NKUMSC5-SIS&RNCSW upgrade
Problem Management completed
Total: 12
Regulatory KPI's Not meeting: 1
plan :1
Coverage KPI not met in some specific areas.
Last month
2G:31386
Short Duration 3G: 32812
Last week
2G :6533
3G: 6373 Increased due to planned BTS and WBTS software upgrades. (CR 567)
Transformation/Project
KPI WK 27 Summary Actions/Reasons[WK27]
Transmission 27/41 completed
Network All Alarms Last month/Last week 2802/18959 This is based on GDC Efficacy report.
TSK status -Wk 27 Count Rejection is mostly for CORE tasks, new
Acknowledged 50 escalation matrix reloaded on 07/07;
Assigned 69 issue solved
Closed 125
Executed 94 OpCo to follow agreed format for
Rejected 228 reporting work orders (Refer format
Total 566 used by other OpCos)
Planned Preventive Maintenance 240/562 for the month 42% done.
Software Upgrades 1 BSC & 3 clusters of BTS upgrade
planned and completed.
IP Training: Part1 target: 31, complete 31.
Trainings wk 28 target - Q&A session with IP
expert.
Customer Appreciation/Highlights
2 cases of abnormal throttling of User
Concerns/Escalation/Lowlights. data speeds in 3G reported (Christophe &
Gurpreet). So far problem seen on Gx
interface. Analysis ongoing by E//
,support and RFO expected by EOD 10th
Jul.
Total: 1609
Uploaded: 1609 Final list compiled
WK 26 Summary Actions/Reasons[WK26]
27/41 completed 14 raised to customer for support
Last month/Last week 1729/35563
Regulatory KPI's Total: 12/ Not meeting: 4/ plan :1 Which are the 4? Plan for all 4 not
meeting targets?
Short Duration Why not populated?
Transformation/Project
KPI WK 27 Summary Actions/Reasons[WK27]
13 actions in dependency with the
customer,
Transmission W26: 20/W27: 20 7 actions ongoing with Nokia. Nokia
Target week27
Network All Alarms Last month/Last week 12172/4748
Escalation matrix to align with GDC on
the "Open ticket" circle(Total167)
TTs/WO status <2 days 10, 3-7 days 55, >7 days 260
Data OK
FOE to create in advance monthly
schedule instead of weekly
Customer Appreciation/Highlights
Resolved/Total
Wk25:Active-26,Passive-23,resolved-47
Wk26:Active-29,Passive-7,resolved-47
WK 26
W25: 21/W26: 20
Link south backbone upgrade capacity impacting 2G/3G Gold and silver/ target of completion 17-07-2017
7 cells corrected, 4 cells waiting for swap to Flexi MR, 1 cell upgrade ongoing
Summary Actions/Reasons[WK26]
No SW upgrade planned
Spare part availability on the ground ( critical spare to be ordered still waiting for
Airtel group approval; faulty modules not sent for repair ).
/ target of completion 17-07-2017
Operations
KPI WK 27
Big Outages
Problem Management
Regulatory KPI's
Short Duration
Transformation/Project
KPI WK 27
Month/Completed.733/74
Planned Preventive Maintenance
Software Upgrades
Customer Appreciation/Highlights
Concerns/Escalation/Lowlights.
Support required
Summary Actions/Reasons[WK27] WK 26
Degradation contributed to mainly by failure in KHBSC33 Aters
Capacity Grow on 78 cells 2G/3G: 59/12
Software parameter optimizations on 108 Cells
Physical Optimization on 7 cells
Summary Actions/Reasons[WK27] WK 26
RAN Modernization Acceptance, RRU Swap, De-Grow affecting the
exercise
Total/Closed 4/2
10830/ 5690
BSS active alarms are tracked on daily basis and shared among
respective line of support teams for daily resolution.
Last month/Last week 3720/2600
Data not correct we currently have over 10K open WO's which are >7
days. OpCo team to provide correct report
AIRTEL MODERNIZATION,
No pending case(s)
Summary Actions/Reasons[WK26]
PM done accordingly but TT not closed due to some of FT having troubles with
mywfm. Their problem is under investigation
<2 days: Dispatched SMS not delivered to respective engineer, being worked
3-7 days: PM Schedule uploading altogether
Tool team is working on clearing all aging till March 17
A total of 632 Scheduled 484 PM were done up to 30thth More WO done than
planed in mywfm due to some of PM uploading failure.
RAN Modernization Acceptance, RRU Swap, Ge-Grow, WCL ,RSL Improvement
exercise hold down the pace
Slow pace due to accessibility of the Nokia Tools for remote engineers,
WIP to image FLM’s laptops ( Slow pace as they are still needed in Operation and
Maintenance
RAN modernization: DAR: CO-MPT (305 sites) and 3G sites rehoming (230 sites)
done. Physical acceptance done for 100 sites and accepted 95 so far and still in
progress
RAN Modernization/ Resource constrain
3 CRs were postponed and I failed hence fall back done.. More CR in PT4 as other
CRs were executed from vendor
Resource constraints to manage KPI trends and acceptance tests for the
modernization project
Data Charging OCS failing frequently no support from Huawei. Moving data
charging to Ericsson CCN by end of July 2017
Resolved/Total
Repeat Sites Active: 7. Closed 4/Pending 3. Passive: 2 Closed 1/Pending 1.
Problem Management
proactive actions pending. 6/6
Field Force KPI's Shared separately on Tuesday
a. Total 238
b. Uploaded Working 190. Faulty 48
Regulatory KPI's
Network Wide all Regulatory KPIs (CSSR/DCR/CBR) are meeting from OSS stats.
Short Duration
Transformation/Project
KPI WK 26
Transmission
Total 23. Closed: 19. Pending: 4
Network All Alarms Last Month ZTE: 274. Huawei: 406.
Last Week ZTE: 132. Pending 09; Huawei: 262. Pending: 11
TTs/WO status
<2 days. P1: 0; P2: 0; P3: 0; P4: 0; P5: 0
3-7 days. P1: 0; P2: 0; P3: 4; P4: 0; P5: 44
>7 days. P1: 0; P2: 0; P3: 1; P4: 2; P5: 74
Planned Preventive Maintenance Monthly PM Planned: 193. Done: 193. Pending: 0.
Software Upgrades
Core: Planned 0 / ompleted 0. TXN: Planned 0 / ompleted 0
Trainings
Total 0/Completed 0. (Include #of attendees)
Projects Status U900 integration of 605 sites completed. LTE1800 integration of 404 sites
completed.
TRM Indoor to Outdoor Site cutover: 43/57. Decomission of site material 37/63.
Return of material to WH: 22/63. Planned completion date 18th July.
Customer Appreciation/Highlights
Concerns/Escalation/Lowlights.
Support required
Summary Actions/Reasons[WK27]
2G: Main challenge is addressing CSSR (45) and DCR (137) which need physical site
audit for validation.
3G: CS Drop still the main challenge. Improvement obersered after change of T314
timers on ZTE RNCs
2G: High temp at Lira BSC.. Airocn was not running Adjusted the VMR voltage
settings. Also adjusted the temperature sensor settings to trigger high temperature
at 28degrees
Gi: RFO: Issue was At BCS end
Active:4 Rugarama changed xpic cables still monitoring. Kalyango and Hoima Airtel
hanged RRU still monitering, Piida Microwave passing over water escalated to Tx
Planning Team. Passive: 1 Kyebando Airtel No batt Backup pending Infra Team
Low traffic Cells should not be Zero Cells. As Zero cells are Cells without any traffic
as all. 3 Cells in 3G.
After refarming 4.2 MHz for U900, on the 15th July, 5MHz was refarmed for the LTE
1800. We expect degradation in 2G due to reduced sepectrum.
NO spare Returned to the warehouse due to the ongoing Audit. Site Returns will be
allowed after the Audit.
Old data already deleted from SPM module. Upload auntheticated spares data
and capture same in W28 report
Summary Actions/Reasons[WK27]
Dubai Zone<>Mengo pending LoS . 1 Rubindi<> Kyeshama need bigger antenna.
Pending customer. 1 Mabale to change ODU pending spare. Kabale RT poor LOS
planned to change to fiber, timeline pending customer.
WIP
Data from Input KPIs report of 05th July. Latest report
Data not correct we have WO's which are >7 days. OpCo team to provide correct
report
Just started on July to report starting next wee27.
Router and BSC / RNC Software updates planned for the next 3 weeks. Plan not yet
drafted
LTE Launch in Central region for 404 Huawei sites on July 4, 2017.
LTE compatible handsets and dongles for testing purposes (Airtel is issuing us 6 sim
cards and asked for extensive testing to be done and feedback shared daily for the
next few weeks)
Training for SLM / NPO engineers to support LTE (Discussion with Airtel ongoing to
have NOKIA engineers as part of Airtel team who will be receiving some LTE O&M
training from Huawei)
Delay in shipping the TEMS tool kit due to non payment for DHL services
3G ZTE expertise on complex faults, unlike Huawei where we have TAC, we don't
have the same for ZTE so resolving complex problems is always a challenge as ZTE
supports reluctantly and doesn't share findings
WK 26
2G: Improved cases (377), New cases
Added (296)
3G: Improved cases (814), New cases
Added (786)
Resolved/Total
Active: 10. Closed 5/Pending 5. Passive: 6
Closed 1/Pending 5.
a. Total 218
b. Uploaded Working 179. Faulty 39
WK 26
4 2G cell Nvara Ward and 1 cell Fairway Hot was an outage. Cells restored
3G 6Cells 2Labnum Apts was an outage, 2Hoima-Airtel. 1Bulisa, 1Dolwe low traffic
cells
After integration of U900, blocking was seen on the U900 band. This has been
cleared, but some cells are still loaded and Huawei are working on balancing traffic
to 2100.
70% of Faulty spares Returned to the warehouse. These were received manually.
The oracle system is till down.
Summary Actions/Reasons[WK26]
U900 integration of 605 sites completed, post optimization ongoing. AFP L1800
Refarming configuration plan shared for review.
TRM Indoor to Outdoor Site cutover: 36/57. Decomission of site material 18/63.
Return of material to WH: 5/63. Planned completion date 18th July.
LTE Launch in Central region for 404 Huawei sites on July 4, 2017.
LTE compatible handsets and dongles for testing purposes (Airtel is issuing us 6 sim
cards and asked for extensive testing to be done and feedback shared daily for the
next few weeks)
Training for SLM / NPO engineers to support LTE (Discussion with Airtel ongoing to
have NOKIA engineers as part of Airtel team who will be receiving some LTE O&M
training from Huawei)
Delay in shipping the TEMS tool kit due to non payment for DHL services
Operations
KPI WK 27
Total 3
Big Outages Passive-2, IPRAN-1
Total 3
Passive-2, IPRAN-1
Short Duration
Transformation/Project
KPI WK 27
Transmission
RSL Total: 32 Closed:17
Network All Alarms
TTs/WO status
Software Upgrades
Fortnightly Prediction in GDC Meeting on
subject Planned: 18 Completed 14
Trainings
Customer Appreciation/Highlights
Concerns/Escalation/Lowlights.
Support required
Summary Actions/Reasons[WK27]
WCL cell count impacted by Project activities, Power fluctuation @ Kasama, BSC07
SSN Congestion
3G RNA stable. 2G impacted by single site outages and RAN MOD project
Open cases on Passive: DG automation and TX faults. Ongoing active: BTS+ & FHY
IDU faults.
Locked /Halted cells signed off with customer: Due to projects, right sizing.
Operational related issues are resolved
Numbers not matching. 12 cases, 4 closed, 5 open makes total of 9.. not 12.
Upload all spares data into SPM and provide report for same
All KPIs are meeting the target
Summary Actions/Reasons[WK26]
RSL corrections ongoing. TX power adjustment and re-alignment. Faulty IDUs
replaced
Most of high ageing alarms due to Legacy BTS/Antenna line issues and FHY TX
frequent faults. Delay to close in PT4 by FM team
Data not correct. We currently have more than 2K WO's that are >7 days old.
2G Data KPIs
Monitoring traffic degradation at BTS level
Last month
2G:31386
3G: 32812
Last week
2G :7375
3G: 4272
WK 26
Total: 32 Closed:11
Last month/Last week 1729/35563
Month/Completed. 205/321
Planned: 18 Completed 14
Open cases mainly due to TX & BTS issues. Ongoing active issue on BTS+ & FHY IDU
faults.
Summary Actions/Reasons[WK26]
RSL corrections ongoing. TX power adjustment and re-alignment. Faulty IDUs being
replaced
Most of high ageing alarms due to Legacy BTS/Antenna line issues and FHY TX
frequent faults
Expected to complete the remaining in next 12 Days. Additional bundles issued to
FLM
MS Team Managing the integration of diverse equipment E//, ZTE and Nokia
RNC/BSC/LTE to Core/MPBN/PACO
2G Data KPIs
Monitoring traffic degradation at BTS level