Sei sulla pagina 1di 5

GE

Gas Power Systems

Energía Valle de México,


Estado de México, México

7HA.02 multi-shaft 2in1, outdoor arrangement


EPC offer (Exhibit A)

Part A: Power Plant


Part B: HV Systems (Original Scope 400KV)
Part B: HV Systems (Addendum: Scope 400KV and 230KV)

Contractor’s Offer (Technical Offer)


Oppty ID# 1154163
Dec, 2017

This Proposal is submitted in confidence for evaluation by Buyer. Its contents are proprietary to General Electric
Company. By taking receipt of this Proposal, Buyer agrees not to reveal its contents in whole or in part beyond those
persons in its own organization necessary to properly evaluate this Proposal or to perform any resulting contract. Buyer
shall not reveal the contents of this Proposal to a third party or make copies of this Proposal without the prior written
consent of General Electric Company.
Table of Contents
Part A: Power Plant

Proposal Summary
Not applicable.......................................................................................................................................................... 1
General Plant Description ................................................................................................................................... 2
Performance, Operation and Design Basis
Performance Guarantees ................................................................................................................................... 3
Design Basis ............................................................................................................................................................. 4
Combined Cycle Performance Curves .......................................................................................................... 5
Plant Operating Philosophy ............................................................................................................................... 6
Power Plant Scope - Equipment and Systems Description
Scope of Work.......................................................................................................................................................... 7
Turbines/Generators Equipment Description ............................................................................................ 8
Heat Recovery Steam Generator .................................................................................................................... 9
Plant Controls Equipment ................................................................................................................................ 10
Mechanical/Fluid/BoP ....................................................................................................................................... 11
Electrical BoP ......................................................................................................................................................... 12
Civil Works .......................................................................................................................................................... 13-1
Building Facilities ............................................................................................................................................. 13-2
Design Characteristics and Assumptions
Base Line Assumptions ..................................................................................................................................... 14
Limits of Supply .................................................................................................................................................... 15
Not applicable....................................................................................................................................................... 16
Codes and Standards ........................................................................................................................................ 17
Data Sheets............................................................................................................................................................ 18
Not applicable....................................................................................................................................................... 19
Quality
Quality ...................................................................................................................................................................... 20
Drawings & Diagrams
Drawings and Diagrams ................................................................................................................................. 21
Services
Project Schedule .................................................................................................................................................. 22
Project Management ......................................................................................................................................... 23
Not applicable....................................................................................................................................................... 24

© 2017 General Electric Company Table of Contents Page ii


CONFIDENTIAL INFORMATION EVM-II 1154163 Rev October 2017
Site Activities ........................................................................................................................................................ 25
Not applicable....................................................................................................................................................... 26
Not applicable....................................................................................................................................................... 27
Training .................................................................................................................................................................... 28
Performance Testing ......................................................................................................................................... 29
Not applicable....................................................................................................................................................... 30
Not applicable....................................................................................................................................................... 31

Appendices
Reference Specifications/Documents ....................................................................................................... 32

© 2017 General Electric Company Table of Contents Page iii


CONFIDENTIAL INFORMATION EVM-II 1154163 Rev October 2017
Table of Contents

Part B: HV Systems

Proposal Summary
Not applicable....................................................................................................................................................... 01
General HV-System Description ..............................................................................................02
Performance, Operation and Design Basis
Not applicable....................................................................................................................................................... 03
Design Criteria ............................................................................................................................04
Not applicable....................................................................................................................................................... 05
Not applicable....................................................................................................................................................... 06
HV System Scope - Equipment and Systems Description
Scope of Work .............................................................................................................................07
Not applicable....................................................................................................................................................... 08
Not applicable....................................................................................................................................................... 09
Not applicable....................................................................................................................................................... 10
Not applicable....................................................................................................................................................... 11
Electrical ......................................................................................................................................12
Civil/Structural............................................................................................................................13
Assumptions
Base Line Assumptions .............................................................................................................14
Limits of Supply...........................................................................................................................15
Not applicable....................................................................................................................................................... 16
Codes and Standards ................................................................................................................17
Not applicable....................................................................................................................................................... 18
Not applicable....................................................................................................................................................... 19
EHS
EHS ................................................................................................................................................20
Proposal Drawings & Diagrams
Proposal Drawings and Diagrams .........................................................................................21
Services
Not applicable....................................................................................................................................................... 22
Project Management .................................................................................................................23
Engineering and Design ............................................................................................................24

© 2017 General Electric Company Table of Contents Page iv


CONFIDENTIAL INFORMATION EVM-II 1154163 Rev October 2017
Site Activities ..............................................................................................................................25
Not applicable....................................................................................................................................................... 26
Not applicable....................................................................................................................................................... 27
Not applicable....................................................................................................................................................... 28
Not applicable....................................................................................................................................................... 29
Not applicable....................................................................................................................................................... 30
Not applicable....................................................................................................................................................... 31
Appendices
Not applicable....................................................................................................................................................... 32