Costos 1

Costos directos mina


perforación 0.07 US$/ton material
tronadura 0.09 US$/ton material
carguío 0.12 US$/ton material
transporte 0.3 US$/ton material
servicio 0.18 US$/ton material

administración mina,
prevención riesgos, RRHH,
servicios médicos, etc.
0.2 US$/ton material
total costo mina 0.96 US$/ton material
depreciación equipos 0.5 US$/ton material
TOTAL COSTOS 1 1.46 US$/ton material
Costos 2
tratamiento de mineral 4.4 US$/ton mineral
administración central 0.9 US$/ton mineral
TOTAL COSTOS 2 5.3 US$/ton mineral
Costos 3
Transporte puerto,
créditos, seguros, etc. 0.38 US$/lb Cu
TOTAL COSTOS 3 0.38 US$/lb Cu
Taylor
Reservas (Mton) 294.5 Lím. Inf. Lím sup.
VOE (años) 26.9 21.5 32.3
ROP (Mt/años) 17.77 14.22 21.33

Mackenzie
Reservas (ton) 294,500,000
ROP subterráneo (t/año) 10,664,511
ROP cielo abierto (t/año) 14,227,771 ------> 1,647 ton/h requerimientos planta
549 m3/h volumen mineral in situ
López Jimeno 659 m3/h volumen mineral esponjado
VOE cobre (años) 25.3
VOE oro (años) 29.6
VOE Pb-Zn (años) 36.5

Densidad mineral 3 ton/m3


Densidad estéril 2.1 ton/m3
Swell mineral 0.20
Swell estéril
entos planta
mineral in situ
mineral esponjado
Consumo camión mixer 0.3 L/km precio ANFO 417.68 USD/ton
precio TNT 219.69 USD/m
mano obra T 23.6 USD/h
dens anfo [g/cc] 0.77 granel
dens tnt [g/cc] 1.18 tronex
Cilindro Tronco cilíndrico
Banco r [m] h [m] V [m ]
3
R [m] r [m] V [m3]
1 250 15 2,945,243 251.3 250 15,488
2 250 15 2,945,243 260.1 251.3 136,585
3 250 15 2,945,243 268.9 260.1 352,629
4 250 15 2,945,243 277.7 268.9 575,993
5 250 15 2,945,243 286.6 277.7 806,676
6 250 15 2,945,243 295.4 286.6 1,044,677
7 250 15 2,945,243 304.2 295.4 1,289,998
8 250 15 2,945,243 313.0 304.2 1,542,638
9 250 15 2,945,243 321.8 313.0 1,802,596
10 250 15 2,945,243 330.6 321.8 2,069,874
11 250 15 2,945,243 339.4 330.6 2,344,471
12 250 15 2,945,243 348.2 339.4 2,626,386
13 250 15 2,945,243 357.1 348.2 2,915,621
14 250 15 2,945,243 365.9 357.1 3,212,175
15 250 15 2,945,243 374.7 365.9 3,516,048
16 250 15 2,945,243 383.5 374.7 3,827,239
17 250 15 2,945,243 392.3 383.5 4,145,750
18 250 15 2,945,243 401.1 392.3 4,471,580
19 250 15 2,945,243 409.9 401.1 4,804,729
20 250 15 2,945,243 418.7 409.9 5,145,197
21 250 15 2,945,243 427.6 418.7 5,492,984
22 250 15 2,945,243 436.4 427.6 5,848,090
23 250 15 2,945,243 445.2 436.4 6,210,514
24 250 15 2,945,243 454.0 445.2 6,580,258
25 250 15 2,945,243 462.8 454.0 6,957,321
26 250 15 2,945,243 471.6 462.8 7,341,703
27 250 15 2,945,243 480.4 471.6 7,733,404
28 250 15 2,945,243 489.2 480.4 8,132,424
29 250 15 2,945,243 498.1 489.2 8,538,763
30 250 15 2,945,243 506.9 498.1 8,952,421
31 250 15 2,945,243 515.7 506.9 9,373,398
32 250 15 2,945,243 524.5 515.7 9,801,694
33 250 15 2,945,243 533.3 524.5 10,237,309
34 250 5 981,748 542.1 533.3 3,560,081
TOTAL 500 98,174,770 151,406,715

Ley Cu 0.01 precio Cu 5,733 US$/ton


Ley Au 0.0000005 precio Au 40,739,822 US$/ton
Ley Ag 0.0000015 precio Ag 580,321 US$/ton
Densidad M 3

Densidad E 2.1
Ancho de berma 7.5

0.010002 981,944 97,192,826


Recuperación al 90%
E/M (masa) Cu [ton] Au Ag Ingresos M[US$] Egresos M[US$]
0.00 79,522 3.98 11.93 625 60
0.03 79,522 3.98 11.93 625 60
0.08 79,522 3.98 11.93 625 61
0.14 79,522 3.98 11.93 625 62
0.19 79,522 3.98 11.93 625 62
0.25 79,522 3.98 11.93 625 63
0.31 79,522 3.98 11.93 625 64
0.37 79,522 3.98 11.93 625 64
0.43 79,522 3.98 11.93 625 65
0.49 79,522 3.98 11.93 625 66
0.56 79,522 3.98 11.93 625 67
0.62 79,522 3.98 11.93 625 68
0.69 79,522 3.98 11.93 625 69
0.76 79,522 3.98 11.93 625 70
0.84 79,522 3.98 11.93 625 71
0.91 79,522 3.98 11.93 625 71
0.99 79,522 3.98 11.93 625 72
1.06 79,522 3.98 11.93 625 73
1.14 79,522 3.98 11.93 625 74
1.22 79,522 3.98 11.93 625 76
1.31 79,522 3.98 11.93 625 77
1.39 79,522 3.98 11.93 625 78
1.48 79,522 3.98 11.93 625 79
1.56 79,522 3.98 11.93 625 80
1.65 79,522 3.98 11.93 625 81
1.74 79,522 3.98 11.93 625 82
1.84 79,522 3.98 11.93 625 83
1.93 79,522 3.98 11.93 625 85
2.03 79,522 3.98 11.93 625 86
2.13 79,522 3.98 11.93 625 87
2.23 79,522 3.98 11.93 625 88
2.33 79,522 3.98 11.93 625 90
2.43 79,522 3.98 11.93 625 91
2.54 26,507 1.33 3.98 208 31
Ganancias M[US$] Ratio (vol) Masa Mineral Masa Estéril metros a barrenar (D=341mm)
565 0.01 8,835,729 32,524 43321.7
565 0.05 8,835,729 286,828 45093.6
564 0.12 8,835,729 740,522 48254.8
563 0.20 8,835,729 1,209,585 51523.1
563 0.27 8,835,729 1,694,019 54898.5
562 0.35 8,835,729 2,193,822 58380.9
561 0.44 8,835,729 2,708,996 61970.5
560 0.52 8,835,729 3,239,539 65667.2
560 0.61 8,835,729 3,785,452 69470.9
559 0.70 8,835,729 4,346,735 73381.7
558 0.80 8,835,729 4,923,388 77399.7
557 0.89 8,835,729 5,515,412 81524.7
556 0.99 8,835,729 6,122,804 85756.8
555 1.09 8,835,729 6,745,567 90096.0
554 1.19 8,835,729 7,383,700 94542.3
553 1.30 8,835,729 8,037,203 99095.7
552 1.41 8,835,729 8,706,076 103756.2
551 1.52 8,835,729 9,390,318 108523.8
550 1.63 8,835,729 10,089,931 113398.4
549 1.75 8,835,729 10,804,913 118380.2
548 1.87 8,835,729 11,535,266 123469.0
547 1.99 8,835,729 12,280,988 128665.0
546 2.11 8,835,729 13,042,080 133968.0
545 2.23 8,835,729 13,818,542 139378.2
544 2.36 8,835,729 14,610,375 144895.4
543 2.49 8,835,729 15,417,577 150519.7
541 2.63 8,835,729 16,240,149 156251.1
540 2.76 8,835,729 17,078,091 162089.6
539 2.90 8,835,729 17,931,402 168035.2
538 3.04 8,835,729 18,800,084 174087.9
536 3.18 8,835,729 19,684,136 180247.7
535 3.33 8,835,729 20,583,558 186514.5
534 3.48 8,835,729 21,498,349 192888.5
177 3.63 2,945,243 7,476,170 66456.5
numero de tiros numero de tiros de precorte radios acumulados cantidad CF unidades
2750.0 171.0 251.3 8421.6
2863.0 349.0 511.4 8938.3
3063.0 532.0 780.4 9722.0
3271.0 722.0 1058.1 10535.7
3485.0 918.0 1344.7 11373.4
3706.0 1120.0 1640.1 12238.1
3934.0 1327.0 1944.2 13129.8
4169.0 1541.0 2257.2 14048.6
4410.0 1761.0 2579.1 14991.4
4659.0 1987.0 2909.7 15964.2
4914.0 2218.0 3249.1 16961.0
5176.0 2456.0 3597.4 17984.8
5444.0 2700.0 3954.4 19032.7
5720.0 2950.0 4320.3 20110.6
6002.0 3206.0 4695.0 21212.5
6291.0 3468.0 5078.5 22341.4
6587.0 3736.0 5470.8 23497.3
6890.0 4010.0 5871.9 24680.2
7199.0 4290.0 6281.8 25887.2
7516.0 4576.0 6700.6 27124.2
7839.0 4868.0 7128.1 28385.2
8169.0 5166.0 7564.5 29673.2
8505.0 5470.0 8009.7 30985.3
8849.0 5780.0 8463.7 32327.3
9199.0 6096.0 8926.5 33693.4
9556.0 6418.0 9398.1 35086.5
9920.0 6746.0 9878.6 36506.6
10291.0 7080.0 10367.8 37953.7
10668.0 7420.0 10865.9 39424.9
11053.0 7767.0 11372.7 40926.1
11444.0 8119.0 11888.4 42451.3
11842.0 8477.0 12412.9 44003.5
12246.0 8841.0 12946.2 45579.7
4219.0 9211.0 13488.3 21868.9
cantidad de ANFO ton cantidad de cable pentrita m camiones de explosivo necesarios
340.8 46760.0 2.0
458.0 48672.5 2.0
585.7 52084.6 2.0
718.3 55612.2 2.0
855.1 59255.5 2.0
996.1 63014.4 2.0
1140.7 66888.8 2.0
1290.2 70878.8 2.0
1443.8 74984.5 2.0
1601.7 79205.7 2.0
1763.1 83542.5 2.0
1929.4 87994.9 2.0
2099.8 92562.9 2.0
2274.5 97246.5 2.0
2453.4 102045.7 2.0
2636.5 106960.4 2.0
2823.8 111990.8 2.0
3015.3 117136.7 2.0
3211.0 122398.3 2.0
3411.0 127775.4 2.0
3615.2 133268.2 2.0
3823.5 138876.5 2.0
4036.0 144600.4 2.0
4252.8 150439.9 2.0
4473.8 156395.0 2.0
4698.9 162465.7 2.0
4928.3 168652.0 3.0
5162.0 174953.9 3.0
5399.7 181371.3 3.0
5642.4 187904.4 3.0
5888.6 194553.0 3.0
6139.1 201317.3 3.0
6393.7 208197.1 3.0
5923.5 71730.9 3.0
costo de tronadura USD/h costo tronadura USD/ton
501.4 0.3
537.8 0.3
589.3 0.4
642.7 0.4
697.8 0.4
754.5 0.5
813.0 0.5
873.3 0.5
935.2 0.6
999.1 0.6
1064.4 0.7
1131.6 0.7
1200.4 0.7
1271.1 0.8
1343.4 0.8
1417.5 0.9
1493.3 0.9
1570.9 1.0
1650.0 1.0
1731.1 1.1
1813.8 1.1
1898.3 1.2
1984.3 1.2
2072.3 1.3
2161.9 1.3
2253.2 1.4
2347.5 1.4
2442.3 1.5
2538.8 1.6
2637.2 1.6
2737.1 1.7
2838.9 1.8
2942.2 1.8
4865.9 3.0
Costo Tronadura USD Costo Perforación USD Costo Tratamiento Mineral
2743308.13 315815.40 USD 37,110,063.2
3026812.43 328732.61 USD 37,110,063.2
3481341.86 351777.67 USD 37,110,063.2
3982960.84 375603.43 USD 37,110,063.2
4532471.65 400209.90 USD 37,110,063.2
5133984.35 425597.07 USD 37,110,063.2
5790411.59 451764.95 USD 37,110,063.2
6505743.00 478713.53 USD 37,110,063.2
7281831.99 506442.82 USD 37,110,063.2
8124714.18 534952.81 USD 37,110,063.2
9035031.02 564243.51 USD 37,110,063.2
10018567.37 594314.92 USD 37,110,063.2
11077274.86 625167.02 USD 37,110,063.2
12218050.76 656799.84 USD 37,110,063.2
13441848.30 689213.36 USD 37,110,063.2
14754312.98 722407.58 USD 37,110,063.2
16159680.13 756382.51 USD 37,110,063.2
17662285.27 791138.15 USD 37,110,063.2
19264653.20 826674.48 USD 37,110,063.2
20975069.08 862991.53 USD 37,110,063.2
22794271.93 900089.28 USD 37,110,063.2
24728903.89 937967.73 USD 37,110,063.2
26781587.62 976626.89 USD 37,110,063.2
28961594.04 1016066.76 USD 37,110,063.2
31269455.73 1056287.33 USD 37,110,063.2
33712508.77 1097288.60 USD 37,110,063.2
36313615.63 1139070.59 USD 37,110,063.2
39043422.92 1181633.27 USD 37,110,063.2
41921712.38 1224976.66 USD 37,110,063.2
44960120.65 1269100.76 USD 37,110,063.2
48157222.00 1314005.56 USD 37,110,063.2
51522209.01 1359691.06 USD 37,110,063.2
55057842.56 1406157.28 USD 37,110,063.2
31283025.23 484468.06 USD 12,370,021.1
USD 26,622,372.9 USD 1,237,002,107.4
Carguío Mineral Carguío Estéril Transporte Mineral Transporte Estéril Factor de Carga
USD 20,256,697.9 USD 96,529.7 21,150,558.8 USD 97,719.9 USD 0.4235264339
USD 20,256,697.9 USD 851,294.4 21,150,558.8 USD 861,790.9 USD 0.4630883631
USD 20,256,697.9 USD 2,197,839.0 21,150,558.8 USD 2,224,938.3 USD 0.4972467586
USD 20,256,697.9 USD 3,590,000.9 21,150,558.8 USD 3,634,265.5 USD 0.5284294665
USD 20,256,697.9 USD 5,027,780.2 21,150,558.8 USD 5,089,772.5 USD 0.5566051446
USD 20,256,697.9 USD 6,511,176.8 21,150,558.8 USD 6,591,459.3 USD 0.5822434864
USD 20,256,697.9 USD 8,040,190.7 21,150,558.8 USD 8,139,326.0 USD 0.6054968338
USD 20,256,697.9 USD 9,614,822.0 21,150,558.8 USD 9,733,372.4 USD 0.6269114886
USD 20,256,697.9 USD 11,235,070.6 21,150,558.8 USD 11,373,598.6 USD 0.6464681091
USD 20,256,697.9 USD 12,900,936.5 21,150,558.8 USD 13,060,004.6 USD 0.6645341845
USD 20,256,697.9 USD 14,612,419.8 21,150,558.8 USD 14,792,590.4 USD 0.6809909176
USD 20,256,697.9 USD 16,369,520.5 21,150,558.8 USD 16,571,356.0 USD 0.6963019342
USD 20,256,697.9 USD 18,172,238.4 21,150,558.8 USD 18,396,301.5 USD 0.7104019868
USD 20,256,697.9 USD 20,020,573.7 21,150,558.8 USD 20,267,426.7 USD 0.7235451646
USD 20,256,697.9 USD 21,914,526.4 21,150,558.8 USD 22,184,731.7 USD 0.7356911257
USD 20,256,697.9 USD 23,854,096.4 21,150,558.8 USD 24,148,216.5 USD 0.7469955111
USD 20,256,697.9 USD 25,839,283.7 21,150,558.8 USD 26,157,881.1 USD 0.7575341161
USD 20,256,697.9 USD 27,870,088.4 21,150,558.8 USD 28,213,725.6 USD 0.7673743997
USD 20,256,697.9 USD 29,946,510.4 21,150,558.8 USD 30,315,749.8 USD 0.7765234396
USD 20,256,697.9 USD 32,068,549.8 21,150,558.8 USD 32,463,953.8 USD 0.785143569
USD 20,256,697.9 USD 34,236,206.5 21,150,558.8 USD 34,658,337.6 USD 0.7931788031
USD 20,256,697.9 USD 36,449,480.5 21,150,558.8 USD 36,898,901.3 USD 0.8007252956
USD 20,256,697.9 USD 38,708,371.9 21,150,558.8 USD 39,185,644.7 USD 0.8077768517
USD 20,256,697.9 USD 41,012,880.6 21,150,558.8 USD 41,518,567.9 USD 0.8144601493
USD 20,256,697.9 USD 43,363,006.6 21,150,558.8 USD 43,897,670.9 USD 0.8207184726
USD 20,256,697.9 USD 45,758,750.0 21,150,558.8 USD 46,322,953.7 USD 0.8266252153
USD 20,256,697.9 USD 48,200,110.8 21,150,558.8 USD 48,794,416.4 USD 0.832206198
USD 20,256,697.9 USD 50,687,088.8 21,150,558.8 USD 51,312,058.8 USD 0.8374849148
USD 20,256,697.9 USD 53,219,684.2 21,150,558.8 USD 53,875,881.0 USD 0.8424469316
USD 20,256,697.9 USD 55,797,897.0 21,150,558.8 USD 56,485,883.0 USD 0.8472354705
USD 20,256,697.9 USD 58,421,727.1 21,150,558.8 USD 59,142,064.9 USD 0.8516946474
USD 20,256,697.9 USD 61,091,174.5 21,150,558.8 USD 61,844,426.5 USD 0.8559290568
USD 20,256,697.9 USD 63,806,239.3 21,150,558.8 USD 64,592,967.9 USD 0.8599223242
USD 6,752,232.6 USD 22,188,973.8 7,050,186.3 USD 22,462,563.0 USD 1.8263179345
USD 675,223,262.7 USD 943,675,039.7 USD 705,018,626.7 USD 955,310,518.7
COSTOS MINA (USD/ton)
N° perforadoras Perforación Tronadura Carguío Transporte Costo mina Total servicios mina
1 0.036 0.3 5.26054925 5.39830946 11.756 2.351
1 0.036 0.3 5.260549172 5.398308514 11.118 2.224
1 0.037 0.4 5.260549172 5.398308406 11.097 2.219
1 0.037 0.4 5.26054918 5.398308379 11.118 2.224
1 0.038 0.4 5.260549178 5.398308368 11.147 2.229
1 0.039 0.5 5.260549176 5.398308361 11.179 2.236
1 0.039 0.5 5.260549175 5.398308394 11.214 2.243
1 0.040 0.5 5.260549175 5.398308386 11.250 2.250
1 0.040 0.6 5.260549177 5.398308379 11.287 2.257
1 0.041 0.6 5.260549176 5.398308375 11.326 2.265
1 0.041 0.7 5.260549176 5.398308371 11.367 2.273
1 0.041 0.7 5.260549175 5.398308368 11.408 2.282
1 0.042 0.7 5.260549177 5.398308382 11.450 2.290
1 0.042 0.8 5.260549176 5.398308378 11.494 2.299
1 0.042 0.8 5.260549176 5.398308376 11.538 2.308
1 0.043 0.9 5.260549177 5.398308373 11.584 2.317
1 0.043 0.9 5.260549176 5.398308371 11.631 2.326
1 0.043 1.0 5.260549176 5.39830838 11.679 2.336
1 0.044 1.0 5.260549176 5.398308378 11.728 2.346
1 0.044 1.1 5.260549177 5.398308376 11.778 2.356
1 0.044 1.1 5.260549176 5.398308374 11.829 2.366
1 0.044 1.2 5.260549176 5.39830838 11.881 2.376
1 0.045 1.2 5.260549177 5.398308378 11.935 2.387
1 0.045 1.3 5.260549176 5.398308377 11.989 2.398
1 0.045 1.3 5.260549176 5.398308375 12.044 2.409
1 0.045 1.4 5.260549177 5.398308374 12.101 2.420
1 0.045 1.4 5.260549176 5.398308379 12.159 2.432
1 0.046 1.5 5.260549176 5.398308377 12.218 2.444
1 0.046 1.6 5.260549177 5.398308376 12.277 2.455
1 0.046 1.6 5.260549176 5.398308375 12.338 2.468
1 0.046 1.7 5.260549176 5.398308379 12.400 2.480
2 0.046 1.8 5.260549176 5.398308378 12.463 2.493
2 0.046 1.8 5.260549176 5.398308376 12.526 2.505
2 0.046 3.0 5.260549177 5.398308382 13.736 2.747
Ley CC Costo Rampa (estimado) utilidades
0.49 0.752 390,567,926
0.47 0.091 388,752,669
0.47 0.038 385,565,403
0.47 0.025 382,238,469
0.47 0.020 378,771,065
0.47 0.016 375,159,082
0.47 0.014 371,399,606
0.47 0.013 367,488,649
0.48 0.012 363,424,355
0.48 0.011 359,200,691
0.48 0.010 354,817,015
0.48 0.010 350,267,541
0.48 0.009 345,550,318
0.48 0.009 340,658,448
0.48 0.008 335,590,980
0.48 0.008 330,342,266
0.49 0.008 324,908,072
0.49 0.008 319,284,062
0.49 0.007 313,467,712
0.49 0.007 307,450,735
0.49 0.007 301,232,394
0.49 0.007 294,806,046
0.49 0.007 288,169,068
0.50 0.007 281,312,190
0.50 0.007 274,234,879
0.50 0.007 266,929,798
0.50 0.007 259,374,086
0.50 0.006 251,597,096
0.51 0.006 243,579,045
0.51 0.006 235,308,298
0.51 0.006 226,786,280
0.51 0.006 218,003,798
0.51 0.006 208,958,092
0.55 0.029 54,854,736
Costos valor [USD] vida
Perforadora 1,081,739.90 30,000 h
H banco [m] 15
Tricono 3,211.41 5,884 m Res. Com Sim [MPa] 170
Estabilizador 1,906.56 11,000 m
Barra 2,183.76 30,000 m
Energía USD/kWh 0.3 - -
Mano de obra/mes 5,979.07 - -

Costos indirectos (CI) Costos producción (CP)


Amortización 36.06 USD/h Tricono 0.55 USD/m
Int. seg. imp. 30.91 USD/h Estabilizador 0.17 USD/m
Total CI 66.96 USD/h Barra 0.07 USD/m
Total CP 0.79 USD/m
Costos directos (CD)
Mantenimiento 54.09 USD/h
COSTO TOTAL 7.29 USD/m
Mano de obra 33.22 USD/h
Energía 55.5 USD/h
Aceites y grasas 11.1 USD/h
Total CD 153.90 USD/h

Velocidad de penetración [m/h] 34


Velocidad de rotación rpm 60
Velocidad media [m/h] 19.8
diámetro [pulg] 13.4 341mm
empuje sobre el tricono [klib] 39
Vida del tricono [m] 5884
Ø [mm] 341
H banco [m] 15
Diámetro [m] 0.341
Burden [m] 7.8
Espaciamiento [m] 9.2
Sobreperforación [m] 1.7
Longitud de barreno [m] 16.7
Retacado [m] 10.9
Volumen arrancado [m3] 1083
Rendimiento [m3/mb] 64.8

Amortización Camion
Tipo Maquinaría Camión
precio de adquisicion 136,364 USD
valor residual 0.00
horas de vida 120,000.00 h
costos de amortizacion 1.14 USD/h
Volumen Mineral (m3) Volumen Estéril (m3)
98,174,770.4 151,406,715.0

Masa Mineral (toneladas) Masa Estéril (toneladas)


294,524,311.3 317,954,101.6

Volumen suelto mineral (m3) Volumen suelto estéril (m3)


117,809,724.5 181,688,058.0

ROP A UTILIZAR (t/año) (mackenzie)


14,228,659.0
1,646.8 t/h

Mineral
Capacidad del Cazo Pala Cable (m3)
36.3 108.9817936279
Tiempo de Ciclo
3 min
726.5 m3/h

Equipos a Utilizar Precios


1 Pala Cable Eléctrica 25,000,000.0 USD
1 Pala Hidráulica 10,000,000.0 USD
2 Cargadores Frontales 5,000,000.0 USD

AMORTIZACIÓN
Tipo Maquinaría
Precio de Adquisición
Valor Residual
Horas de Vida
Ca

COSTOS DE INTERÉS, SEGUROS E


n=número de años de vida
precio de adquisición
horas de trabajo al año
impuesto
seguro
interes
Ci

MANTENIMIENTO Y REPARA
precio del equipo
factor de reparacion
Cm

MANO DE OBRA DE MANTE


pago
horas
costo de total
Co

COMBUSTIBLE O ENERG
potencia (HP)
Precio combustible
Factor de combustible
Ce

ACEITES, GRASAS O FILTR


15% del valor de combustible
Cl
Costo Total Carguío
1,653,235,663.2 USD

Subnivel Volumen Mineral (m3)


1 2,945,243.1
2 2,945,243.1
3 2,945,243.1
4 2,945,243.1
5 2,945,243.1
6 2,945,243.1
7 2,945,243.1
8 2,945,243.1
9 2,945,243.1
10 2,945,243.1
11 2,945,243.1
12 2,945,243.1
13 2,945,243.1
14 2,945,243.1
15 2,945,243.1
16 2,945,243.1
17 2,945,243.1
18 2,945,243.1
19 2,945,243.1
20 2,945,243.1
21 2,945,243.1
22 2,945,243.1
23 2,945,243.1
24 2,945,243.1
25 2,945,243.1
26 2,945,243.1
27 2,945,243.1
28 2,945,243.1
29 2,945,243.1
30 2,945,243.1
31 2,945,243.1
32 2,945,243.1
33 2,945,243.1
34 981,747.7
TOTAL 98,174,770.4
Esponjamiento Densidad mineral
20% Densidad estéril

658.7 m3/h

Estéril
Capacidad Pala Hidráulica (m3)
15.49
Tiempo de Ciclo
3 min
309.7 m3/h
738.6

CARGUIO

AMORTIZACIÓN
Pala Cable
25,000,000 USD
2,043,651
180,000 h
127.54 USD/h

TOS DE INTERÉS, SEGUROS E IMPUESTOS


30.00
25,000,000 USD
6,000 h
19%
2%
10%
667.36 USD/h

MANTENIMIENTO Y REPARACIÓN
25,000,000.00 USD
15%
3,750 USD/h

MANO DE OBRA DE MANTENCIÓN


6,000.00 USD
180.00 h
133.33
33.33 US$/h

COMBUSTIBLE O ENERGÍA
3,000.00 HP
0.60 US$
0.70
277.20 U$$/h

ACEITES, GRASAS O FILTROS


15%
41.58 USD/h
Costo Total Carguío

1.65 GIGADOLARES

Volumen Estéril (m3) Masa Mineral (t) Masa Estéril


15,487.6 8,835,729.3 32,523.9
136,584.8 8,835,729.3 286,828.1
352,629.4 8,835,729.3 740,521.8
575,993.0 8,835,729.3 1,209,585.4
806,675.7 8,835,729.3 1,694,018.9
1,044,677.3 8,835,729.3 2,193,822.3
1,289,997.9 8,835,729.3 2,708,995.7
1,542,637.6 8,835,729.3 3,239,539.0
1,802,596.3 8,835,729.3 3,785,452.2
2,069,874.0 8,835,729.3 4,346,735.4
2,344,470.7 8,835,729.3 4,923,388.5
2,626,386.4 8,835,729.3 5,515,411.5
2,915,621.2 8,835,729.3 6,122,804.5
3,212,174.9 8,835,729.3 6,745,567.3
3,516,047.7 8,835,729.3 7,383,700.2
3,827,239.5 8,835,729.3 8,037,202.9
4,145,750.3 8,835,729.3 8,706,075.6
4,471,580.1 8,835,729.3 9,390,318.2
4,804,728.9 8,835,729.3 10,089,930.8
5,145,196.8 8,835,729.3 10,804,913.2
5,492,983.6 8,835,729.3 11,535,265.6
5,848,089.5 8,835,729.3 12,280,988.0
6,210,514.4 8,835,729.3 13,042,080.2
6,580,258.3 8,835,729.3 13,818,542.4
6,957,321.2 8,835,729.3 14,610,374.6
7,341,703.2 8,835,729.3 15,417,576.6
7,733,404.1 8,835,729.3 16,240,148.6
8,132,424.1 8,835,729.3 17,078,090.6
8,538,763.1 8,835,729.3 17,931,402.4
8,952,421.0 8,835,729.3 18,800,084.2
9,373,398.1 8,835,729.3 19,684,135.9
9,801,694.1 8,835,729.3 20,583,557.6
10,237,309.1 8,835,729.3 21,498,349.2
3,560,081.1 2,945,243.1 7,476,170.2
151,406,715.0
3.0 ton/m3
2.1 ton/m3

Estéril
Capacidad Cargadores Frontales (m3)
7.1
Tiempo de Ciclo
2 min
428.8 m3/h
738.6 m3/h

CARGUIO

TRABAJO
Rendimiento Efectivo Estéril
Rendimiento Efectivo Estéril
DATOS MINERAL
Volumen a remover
Densidad de material
Densidad Real
toneladas a remover
Costo Total Estéril
Costo total Estéril
Costo Total Estéril
Costo Total Estéril

Costo Total Estéril

Costos
Costo Total Estéril
Costo total Estéril
Costo Total Estéril
Carguío Mineral (USD) Carguío Estéril
20,256,697.9 96,529.7 USD
20,256,697.9 USD 851,294.4 USD
20,256,697.9 USD 2,197,839.0 USD
20,256,697.9 USD 3,590,000.9 USD
20,256,697.9 USD 5,027,780.2 USD
20,256,697.9 USD 6,511,176.8 USD
20,256,697.9 USD 8,040,190.7 USD
20,256,697.9 USD 9,614,822.0 USD
20,256,697.9 USD 11,235,070.6 USD
20,256,697.9 USD 12,900,936.5 USD
20,256,697.9 USD 14,612,419.8 USD
20,256,697.9 USD 16,369,520.5 USD
20,256,697.9 USD 18,172,238.4 USD
20,256,697.9 USD 20,020,573.7 USD
20,256,697.9 USD 21,914,526.4 USD
20,256,697.9 USD 23,854,096.4 USD
20,256,697.9 USD 25,839,283.7 USD
20,256,697.9 USD 27,870,088.4 USD
20,256,697.9 USD 29,946,510.4 USD
20,256,697.9 USD 32,068,549.8 USD
20,256,697.9 USD 34,236,206.4 USD
20,256,697.9 USD 36,449,480.5 USD
20,256,697.9 USD 38,708,371.9 USD
20,256,697.9 USD 41,012,880.6 USD
20,256,697.9 USD 43,363,006.6 USD
20,256,697.9 USD 45,758,750.0 USD
20,256,697.9 USD 48,200,110.7 USD
20,256,697.9 USD 50,687,088.8 USD
20,256,697.9 USD 53,219,684.2 USD
20,256,697.9 USD 55,797,897.0 USD
20,256,697.9 USD 58,421,727.1 USD
20,256,697.9 USD 61,091,174.5 USD
20,256,697.9 USD 63,806,239.3 USD
6,752,232.6 USD 22,188,973.8 USD
675,223,262.83 USD 943,675,039.7 USD

1,618,898,302.5 USD
TRABAJO
726.5 m3/h
1271.5 ton/h
DATOS MINERAL
151,406,715.04 m3
2.1 ton/m3
1.75 ton/m3
264961751.315237 ton
4,997.01 USD/h
6.8777676781 USD/m3
3.93 USD/t
1,041,340,210.9 USD
1,041,340,210.9 USD

Costos
4997.0097180763 USD/h
6.8777676781 USD/m3
3.9301529589 USD/t
CARGUIO

AMORTIZACIÓN
Tipo Maquinaría Pala Hidráulica
Precio de Adquisición 10,000,000 USD
Valor Residual 442,537
Horas de Vida 100,000 h
Ca 95.57 USD/h

COSTOS DE INTERÉS, SEGUROS E IMPUESTOS


n=número de años de vida 20.00
precio de adquisición 10,000,000 USD
horas de trabajo al año 5,000 h
impuesto 19%
seguro 2%
interes 10%
Ci 325.50 USD/h

MANTENIMIENTO Y REPARACIÓN
precio del equipo 10,000,000.00 USD
factor de reparacion 15%
Cm 1,500 USD/h

MANO DE OBRA DE MANTENCIÓN


pago 6,000.00 USD
horas 180.00 h
costo de total 133.33
Co 33.33 US$/h

COMBUSTIBLE O ENERGÍA
potencia (HP) 1,530.00 HP
Precio combustible 0.60 US$
Factor de combustible 0.70
Ce 141.37 U$$/h

ACEITES, GRASAS O FILTROS


15% del valor de combustible 15%
Cl 21.21 USD/h
CARGUIO

TRABAJO
Rendimiento Efectivo Estéril 309.7 m3/h
Rendimiento Efectivo Estéril 774.3 ton/h
DATOS ESTERIL
Volumen a remover 49,087,385.21 m3
Densidad de material 3.0 ton/m3
Densidad Real 2.5 ton/m3
toneladas a remover 122718463.030851 ton
Costo Total Estéril 2,216.99 USD/h
Costo total Estéril 7.1575947549 USD/m3
Costo Total Estéril 2.86 USD/t
Costo Total Estéril 351,347,610.9 USD
Costo Total Estéril 351,347,610.9 USD
Costo Total Estéril 2,217.0 USD/h
Costo total Estéril 7.2 USD/m3
Costo Total Estéril 2.9 USD/t
Costo Total Estéril 351,347,610.9 USD

Costo Total Estéril 1,138.1 USD/h


Costo total Estéril 5.3 USD/m3
Costo Total Estéril 2.1 USD/t
Costo Total Estéril 130,273,920.7 USD

Costo Total Estéril 1,138.1 USD/h


Costo total Estéril 5.3 USD/m3
Costo Total Estéril 2.1 USD/t
Costo Total Estéril 130,273,920.7 USD

Costo Total Estéril 4,997.0 USD/h


Costo total Estéril 6.9 USD/m3
Costo Total Estéril 3.9 USD/t
Costo Total Estéril 1,041,340,210.9 USD
AMORTIZACIÓN
Tipo Maquinaría Cargador Frontal
Precio de Adquisición 5,000,000
Valor Residual 138,579
Horas de Vida 75,000
Ca 64.82

COSTOS DE INTERÉS, SEGUROS E IMPUESTOS


n=número de años de vida 15.00
precio de adquisición 5,000,000
horas de trabajo al año 6,000
impuesto 19%
seguro 2%
interes 10%
Ci 137.78

MANTENIMIENTO Y REPARACIÓN
precio del equipo 5,000,000.00
factor de reparacion 15%
Cm 750

MANO DE OBRA DE MANTENCIÓN


pago 5,000.00
horas 180.00
costo de total 111.11
Co 27.78

COMBUSTIBLE O ENERGÍA
potencia (HP) 700.00
Precio combustible 0.60
Factor de combustible 0.70
Ce 64.68

ACEITES, GRASAS O FILTROS


15% del valor de combustible 15%
Cl 9.70

Costos
Costo Total Estéril 4,493.2 USD/h
Costo total Estéril 17.8 USD/m3
Costo Total Estéril 7.1 USD/t
Costo Total Estéril 611,895,452.3 USD
CARGUIO

N TRABAJO
argador Frontal Rendimiento Efectivo Estéril 214.4 m3/h
USD Rendimiento Efectivo Estéril 536.0 ton/h
h
USD/h

S E IMPUESTOS

USD
h

DATOS ESTERIL
Volumen a remover 24,543,692.61 m3
USD/h Densidad de material 3.0 ton/m3
Densidad Real 2.5 ton/m3
ARACIÓN toneladas a remover 61359231.51543 ton
USD Costo Total Estéril 1,138.09 USD/h
Costo total Estéril 5.3078370384 USD/m3
USD/h Costo Total Estéril 2.12 USD/t
Costo Total Estéril 130,273,920.7 USD
NTENCIÓN Costo Total Estéril 130,273,920.7 USD
USD
h

US$/h

HP
US$

U$$/h

LTROS

USD/h
AMORTIZACIÓN
Tipo Maquinaría
Precio de Adquisición
Valor Residual
Horas de Vida
Ca

COSTOS DE INTERÉS, SEGUROS E IMP


n=número de años de vida
precio de adquisición
horas de trabajo al año
impuesto
seguro
interes
Ci

MANTENIMIENTO Y REPARACIÓ
precio del equipo
factor de reparacion
Cm

MANO DE OBRA DE MANTENCI


pago
horas
costo de total
Co

COMBUSTIBLE O ENERGÍA
potencia (HP)
Precio combustible
Factor de combustible
Ce

ACEITES, GRASAS O FILTROS


15% del valor de combustible
Cl
CARGUIO

ORTIZACIÓN TRABAJO
Cargador Frontal Rendimiento Efectivo Estéril
5,000,000 USD Rendimiento Efectivo Estéril
138,579
75,000 h
64.82 USD/h

ÉS, SEGUROS E IMPUESTOS


15.00
5,000,000 USD
6,000 h
19%
2% DATOS ESTERIL
10% Volumen a remover
137.78 USD/h Densidad de material
Densidad Real
IENTO Y REPARACIÓN toneladas a remover
5,000,000.00 USD Costo Total Estéril
15% Costo total Estéril
750 USD/h Costo Total Estéril
Costo Total Estéril
BRA DE MANTENCIÓN Costo Total Estéril
5,000.00 USD
180.00 h
111.11
27.78 US$/h

E O ENERGÍA
700.00 HP
0.60 US$
0.70
64.68 U$$/h

GRASAS O FILTROS
15%
9.70 USD/h
TRABAJO
214.4 m3/h
536.0 ton/h
DATOS ESTERIL
24,543,692.61 m3
3.0 ton/m3
2.5 ton/m3
61359231.515426 ton
1,138.09 USD/h
5.3078370384 USD/m3
2.12 USD/t
130,273,920.7 USD
130,273,920.7 USD
Volumen Mineral (m3)
981,747.7

Masa Mineral (toneladas)


2,945,243.1

Volumen suelto mineral (m3)


1,178,097.2

ROP A UTILIZAR (t/año) (mackenzie)


14,228,659.0
1,646.8

Mineral
Capacidad del Cazo Pala Cable (m3)
36.3
Tiempo de Ciclo
3
726.5

Capacidad del Volquete Mineral


263.372667934

Numero de Ciclos por hora Pala Cable (Ciclos/hora)


Tiempo de Carga
Tiempo de Levante
Tiempo de Descarga
Tiempo de Regreso
Tiempo del Ciclo
Ciclos por hora
Rendimiento Efectivo Pala Cable (Ton/h)
Capacidad del Balde
Ciclos por Hora
Rendimiento Efectivo

Numero de Pases
Capacidad Nominal Camion (ton)
Capacidad Nominal Pala (ton)
Nº de Pases
Nº de Pases
Tiempo de Ciclo de equipo de carguío
Tiempo de Carga (min)

Rendimiento Horario Camión (ton/hora)


NC (vueltas/hora)

Capacidad de Tolva o factor de carga (ton / vueltas)


Tiempo de Carga
Tiempo de Viaje Ida
Tiempo de Descarga
Tiempo de Regreso
Tiempo de Espera

Rendimiento Horario Camión (ton/hora)

Veocidad
cargado
30
descargado
50
distancia
2
regreso
0.04
ida
0.0666666667

Número de Camiones
Rendimiento Hr Pala
Rendimiento Hr Camión
# Camiones
Costo Total
Costo Total Mineral
Costo Total Estéril

COSTO TOTAL (material)

Subnivel
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
TOTAL
Volumen Estéril (m3) Esponjamiento
3,560,081.1 20%

Masa Estéril (toneladas)


7,476,170.2

Volumen suelto estéril (m3)


4,272,097.3

t/h 658.7

min
m3/h

ton

a)
3
0.5
0.5
2
6
10

130.7781523534
10
1307.7815235345

263.372667934
130.7781523534
3
3
6
12

263.372667934
12
4
1.5
2
4

661

km/h

km/h

km

h
h

amiones
1307.7815235345
661
2

TRANSPORTE

Amortización
Tipo Maquinaría Camión
precio de adquisicion 5,000,000
valor residual 286,716.67
horas de vida 40,000.00
costos de amortizacion 117.83

Costos de interes seguros e impuestos


n=numero de años de vida 10.00
precio de adquisicion 5,000,000
horas de trabajo al año 4,000.00
impuesto 19%
seguro 2%
interes 10%
Costos de interes seguros e impuestos 213.13

mantenimiento y reparacion
precio del equipo 5,000,000
factor de reparacion 15%

mantencion 750.00

mano de obra mantencion


pago 5,000.00
horas 180.00
costo de total 55.56
27.78

combustible o energia
potencia (HP) 3,500
precio combustible 0.60
factor de energia 0.70
combustible (U$$/h) 323.40

Aceites, grasas y filtros


15% del valor de combustible 15%
aceites, grasas y filtros 48.51

Neumaticos
valor neumatico 41,791
n° neumatico 8
horas 4,500.00
costo us$/h 74.30

costo total 1,582.72

Costo Total
2.39 USD/ton
2.41 USD/ton

4.80 USD/ton

Volumen Mineral (m3) Volumen Estéril (m3)


2,945,243.1 15,487.6
2,945,243.1 136,584.8
2,945,243.1 352,629.4
2,945,243.1 575,993.0
2,945,243.1 806,675.7
2,945,243.1 1,044,677.3
2,945,243.1 1,289,997.9
2,945,243.1 1,542,637.6
2,945,243.1 1,802,596.3
2,945,243.1 2,069,874.0
2,945,243.1 2,344,470.7
2,945,243.1 2,626,386.4
2,945,243.1 2,915,621.2
2,945,243.1 3,212,174.9
2,945,243.1 3,516,047.7
2,945,243.1 3,827,239.5
2,945,243.1 4,145,750.3
2,945,243.1 4,471,580.1
2,945,243.1 4,804,728.9
2,945,243.1 5,145,196.8
2,945,243.1 5,492,983.6
2,945,243.1 5,848,089.5
2,945,243.1 6,210,514.4
2,945,243.1 6,580,258.3
2,945,243.1 6,957,321.2
2,945,243.1 7,341,703.2
2,945,243.1 7,733,404.1
2,945,243.1 8,132,424.1
2,945,243.1 8,538,763.1
2,945,243.1 8,952,421.0
2,945,243.1 9,373,398.1
2,945,243.1 9,801,694.1
2,945,243.1 10,237,309.1
981,747.7 3,560,081.1
98,174,770.4 151,406,715.0
Densidad mineral
Densidad estéril

m3/h

Estéril
Capacidad Pala Hidráulica (m3)
15.49
Tiempo de Ciclo
3 min
309.7 m3/h
738.6

Capacidad del Volquete Estéril


39.3097605334 ton

Numero de Ciclos por hora CargadorFrontal (Ciclos/hora)


Tiempo de Carga 2
Tiempo de Levante 0.5
Tiempo de Descarga 0.5
Tiempo de Regreso 1
Tiempo del Ciclo 4
Ciclos por hora 15
Rendimiento Efectivo Cargador Frontal (Ton/h)
Capacidad del Balde 18.0110175535
Ciclos por Hora 15
Rendimiento Efectivo 270.1652633026

Numero de Pases
Capacidad Nominal Camion (ton) 27
Capacidad Nominal Pala (ton) 10
Nº de Pases 3
Nº de Pases 3
Tiempo de Ciclo de equipo de carguío 4
Tiempo de Carga (min) 12

Rendimiento Horario Camión (ton/hora)


NC (vueltas/hora) 3
Capacidad de Tolva o factor de carga
(ton / vueltas) 39.3097605334
Tiempo de Carga 12
Tiempo de Viaje Ida 0.3
Tiempo de Descarga 1.5
Tiempo de Regreso 0
Tiempo de Espera 4

Rendimiento Horario Camión (ton/hora) 131

Veocidad
cargado
40 km/h
descargado
60 km/h
distancia
0.2 km
regreso
0.0033333333 h
ida
0.005 h

Número de Camiones
Rendimiento Hr Pala 270.1652633026
Rendimiento Hr Camión 131
# Camiones 2.0618181818

TRANSPORTE

mortización

USD

h
USD/h

es seguros e impuestos

USD
h

USD/h

iento y reparacion
USD

USD/h

obra mantencion
USD
h

USD/h

stible o energia
USD/L

U$$/h

grasas y filtros

USD/h

eumaticos
USD

USD/h

USD/h

Costo Total Transporte


1,660,329,145.4 USD

Masa Mineral (t) Masa Estéril


8,835,729.3 32,523.9
8,835,729.3 286,828.1
8,835,729.3 740,521.8
8,835,729.3 1,209,585.4
8,835,729.3 1,694,018.9
8,835,729.3 2,193,822.3
8,835,729.3 2,708,995.7
8,835,729.3 3,239,539.0
8,835,729.3 3,785,452.2
8,835,729.3 4,346,735.4
8,835,729.3 4,923,388.5
8,835,729.3 5,515,411.5
8,835,729.3 6,122,804.5
8,835,729.3 6,745,567.3
8,835,729.3 7,383,700.2
8,835,729.3 8,037,202.9
8,835,729.3 8,706,075.6
8,835,729.3 9,390,318.2
8,835,729.3 10,089,930.8
8,835,729.3 10,804,913.2
8,835,729.3 11,535,265.6
8,835,729.3 12,280,988.0
8,835,729.3 13,042,080.2
8,835,729.3 13,818,542.4
8,835,729.3 14,610,374.6
8,835,729.3 15,417,576.6
8,835,729.3 16,240,148.6
8,835,729.3 17,078,090.6
8,835,729.3 17,931,402.4
8,835,729.3 18,800,084.2
8,835,729.3 19,684,135.9
8,835,729.3 20,583,557.6
8,835,729.3 21,498,349.2
2,945,243.1 7,476,170.2
3.0 ton/m3
2.1 ton/m3

Estéril
Capacidad Cargadores Frontales (m3)
7.1
Tiempo de Ciclo
2 min
428.8 m3/h
m3/h
CAMIÓN
Distancia 0.20 km
Distancia Total Recorrida 0.40 km

capacidad 240.00 ton


Esponjamiento 20%
Capacidad Real 192.00 ton
tiempo ida/vuelta 0.11 h
Rendimiento Nominal 661.99 ton/h
Disponibilidad Física 80%
Rendimiento efectivo 661.19 ton/h

COSTO TOTAL 2.39 USD/ton


Costo Total Carguío

1.66 GIGADOLARES

Transporte Mineral Transporte Estéril


21,150,558.8 USD 97,719.9 USD
21,150,558.8 USD 861,790.9 USD
21,150,558.8 USD 2,224,938.3 USD
21,150,558.8 USD 3,634,265.5 USD
21,150,558.8 USD 5,089,772.5 USD
21,150,558.8 USD 6,591,459.3 USD
21,150,558.8 USD 8,139,326.0 USD
21,150,558.8 USD 9,733,372.4 USD
21,150,558.8 USD 11,373,598.6 USD
21,150,558.8 USD 13,060,004.6 USD
21,150,558.8 USD 14,792,590.4 USD
21,150,558.8 USD 16,571,356.0 USD
21,150,558.8 USD 18,396,301.5 USD
21,150,558.8 USD 20,267,426.7 USD
21,150,558.8 USD 22,184,731.7 USD
21,150,558.8 USD 24,148,216.5 USD
21,150,558.8 USD 26,157,881.1 USD
21,150,558.8 USD 28,213,725.6 USD
21,150,558.8 USD 30,315,749.8 USD
21,150,558.8 USD 32,463,953.8 USD
21,150,558.8 USD 34,658,337.6 USD
21,150,558.8 USD 36,898,901.3 USD
21,150,558.8 USD 39,185,644.7 USD
21,150,558.8 USD 41,518,567.9 USD
21,150,558.8 USD 43,897,670.9 USD
21,150,558.8 USD 46,322,953.7 USD
21,150,558.8 USD 48,794,416.4 USD
21,150,558.8 USD 51,312,058.8 USD
21,150,558.8 USD 53,875,881.0 USD
21,150,558.8 USD 56,485,883.0 USD
21,150,558.8 USD 59,142,064.9 USD
21,150,558.8 USD 61,844,426.5 USD
21,150,558.8 USD 64,592,967.9 USD
7,050,186.3 USD 22,462,563.0 USD
705,018,626.70 USD 955,310,518.7 USD

1,660,329,145.4 USD
dd
TRANSPORTE

Amortización
Tipo Maquinaría Camión
precio de adquisicion 300,000 USD
valor residual 12,000.00
horas de vida 50,000.00 h
costos de amortizacion 5.76 USD/h

Costos de interes seguros e impuestos


n=numero de años de vida 20.00
precio de adquisicion 300,000 USD
horas de trabajo al año 4,000.00 h
impuesto 19%
seguro 2%
interes 10%
Costos de interes seguros e impuestos 12.21 USD/h

mantenimiento y reparacion
precio del equipo 300,000 USD
factor de reparacion 15%

mantencion 45.00 USD/h

mano de obra mantencion


pago 4,000.00 USD
horas 180.00 h
costo de total 44.44
22.22 USD/h

combustible o energia
potencia (HP) 470
precio combustible 0.60 USD/L
factor de energia 0.70
combustible (U$$/h) 43.43 U$$/h

Aceites, grasas y filtros


15% del valor de combustible 15%
aceites, grasas y filtros 6.51 USD/h

Neumaticos
valor neumatico 746 USD
n° neumatico 8
horas 4,500.00
costo us$/h 1.33 USD/h

costo total 158.68 USD/h


PORTE

CAMIÓN
Distancia 0.20 km
Distancia Total Recorrida 0.40 km

capacidad 40.00 ton


Esponjamiento 20%
Capacidad Real 32.00 ton
tiempo ida/vuelta 0.01 h
Rendimiento Nominal 131.03 ton/h
Disponibilidad Física 80%
Rendimiento efectivo 131.83 ton/h

COSTO TOTAL 1.20 USD/ton


Subnivel Ley CC Subnivel Ley CC Subnivel Ley CC
1 0.47 1 0.47 9 0.46
2 0.45 2 0.45 10 0.46
3 0.45 3 0.45 11 0.46
4 0.45 4 0.45 12 0.46
5 0.45 5 0.45 13 0.46
6 0.45 6 0.45 14 0.46
7 0.46 7 0.46 15 0.46
8 0.46 8 0.46 16 0.47
9 0.46
10 0.46
11 0.46
12 0.46 78,294.50
13 0.46 690,478.60
14 0.46 1,782,650.90
15 0.46 2,911,823.20
16 0.47 4,077,995.30
17 0.47 5,281,167.30
18 0.47 6,521,339.10
19 0.47 7,798,510.90
20 0.47 9,112,682.60
21 0.47 10,463,854.10
22 0.48 11,852,025.50
23 0.48 13,277,196.80
24 0.48 14,739,368.00
25 0.48 16,238,539.10
26 0.48 17,774,710.10
27 0.48 19,347,881.00
28 0.49 20,958,051.70
29 0.49 22,605,222.40
30 0.49 24,289,392.90
31 0.49 26,010,563.30
32 0.49 27,768,733.60
33 0.49 29,563,903.80
34 0.53 31,396,073.80
33,265,243.80
35,171,413.60
37,114,583.40
39,094,753.00
41,111,922.50
43,166,091.90
45,257,261.10
47,385,430.30
49,550,599.30
51,752,768.30
17,997,312.40
Subnivel Ley CC Subnivel Ley CC Subnivel Ley CC
17 0.47 25 0.48 33 0.49
18 0.47 26 0.48 34 0.53
19 0.47 27 0.48
20 0.47 28 0.49
21 0.47 29 0.49
22 0.48 30 0.49
23 0.48 31 0.49
24 0.48 32 0.49