED ELBASYOUNI
Including  The  PMI  Talen  Triangle  (Technical  Project  Management, 

Leadership, Strategic And Business Management).
Planning & Project Control Engineer

PMP®, PMI-RMP®, TOT®, MSc (Cand.)
Added New Appendix (APPENDIX X3) about AGILE PRACTICE GUIDE, it`s

describes  the  use  of  agile from  the  perspective  of  the  Project  Management 

Process Groups.

• Added,  Moved,  Eliminated,  and  Change  Name  on  some  of KNOWLEDGE  AREA 

AND PROCESS. 
What`s New in PMBOK Guide Sixth Edition

3. Structure

Prepared By Engr. :
Added, Moved, Eliminated, and Change Name on some of KNOWLEDGE AREA AND PROCESS. 

WALEED ELBASYOUNI
Planning & Project Control Engineer
PMP®, PMI-RMP®, TOT®, MSc (Cand.)
What`s New in PMBOK Guide Sixth Edition

3. Structure

Prepared By Engr. :
Added, Moved, Eliminated, and Change Name on some of KNOWLEDGE AREA AND PROCESS. 

WALEED ELBASYOUNI
Planning & Project Control Engineer
PMP®, PMI-RMP®, TOT®, MSc (Cand.)
• Close  Procurement  Process  has  been  removed  as  a  process  and 

moved to  Control Procurement and Close Project or Phase Process.

• Estimate  Activity  Resources moved  to  Project  Resource 

Management.
What`s New in PMBOK Guide Sixth Edition

3. Structure

Prepared By Engr. :
Added, Moved, Eliminated, and Change Name on some of KNOWLEDGE AREA AND PROCESS. 

WALEED ELBASYOUNI
Planning & Project Control Engineer
PMP®, PMI-RMP®, TOT®, MSc (Cand.)
What`s New in PMBOK Guide Sixth Edition

3. Structure

Prepared By Engr. :
Added, Moved, Eliminated, and Change Name on some of KNOWLEDGE AREA AND PROCESS. 

WALEED ELBASYOUNI
Planning & Project Control Engineer
PMP®, PMI-RMP®, TOT®, MSc (Cand.)
49
Processes
For More info. About PMBOK Changes follow
Appendix X1 Page 639 in PMBOK 6th Edition
Prepared By Engr. :
WALEED ELBASYOUNI
COURSE CONTENTS
Planning & Project Control Engineer
PMP®, PMI-RMP®,
To Cover 35 Hours PDUsTOT®,
Required toMSc (Cand.)
PMP Exam
Course Contents

PART 1

Prepared By Engr. :
• INTRODUCTION IN PROJECT MANAGEMENT 
Course Contents

WALEED ELBASYOUNI
PART 2
Planning & Project Control Engineer
• THE ROLE OF THE PROJECT MANAGER

PMP®, PMI-RMP®,
PART 3
TOT®, MSc (Cand.)
• KNOWLEDGE ARIA (10 KNOWLEDGE ARIAS)

PART 4
• CORE COURSE BY PROCESS GROUPS (5 PROCESS GROUPS)
Course Contents
1. INTRODUCTION IN PROJECT MANAGEMENT 
• Overview, Foundational Elements, Terminologies, Code Of Ethics And Professional Conduct. 
2.
3.
THE ROLE OF THE PROJECT MANAGER.
Prepared By Engr. :
EACH KNOWLEDGE ARIA (10 KNOWLEDGE ARIAS) 


WALEED ELBASYOUNI
Overview About All Processes.
Key Concepts


Planning
Trends And Emerging Practices
Tailoring Considerations
& Project Control Engineer
• PMP®, PMI-RMP®, TOT®, MSc (Cand.)
Considerations For Agile/Adaptive Environments
4. CORE COURSE, STUDY PMP®  PREPARATION BY PROCESS GROUPS.
• Overview About All Process Groups.
• Each Process Groups (5 Process Groups) 
• Definition, Key Benefits, Inputs, Outputs, Tools And Techniques
• Application On All Most PM Forms And Templates
• Solve All Most Practical Questions About Each Process Groups
• Focus On Each Process Key Words  
Prepared By Engr. :
Lecture 1
WALEED ELBASYOUNI
PROJECT MANAGEMENT FRAMEWORK 
Planning & Project Control Engineer
PMP®, PMI-RMP®, TOT®, MSc (Cand.)
Course Contents

KNOWLEDGE AREA 
Prepared By Engr. :
PM FRAMEWORK & ROLE 
OF THE PROJECT MANAGER 
OVERVIEW  

5 Lecture 1 2
WALEED ELBASYOUNI 5 Lecture
(10 KNOWLEDGE AREAS)

Planning & Project Control Engineer


PMP®, PMI-RMP®, TOT®, MSc (Cand.)

PROCESS GROUPS 
3 4 AGILE‐ EXAM STRATEGY‐
(5 PROCESS GROUPS) MOCK EXAM‐FINAL REVISION 
12 Lecture 4 Lecture
Course Availability
First 4 Lecture will be available in:
Prepared By Engr. :
WALEED ELBASYOUNI
Planning & Project Control Engineer
PMP®, PMI-RMP®, TOT®, MSc (Cand.)
All Course Contents
with 35 Hours PDUs Certificate
Required to PMP Exam
Lecture 1 Agenda
PROJECT MANAGEMENT FRAMEWORK

Prepared By Engr. :
1. OVERVIEW AND PURPOSE
WALEED ELBASYOUNI
Planning & Project Control Engineer
2. FOUNDATIONAL ELEMENTS

PMP®, PMI-RMP®, TOT®, MSc (Cand.)


TH
3. PMBOK 6 STRUCTURE

This info. It Will Cover PMBOK 6th Edition

From Page 1 To Page 25


Project Management Framework
Overview and Purpose
HISTORICAL BACKGROUND
• Project Management Is Not New. It Has Been In Use For Hundreds Of Years. 

• Prepared By Engr. :
Outcomes Of These Projects Were The Result Of Leaders And Managers Applying Project Management Practices, 

WALEED ELBASYOUNI
Principles, Processes, Tools, And Techniques To Their Work.

Planning & Project Control Engineer


PMP®, PMI-RMP®, TOT®, MSc (Cand.)

Pyramids of Giza‐ Egypt Taj Mahal ‐ India Great Wall ‐ China


Project Management Framework
Overview and Purpose
CODE OF ETHICS AND PROFESSIONAL CONDUCT

Prepared By Engr. :
Why PMI Publishes The Code Of Ethics and Professional Conduct?

• To Instill Confidence In The Project Management Profession. 
WALEED• ELBASYOUNI
To  Help  An  Individual  In  Making  Wise  Decisions,  Particularly 
Planning & Project Control Engineer
When Faced With Difficult Situations .

PMP®, PMI-RMP®,•
TOT®, MSc (Cand.)
The Code Of Ethics and Professional Conduct Affirms These Four 

Values As Its Foundation (Responsibility, Respect, Fairness, And 

Honesty).
Project Management Framework
FOUNDATIONAL ELEMENTS

Prepared By Engr. :
WALEED ELBASYOUNI
Planning & Project Control Engineer
WHAT IS THE PROJECT ? 
PMP®, PMI-RMP®, TOT®, MSc (Cand.)
Project Management Framework
FOUNDATIONAL ELEMENTS
WHAT IS THE PROJECT ? 
A Project is a Temporary Endeavor Undertaken To Create a Unique Product, Service, Or Result.
Prepared By Engr. :
WALEED ELBASYOUNI
Planning & Project Control Engineer
PMP®, PMI-RMP®, TOT®, MSc (Cand.)

Exploring for Oil in a Region Web Design (IT‐Projects) Constructing a Building Research Development


Project Management Framework
FOUNDATIONAL ELEMENTS

THE PROJECT DEFINITION ? 

01
1.Temporary

3.Projects Drive Change Prepared By Engr. : Indicates That a Project Has a Definite 


Beginning and End.

WALEED ELBASYOUNI
Projects  Drive  Change  In  Organizations  It`s  Moving 

04
An Organization From One State To Another State In 

Planning & Project Control Engineer


Order To Achieve A Specific Objective

PMP®, PMI-RMP®, TOT®, MSc (Cand.)


03
4. Business Value Creation
Projects Refers To The Benefit That The 
Results Of  A  Specific Project  Provide  To 
Its  Stakeholders.  The  Benefit  From 
2.Unique Projects May Be Tangible, Intangible, Or 

02
Because The Characteristics of The  Both.
Project Will Not Be Repeated.
Project Management Framework
FOUNDATIONAL ELEMENTS

THE PROJECT DEFINITION ? 

Prepared By Engr. :
3.Projects Drive Change
Projects Drive Change In Organizations It`s Moving 

WALEED ELBASYOUNI
An Organization From One State To Another State 

Planning & Project Control Engineer


In Order To Achieve a Specific Objective.

PMP®, PMI-RMP®, TOT®, MSc (Cand.)


Project Management Framework
FOUNDATIONAL ELEMENTS

THE PROJECT DEFINITION ? 
4. Business Value Creation
Prepared By Engr. :‫ﻣﻧﺎﻓﻊ ﻣﺎﺩﻳﺔ ﻭﻣﻧﺎﻓﻊ ﻣﻌﻧﻭﻳﺔ‬
The Benefit From Projects May Be Tangible, Intangible, Or Both.

01 WALEED ELBASYOUNI 02

Planning &
Examples of 
Tangible Elements
Project Control Engineer
Examples of 
Intangible Elements
PMP®, PMI-RMP®, TOT®, MSc
• Monetary assets (Cand.)
• Goodwill
• Stockholder equity • Brand recognition
• Utility • Public benefit
• Fixtures • Trademarks
• Tools • Strategic alignment
• Market share • Reputation
Project Management Framework
FOUNDATIONAL ELEMENTS

PROJECT INITIATION CONTEXT
‫ﺳﻳﺎﻕ ﺑﺩء ﺍﻟﻣﺷﺎﺭﻳﻊ‬
Prepared
• Organizational  Leaders  Initiate  Projects  in  Response 
to Factors Acting Upon Their Organizations. 
By Engr. :
• WALEED
There  are  Four  Fundamental  Categories  for  These ELBASYOUNI
Factors.
Planning & Project Control Engineer
PMP®, PMI-RMP®, TOT®, MSc (Cand.)
Project Management Framework
FOUNDATIONAL ELEMENTS

FACTORS THAT LEAD TO THE CREATION OF A PROJECT New 
technology

Prepared By Engr. :
Environmental  Competitive 
These  Factors  Ultimately  Should  Link  to  the  Strategic  considerations forces

Objectives of  The  Organization  and  the  Business  Value  of 


Each Project. WALEED ELBASYOUNI Social need

Examples of 
Political 
changes

Planning & Project Control Engineer Factors that 

PMP®, PMI-RMP®, TOT®, MSc (Cand.)


Lead to the 
Strategic & 
business need
Market 
demand

Creation of a 
Business 
Project
Economic 
process 
changes
improvements

Legal  Customer 
requirement request
Stakeholder 
demands
Project Management Framework
FOUNDATIONAL ELEMENTS

Prepared By Engr. :
WHAT IS A DIFFERENCE AND SIMILARITIES BETWEEN 
WALEED ELBASYOUNI
PROJECT & OPERATION?
Planning & Project Control Engineer
PMP®, PMI-RMP®, TOT®, MSc (Cand.)
Project Management Framework
FOUNDATIONAL ELEMENTS

WHAT IS A DIFFERENCE AND SIMILARITIES BETWEEN PROJECT & OPERATION?

Prepared By Engr. :
Differences
WALEED ELBASYOUNI


Planning & Project Control Engineer
Project is  Temporary and Unique. 
Operation is On‐going and Repetitive. 
PMP®, PMI-RMP®, TOT®, MSc (Cand.)
Similarities

• Both of them Planned, executed and controlled.
• Both of them Need and Performed By Man Power.
Project Management Framework
FOUNDATIONAL ELEMENTS

Prepared By Engr. :
WHAT IS PROJECT MANAGEMENT?
WALEED ELBASYOUNI
Planning & Project Control Engineer
PMP®, PMI-RMP®, TOT®, MSc (Cand.)

WHAT IS THE IMPORTANCE OF PROJECT 
MANAGEMENT ?
Project Management Framework
FOUNDATIONAL ELEMENTS

WHAT IS PROJECT MANAGEMENT?

Prepared By Engr. :
• Project Management is the Application of Knowledge, Skills, Tools, and Techniques

WALEED ELBASYOUNI
to Project Activities to Meet the Project Requirements. 

Planning & Project Control Engineer



PMP®, PMI-RMP®, TOT®, MSc (Cand.)
Project Management is Accomplished Through The Appropriate 

Application  and  Integration Of  The  Project  Management 

Processes Identified For The Project. 

• Project Management Enables Organizations To Execute Projects 

Effectively and Efficiently.


Project Management Framework
FOUNDATIONAL ELEMENTS

Prepared By Engr. :
WALEED ELBASYOUNI
Planning & Project Control Engineer
WHAT IS THE IMPORTANCE OF 
PMP®, PMI-RMP®, TOT®, MSc (Cand.)
PROJECT MANAGEMENT ?
Project Management Framework
FOUNDATIONAL ELEMENTS
THE IMPORTANCE OF PROJECT MANAGEMENT

Effective
Prepared By Engr. :
Poorly
Project Management
WALEED ELBASYOUNI Project Management

Planning & Project Control Engineer


PMP®, PMI-RMP®,
Effective  Project  Management  Helps  Individuals, 
Groups, and Public and Private Organizations To:
TOT®, MSc (Cand.)
Poorly  managed  projects  of  project  management 
may result in:
• Meet business objectives • Missed deadlines
• Increase chances of success • Poor quality  and Rework
• Resolve problems and issues • Loss of reputation for the organization
• Manage constraints • Unsatisfied stakeholders
• Manage change in a better manner. • Failure in achieving the objectives
Project Management Framework
FOUNDATIONAL ELEMENTS

Prepared By Engr. :
WALEED ELBASYOUNI
The Relationship Between 
Planning & Project
PROJECT, PROGRAM, PORTFOLIO,  Control Engineer
PMP®, PMI-RMP®,
AND OPERATIONS MANAGEMENT TOT®, MSc (Cand.)
Project Management Framework
FOUNDATIONAL ELEMENTS
RELATIONSHIP OF PROJECT, PROGRAM, PORTFOLIO, AND OPERATIONS MANAGEMENT

Prepared By Engr. : Be  Managed  In  Three  Separate 


A  Project  May 

WALEED ELBASYOUNI
Scenarios: 
• As  a  Stand‐alone Project  (Outside  Of  A  Portfolio 

Planning & Project Control Engineer


Or Program).

PMP®, PMI-RMP®, TOT®, MSc (Cand.)


• Within a Program
• Within a Portfolio.
Project Management Framework
FOUNDATIONAL ELEMENTS
DEFINATION OF PROJECT, PROGRAM, PORTFOLIO.

Prepared By Engr. :
• Projects: a temporary endeavor undertaken to create 
a unique product, service, or result.


WALEED ELBASYOUNI
Planning & Project Control Engineer
Programs: is  a  group  of  related  projects,  subsidiary 
programs, and program activities that are managed in 

PMP®, PMI-RMP®,
a  coordinated  manner  to  obtain  benefits  not 
available from managing them individually.
TOT®, MSc (Cand.)
• Portfolios:  is  a  collection  of  projects,  programs, 
subsidiary  portfolios,  and  operations  managed  as  a 
group to achieve strategic objectives.
Project Management Framework
FOUNDATIONAL ELEMENTS
PROJECT, PROGRAM, PORTFOLIO AND OPERATIONS MANAGEMENT WITH ORGANIZATIONAL STRATEGY

Prepared By Engr. : The  Project,  Program,    Portfolio  and  Operations  

WALEED ELBASYOUNI
Components are Grouped Together in Order To Facilitate 

The Effective Governance and Management of The Work 
Planning & Project Control Engineer
That  Helps  To  Achieve  Organizational  Strategies  and 

PMP®, PMI-RMP®, TOT®,


Priorities. MSc (Cand.)
Project Management Framework
FOUNDATIONAL ELEMENTS
PROGRAM MANAGEMENT CHARACTERISTIC
• Aligning with the organizational or strategic direction that affects 

Prepared By Engr. :
program and project goals and objectives.

WALEED ELBASYOUNI
• Managing program risks that may impact multiple projects in the 
program.

Planning & Project Control


• Resolving  constraints  and Engineer
conflicts  that  affect  multiple  projects 

PMP®, PMI-RMP®, TOT®, MSc (Cand.)


within the program.

• Resolving  issues  between  component  projects  and  the  program 


level.
• Managing change requests within a shared governance framework.
• Allocating budgets across multiple projects within the program.
Project Management Framework
FOUNDATIONAL ELEMENTS
PORTFOLIO MANAGEMENT CHARACTERISTIC

Prepared By Engr.‫ﺇﺩﺍﺭﺓ‬
‫ﺍﻟﻣﺣﺎﻓــــﻅ‬ :
WALEED• Guide Organizational Investment Decisions.
ELBASYOUNI
Planning & Project Control Engineer
• Select The Optimal Mix Of Programs and Projects To Meet Strategic 

PMP®, PMI-RMP®, TOT®, MSc (Cand.)


Objectives.
• Provide Decision‐making Transparency.
• Prioritize Team and Physical Resource Allocation.
• Increase  The  Likelihood  Of  Realizing  The  Desired  Return  on 
Investment.
• Centralize  The  Management Of  The  Aggregate  Risk  Profile  Of  All 
Components.
Project Management Framework
FOUNDATIONAL ELEMENTS
DEFINATION OF OPERATIONS MANAGEMENT.

Prepared By Engr. :
Operations Management: is an area that is outside the scope of formal project management as described in this guide, is 
concerned with the ongoing production of goods and/or services.

WALEED ELBASYOUNI
OPERATIONS AND PROJECT MANAGEMENT:

Planning & Project Control Engineer


Projects can intersect with operations in:
• When  developing  a  new  product,  upgrading  a 
PMP®, PMI-RMP®, TOT®,product. MSc (Cand.)
• improving  operations  or  the  product 
development process.
• At the end of the product life cycle
• At each closeout phase
Project Management Framework
FOUNDATIONAL ELEMENTS
PROJECT, PROGRAM, PORTFOLIO. Comparison

Prepared By Engr. :
WALEED ELBASYOUNI
Planning & Project Control Engineer
PMP®, PMI-RMP®, TOT®, MSc (Cand.)

PMBOK 6th Edition - Page 13


Project Management Framework
FOUNDATIONAL ELEMENTS

Prepared By Engr. :
WALEED ELBASYOUNI
Planning & Project Control Engineer
PROJECT 
PMP®, PMI-RMP®, TOT®, MSc (Cand.)
AND DEVELOPMENT LIFE CYCLES
Project Management Framework
FOUNDATIONAL ELEMENTS

PROJECT LIFE CYCLES 4. Ending the Project
Closing Processes PHASE 4

Prepared By Engr. :
3. Carrying Out the Work

WALEED ELBASYOUNI
Executing Processes PHASE 3

2. Organizing and Preparing
Planning & Project ControlMonitoring And Controlling Processes
Planning Processes PHASE 2 Engineer
Throughout the project Timeline we handling 

PMP®, PMI-RMP®, TOT®, MSc (Cand.) All Time  


1. Starting The Project
Initiating Processes
PHASE 1

PROJECT AND DEVELOPMENT LIFE CYCLES
Project Management Framework
FOUNDATIONAL ELEMENTS
PROJECT AND DEVELOPMENT LIFE CYCLES
The Project Life Cycle Needs To Be Flexible Enough, This Flexibility May Be Accomplished By:
Prepared By Engr. :

WALEED ELBASYOUNI
Identifying The Process Or Processes Needed To Be Performed 

Planning & Project Control Engineer


In Each Phase.

• PMP®,
Performing  PMI-RMP®,
The  Process  TOT®,
Or  Processes  Identified  In  The  MSc (Cand.)
Appropriate Phase.
Project Management Framework
FOUNDATIONAL ELEMENTS
PROJECT AND DEVELOPMENT LIFE CYCLES

Prepared By Engr. : At Beginning of Project

WALEED ELBASYOUNI
• Costs and the Team is a little

Planning & Project Control Engineer


• Risk and the impact of stakeholders is To High.

PMP®, PMI-RMP®, TOT®, MSc (Cand.)


• Costs of Change is a Low .
Project Management Framework
PMBOK 6th STRUCTURE

Prepared By Engr. :
WALEED ELBASYOUNI
Planning & Project Control Engineer
PMP®, PMI-RMP®, TOT®, MSc (Cand.)
Project Management Framework
FOUNDATIONAL ELEMENTS
PROJECT LIFE CYCLES TYEPS 

Prepared By Engr. :
1. In a Predictive Life cycle:
• The  Project  Scope,  Time,  And  Cost  Are  Determined  In  The  Early 
Phases Of The Life Cycle.  WALEED ELBASYOUNI

Planning & Project Control Engineer


• Any  Changes  To  The  Scope  Are  Carefully  Managed.  Predictive  Life 
Cycles May Also Be Referred To As Waterfall Life Cycles.

PMP®, PMI-RMP®, TOT®, MSc (Cand.)


2. In An Iterative Life Cycle:
• The Project Scope Is Generally Determined Early In The Project Life Cycle, 
But Time And Cost Estimates Are Routinely Modified As The Project Team’s 
Understanding Of The Product Increases. 
• Iterations  Develop  The  Product  Through  a  Series  Of  Repeated  Cycles, 
While Increments Successively Add To The Functionality Of The Product.
Project Management Framework
FOUNDATIONAL ELEMENTS
PROJECT LIFE CYCLES TYEPS 

3. In An Incremental Life Cycle:
Prepared By Engr. :
WALEED ELBASYOUNI
• The  Deliverable  Is  Produced  Through  A  Series  Of  Iterations  That 
Successively Add Functionality Within A Predetermined Time Frame. 
• Planning & Project Control Engineer
The Deliverable Contains The Necessary And Sufficient Capability To 

PMP®, PMI-RMP®, TOT®, MSc (Cand.)


Be Considered Complete Only After The Final Iteration.

4. Adaptive life cycles are agile, iterative, or incremental:

• The  detailed  scope  is  defined  and  approved  before  the  start  of  an 
iteration. 
• Adaptive life cycles are also referred to as agile or change‐driven life 
cycles. See Appendix X3.
Project Management Framework
FOUNDATIONAL ELEMENTS
PROJECT LIFE CYCLES TYEPS 

5. A Hybrid Life Cycle:
Prepared By Engr. :
WALEED ELBASYOUNI
• Is A Combination Of A Predictive And An Adaptive Life Cycle. 
Planning & Project Control
• Those Elements Of The Project That Are Well Known Or Have Fixed 
Engineer
PMP®,
Requirements  Follow  A PMI-RMP®,
Predictive  Development  Life TOT®,
Cycle,  And  MSc (Cand.)
Those  Elements  That  Are  Still  Evolving  Follow  An  Adaptive 

Development Life Cycle.
Project Management Framework
PMBOK 6th STRUCTURE

Prepared By Engr. :
WALEED ELBASYOUNI
Planning & Project Control Engineer
PMBOK 6 STRUCTURE
TH
PMP®, PMI-RMP®, TOT®, MSc (Cand.)
Project Management Framework
PMBOK 6th STRUCTURE

Prepared By No.
Page Engr.25 :
WALEED• ELBASYOUNI
Project Management Knowledge Areas ( 10 Knowledge Areas)

Planning & •Project Control Engineer


Project Management Process Groups ( 5 Process Groups With

PMP®, PMI-RMP®, TOT®, MSc (Cand.)


49 Process )

( 10 Knowledge Areas)
(5 Process Groups )
Project Management Framework
PMBOK 6th STRUCTURE

Each Process From 49 Process have :

Prepared By Engr. :
WALEED ELBASYOUNI Outputs
• Outputs 1
Planning & Project Control Engineer •• Outputs 2
Outputs 3
PMP®, PMI-RMP®, TOT®, MSc (Cand.)• Outputs 4
Inputs
• Input 1
• Input 2
• Input 3
• Input 4 Tools & Techniques
Project Management Framework
PMBOK 6th STRUCTURE

Do You Implement All 49 Process In Your Project ? Do You Have any Categorization?

• Prepared By Engr. :
The Number Of Process Iterations and Interactions Between Processes Varies Based 

WALEED ELBASYOUNI
on the Needs of the Project.


Planning & Project Control Engineer
Processes Generally Fall Into One Of Three Categories.

PMP®, PMI-RMP®, TOT®, MSc (Cand.)


Process Categories

1. Processes Used Once Or At Predefined Points In The 
Project. 
The Processes Develop Project Charter And Close Project Or Phase
Project Management Framework
PMBOK 6th STRUCTURE

Do You Implement All 49 Process In Your Project ? Do You Have any Categorization?

• Prepared By Engr. :
The Number Of Process Iterations and Interactions Between Processes Varies Based 

WALEED ELBASYOUNI
on the Needs of the Project.


Planning & Project Control Engineer
Processes Generally Fall Into One Of Three Categories.

PMP®, PMI-RMP®, TOT®, MSc (Cand.)


Process Categories

2. Processes That Are Performed Periodically As Needed. 
The Process Acquire Resources Is Performed As Resources Are Needed.
Project Management Framework
PMBOK 6th STRUCTURE

Do You Implement All 49 Process In Your Project ? Do You Have any Categorization?

• Prepared By Engr. :
The Number Of Process Iterations and Interactions Between Processes Varies Based 

WALEED ELBASYOUNI
on the Needs of the Project.


Planning & Project Control Engineer
Processes Generally Fall Into One Of Three Categories.

PMP®, PMI-RMP®, TOT®, MSc (Cand.)


Process Categories

3. Processes That Are Performed Continuously Throughout 
The Project. 
The Process Define Activities May Occur Throughout The Project Life Cycle, Many 
Of The Monitoring And Control Processes Are Ongoing From The Start Of The 
Project
Project Management Framework
Summary

• Prepared By Engr. :
Project Management Historical Background


WALEED
Code Of Ethics and Professional Conduct
ELBASYOUNI
Planning & Project Control Engineer
What is The Project ? 

• Project Definition and Characteristic? 

• PMP®, PMI-RMP®,
What is a Difference and Similarities Between  TOT®, MSc (Cand.)
Project & Operation?

• What is Project Management?

• What Is The Importance of Project Management ?

• The Relationship Between  Project, Program, Portfolio, and Operations Management

• Project and Development Life Cycles and Project Life Cycles Types 

• PMBOK 6th Structure


Prepared By Engr. :
Lecture 2
WALEED ELBASYOUNI
PROJECT MANAGEMENT FRAMEWORK 
Planning & Project Control Engineer
PMP®, PMI-RMP®, TOT®, MSc (Cand.)
Lecture 2 Agenda
PROJECT MANAGEMENT FRAMEWORK

Prepared By Engr. :
WALEED ELBASYOUNI
1. Project Management Data and Information Flow

2. Tailoring
Planning & Project Control Engineer
3. Project Management Business Documents

PMP®,4.PMI-RMP®, TOT®, MSc (Cand.)


The Environment In Which Projects Operate

This info. It Will Cover PMBOK 6th Edition

From Page 26 To Page 41


Prepared By Engr. :
WALEED ELBASYOUNI
Planning & Project Control Engineer
PROJECT MANAGEMENT 
PMP®, PMI-RMP®, TOT®, MSc (Cand.)
DATA & INFORMATION FLOW
Project Management Framework
Project Management Data & Information Flow

Through Project Life Cycle 3
Prepared By 2 Engr. :Work Performance Reports
1 WALEED ELBASYOUNI
Work Performance Information
Work Performance Data
Planning
Aggregation
& Project
Transfer Control Engineer
Analysis
PMP®, PMI-RMP®, TOT®, MSc (Cand.) Overall
Executing  Project Control
Processes Controlling
Processes
Project Management Framework
Project Management Data & Information Flow

Prepared By Engr. :
WALEED ELBASYOUNI
Planning & Project Control Engineer
PMP®, PMI-RMP®, TOT®, MSc (Cand.)

This info. In PMBOK 6th Edition

Page 27
Prepared By Engr. :
WALEED ELBASYOUNI
Planning & Project Control Engineer
PMP®, PMI-RMP®, TOT®, MSc (Cand.)
TAILORING
‫ﺍﻟﺗﺧـﺻﻳــﺹ‬
Project Management Framework
Tailoring

Tailoring Project Management To The Project

Prepared

By Engr. :
Selection Project  Management  Processes,  Inputs,  Tools,  Techniques,  Outputs, 

WALEED ELBASYOUNI
and Life Cycle Phases Should Be Selected To Manage a Project. This Selection 

Planning & Project Control Engineer


Activity Is Known As Tailoring Project Management To The Project. 

PMP®, PMI-RMP®, TOT®, MSc (Cand.)


The  Project  Manager  Collaborates With  The  Project  Team,  Sponsor
and Organizational Management In The Tailoring Process. 

‫ﻳﺟ ﺏ ﻋﻠ ﻰ ﻣ ﺩﻳﺭ ﺍﻟﻣﺷ ﺭﻭﻉ ﺍﻥ ﻳﺗﻌ ﺎﻭﻥ ﺑﺩﺭﺟ ﺔ ﻛﺑﻳ ﺭﺓ ﻣ ﻊ ﻓﺭﻳ ﻖ ﺍﻟﻣﺷ ﺭﻭﻉ ﻭﺍﻟﺟﻬ ﻪ‬
.‫ﺍﻟﺭﺍﻋﻳﺔ ﻟﻪ ﻭﺍﻻﺩﺍﺭﺓ ﺍﻟﺗﻧﻅﻳﻣﻳﺔ ﻟﻠﻣﻧﻅﻣﺔ ﻓﻰ ﻋﻣﻠﻳﺔ ﺍﻟﺗﺧﺻﻳﺹ ﻭﺗﺣﺩﻳﺩﻫﺎ ﺑﻌﻧﺎﻳﺔ ﺷﺩﻳﺩﺓ‬
Project Management Framework
Tailoring

Why Tailoring is Necessary for Each Project ?

Prepared By Engr. :
Because Each Project Is Unique, So Not Every Process, Tool, Technique, Input, 

WALEED ELBASYOUNI
Or Output Identified In The PMBOK® Guide Is Required On Every Project. 

• Planning & Project Control Engineer


Tailoring Should Address The Constraints Of Scope, Schedule, Cost, Resources, 

PMP®,
Quality,  and  Risk  and PMI-RMP®,
Make  Balance Between  The TOT®,
Importance  Of MSc
Each  (Cand.)
Constraint Is Different For Each Project.

• The  Project  Manager  Tailors  the  Approach  for  Managing  These  Constraints  Based  on  the  Project  Environment, 

Organizational Culture, Stakeholder Needs, and other Variables.
Prepared By Engr. :
WALEED ELBASYOUNI
PROJECT MANAGEMENT
Planning & Project Control Engineer
PMP®, PMI-RMP®, TOT®, MSc (Cand.)
BUSINESS DOCUMENTS
Project Management Framework
Project Management Business Documents

Prepared By• Engr.


The  Project  :Manager  Needs  To  Ensure  That  The 

WALEED ELBASYOUNIProject Management Approach Captures The Intent 

Planning & Project Control Engineer


Of Business Documents. 
PMP®, PMI-RMP®, TOT®, MSc (Cand.)
• These  Documents  Are  Defined  In  4  Documents  Are 

Interdependent  and  Iteratively  Developed  and 

Maintained Throughout The Project Life Cycle.
Project Management Framework
Project Management Business Documents

01
Project Business Documents Project 
Prepared By Engr. : Business Case

WALEED ELBASYOUNI
Planning 04
& Project Control Engineer
Project Charter 
PMP®, PMI-RMP®, TOT®, MSc Project  (Cand.)
03 Management Plan

Project
Benefits Management Plan 02
Project Management Framework
Project Management Business Documents

Interrelationship of Needs Assessment and Critical

Prepared By Engr. :
Business/Project Documents

WALEED ELBASYOUNI
Pre‐Project Work (Before Initiating)

Planning & Project Control Engineer


(Needs Assessment – Business Case – Benefits Management Plan

PMP®, PMI-RMP®, TOT®, MSc (Cand.)


Starting the Project (Initiating)

Project Charter

Organizing and Preparing (Planning)

Project Management Plan
Project Management Framework
Project Management Business Documents

1
Project Business Documents
Prepared
PROJECT BUSINESS CASE By Engr. :
WALEED ELBASYOUNI

Planning & Project Control Engineer
A  Documented  Economic  Feasibility  Study Used  To 

PMP®, PMI-RMP®, TOT®, MSc (Cand.)


Select  The  Objectives  And  Reasons  For  Project 

Initiation.

• It  Helps  Measure  The  Project  Success  at  The  End  Of 

The Project Vs The Project Objectives.
Project Management Framework
Project Management Business Documents

1 Project Business Documents

Prepared BySITUATION ANALYSIS
PROJECT BUSINESS CASE Engr. :
WALEED ELBASYOUNI • Identification Of Organizational Strategies, Goals, 

Planning & Project Control


BUSINESS NEEDS Engineer
And Objectives.

PMP®,
Precedes  The PMI-RMP®, TOT®, MSc (Cand.)
• Identification Of Root Cause(s) Of The Problem 
• Often  Business  Case  To 
• Identification Of Known Risks
Understanding  Business  Goals,  Objectives, 
• Identification Of Critical Success Factors
Issues,  and  Opportunities  and  Recommending 
Proposals to Address Them. • Identification Of Decision Criteria
Project Management Framework
Project Management Business Documents

2 Prepared
Project Business Documents
PROJECT BENEFITS MANAGEMENT PLAN
By Engr. :
WALEED ELBASYOUNI
Planning & Project Control Engineer

PMP®, PMI-RMP®, TOT®, MSc (Cand.)
Is The Document That Describes How and When the Benefits of 

The  Project  Will  Be  Delivered,  and  Describes  The  Mechanisms 

That Should Be In Place To Measure Those Benefits.
Project Management Framework
Project Management Business Documents

2
Project Business Documents

Prepared By Engr. :
PROJECT BENEFITS MANAGEMENT PLAN

• WALEED ELBASYOUNI
Target Benefits

• Planning
Strategic Alignment& Project Control Engineer

PMP®,

PMI-RMP®, TOT®, MSc (Cand.)
Timeframe For Realizing Benefits

• Benefits Owner

• Metrics

• Assumptions

• Risks
Project Management Framework
Project Management Business Documents

Project Business Documents
Prepared
3 By Engr. :
PROJECT CHARTER
WALEED ELBASYOUNI
Planning & Project
• Control Engineer
One of Most Important Document of any Project 

PMP®, PMI-RMP®,
• TOT®,
Defined  as  a  Document MSc (Cand.)
Issued  By  The  Project 

Sponsor That Formally Authorizes The Existence of a 

Project.

• Provides The Project Manager With The Authority .
Project Management Framework
Project Management Business Documents

Project Business Documents

4 Prepared By Engr.
PROJECT MANAGEMENT PLAN :
WALEED ELBASYOUNI
• Planning & Project Control Engineer
Defined as The Document That Describes How The 

PMP®, PMI-RMP®, TOT®, MSc (Cand.)


Project Will Be Executed, Monitored, and Controlled.

HOW TO MANAGE
PROJECT 
Prepared By Engr. :
SUCCESS MEASURES
WALEED ELBASYOUNI
Planning & Project Control Engineer
PMP®, PMI-RMP®, TOT®, MSc (Cand.)
Project Management Framework
Project Success Measures

Challenges in Project Management 
Prepared By Engr. :
WALEED ELBASYOUNI
Planning & Project Control Engineer
PMP®, PMI-RMP®, TOT®, MSc One  Of  The (Cand.)
Most  Common  Challenges  in 

Project  Management  is  Determining 

Whether or Not a Project is Successful.
Project Management Framework
Project Success Measures

We Have Three Questions That The Project Manager And Key Stakeholders Should 
Answer:
Prepared By Engr. :
WALEED ELBASYOUNI
Planning & Project Control Engineer
PMP®, PMI-RMP®, TOT®, MSc (Cand.)
Project Management Framework
Project Success Measures

Project Success Objectives May Include but are not Limited to:

Prepared By Engr. :
• Completing The Project Benefits Management Plan
• Meeting The Financial Measures Documented In The Business Case.

WALEED ELBASYOUNI
• Net Present Value (NPV)

Planning & Project Control Engineer


• Return On Investment (ROI)
• Internal Rate Of Return (IRR)
•PMP®, PMI-RMP®, TOT®, MSc (Cand.)
Payback Period (PBP)
• Benefit‐cost Ratio (BCR)
• Meeting Business Case Nonfinancial Objectives
• Meeting Organizational Strategy, Goals, And Objectives
• Achieving Stakeholder Satisfaction
• Integration Of Deliverables Into The Organization’s Operating Environment
Prepared By Engr. :
WALEED ELBASYOUNI
Planning & Project Control Engineer
PMP®, PMI-RMP®, TOT®, MSc (Cand.)

THE PROJECTS ENVIRONMENT
Project Management Framework
The Projects Environment

Project Influences
Prepared By Engr. : Project 
WALEED ELBASYOUNI
Projects exist and operate in environments that may have an 
influence on them, These influences can have a Positive or 
Influences

Planning & Project Control Engineer


negative impact on the project. 

1 PMP®, EEF PMI-RMP®, TOT®, MSc (Cand.)


EEFs  originate  from  the  environment  outside  of 
the project and often outside of the enterprise
EEF OPA

2 OPA
OPAs are internal to the organization.
Project Management Framework
The Projects Environment

Prepared
EEFs and OPAs 
By Engr. :
WALEED ELBASYOUNI
• Are Considered As Inputs To Many Project Management Processes, 
Planning & Project Control Engineer
Specifically For Most Planning Processes.

PMP®, PMI-RMP®, TOT®,


• These  Factors  MSc
May  Enhance  (Cand.)
Or  Constrain  Project  Management 

Options. 

• In  Addition,  These  Factors  May  Have  A  Positive  Or  Negative 

Influence On The Outcome.
Project Management Framework
The Projects Environment

Prepared By Engr. :
WALEED ELBASYOUNI
Planning & Project Control Engineer
PMP®, PMI-RMP®, TOT®, MSc (Cand.)
Project Management Framework
The Projects Environment

1 EEF
Prepared By
ENTERPRISE ENVIRONMENTAL FACTORS Engr. :
 EEFs Internal To The Organization
WALEED ELBASYOUNI • Organizational Culture, Structure, And Governance

Planning & Project Control
Not Under The Control Of The Project Team, That 
Engineer
• Geographic Distribution Of Facilities And Resources

PMP®, PMI-RMP®, TOT®, MSc (Cand.)


Influence, Constrain, Or Direct The Project. 
• Infrastructure
• These  Conditions  Can  Be  Internal  And  /  Or 
• Information Technology Software
External To The Organization.
• Resource Availability

• Employee Capability
Project Management Framework
The Projects Environment

1 EEF
Prepared By
ENTERPRISE ENVIRONMENTAL FACTORS Engr. :
 EEFs EXTERNAL TO THE ORGANIZATION
WALEED ELBASYOUNI • Marketplace conditions

Planning & Project Control
Not Under The Control Of The Project Team, That 
Engineer
• Social and cultural influences and issues

PMP®, PMI-RMP®, TOT®, MSc (Cand.)


Influence, Constrain, Or Direct The Project. 
• Legal restrictions
• These  Conditions  Can  Be  Internal  And  /  Or 
• Commercial databases
External To The Organization.
• Academic research

• Physical environmental elements
Project Management Framework
The Projects Environment

2 OPA
Prepared By
ORGANIZATIONAL PROCESS ASSETS Engr. :
 Processes, Policies, and Procedures

WALEED ELBASYOUNI • Guidelines And Criteria For Processes Tailoring



Planning & Project Control
(OPAs)  Are  The  Plans,  Processes,  Policies, 
Engineer
• Specific Organizational Standards Such as Policies

PMP®, PMI-RMP®, TOT®, MSc (Cand.)


Procedures,  and  Knowledge  Bases  Specific  To  and 
• Project Life Cycles, and Methods and Procedures
Used By The Performing Organization. 
• Templates, Report Formats and Project Documents
• They May Be Grouped Into Two Categories.
• Change Control Procedures

• Issue and Defect Management Procedures

• Project Closure Guidelines or Requirements
Project Management Framework
The Projects Environment

2 OPA
Prepared By• Engr.
ORGANIZATIONAL PROCESS ASSETS
 Organizational Knowledge Repositories
:
WALEED ELBASYOUNI
Configuration  Management  (Software  And 

Hardware  Organization  Standards,  Policies, 



Planning & Project Control
(OPAs)  Are  The  Plans,  Processes,  Policies, 
Engineer
Procedures, And Any Project Documents

PMP®, PMI-RMP®, TOT®, MSc (Cand.)


Procedures,  and  Knowledge  Bases  Specific  To  and 
• Financial Data Base (Costs, Budgets)
Used By The Performing Organization. 
• Historical Information And Lessons Learned
• They May Be Grouped Into Two Categories.
• Issue And Defect Management Data

• Measurement Data On Processes

• Project Files From Previous Projects
Project Management Framework
Summary

• Prepared By Engr. :
Project Management  Data & Information Flow


WALEED
Tailoring Project Management To The Project
ELBASYOUNI
Planning & Project Control Engineer
Project Management  Business Documents

• Project Business Case

• PMP®, PMI-RMP®, TOT®, MSc (Cand.)


Project Benefits Management Plan

• Project Charter 

• Project Management Plan

• Project Success Measures

• The Projects Environment

• Enterprise Environmental Factors  ‐ Organizational Process Assets
Prepared By Engr. :
Lecture 3
WALEED ELBASYOUNI
PROJECT MANAGEMENT FRAMEWORK 
Planning & Project Control Engineer
PMP®, PMI-RMP®, TOT®, MSc (Cand.)
Lecture 3 Agenda
PROJECT MANAGEMENT FRAMEWORK

Prepared By Engr. :
1. ORGANIZATIONAL SYSTEMS
WALEED ELBASYOUNI
2. PROJECT MANAGEMENT OFFICE
Planning & Project Control Engineer
PMP®, PMI-RMP®, TOT®, MSc (Cand.)
3. PROJECT CONSTRAINTS

4. PROJECT STAKEHOLDERS

This info. It Will Cover PMBOK 6th Edition

From Page 42 To Page 50


Prepared By Engr. :
ORGANIZATIONAL SYSTEMS
WALEED ELBASYOUNI
Planning & Project Control Engineer
PMP®, PMI-RMP®, TOT®, MSc (Cand.)
Project Management Framework
Organizational Systems

Project Manager Needs To Understand his Responsibility 
Prepared By Engr. :
WALEED ELBASYOUNI
The  Project  Manager  Needs  to  Understand  Where  Responsibility, 

Planning & Project Control Engineer


Accountability, And Authority Reside Within The Organization to Help him  

PMP®, PMI-RMP®, TOT®, MSc (Cand.)


to  be  Effectively Use  His  Or  Her  Power,  Influence,  Competence, 

Leadership,  and  Political  Capabilities  To  Successfully  Complete  The 

Project.

‫ﻋﻠ ﻲ ﻣ ﺩﻳﺭ ﺍﻟﻣﺷ ﺭﻭﻉ ﺍﻥ ﻳ ﺗﻔﻬﻡ ﺣ ﺩﻭﺩ ﻭﺍﺟﺑﺎﺗ ﻪ ﻭﺻ ﻼﺣﻳﺎﺗﻪ ﺟﻳ ﺩﺍ ﻟﻳﺻ ﺑﺢ ﺍﻛﺛ ﺭ ﺗ ﺎﺛﻳﺭﺍ‬

.‫ﻭﺗﻛﻭﻥ ﻟﻪ ﺍﻟﻘﺩﺭﻩ ﻋﻠﻰ ﺍﺳﺗﺧﺩﺍﻡ ﻗﻭﺗﻪ ﻭﺗﺎﺛﻳﺭﻩ ﻓﻰ ﺍﻛﻣﺎﻝ ﻋﻣﻠﻳﺔ ﻧﺟﺎﺡ ﺍﻟﻣﺷﺭﻭﻉ‬
Project Management Framework
Organizational Systems

Organizational Governance Frameworks ‫ﺍﻟﺣﻭﻛﻣﺔ ﻫﻲ ﺍﻹﻁﺎﺭ ﺍﻟﺫﻱ ﺗﻣﺎﺭﺱ ﺩﺍﺧﻠﻪ ﺍﻟﺳﻠﻁﺔ ﺩﺍﺧﻝ ﺍﻟﻣﺅﺳﺳﺎﺕ‬


Prepared By Engr. :
Governance  Is  The  Framework  Within  Which  Authority  Is  Exercised  In 

WALEED ELBASYOUNI
Organizations. This Framework Includes But Is Not Limited To:

Planning & Project Control Engineer


PMP®,
Rules
PMI-RMP®,
Policies
TOT®,
Procedures
MSc (Cand.)

Processes Systems Relationships


Project Management Framework
Organizational Systems

ORGANIZATIONAL STRUCTURE TYPES

Prepared
What is the Factors In Organization Structure Selection ?

By Engr. :
WALEED ELBASYOUNI
Degree of alignment with organizational objectives

• Specialization

• Planning & Project


Span of control, efficiency, and effectiveness Control
‫ﺍﻟﻛﻔﺎءﺓ ﻭﻓﻌﺎﻟﻳﺗﻬﺎ‬ ‫ﻧﻁﺎﻕ‬ Engineer


PMP®,
Delegation capabilities

Responsibility
PMI-RMP®, TOT®, MSc (Cand.)
• Efficiency of performance

• Cost considerations

• Clear communication

• locations
Project Management Framework
Organizational Systems
ORGANIZATIONAL STRUCTURE TYPES
1. Organic or Simple
Prepared By Engr. :
2. Functional (centralized)

WALEED 3.ELBASYOUNI
Multi‐divisional

Planning & Project Control


4. Matrix – strong

5. Matrix – weak
Engineer
PMP®, PMI-RMP®, TOT®, MSc (Cand.)
6. Matrix – balanced

7. Project‐oriented

8. Virtual

9. Hybrid 

10. PMO
Page 47
Project Management Framework
Organizational Systems

ORGANIZATIONAL STRUCTURE TYPES

Prepared By Engr. :
Organizational Structures on Projects can classify by some Factors

WALEED
Project Manager’s Authority ELBASYOUNI
Resource Availability

Planning & Project Control Engineer


PMP®, PMI-RMP®, TOT®, MSc
Project Manager’s Role
(Cand.)
Who Manages the Project Budget?

Work Groups Arranged by Project
Management Administrative Staff
Project Management Framework
Organizational Systems

ORGANIZATIONAL STRUCTURE TYPES

Prepared By Engr. :
Organic or Simple

WALEED ELBASYOUNI
Planning & Project Control Engineer
PMP®, PMI-RMP®, TOT®, MSc (Cand.)

Functional(centralized)
Project Management Framework
Organizational Systems

ORGANIZATIONAL STRUCTURE TYPES

Multi‐Divisional Prepared By Engr. :


WALEED ELBASYOUNI
Planning & Project Control Engineer
PMP®, PMI-RMP®, TOT®, MSc (Cand.)
Project Management Framework
Organizational Systems
ORGANIZATIONAL STRUCTURE TYPES
Matrix
Prepared By Engr. :
WALEED ELBASYOUNI
Planning & Project Control Engineer
PMP®, PMI-RMP®, TOT®, MSc (Cand.)
Project Management Framework
Organizational Systems
ORGANIZATIONAL STRUCTURE TYPES
Project – Oriented, Virtual, Hybrid and PMO
Prepared By Engr. :
WALEED ELBASYOUNI
Planning & Project Control Engineer
PMP®, PMI-RMP®, TOT®, MSc (Cand.)
Prepared By Engr. :
WALEED ELBASYOUNI
Planning & Project Control Engineer
PROJECT MANAGEMENT 
PMP®, PMI-RMP®, TOT®, MSc (Cand.)
OFFICE
Project Management Framework
Project Management Office

Project Management Office (PMO) Types 
01
• Prepared By Engr. :
A  Project  Management  Office  (PMO)  Is  an 
Supportive
WALEED ELBASYOUNI
Organizational  Structure  That  Standardizes  The 

Planning & Project Control 02 Engineer


Project‐related  Governance  Processes  And  Facilitates 

PMP®, PMI-RMP®, TOT®, MSc (Cand.)


The Sharing Of Resources, Methodologies, Tools, And 
Controlling
Techniques.

• There  Are  Several  Types  Of  PMOs  In  Organizations, 


03
Each  Type  Varies  In  The  Degree  Of  Control  And 
Directive
Influence It Has On Projects Within The Organization
Project Management Framework
Project Management Office

Project Management Office (PMO) Types 
Supportive. 
Prepared By Engr. :
• Provide  A  Consultative  Role  To  Projects  By  Supplying  Templates,  Best  Practices, 
Training, Access To Information, And Lessons Learned From Other Projects.
WALEED ELBASYOUNI
• The Degree Of Control Provided By The PMO Is Low.

PlanningControlling. 
& Project Control Engineer
PMP®, PMI-RMP®, TOT®, ‐ Use  Of MSc (Cand.)
• Provide Support And Require Compliance Through Various Means (Conformance 
To  Governance  Frameworks  Specific  Templates,  Forms,  Methodologies 
And Tools)
• The Degree Of Control Provided By The PMO Is Moderate. 

Directive. 
• Take Control Of The Projects By Directly Managing The Projects. Project 
Managers Are Assigned By And Report To The PMO. 
• The Degree Of Control Provided By The PMO Is High.
Project Management Framework
Project Management Office

Project Management Office (PMO) a Primary Function and Authority

Prepared By Engr. :
PMO Authority 
A PMO may have the authority to act as an integral stakeholder and a key decision 

WALEED
maker  throughout  the  life  ELBASYOUNI
of  each  project  in  order  to  keep  it  aligned  with  the 

Planning & Project Control Engineer


business objectives.

PMO Primary Function 
PMP®, PMI-RMP®, TOT®, MSc (Cand.)
• Managing shared resources across all projects

• Identifying  and  developing  project  management  methodology,  best 


practices, and standards

• Coaching and training

• shared documentation (organizational process assets)

• Coordinating communication across projects
Prepared By Engr. :
WALEED ELBASYOUNIProject
Planning & Project Control Engineer
PMP®, PMI-RMP®, TOT®, MSc (Cand.)
Constraint
Project Management Framework
Project Constraint

Customer Satisfaction

Prepared By Engr. :
WALEED ELBASYOUNI
Planning & Project Control Engineer
PMP®, PMI-RMP®, TOT®, MSc
Resources Risk
(Cand.)
Prepared By Engr. :
WALEED ELBASYOUNI
Planning & Project Control Engineer
PMP®, PMI-RMP®, TOT®, MSc (Cand.)
Project

STAKEHOLDERS
Project Management Framework
Project Stakeholders

A  Stakeholder  Is  An  Individual,  Group,  Or  Organization  That  May 

Prepared By Engr. :
Affect, Be Affected By, Or Perceive Itself To Be Affected By A Decision, 
Activity,  Or  Outcome  Of  A  Project,  May  Be  Internal  Or  External  May 
WALEED
Have A Positive Or Negative Impact On The Project .  ELBASYOUNI
Planning & Project Control Engineer
PMP®, PMI-RMP®, TOT®, MSc (Cand.)
Project Management Framework
Project Stakeholders

Prepared By Engr. :
WALEED ELBASYOUNI
Internal Stakeholders
• Sponsor
Planning
• Resource Manager
& Project Control Engineer
External Stakeholders
• Customers
PMP®, PMI-RMP®, TOT®,
• Project Management Office  MSc (Cand.)
• End users
(PMO) • Suppliers
• Portfolio Manager   • Shareholders
• Program Manager • Regulatory bodies
• Project Managers Of Other  • Competitors
Projects Team Members
Project Management Framework
Summary

• ORGANIZATIONAL SYSTEMS Prepared By Engr. :


WALEED ELBASYOUNI
– Organizational Governance Frameworks

Planning & Project Control Engineer


– What is the Factors In Organization Structure Selection ?

PMP®, PMI-RMP®, TOT®, MSc (Cand.)


– ORGANIZATIONAL STRUCTURE TYPES

– Organizational Structures on Projects can classification Factors

• PROJECT MANAGEMENT OFFICE

• Project Management Office (PMO) a Primary Function and Authority

• Project  Constraint

• Project Stakeholders ( Internal – External ) 
Thank You
Prepared By Engr. :
‫ﻙ‬WALEEDُ َ ‫ﺭﻙ َﻭﺃﺗ‬
‫ﻭﺏ ﺇﻟ ْﻳ‬ ْ ELBASYOUNI
َ ‫ﺳﺗ ْﻐ ِﻔ‬ ‫ﺃﻥ ﻻ ﺇﻟﻪ ﺇﻻ ﺃ ْﻧﺕ ﺃ‬ َ ‫ﺳ ْﺑﺣﺎﻧَﻙ ﺍﻟﻠﱠ ُﻬ ّﻡ ﻭﺑ َﺣ ْﻣ‬
ْ ‫ﺩﻙ ﺃﺷْﻬ ُﺩ‬
Planning & Project Control Engineer
PMP®, PMI-RMP®, TOT®, MSc (Cand.)
‫ﻻﺗﻧﺳﻲ ﺍﻹﺷﺗﺭﺍﻙ ﻓﻰ ﺍﻟﻘﻧﺎﺓ ﻟﻳﺻﻠﻙ ﻛﻝ ﺟﺩﻳﺩ‬

If You Need Any Further Comments Or Help Feel Free To Contact With Me On