a)
I.

II. Slack for activity :


A:0
B : 15 - 10 = 5
C:8–8=0
D : 10 – 10 = 0
E : 19 – 14 = 5
F : 15 – 15 = 0
G : 15 – 11 = 4
H : 19 -19 = 0
I : 21 -21 = 0

III. CP = A-C-D-F-H-I
IV. 21

b) Advantages
 Simple
AIMAN AMRI BIN MOKMIN
2016239048

 Good visual communication to others


 Task durations can be compared easily
 Good for scheduling resources

Disadvantages

 Dependencies are more difficult to visualise


 Minor changes in data can cause major changes in the chart
AIMAN AMRI BIN MOKMIN
2016239048

QUESTION 2

a) Resource levelling involves attempting to even out varying demands on


resources by using slack (delaying noncritical activities) to manage resource
utilization when resources are adequate over the life of the project.
Resource loading is the act of using the resources available such as the
equipments and workers in the tasks.

ID RES DUR ES LF SL 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
A 1 4 0 5 1 1 1 1 1
B 2 5 0 5 0 2 2 2 2 2
C 2 4 4 10 1 X 2 2 2 2
D 1 5 5 10 0 1 1 1 1 1
E 2 3 5 10 -2 X X X X 2 2 2
F 2 2 10 12 -2 X X 2 2
RESOURCE SCHEDULED
RESOURCES AVAILABLE 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3

New schedule :
AIMAN AMRI BIN MOKMIN
2016239048
AIMAN AMRI BIN MOKMIN
2016239048

QUESTION 3

a) 4 common reasons for crashing a project are


i. The project adaptability
ii. The unforeseen delays
iii. The incentive contracts
iv. Imposed deadlines

b) Total cost = $730

At 15 time unit
Indirect = $90
Direct = $730
Total = $90 + 730 = 820

At 14 time unit
Indirect = $70
Direct = $730 + $10 = $740
Total = $740 + $70 = 810

At 13 time unit
Indirect = $50
Direct = $740 + $20 = $760
Total = $760 + $50 = $810

At 12 time unit
Indirect = $40
Direct = $760 + $200 = $960
Total = $1000

At 11 time unit
Indirect = $30
Direct = $960 + $30 = $990
AIMAN AMRI BIN MOKMIN
2016239048

Total = $1020

The optimum cost time schedule is 12 time unit with the total cost of $1000.