Sei sulla pagina 1di 8

Section 8: Engineering Services Outline Development Control Plan

Outline Development Control Plan

8.0 Engineering Services At a future stage when the OPD site is redeveloped there would be the approx. 3.5 MVA of which approx. 1.1MVA is supported by the Hospital’s
opportunity in extending the service tunnel through the basement area CHP plant located in the Energy Centre.
providing an underground services route to all major areas of the Hospital
8.1. Engineering Services Distribution Routes From the load assessment, it is estimated that the total revised maximum
8.1.2 Electrical Services demand based on the new developments within the ODCP is in the region of
8.1.1 Mechanical Services 14.5MVA. This figure includes 25% spare capacity for future expansion. With
the support of the existing on site 1MW CHP plant, it will require a 13.5MVA
electrical supply delivered from the ESB network. The indicative electrical
In general, the route of the new electrical engineering system distribution
The proposal for the Mechanical Engineering Services Distribution is to load profile is as follows:
would be designed to follow the major site wide development dictated
provide an infrastructure on the site that not only meets the requirements within the ODCP. This will encompass the following systems:
of the Outline Development Control Plan but also allows flexibility for the
future Year Present Additional Load Total Actual Electrical
Maximum due to New Revised Load on site ( inc 1
- 2 No. electrical medium voltage ring mains
A base infrastructure shall be provided for all main services that can be Demand Developments Electrical MW supported by
extended to meet the changing requirements of the Hospital and Health required ( kVA ) Demand the CHP Plant )
- duct and pit system for voice and data cable infrastructure
Care needs without disruption to the normal operation of the site from ESB from ESB
(kVA )
- duct and pit system for electrical specialist systems including
Various options have been considered within the development control plan ( kVA ) (kVA )
security system, fire alarm system and cable television, etc
for the distribution of the primary mechanical services
2006 2500 - - 3600
It is not intended to utilise the existing underground walkway services duct
These options include;
for new cable distribution as there is not sufficient space to accommodate
2011 - 1600 4100 5200
all new electrical cables while the existing services are still in place.
x A complete underground tunnel system around the site linking the
Energy Centre to each building 2016 - 2800 6900 8000
x An above ground service corridor linking the Energy Centre to each 8.2 Expansion Capabilities 2021 - 4000 10900 12000
building
2026 - 2500 13400 14500
It is considered however that the existing service tunnel and service spine in 8.2.1 Mechanical
the Main hospital Building provides a suitable ‘backbone’ for the future Beyond - >13400 >14500
distribution of the mechanical services All major items of primary plant and service mains shall be sized to cater 2026
for the final scheme requirements of the Outline Development Control Plan
This is considered to provide the most flexible cost effective solution albeit plant may be installed on a phased basis to suit the work stages

The existing services tunnel running between the Energy Centre and the All primary equipment shall be designed with 25% spare capacity for future Based on the above figures, the existing incoming electrical supply and MV
main building is to be reused as the primary service route for all mechanical expansion electrical infrastructure is not capable to handle the new electrical
services with the exception of Water and Gas which is to be routed within demand. As a result, it is recommended that a new supply and electrical MV
the ground around the perimeter of the site All plant rooms and service routes within all new buildings shall be provided infrastructure be provided to cope with the substantial increase in the
with space for future expansion electrical demand and future growth. To provide an equivalent level of
From the Tunnel the services shall rise through the vertical builders work resilience of the incoming supplies, ESB has been requested to provide 2 no
duct to roof level to enter the horizontal service spine linking the phase 1 Where feasible pipe work systems shall be provided with valved and capped 15MVA supply to the site. ESB has agreed to undertake a Network studies
plant rooms branches in suitable locations to allow extension of the system for future based on the above indicative increased electrical load profile over the next
development without disrupting operation 15-25 years. However, no response has been received from ESB to-date.

8.2.2 Electrical It should also be noted that the existing position of a number of sub stations
A new services link is to be provided from the Services Spine through the will have an impact on the space planning of the new developments within
Phase 1H buildings to the new development sites to the eastern side of the the ODCP. They will need to be relocated temporarily, wherever required.
Hospital Site Electrical Supply
The car park sub station H1 will be reconnected to one of the new MV ring
It is understood that the current capacity of the incoming MV supply cable mains.
Temporary and permanent branches shall be provided from this primary
services distribution route to connect to the various existing and new from the Marrowbow Lane sub station ( and the on-site electrical
buildings infrastructure ) is 6MVA, but the current capacity of the secondary supply
cable is unknown. The agreed maximum import capacity from ESB is Telecommunication
Generally in new buildings plant rooms will be located at Basement level currently 3.7MVA. From the load profiles, it is noted that the loads across
with local distribution through designated routes within the car park areas the year is reasonably level due to cooling demands in Summer ( Sample site It is understood that although the current telephone exchange system can
load 18th April midday = 3.6MVA peak ). The highest maximum demand is provide 2200 extensions in total, the capacity of the present telephone
cable network is virtually up to its limit. There is no spare capacity
Page 1
March 2008 Page 129
Feb 2007 Volume 1 – “Section Name” (example: Executive Summary)
Anshen+Allen Team
Section 8: Engineering Services Outline Development Control Plan
Outline Development Control Plan

available in the existing cables for any new demands. If any new buildings This is specifically relevant in the areas of Energy Conservation and It is understood that the normal operation of the Hospital must not be
require telephone facilities, then new telephone cables will need to be Sustainability disrupted during the construction/demolition phases within the ODCP.
installed from the main distribution frame ( MDF ) in Phase 1C. Therefore, the engineering proposal/solution for the system
All future design and installation should be undertaken to provide a flexible upgrade/replacement must take into account this requirement. All existing
It is also understood that the Hospital has planned to install a complete new engineering solution which would accommodate change electrical engineering services will be maintained while the works are in
telephone system in the near future. The new system should take into progress.
account the demand of the new developments and future growth within the
ODCP. 8.3.2 Electrical Electrical Supply

There is a strategy to integrate the existing telecommunication network It is proposed that the existing and new electrical infrastructure support the
into the data network to form a VoIP to enhance the service and capacity of Electrical Supply
entire Hospital site in parallel at an early stage. The existing infrastructure,
the telecommunication system. The programme of the proposal is together with all existing 3 no ESB supplies will then be removed when they
approximately 2 years. are no longer required at a later date.
All new sub stations will be strategically located on site to serve the revised
It is noted that under the proposal for the IT rationalisation, the existing electrical load centres. The new sub station will generally consist of an MV
PABX room might potentially be relocated subject to the confirmation from switchboard, transformer and LV switchboard as existing. This will facilitate Telecommunication
the IT Specialist. It is considered that there is no consequential effect on full availability and flexibility of the MV or LV supplies in connecting future
the ODCP provided that the new duct and pit system is to be installed at an adjacent buildings into the electrical infrastructure. There is no major impact of the existing telecommunication services as all
early stage. new cables will emanate from the PABX system in the Phase 1C building to
each new building via a new duct and pit system. The redundant
Telecommunication and Data Communication underground cables will be removed as required.
Data Communication

The layout of the new duct and pit system for both telecommunication and Data Communication
Fibre cables are generally contained in accessible ducts, but no up-to-date data services will be designed to give a full flexibility for future wiring.
records of the cable routes or details of spare capacity are available. It is proposed that a duplicate data server be installed in the new FM
However, as highlighted in the above section, it is understood that an Centre. The new server will be connected to the existing server in the IMS
extensive IT rationalisation/ upgrade work of the existing data network is to Electrical Specialist Systems building and the existing data infrastructure for testing at an early stage.
be undertaken shortly. This should take into the extent of the new Upon satisfactory testing and commissioning, the existing server will then
developments within the ODCP. The specification and drawings prepared by be removed. The existing data infrastructure will be adopted and modified
the IT Specialist was planned to be issued to tender in mid June this year. It to suit the new developments within the ODCP. In addition, any incoming
The layout of the new duct and pit system for the electrical specialist
is envisaged that this project will have an impact on the ODCP. Close co- data services entering the site from the east of the site will be re-provided
systems including security system, cable television, fire alarm system and
ordination between the two projects needs to be undertaken at an early in order that they will enter the site from the west of the site.
BMS, etc will follow the route of the new duct and pit system for voice and
stage, e.g. the potential demolition of the IMS building under the OCDP will data systems. This will be designed to give a full flexibility for future
have a significant cost and phasing implication wiring. 8.5 Main Plant Room Strategy
Security Systems 8.4 Maintaining Existing Services 8.5.1 Mechanical
The diversion of the CCTV cables and new fibre cables for access control The recommendation of the Outline Development Control Plan is that the
systems will be required to suit the locations of the new developments. existing Energy Centre is retained to provide the central heat source for the
8.4.1 Mechanical
Hospital site utilising steam systems
Consultation with the security designer is required to ensure there is a
sufficient spare capacity within the security systems to meet the security A distribution network of Steam and Condensate pipe work shall be provided
requirements for the new developments. The existing Engineering Systems serving the Hospital are to be maintained
in full operation until such time as any new systems become live from the Energy Centre to connect to both existing and new buildings within
the site
Future designs shall allow for all necessary temporary works to ensure
8.3 Technical Flexibility Provision minimum disruption to the delivery of Health Care Each main building shall be provided with an independent plant room
containing Steam to Water calorifier plant at which point LTHW Heating and
Engineering Service installations shall be designed and installed in Domestic Hot Water will be generated and distributed to the serviced areas
8.3.1 Mechanical accordance with the requirements of HTM2023 to ensure adequate space is
allowed for access to achieve suitable levels of maintenance Boosted Cold Water, LP Gas, Medical Gases and Pneumatic Tube
connections from the site infrastructure and central systems will be
provided to the independent plant room within each building for
The works resulting from the Outline Development Control Plan
distribution to the serviced areas
recommendations must be progressed with consideration of the changing 8.4.2 Electrical
Technical Requirements of Health Care delivery and of Legislation and Good
Practice
General
Page 2
March 2008 Page 130
Feb 2007 Volume 1 – “Section Name” (example: Executive Summary)
Anshen+Allen Team
Section 8: Engineering Services Outline Development Control Plan
Outline Development Control Plan

BMS Outstations will be provide in each plant room to provide local control This relates to the Central Store of water only, additional storage relating
and monitoring of the installed systems linking back to the central station in Telecommunication and Data Communication to a minimum of 8 hours storage capacity will be provided within each
the FM and Energy Centre individual building
Each new building will incorporate at least one main Comm room or Hub
The BMS System shall provide for the sub metering of all primary service room for IT cabinets. Depending on the floor area of the building, additional The tanks will connect to the existing booster equipment which will be
connections to the connected building as well as zoned metering to Hub rooms might be required. As a rule of thumb, the furthest RJ45 data upgraded to suit the requirements of the redeveloped site
departments outlet to each local hub room must not exceed 90 metre.
Local plant rooms shall be provided within each building to accommodate 8.7 IMT
cold water storage tanks, Air Handling Plant and Cooling Equipment and
ancillary services 8.6 Water Storage
The existing data servers are located in the IMT building. The building will
be demolished under the ODCP. It is proposed that the existing services and
The original Strategy at the St James Hospital for Water Storage provides facilities including data servers and equipment be relocated to a new FM
8.5.2 Electrical central site storage covering a 24 hour period within the Energy Centre Centre which is to be located adjacent to the Energy Centre. A
utilising duplicate tanks comprehensive duct and pit system will be provided for the voice and data
Electrical Supply infrastructure which will link the new FM Centre to all other developments
Currently one of these tanks has been isolated from the system and the full on the hospital site, wherever required.
requirement of the site is met by the remaining operating tank. The
All new sub stations will generally consist of an MV switchboard, disconnected tank is available for use and provides back up for maintenance
transformer and LV switchboard as existing. This will facilitate full and emergency usage
availability and flexibility of the MV or LV supplies in connecting future
adjacent buildings into the electrical infrastructure. The sub Stations will
be located in the following areas: The tanks connect to cold water booster pumps within the Energy Centre
which feed a boosted cold water Ring Main around the site
MV Ring Main no 1
Individual connections are taken from the Ring Main to serve daily storage
- external area adjacent to Hospital 2 within new Radiation Oncology tanks and drinking water requirements within each building
Centre
- adjacent to the new Chapel This strategy is considered suitable for the future development of the site

( Note: existing sub station H1 will be upgraded and re-connected to the The existing Central Storage Tank Room within the Energy Centre is to be
ring main no1. ) demolished as part of the ODCP Enabling Works to provide the new
vehicular access rout to the FM Centre
MV Ring main no 2
New Cold water storage tanks replacing the existing are to be provided
- external area adjacent to Site C within the Energy Centre in the location of the existing Hopper Building
- external area adjacent to Site A
- external area between Site F2 and A+E The new tanks will provide central storage for the future developed site
In principle, where future new building requires a heavy electrical demand, utilising two number tanks each with a central division plate
a local transformer room will be provided locally within the building. The
following buildings/ development site will warrant a dedicated transformer The storage capacity will be based on the final occupancy of the site
room:
This has currently been assessed on the following basis

- Future expansion area for Site C Total storage = 440,000 litres


- Future expansion area ( area between Site A and A+E )
- Site D Maximum litres/bed/day = 900 litres
- Future expansion area between site E and Site D
- Site E 24 hour storage = 488 beds
- Site B: Radiation Oncology Centre
- Future expansion area where the current Central Pathology Laboratory
12 hour storage = 1096 beds
Building is located
8 hour storage = 1464 beds
Main LV switchroom will be provided for each building accordingly.

Each new building will incorporate a generator room for a low voltage
generator system to provide a standby generation supply, if required.
Page 3
March 2008 Page 131
Feb 2007 Volume 1 – “Section Name” (example: Executive Summary)
Anshen+Allen Team
Section 8: Engineering Services Outline Development Control Plan
Outline Development Control Plan

3. Provide Mechanical Services Installations as required to the new


FM Centre Development
8.8 Development Phasing Building Services 1. Disconnect and make safe the existing Water, Gas, Steam & 4. Provide new Water, Gas, Steam & Condensate Services
Condensate and Medical Gas Services to the following Buildings to connections to Site H from the existing site infrastructure
8.8.1 Mechanical Engineering Services Works allow demolition works 5. Provide Mechanical Services Installations as required to the new
x The Vacant Assembly Building Site H Development
x The Laundry Building 47 6. Divert the existing Gas & Cold Water mains in the vicinity of the
General x The Medical records Building 23 Research & MRI Building
x The building being demolished at the end of the Phase 1C 7. Extend existing Steam & Condensate mains from existing
The Existing Mechanical Engineering Services Installations within the St Building termination point in Spine services duct above the existing Phase
James’s Hospital site are to be Modified, Extended or Renewed in a manner 1 Buildings to the Research & MRI Building
to suit all stages of the Development Phasing within the Development
2. Provide new Cold Water Storage Tanks located within the Hopper area 8. Provide new Water, Gas, Steam & Condensate Services and
Control Plan
of the Energy Centre together with associated pipe work and control Medical Gas connections to the Research & MRI Building
These works shall include the following works connections 9. Provide Mechanical Services Installations as required to the new
3. Reroute / Replace existing Boosted Cold Water Ring Main and Incoming Research & MRI Building
x The disconnection and making safe of all redundant plant and Cold Water Main to suit the repositioned Cold water storage Tanks 10. Provide Mechanical Services Installations as required to the new
equipment (Note. Existing Cold Water Booster Pumps to be retained in operation) RC Church Development & On Call Building
x The diversion and renewal of the site infrastructure services to suit 4. Upon completion the installation of the new water tanks the existing 11. Extend existing LTHW Heating from the existing Phase 1 H boiler
the proposed development areas Cold Water Storage Tanks are to be removed allowing the demolition room to serve the new Chapel & On Call Building
x The provision of new primary plant and equipment to suit the of the existing Tank Room 12. Provide Mechanical Services Installations as required to the new
proposals 5. Reroute existing HP Gas Main serving the Energy Centre to avoid the RC Church Development & On Call Building
x The provision of all temporary services required to ensure the New FM Centre Construction Site 13. Provide new Water, Gas, Steam & Condensate Services and
continuous operation of occupied parts of the Hospital Site 6. Replace 2 no. existing Steam Boilers within the Energy Centre together Medical Gas connections to the New Temporary Radiotherapy Site
x The provision of all new services associated to the new Build and with associated pipe work connection and controls from the existing site infrastructure
Refurbished Buildings 7. Service and repair existing Steam & Condensate equipment within the 14. Provide Mechanical Services Installations as required to the New
Energy Centre Temporary Radiotherapy Site from the existing site infrastructure
8. Relocate the existing Foam Inlet serving the Energy Centre to avoid 15. Disconnect and remove the existing Mechanical Services
Where existing Services are disconnected and become redundant they must
the New FM Centre Construction Site Installations within Hospital 1 to allow refurbishment Works
always be removed
9. Relocate the existing Oil Fill Point serving the Energy Centre to avoid 16. Provide New Mechanical Services Installations as required to the
At each stage of the development works it is essential that detailed the New FM Centre Construction Site Hospital 1 Refurbishment
investigation is undertaken into the existence of existing underground 10. Provide new Water, Gas, Steam & Condensate Services connections to 17. Extend the existing steam and condensate and Cold water main
engineering services in the vicinity of the development site the New Temporary Decant Building from the existing site from the site infrastructure to serve the first floor extension to
infrastructure Building 10 & the New Clinical Skills Lab
11. Reroute/replace the existing MCW ring Main to allow construction of 18. Provide Mechanical Services Installations as required to the New
Investigation will be undertaken utilising existing Record Drawings and
the Temp Decant Building first floor extension to Building 10 & the New Clinical Skills Lab
retained information together with detailed survey of the specific site
utilising scanning equipment and exploratory investigation 19. Extend the existing steam and condensate Medical Gases & Cold
water main from the site infrastructure to serve the Theatre
The following sections of this report describe the works to be undertaken at Expansion
each stage of the Development Control Plan based on Anshen & Allen Phase 1A Construction Stage 20. Provide Mechanical Services Installations as required to serve the
Drawing Nos. SJH- A-O-Sk0142-P03 to Sk0151-P03 Theatre Expansion
21. Provide new Medical Gas Plant room within the FM Centre for
Works as indicated on Faber Maunsell Drawing Medical Compressed Air and Nitrous Oxide Systems to replace
plant being relocated within Phase 1B
47080/1A/SCH/M01 22. Provide new Medical Gas Master Alarm Panel within the FM Centre
47080/1A /CW/M01 to replace plant being relocated within Phase 1B. New panel to
47080/1A /G/M01
connect to existing retained Alarm systems and extended to new
Enabling Decant & Demolition Phase 47080/1A /MG/M01
systems as the development progresses
1. Provide a new Primary gas meter on the existing LP Gas Main 23. Provide new BMS Central Station within the FM Centre to replace
converting local individual building Primary meters to Secondary plant being relocated within Phase 1B. The New Central BMS
Works as indicated on Faber Maunsell Drawing Series
Meters Station to connect to existing retained systems and extended to
2. Provide new Water, Gas, Steam & Condensate Services new systems as the development progresses
47080/EN/SCH/M01
47080/EN/CW/M01 connections to the New FM Centre Site from the existing site
47080/EN/G/M01 infrastructure
47080/EN/MG/M01
Page 1
March 2008 Page 132
1 October 2006 Volume 1 – “Section Name” (example: Executive Summary)
Anshen+Allen Team
Section 8: Engineering Services Outline Development Control Plan
Outline Development Control Plan

Phase 1B Demolition & Decanting 47080/2B /G/M01


Works as indicated on Faber Maunsell Drawing 47080/2B /MG/M01

47080/2A/SCH/M01 1. Strip out services in buildings to be refurbished Building 18


Works as indicated on Faber Maunsell Drawing
47080/2A /CW/M01 & Ward Block Phase 1G
47080/2A /G/M01 2. Provide temporary heating connection between Plant Room
47080/1B/SCH/M01
47080/2A /MG/M01 49 and Building 7 to allow demolition of Northern end of
47080/1B /CW/M01
47080/1B /G/M01 Building 7
1. Upgrade Medical Gas pipe work throughout the service tunnel,
47080/1B /MG/M01 3. Disconnect and remove existing Water, Gas, Steam &
The main Riser Duct and the Spine duct to suit final Medical Gas
Condensate and Medical Gas Services as applicable from the
1. Increase the capacity of the existing VIE plant adjacent to the requirements
following Buildings
Energy Centre to allow for the future development of the site 2. Provide new Water, Gas, Steam & Condensate and Medical Gas
x Jonathon Swift Clinic Building 5
Oxygen Distribution System Services connections to the New Private Hospital Site C from
x Geriatric Unit Building 6
2. Upgrade initial sections of the existing Oxygen distribution system the existing site infrastructure
3. Provide Mechanical Services Installations as required to the new x Northern end of Building 7
for the future development areas and to allow the removal of the
Private Hospital Site C Development x Orthodontic Department Building 14
existing VIE Plant located adjacent to Building 17
4. Provide new Water, Gas, Steam & Condensate and Medical Gas x Anaesthetic Dental Clinic Building 15
3. Extend the existing oxygen system from it’s current termination
Services connections to the New Phase 1 ODCP Site A from the x Speech & Language Therapy Unit Building 35
point in Phase 1H to serve the ROC Radiotherapy Unit and to
existing site infrastructure x Private Clinic Building 39
connect to the existing retained supplies served by the VIE plant
adjacent to Building 17 allowing removal 5. Provide Mechanical Services Installations as required to the New x Ambulance Centre Building 43
4. Disconnect and remove the VIE plant adjacent to Building 17 Phase 1 ODCP Site A Development x The Temp radiotherapy Unit
5. Connect New Central Medical Air and Nitrous Oxide Systems 6. Provide new Water, Gas, Steam & Condensate and Medical Gas x The Temp On Call Building
within the FM centre into the upgraded system Services connections to the New Phase 1 ODCP Site D from the
6. Disconnect and remove existing Medical Gas Installations in existing site infrastructure Phase 3A Construction
Medical Gas Plant Room Building 42 to allow Demolition 7. Provide Mechanical Services Installations as required to the New
7. Disconnect and remove existing BMS Central Station in Technical Phase 1 ODCP Site D Development
Services Building to allow Demolition 8. Provide new Water, Gas, Steam & Condensate and Medical Gas Works as indicated on Faber Maunsell Drawing
8. Reroute existing LP Gas Main and Cold Water Main entering the Services connections to the New Phase 1 ODCP Site B from the
SW corner of the site from Rialto Bridge to avoid the New existing site infrastructure 47080/3A/SCH/M01
9. Provide Mechanical Services Installations as required to the New 47080/3A /CW/M01
Construction Site A
Phase 1 ODCP Site B Development 47080/3A /G/M01
9. Disconnect and make safe the existing Water, Gas, Steam & 47080/3A /MG/M01
Condensate and Medical Gas Services as applicable to the 10. Provide new Water, Gas, Steam & Condensate and Medical Gas
following Buildings to allow demolition works Services connections to the New Community Bed Unit
Development from the existing site infrastructure 1. Replace the dismantled Steam Boiler Within the Energy
x Admin Planning Office Building 19 11. Provide Mechanical Services Installations as required to the New Centre together with it’s associated pipe work connections
x Dept of Clinical Nutrition Building 20 Community Bed Unit Development and controls and bring into operation with the 2 new boilers
12. Provide new Water, Gas, Steam & Condensate and Medical Gas 4. Replace one of the remaining existing steam boilers
x Hope Directorate Building 21
Services connections to the New Emergency Dept Expansion together with it’s associated pipe work connections and
x Occupational Health Dept Building 24
Development from the existing site infrastructure controls and bring into operation with the 3 other new
x On Call Accommodation Building 25 boilers
13. Provide Mechanical Services Installations as required to the New
x Social Recreation Club Building 28 5. Remove the remaining existing steam boiler together with
Emergency Dept Expansion Development
x RC Church Building 29 14. Extend new Water, Gas, Steam & Condensate and Medical Gas
it’s associated pipe work connections and controls and
x Rheumatology Day Centre Building 30 retain space for future additional steam boiler if required in
Services connections from site D to Building 17
x General support services Building 31 expansion development
15. Disconnect and remove existing Steam & Condensate from the 6. Extend Steam & Condensate Mains Site B to connect to
x Old Pump Room Building 32 Refurbished Hospital Building 17 existing supplies serving the IBTS Lab, Hospital 2 Building
x Information & Management Services Building 40 16. Disconnect the existing Steam & Condensate connections from 18, and the Steam manifold Room in the Path Lab
x Technical services Building 41 the Jonathon Swift Clinic and reconnect to new supplies 7. Extend Steam & Condensate Mains from Site B to connect to
x Medical Gases Building 42 Phase 2 ODCP Site E
x Materials Management Building 48 8. Extend the Steam & Cond.from the Temp Radiotherapy site
Phase 2B Demolition & Decanting
x Recycling Centre Building 50 to Building 16
9. Disconnect and Remove existing Steam & Condensate
x Burns Unit
serving the Building 16
x Temp Decant Building Works as indicated on Faber Maunsell Drawing
10. Disconnect and Remove existing Steam & Condensate
serving the IBTS Lab, Hospital 2 Building 18, and the Steam
47080/2B/SCH/M01
Phase 2A Construction 47080/2B /CW/M01
Page 2
March 2008 Page 133
1 October 2006 Volume 1 – “Section Name” (example: Executive Summary)
Anshen+Allen Team
Section 8: Engineering Services Outline Development Control Plan
Outline Development Control Plan

manifold Room in the Path Lab and reconnect to extended 47080/4A /CW/M01
service from Site B 47080/4A /G/M01 x The disconnection and making safe of all redundant plant and
11. Reroute the existing incoming Mains Cold water and the 47080/4A /MG/M01 equipment
Boosted Water Main in the vicinity of Buildings 33 and 35 x The diversion and renewal of the site infrastructure services to suit
12. Reroute the existing Boosted Cold Water Main section from 1. Provide new Steam & Condensate Connection to Site F1 and the proposed development areas
the rear of the Public car Park to run on the South side of Site F2
the new Hospital Road 2. Reroute existing HP gas around Development Site A x The provision of new primary plant and equipment to suit the
13. Provide new Boosted Cold water Main connections from the 3. Provide new Boosted Cold Water Main Connection to Site F1 proposals
rerouted ring main to connect to Hospital 1 Building 17 and and Site F2 x The provision of all temporary services required to ensure the
Hospital 2 Building 18 4. Provide new Medical Gases Connection to Site F1 and Site F2 continuous operation of occupied parts of the Hospital Site
14. Provide new Boosted Cold water Main connections from the 5. Provide New Mechanical Services Installations as required to x The provision of all new services associated to the new Build and
existing ring main to connect to Phase 2 ODCP Site E the New Site F1 and Site F2 accommodation Refurbished Buildings
15. Refurbish the Mechanical service Installations within
Hospital 2 Building 18 Where existing Services are disconnected and become redundant they must
16. Provide LP Gas and Medical Gas Connections from existing always be removed
distribution to the ODCP Site E Development
17. Provide New Mechanical Services Installations as required to Phase 4B Demolition & Decanting- Future Vision At each stage of the development works it is essential that detailed
the New Phase 2 ODCP Site E Development investigation is undertaken into the existence of existing underground
engineering services in the vicinity of the development site
Works as indicated on Faber Maunsell Drawing
Investigation will be undertaken utilising existing Record Drawings and
Phase 3B Demolition & Decanting 47080/4B/SCH/M01 retained information together with detailed survey of the specific site
47080/4B /CW/M01 utilising scanning equipment and exploratory investigation
Works as indicated on Faber Maunsell Drawing 47080/4B /G/M01
47080/4B /MG/M01 The following sections of this report describe the works to be undertaken at
47080/3B/SCH/M01 each stage of the Development Control Plan based on Anshen Allen Drawing
47080/3B /CW/M01 1. Disconnect remove existing Mechanical Services connections Nos. SJH- A-O-Sk0090-P01 to Sk0101-P01. These should be read in
47080/3B /G/M01 to and installation within all existing Building being conjunction with Faber Maunsell’s relevant drawings.
47080/3B /MG/M01 proposed for demolition
2. Provide permanent connection of steam and cond. to site A
1. Reroute and replace the existing cold water main in the and remove temp services
south east corner of the site
2. Disconnect and remove the existing Gas connections to The Enabling Demolition Phase
following Buildings
x Physiotherapy Department Building 34 Phase 5A Construction – Future Vision Refer to Faber Maunsell Drawing No 47080/ED/E/E01 and 47080/ED/T/E01
x Hospital 7 Building 27
3. Disconnect and remove the existing Medical Gases Works as indicated on Faber Maunsell Drawing - Remove all redundant power, voice, data and all other electrical specialist
connection to Hospital 7 Building 27 systems entering the buildings to be demolished
4. Disconnect and remove the existing Steam & Condensate 47080/5A/SCH/M01 - Relocate existing sub station A2/A4
connection to Hospital 7 Building 27 47080/5A /CW/M01 - Re-provide all outgoing circuits from the sub station A2/A4 accordingly
5. Disconnect and remove the existing Steam & Condensate 47080/5A /G/M01 - Re-route ESB’s no3 incoming supply to sub A2/A4
connection to Building 5, 27 & 22 47080/5A /MG/M01 - Divert underground cables as necessary
6. Disconnect and remove the existing Boosted Cold water
connections to the following buildings; 1. Provide new Steam & Condensate services, Boosted Cold
x Hospital 7 water main services, Gas and Medical Gases services
x Building 27 connections to all Future Expansion sites as required
x Physiotherapy Department Building 34
x Heating Plant Room Building 49 8.8.2 Electrical Engineering Services Works Phase 1A – Construction

Refer to Faber Maunsell Drawing No 47080/1A/E/E01, 47080/1A/SCH/E01


General and 47080/1A/T/E01

The Existing Electrical Engineering Services Installations within the St - Apply MIC increase from 3.7MVA to 4.5MVA
Phase 4A Construction James’s Hospital site are to be modified, extended or renewed in a manner - Construct a new electrical sub station compound to accommodate SJH’s
to suit all stages of the Development Phasing within the Development new MV switchroom, future transformer room and HV intake room,
Works as indicated on Faber Maunsell Drawing Control Plan together with future ESB’s HV room
- Provide power supply to the new developments from the existing
47080/4A/SCH/M01 These works shall include the following works: network

Page 3
March 2008 Page 134
1 October 2006 Volume 1 – “Section Name” (example: Executive Summary)
Anshen+Allen Team
Section 8: Engineering Services Outline Development Control Plan
Outline Development Control Plan

- Provide a new duct and pit system for voice and data systems Phase 3B – Decanting & Demolition
- Test and changeover the existing data system from existing to new
- Provide a new duct and pit system for all other electrical specialist
Refer to Faber Maunsell Drawing No 47080/3B/E/E01 and 47080/3B/T/E01
systems
- Remove all redundant power, voice, data and all other electrical specialist
systems entering the buildings to be demolished
Phase 1B – Decanting & Demolition - Divert any obstructed underground cables as necessary

Refer to Faber Maunsell Drawing No 47080/1B/E/E01 and 47080/1B/T/E01 Phase 4A - Construction

- Remove all redundant power, voice, data and all other electrical specialist Refer to Faber Maunsell Drawing No 47080/4A/E/E01 and 47080/4A/T/E01
systems entering the buildings to be demolished
- Divert any obstructed underground cables as necessary - Construct new sub stations
- Connect the new sub stations to the new MV ring Main no 1 and 2
respectively
- Provide electrical engineering systems to the new buildings
Phase 2A - Construction - Re-feed any electrical circuits as required

Refer to Faber Maunsell Drawing No 47080/2A/E/E01, 47080/2A/SCH/E01 Phase 4B – Decanting & Demolition
and 47080/2A/T/E01
Refer to Faber Maunsell Drawing No 47080/4B/E/E01 and 47080/4B/T/E01
- Upgrade ESB’s incoming MV cables
- Provide a temporary supply to live up the new SJH’s MV switchboard - Remove the existing MV ring on site
- Provide new MV ring main no1 and 2 with associated new sub stations - Remove all redundant power, voice, data and all other electrical specialist
- Provide a dedicated ESB’s MV electrical supply to the Private systems entering the buildings to be demolished
Hospital from the street - Divert any obstructed underground cables as necessary

- Extend the new duct and pit system for voice and data systems to serve
the new buildings
- Extend the new duct and pit system for all other electrical specialist
Phase 5A – Construction
systems to the new buildings
Refer to Faber Maunsell Drawing No 47080/5A/E/E01 and 47080/5A/T/E01

- Provide electrical engineering systems to the new buildings


Phase 2B – Decanting & Demolition - Re-feed any electrical circuits as required

Refer to Faber Maunsell Drawing No 47080/2B/E/E01 and 47080/2B/T/E01

- Remove all redundant power, voice, data and all other electrical specialist
systems entering the buildings to be demolished
- Divert any obstructed underground cables as necessary

Phase 3A – Construction

Refer to Faber Maunsell Drawing No 47080/3A/E/E01 and 47080/3A/T/E01

- Obtain HV supply from ESB


- Provide new SJH’s transformers and HV switchgear/ switchboard
- Extend duct and pit systems for electrical specialist systems to the new
developments
- Provide electrical engineering systems to the new buildings

Page 4
March 2008 Page 135
1 October 2006 Volume 1 – “Section Name” (example: Executive Summary)
Anshen+Allen Team
Outline Development Control Plan
Section 9: Civil and Structural Outline Development Control Plan

9.0 Civil and Structural x Flexibility for first and second-generation builders’ works in connection x Night wards
with services
x Operating theatres
The following section outlines the civil and structural considerations of the x Integration of services
preferred option. The phasing as described in this section is supported by x Sensitive scanning equipment
drainage drawing series No. 47080/##/D/C01. This section is supported by x Buildability to facilitate construction
Sensitive equipment should be placed on ground floors where possible.
the risk register and infrastructure matrix located in the appendices for x Maximise elements suitable for repetitive construction However, because of the limited building footprints, sensitive equipment
further information relating to each site. will have to be provided on suspended floors. Design of the concrete slab
x Provide a sustainable design and construction solution to minimise the
will have to ensure that the stringent vibration requirements are taken into
impact on the environment
9.1 Foul Water Drainage consideration.
x Provide a design solution to meet the needs for future development
The proposed principal of the foul water drainage is to make a transition Vibration is not readily controlled as it propagates through buildings and it
x Due regard for site conditions including soil strata, groundwater,
from the current philosophy of draining towards the Drimnagh Sewer to is also almost impossible to predict with any certainty, so vibration control
topography, site constraints, and continued beneficial access to
draining towards the proposed pumping station at the southwest side of the is usually best undertaken at source. There are two basic types of sources
surrounding buildings
site. The pumping station will discharge towards the Grand Canal Sewer of vibration likely to be present within the hospital – controlled sources
approximately 1km to the south of the site. x Health, safety and welfare of workforce and patients during (such as building services plant and equipment), and uncontrolled sources
construction (such as people and trolley movement).
The main site drainage at the critical phases is shown on drawings x Future maintenance and installation of equipment, plant and building
47080/C/01 to 04. It is usual to isolate the vibration source rather than treating the receiver.
fabric
In the case of controlled sources, such as building services systems where
x Coordinated design solution the frequency of vibration is readily predicted, vibration isolation can be
9.2 Surface Water Drainage readily implemented at source. All building services plant will be mounted
x Architectural/Aesthetic qualities
on appropriate anti-vibration mounts and fixings to prevent these being
The proposed principle of the surface water drainage is to continue to x Repetitive construction sources of unwanted vibration. Where appropriate, inertia bases and the
discharge into the Drimnagh Sewer. Additional surface water attenuation resilient fixing of distribution services will also be included to complement
can be provided through oversized pipes. Full negotiations with DCC will 9.4.2 Structural Form these anti-vibration measures.
have to be completed with regards to the required attenuation. DCC have
suggested that it may be required for an additional surface water drainage It is recommended that the clinical buildings should be of reinforced Sources of uncontrolled vibration, such as people, activities and trolley
connection to be installed, discharging towards the Camac River. This concrete flat slab construction. movements, do not have predictable frequencies of excitation.
connection could exit the site to the northeast at the James’s Street Consequently, it is far harder to achieve the required standards set down
entrance. Flat slab construction is particularly suited to hospital development as there are a number of variables to consider.
through the following advantages:
9.3 Drimnagh Sewer 9.4.5 Structural Grid
x Simple service distribution
The Drimnagh Sewer will remain operational for the early phases. During x Vibration performance Each site is tightly constrained by existing buildings which will largely
phase 4, the site F buildings span across the sewer. At this stage it should dictate the footprint shape. The emphasis on the general structural
be considered to divert the Drimnagh Sewer to the pumping station. This x Acoustic performance
philosophy of the new buildings should be of simplicity and regularity with
will enable the unrestricted development of site F. x Permits future adaptability structural spans between 7 to 8m. This approach leads to a more flexible
building suitable for the future development needs of the hospital.
x Considered fast method of construction
9.4 General Structural Philosophy
x Cost effective 9.4.6 Future Adaptability and Flexibility
9.4.1 Key Considerations x Inherent fire resistance
Hospital building use is likely to change significantly within the design life
Key considerations to developing the Civil and Structural Engineering design 9.4.3 Service Distribution of the structure and beyond the period of the ODCP. Two reasons for this
are: are development in medical practices and advances in medical equipment.
Flat soffits provide straight forward service distribution. Vertical service Changes are likely to require structural modifications. The building should
x Adaptable open spaces distribution though riser cores should be positioned with no surrounding be designed to accommodate specific needs whilst providing the flexibility
concrete stability walls. This will allow services to exit in all directions and required for the building to be developed within the overall site strategy.
x Provide future flexibility for equipment maintenance and clinical enhance the flexibility of future services provision. Each structure should be designed for the following:
operation
x Adaptation for anticipated future development in clinical practice and 9.4.4 Vibration Requirements x Allowance for future slab penetrations and modified loading regimes
treatment methodologies x Potential future vertical expansion
x Economics for the proposed structural grid Hospitals demand high vibration performance of the structure from the
following areas: x Potential future horizontal expansion
x Robustness and resistance to vibration
Page 1

1 October 2006 Volume 1 – “Section Name” (example: Executive Summary)


March 2008 Page 136

Anshen+Allen Team

Potrebbero piacerti anche