Progress Summary by Project Area-Piping Fabrication

Project
Quantity(Dia-inch) Man hour Weighting Progress by Area Weighting (Overall) Overall Progress
Area
A 1000 6000 0.43 100% 0.0869566478 8.7%
B 1500 8000 0.57 100% 0.115942197 11.6%
Total 2500 14000 1.00

Progress Summary by Project Area-Piping Erection


Project
Quantity (Dia-inch) Man hour Weighting Progress by Area
Area
A 300 4000 0.40 100% 0.0579768956 5.8%
B 450 6000 0.60 100% 0.0869551985 8.7%
Total 750 10000 1.00

Progress Summary by Project Area-Steel Fabrication


Project
Quantity (Tonage) Man hour Weighting Progress by Area
Area
A 100 4800 0.61 100% 0.0695653182 6.9%
B 70 3100 0.39 100% 0.0449276013 4.5%
Total 170 7900 1.00

Progress Summary by Project Area-Steel Erection


Project
Quantity (Tonage) Man hour Weighting Progress by Area
Area
A 100 4800 0.61 100% 0.0695653182 6.9%
B 70 3100 0.39 100% 0.0449276013 4.5%
Total 170 7900 1.00

Progress Summary by Project Area-Tie-in Installation


Project
Qty (Pcs) Man hour Weighting Progress by Area
Area
A 10 1500 0.45 100% 0.0217391619 2.2%
B 5 1800 0.55 100% 0.0260869943 2.6%
Total 15 3300 1.00

Progress Summary by Project Area-Piping Hydro Testing


Project
Quantity (Meter) Man hour Weighting Progress by Area
Area
A 5000 2800 0.44 92% 0.040579769 3.7%
B 7000 3500 0.56 52% 0.0507247112 2.6%
Total 12000 6300 1.00

Progress Summary by Project Area-Equipment Erection


Project
Quantity (Tonage) Man hour Weighting Progress by Area
Area
A 159 1600 0.44 80% 0.0231884394 1.8%
B 168 2000 0.56 89% 0.0289797521 2.6%
Total 327 3600 1.00

Progress Summary by Project Area-Painting


Project
Quantity (Tonage) Man hour Weighting Progress by Area
Area
A 300 2000 0.36 36% 0.0289797521 1.1%
B 450 3500 0.64 57% 0.0507305083 2.9%
Total 750 5500 1.00

Progress Summary by Project Area-Insulation


Project
Quantity (Tonage) Man hour Weighting Progress by Area
Area
A 2000 4500 0.43 100% 0.0652174858 6.5%
B 3000 6000 0.57 87% 0.0869566478 7.6%
Total 5000 10500 1.00

Progress Summary by Project Area-all disciplines


Project
Man hour Weighting(Overall) Overall Progress by Area
Area
A 32000 0.464 43.7%
B 37000 0.536 47.6%
Total 69000 1.000 91.3%