Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
OF GIRDERS
BOILER 04. PRE-ASSEMBLY AND
ERECTION ERECTION OF GIRDERS
- Position the girder pieces over the pre assembly bed inside the furnace cavity
keeping left, middle and right side pieces following shop punch mark details.
Typical details of girder pieces are given in Annexure I.
- Web height at extended portion and compare with flange to flange inner distance
( For easy insersion 1 mm gap to be ensured on either side. If required grind web
ends to achieve the above).
i) Repeat the dimensional check, carried out prior to welding, after Post Weld Heat
Treatment and compare the two.
v) Ensure pre-assembly bed is made on the leveled and consolidated area to avoid
sinking during placement of girders on the bed.
vi) Ensure the pre –assembly bed members are properly spaced to avoid sagging of
girder pieces when they are placed over it. ( Refer Fig . 22);
vii) Match the pieces as per match marks provided in the pieces. Ensure the
orientation of girder pieces as per drawing (Ref.Fig. 23 A & 23B)
1
2
BOILER 04. PRE-ASSEMBLY AND
ERECTION ERECTION OF GIRDERS
1.0 Fit Up :
a) While leveling the pieces, the reference lines punched on the web at about 1 to 1.5M
level from bottom flange may be taken as reference.
b) While adjusting the overall length of the girder, check the distance between girder pin
connection bolt hole centers which is marked in the bottom flange and as well as on
the top flange.
c) While adjusting the overall straightness of the girder piece the longitudinal centerline
of the girders and web line marked on the pieces may be taken as reference.
d) While matching the piece, flange root gap and web root gap shall be maintained
between 4 to 6mm and 6 to 8mm respectively in the field joint areas (Ref. Fig.23B).
h) No tack weld to be made in the web for aligning. Instead ‘L’ clamps and wedges shall
be used for web alignment to keep the joint free during the welding of flange joint.
i) Ensure after dimensional check-up the girder assembly is properly locked in position
by using stoppers, ‘L’ clamps, wedges, guy ropes and struts or by any suitable device
to avoid distortion during welding and Post Weld Heat Treatment operations. Ensure
proper locking, in such a way that the girder assembly can move longitudinally during
welding and Post Weld Heat Treatment operations to avoid accumulation of thermal
stress.
2.0 b) Check the following dimensions prior to clearing the assembly for welding and are
to be recorded in the log sheet.
b) It is desirable to pre-heat using electric resistance coil heaters. Use of self pre-
heat is not permitted.
c) When electrode of 3mm and below are used the minimum pre-heat temperature
shall be increased by 50º C from the pre-heat temperature mentioned above.
5
BOILER 04. PRE-ASSEMBLY AND
ERECTION ERECTION OF GIRDERS
5.0 Welding
a) Welders shall be qualified as per Welding Manual.
d) Welding consumables used for this are to be stored properly and issued after
necessary baking. Electrodes issued for job should be kept in holding ovens
and maintain the temperature. The above are to be carried out as per welding
manual.
g) Complete the root plus three runs on inner side as per the sequence shown in
Fig. 24A.
h) Back gouge/chip the weld from outer side and carryout LPI/MPI tests for
ensuring defect free root weld.
i) Complete the outer side weld for three runs as per the sequence indicated in
Fig. No.24A.
j) Complete the flange joint weld, around 60% thickness of the joint on both sides of
flange alternately ( inner and outer) as per the sequence shown in Fig. 24B
k) After completion of 60% of flange welding check the web alignment (adjust with
wedges to achieve web alignment if required.)
m) Preheat to 150º C and adopt the weld sequence for the web root welding plus
two runs as shown in Fig. 24A.
n) Back gouge /chip the second side of the weld to achieve defect free root weld.
p) Complete the two runs of weld on the second side as per the sequence shown
in Fig.24B.
q) Complete the balance flange joint and then the balance web joint as per the
sequence indicated respectively in Fig. 24A & 24B.
Note: The welding sequence of flange and web can be changed depending
on the number of welders engaged.
6
7
8
9
BOILER 04. PRE-ASSEMBLY AND
ERECTION ERECTION OF GIRDERS
r) Complete the fillet welding between flange and web on both sides.
s) Carry out the post heating of weld joint for 1 hour at 250ºC
t) Welding shall not be done when the surfaces are wet, oil traces are seen or exposed
to rain or high wind or when the welders are exposed to inclement conditions.
u) The sizes and length of weld shall not be less or substantially in excess than the
specified in the drawing.
a) Butt welds in plates over 50mm thick shall be subjected to Post Weld Heat Treatment.
For unequal thickness of plates, the groove depth at the weld shall be considered for
Post Weld Heat Treatment.
b) The fillet welds for fixing attachments like pads etc. made on tension flanges over
50mm thick shall also be post weld-heat treated.
a) Butt welds in plates 50mm and above thick shall be Post Weld Heat Treated. For
unequal thickness of plates, the groove depth at the weld shall be considered for Post
Weld Heat Treatment.
b) The fillet welds for fixing attachments like pads etc. made on tension flanges 50mm
and above thickness shall also be post weld heat treated.
For the fillet welds joining the tension flange to web need not be out post weld heat treated.
All the post weld heat treatment cycle range shall be 600ºC to 650ºC. The above cycle shall
be controlled within a tolerance of ± 10ºC. The recommended temperature for Post Weld
Heat Treatment must be selected as the mid point of the recommended range.
Soaking time for Post Weld Heat Treatment shall be 1 hr. /25mm thick upto 50mm and 2 hr
+15 minutes for each additional 25mm thickness over 50mm.
The heating rate above 400ºC and cooling rate after Post Weld Heat Treatment upto 400ºC
shall be as follows:
Thickness range Rate of Rate of Cooling ( Max)
Heating (Max)
Upto 25mm thick 220ºC /hr 110ºC/hr
Over 25 – 50mm thick 110ºC/hr 110ºC/hr
Over 50 – 75mm thick 75ºC/hr 110ºC/hr
Over 75mm thick 55ºC/hr 65ºC/hr
10
BOILER 04. PRE-ASSEMBLY AND
ERECTION ERECTION OF GIRDERS
Autographic calibrated recorder shall be used to record rate of heating, soaking and rate of
cooling. Fixing and location of thermocouple shall be made as per details in Welding
Manual. (Typical case – Refer to Fig. 25 & 26).
5. Temporary platform shall be made around the column top so as to facilitate column
bolting with the ceiling girder.
6. Connected welded beams shall be kept ready for erection immediately after girder
erection.
7. Guy ropes with pulling machines shall be tied to the columns and anchored at both
sides of columns so as to have adjustment at the top during erection.
(B) Preparation of Heavy duty crane ( FMC crane) for girder lifting
After completion of preassembly of girders all the four ceiling girders are erected
with the help of FMC crane/ Heavy duty crane with ringer attachment.
The FMC crane LS 718 HL 250 T cap. /heavy duty crane shall be assembled with
310 ft boom with ringer attachment. The crane shall be assembled near Electrostatic
Precipitator area and moved inside the furnace cavity.
Heavy duty crane with ring horse attachment involves following assembles.
a) Crawler and cabin
b) Ringer attachement
c) Mast assembly
d) Boom assembly
e) Arrangement of jacks
f) Reeving of boom wire rope.
g) Loading of counter weights.
h) Fixing of jib.
After complete assembly, the crane shall be moved to the furnace cavity.
Girders shall be erected from the predetermined positions in furnace cavity as per
Fig.27 welded beams on front side, Girder – B & Girder – C shall be lifted from
position – I. The girder ‘D’ & ‘E’ shall be lifted from position – II.
1. Preassembled ceiling girder shall be shifted from preassembly bed to the nearest
columns.
2. The girder shall be assembled with pin connection assemblies at both ends.
3. The girder shall be kept over the wooden sleepers.
4. The girder shall be kept at angle of 20 degree to the horizontal plane as the length
of the girders is more compared to the span of the column.
5. Temporary Platform shall be made around girder for easy movement at top. The
typical arrangement is shown in Fig. 28.
12
BOILER 04. PRE-ASSEMBLY AND
ERECTION ERECTION OF GIRDERS
1. 80mm wire rope 16 M long – 2no’s shall be tied to the girder at the center as
shown in Fig. 29.
2. Two Nos. D-Shackles shall be tied to each one of top portion of slings.
3. Two Nos arrestor channels shall be provided to keep both the slings at a
distance.
4. The details of slinging is shown in Fig.29
5. Small tools like spanners, pulling machine etc. shall be kept ready.
6. The list of Tools and Tackles for ceiling girder lifting is given in Annexure – II.
1. Erection check list shall be completed before erection of ceiling girder. Typical
check list is shown in Annexure – III.
2. Heavy duty crane shall be positioned at a predetermined distance in the
furnace cavity.
3. It is preferable to start girder erection early morning so as to avoid heavy wind.
4. The girder shall be lifted slowly at an inclined direction with respect to
horizontal plane.
5. Manila rope tied at the both ends shall be controlled to avoid sway during
erection.
6. After reaching top of column, the girder shall be made parallel to column and
kept over the columns.
13
ANNEXURE – I
14
15
16
17
BOILER 04. PRE-ASSEMBLY AND
ERECTION ERECTION OF GIRDERS
ANNEXURE - I
18
BOILER 04. PRE-ASSEMBLY AND
ERECTION ERECTION OF GIRDERS
ANNEXURE – II
19
BOILER 04. PRE-ASSEMBLY AND
ERECTION ERECTION OF GIRDERS
ANNEXURE : III
SHEET : 01/04
CEILING GIRDER ERECTION
CHECKS FOR LIFTING
20
BOILER 04. PRE-ASSEMBLY AND
ERECTION ERECTION OF GIRDERS
Annexure : III
Sheet : 02/04
9. Persons to be recognized for
Lifting directions.
10. Communication arrangement
11. Manpower availability
Remarks CONTRACTOR
Remarks BHEL/ERN.
Remarks BHEL/QAE
CUSTOMER
21
BOILER 04. PRE-ASSEMBLY AND
ERECTION ERECTION OF GIRDERS
ANNEXURE : III
SHEET : 03/04
SL PARTICULARS CHECKS SIGNATURE REMARKS
NO
1. Girder supporting columns.
2. Verticality of columns
(All required).
3. Level of top of columns.
4. Marking of column top bolt holes center
5. Distance between two column centers at
top
6. Tightening of column bolts
7. All the necessary horizontal beams and
bracings to be aligned, welded & bolted
8. Main brace level structure at 9M, 21M,
31.2M, 43M, 56M & 68M on left, right and
front to be completed.
9. Cleaning of all mating surfaces like
column top, ceiling girder bottom, pin
connection surfaces.
10. Bolts to be tried thru holes for no
obstruction.
11. Lubrication of pin surfaces.
22
BOILER 04. PRE-ASSEMBLY AND
ERECTION ERECTION OF GIRDERS
Annexure : III
Sheet : 04/04
12. Bolting of pin connection on top of column & checking
of gaps prior to ceiling girder erection
13. Inspection of locking plate for pin connection.
14. Inspection of welding of bolt hole lugs to pin
connection
15. Pre-assembly clearance of ceiling Girder
( Dimensional & welding, NDT and stress relieving)
16. Fixing (Clamping) of temporary rails on top of the
flange of ceiling Girder for safety use. Welding of
temporary ladders on sides of girder.
17. Clamping of temporary angles on bottom flange of
ceiling girders for facilitating the scaffolding making
after erection.
18. Cross beams required to-connect should be kept
ready.
19. Arrangements for lifting and fixing of cross beams.
23