Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Approved 1st
2nd Revised Cost
As per DPR Revised Cost Variations w.r.t 1st
Estimate
Works (March 2008 Price Estimate RCE (March,14
(March 2016 Price
Level) (March 2014 Price P.L.)
Level)
Level)
Note: The Revised Cost Estimate is exclusive of Taxes & Duties in India and Bhutan
MANGDECHHU HYDROELECTRIC PROJECT, BHUTAN
VARIATION STATEMENT FOR SECOND REVISED COST ESTIMATE (March 2016 Price Level) vis-à-vis 1st Approved RC
Variation
As Per DPR 1st Approved RCE 2nd Revised Cost
Sl. Variation w.r.t. 1st
Name of Component (March, 2008 Price (March 2014 Price Estimate (March 2016 Price Escalation Change
No. RCE(March,14 PL)
Level) Level) Price Level) upto March 2016 in Scope
(i) Power Tunnel Intake Structure 549.91 844.71 531.32 -313.38 -33.68 -17.74
Intake Tunnels, Branch HRT, SFT,
Branch SFT, Adit to Desilting
(ii) 292.01 607.46 533.63 -73.83 -13.54 -167.44
Chamber, Adit to GoC of Dc, Adit to
GoC of SFT and Vertical Shaft
(iii) Desilting Chamber 561.75 782.65 776.21 -6.43 -8.79 -79.41
(iv) Head Race Tunnel including Adits 3,374.06 3,934.76 5,270.28 1,335.52 52.22 -331.12
4.00 Electro Mechanical Works 6,032.84 8,912.50 9,534.41 621.91 0.00 16.13
2 INDIRECT CHARGES
Capitalised Value of Abatement of Land revenue
I 0.16 0.00 0.00 0.00
(5% of cost of culturable land)
II Audit & Account Charges (0.25% of I-Works) 50.00 55.00 55.00 0.00
Total Indirect Charges 50.16 55.00 55.00 0.00
ABSTRACT OF COST
J-POWER PLANTS (CIVIL WORKS)
6 Pressure Shaft, bifurcation shaft and Intermediate Adits 747.85 942.64 1,361.98 419.34
8 Power House, Transformer Cavern and Bus Duct 1,143.50 1,421.03 1,568.61 147.58
10 TRT, Branch Tunnel and Outlet portal 375.26 540.35 540.82 0.47
Remarks
As per CEA Guideline
for formulation of
DPR, January,2015
(Revision 5.0)
3% of Total Cost
MANGDECHHU HYDROELECTR
SECOND REVISED COST ESTIMATE
ELECTRO MECHANI
1 2 3 4
26.60 0.00
261.09 179.51
40.79 0.00
486.09 139.77
43.51 0.90
Additional Other
Requirement Causes
10 11
0.00 0.00
0.00 -11.31
0.00 -14.54
0.00 0.00
0.00 0.00
0.00 -25.85
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 113.66
0.00 0.00
0.00 0.00
0.00 113.66
179.51
179.51 87.81
139.77
0.90
320.18 87.81
Annexure-VIII
1 2 3 4 5 6
1 DIVERSION TUNNEL
a Location Right Bank Right Bank
NHMN-2BC1-41-DD-001/01
b Number one one NHMN-2BT1 - 41-GA- 001
c Shape Horse Shoe Horse Shoe NHMN-2BT1 - 41-GA- 001 NHMN-2BC1-41-DD-001/01
d Size 8m Dia(finished) 8.5m Dia(finished) NHMN-2BT1- 41 - GA- 004 NHMN-2BC1-41-DD-106
e Max. Discharge 700Cumecs 822Cumecs
h Gates
4 DAM
a Type Concrete Gravity Dam Concrete Gravity Dam
b Top of Dam EL1750.0m EL1750.0m NHMN-2DT1 - 41-GA-001 NHMN-2DC1 - 41-SD-101
c River Bed Elevation EL1694.0 m EL1694.0 m NHMN-2DT1 -41-GA- 009 NHMN-2DC1 - 41-SD-105
d Length of dam(top) 141.0m 141.28m NHMN-2DT1 -41-GA- 003 NHMN/2DC1/41/GA/202/00
SL. DPR Tender Construction Drawings (NHPC)
Component Tender Drawing Number
No specifications/sizes specifications/sizes
5 Sluice Bay
a Type Radial Gate Radial Gate NHMN-2DT1 -41-GA- 003
b Nos 4 4 NHMN-2DT1 - 41-GA-003
c size 10m(W)X16m(H) 10m(W)X16m(H) NHMN-2DT1 -41-GA- 003
d Crest level
e Energy Dissipater Ski Jump Buket Type Ski Jump Buket Type
6 Spillway
a Type Orifice type spillway Orifice type spillway NHMN-2DT1 - 41-GA-001
b Number 1 1
c size 70m length 70m length NHMN-2DT1 - 41-GA-002
d Crest level EL.1702.0m EL.1702.0m NHMN-2DT1 - 41-GA-003
e Energy Dissipater Ski Jump Buket Type Ski Jump Buket Type
f stop log gate 10mX18m 10mX18m NHMN-2DT1 - 41-GA-003
5m dia, D-
shapedwith length of
130.186m & 139.775
for branch HRT 2 and
Branch HRT 1 & 2 1 respectively. NHMN-2HT1 -41-GA- 002 NHMN-2HC1 - 41-DD-004
SL. DPR Tender Construction Drawings (NHPC)
Component Tender Drawing Number
No specifications/sizes specifications/sizes
Revise Drawing by MHPA
Adit to HRT
6 Intake
Number 2 2 NHMN-2GT1-41-GA - 001 NHMN-2GC1 - 41-DD-001
shape Horse Shoe D-Shape NHMN-2GT1-41-GA - 001 NHMN-2GC1 - 41-DD-001
Inner diameter 5m 5m NHMN-2GT1-41-GA - 001 NHMN-2GC1 - 41-DD-001
length 196m and 150m for 173m and 126m for NHMN-2GC1 - 41-DD-001
tunnel 2and 1 tunnel 2and 1
respectively respectively NHMN-2GT1-41-GA - 001
9 SFT
UTAN
tion Stage
Right Bank
one
Horse Shoe
8.5m Dia(finished)
822Cumecs
Radial Gate
4
10m(W)X16m(H)
2
40
El. 1750.00
47
Construction Stage Reason for Change Attributed to:
Specifications/ Sizes
2
300m (L) x 14m (W) x
17.7 m(H)
7.5m x 7.5m, D-shaped, Increase in size to 7.5m from 6.5m for
adit of length 262.213m the equipment mobility, to expedite the
work based on the decisions of 5th TCC
meeting.
5m dia D-shaped
Branch HRT 1 & 2 with
length139.734m &
130.189m respectively
Construction Stage Reason for Change Attributed to:
Specifications/ Sizes
7.5m x 7.5m, D-shaped To get additional work front, to expedite
adit of length 359.10m the work
2
D-Shape
5m dia D-Shape
176m and 127m for
tunnel 2and 1
respectively
2
D
3.5m
308.808m
EL.1698m
2
D
2.0mx1.5m
113m &151m As per issued drawing
Construction Stage Reason for Change Attributed to:
Specifications/ Sizes
31m (L)X 6.9m(W) As per issued drawing
X8.5m(H)
1 2 3 4
1 SURGE SHAFT
1 No. restricted orifice type, 13.5m Dia 1 No. restricted orifice type, 13.5m Dia &
& 152m length 152m length
Excavation methodology Boring, reaming and slashing. Boring, reaming and slashing.
2 PRESSURE SHAFT
Number and type 2 No. Circular 2 No. Circular
Diameter and shape 5.50m excavated dia D-shaped and 5.50m excavated dia D-shaped and 3.5m
3.5m dia circular finished section dia circular finished section
3 PRESSURE SHAFT
CONSTRUCTION ADIT
Intermediate Adit 1 to 6.5mx6.5m-D-shaped Length 520m 6.5m x 6.5m D-shaped 664.013m long
Pressureshaft
1 2 3 4
Adit to PEG 1 6.5m x 6.5m D-shaped and 141.6m long
PEG-3
PENSTOCK ERECTION PEG-2 3 No. of size 8m (W) x 10m (H) x 60m (L)
GALLERY
PEG-1
Adit to Vl-3
Adit to Vl-1
VENTILATION TUNNEL
Ventilation Tunnel to 6.5m x 6.5m D-shaped & 285m long 7m x 6.5m D-shaped & 280.041m long
5 Powerhouse with portal invert EL 1071m with portal invert EL 1071m
Change in Salient Features at DPR vs Tender/Cons
5
1 2 3 4
Ventilation Tunnel to 7m x 6.5m D-shaped & 133.658m long
Transformer cavern with portal invert EL 1071m.
6 POWERHOUSE
Type Underground Underground
Size 155m x 23m x 41m 155m x 23m x 41m
Rock support Crown - 36mm dia. 7.5m long c/c and Crown - 36mm dia. 7.5m long c/c and
and 9m long at 3m c/c, plus 200mm and 9m long at 3m c/c, plus 200mm
SFRS. Wall - 36mm dia. SFRS. Wall - 36mm dia.
9m long at 1.5m c/c and 36mm dia. 9m long at 1.5m c/c in the u/s wall with
12m long at 3m c/c, plus 150mm 150mm thick SFRS. For d/s wall
SFRS. additional 36mm dia. 12m long at 3m c/c.
TRANSFORMER HALL
Type Underground Underground
Size 111.5m x 18m x 23m 135.5m x 18m x 23m
Rock support Crown - Rock bolt of 36mm dia. 7.5m Crown - Rock bolt of 36mm dia. 9m long
long at 1.5m c/c and 36mm dia. 9m at 1.5m c/c with 150mm SFRS. Walls -
long at 3m c/c with 200mm SFRS. Wall Rock bolt of 36mm dia. 9m long at 1.5m
- 36mm dia 9m long at 1.5m c/c and c/c with 150mm SFRS.
36mm dia. 12m long at 12m c/c with
150mm SFRS.
7
ESCAPE TUNNEL
Change in Salient Features at DPR vs Tender/Cons
1 2 3 4
BUS DUCT 4 No. of size 5m x 5m D-shaped and 4 No. of size 6m x 6.9m and 40m long
40m long.
CABLE TUNNEL 1 No. 6m dia. D-shaped and 362m 1 No. 6m dia. D-shaped and 362.22m
long. long
8 CABLE SHAFT 1 No. 5m dia. circular and 31m high. 1 No. 5m dia. circular and 31m high.
ADIT TO CABLE
TUNNEL
10 CONNECTING TUNNEL 1 No. 40m long 1 No. 40m long
11 DRAINAGE GALLERY 1 No. 3m dia. D-shaped and 152.208m 1 No. 3m dia. D-shaped and 152.208m
long. long.
12 POTHEAD YARD 95m x 35m 95m x 35m with cut slope of 1.5(V):1(H).
El.1078m
13 TAILRACE TUNNEL 8m dia. D-shaped and 1310m long 8m dia. horse-shoe shaped and 1295m
long.
TRT BRANCH TUNNEL 4 No. of size 4.5m x 5m D-shaped and 4 No. of size 4.5m x 5m D-shaped and
length 74m, 84m, 109m and 145m length 74m, 84m, 109m and 145m long.
long.
Adit to TRT
Annexure-XI
Change in Salient Features at DPR vs Tender/Construction Stage
Tender Drg No. Construction Drawings Issued from NHPC Ltd. Construction Stage Specifications/ Sizes
5 6 7
NHMN-3DT3-41-GA-001-00 NHMN- NHMN-3DC3-41-DD-102-00 1 No. restricted orifice type, 13.5m Dia & 152m
3DT3-41-GA-002-00 NHMN-3DC3-41-DD-105-02 length
NHMN-3DC3-41-DD-106-02
NHMN-3DC3-41-DD-107-01
NHMN-3DC3-41-DD-108-01
NHMN-3DC3-41-DD-109-01
NHMN-3DC3-41-DD-110-01
NHMN-3DC3-41-DD-111-01
Tender Drg No. Construction Drawings Issued from NHPC Ltd. Construction Stage Specifications/ Sizes
5 6 7
NHMN-3KT3-41-GA-001-00 NHMN-3KC3-41-DD-014-01 6.5m x 6.5m-D-shaped Length 161.071m
NHMN 4AT3 41 GA 001 00 NHMN 3KC3 41 DD 004 7.5m dia. D-shaped and 386.384m long.
NHMN 4CT3 41 GA 017 00 /018 00 / NHMN 4CC3 41 DD 001 00 / 103 00 8m x 7.6 m, D-Shaped Tunnel, Length
019 00. 679.672m with portal invert EL 1077m.
NHMN 4CT3 41 STD 022 00 / NHMN NHMN 4CC3 41 DD 002 00 / NHMN 4CC3 41 DD 7m x 6.5m D-shaped & 360.821m long with
3CT3 41 GA 025 00 110 00 portal invert EL 1077m.
Change in Salient Features at DPR vs Tender/Construction Stage
Tender Drg No. Construction Drawings Issued from NHPC Ltd. Construction Stage Specifications/ Sizes
5 6 7
NHMN 4CT3 41 STD 023 00 NHMN 4CC3 41 DD 003 00 7m x 6.5m D-shaped & 120.728m long with
invert EL 1077m.
Underground
NHMN 4AT3 4A GA 001 00 / NHMN 4CC3 41 DD 004 00 / 155m x 23m x 41m
NHMN 4CT3 41 GA 002 00 / NHMN 4CC3 41 DD 116 00 /
NHMN 4CT3 41 GA 003 00 /
NHMN 4CT3 41 GA 004 00
/ 005 00 / 006 00 / 007 00
NHMN 4CT3 41 GA 014 00 Crown - Steel rib RD 0-35m & 100-155m, and 36mm NHMN 4CC3 41 DD 133 00
dia. 12m long at 3m c/c extra over Tender
specification. 36mm dia 18m long additional rock
bolt in the wall below EL 1042m.
Underground
NHMN 4CT3 41 GA 014 00 NHMN 4CC3 41 DD 004 00 / NHMN 4CC3 41 DD 135.5m x 18m x 23m
101 00
NHMN 4CT3 41 GA 014 00 Crown - Steel rib RD 0-20m & 60-120m, and 36mm NHMN 4GC3 41 DD 104 01
dia. 12m long at 1.5m c/c extra over Tender
specification. Wall - Rock bolt 36mm dia. 9m at 1.5m
c/c in the upstream and 36mm dia. 12m at 1.5m c/c
in the downstream,Rockbolt 36mm Dia 18m & 15m
in poor reach area
Tender Drg No. Construction Drawings Issued from NHPC Ltd. Construction Stage Specifications/ Sizes
5 6 7
NHMN 4CT3 41 GA 003 00 NHMN 4CC3 41 DD 009 00 4 No. of size 6m x 6.9m and 41.06m long
NHMN 4CC3 41 DD 122 00 each, Rockbolt 32mm dia 17m on the inclined
NHMN 4CC3 41 DD 123 00 portion of Bus duct
NHMN 4CC3 41 DD 124 00
NHMN 4CC3 41 DD 347 00
NHMN 4CC3 41 DD 236 00
NHMN 4CT3 41 GA 020 00 NHMN 4CC341 DD 006 00 1 No. 6m D-shaped and 347.218m long
NHMN 4CT3 41 GA 020 00 NHMN 4CC3 41 DD 006 00 1 No. 5m dia. circular and 12m high.
NHMN 4CC341 DD 006 00 7m x 6.5m D-shaped and 107.71m long.
NHMN 4AT3 41 GA 001 00 NHMN 4CC3 41 DD 004 00 2 No.: 1 No. os size 2.5m dia. D-shaped 4m
long, and 1 No. 8m x 7.6m D-shaped and 47m
long.
NHMN 4CT3 41 GA 026 00 NHMN 4CC3 41 DD 005 01 / NHMN 4CC3 DD 121 1 No. 3m dia. D-shaped and 213.791m long.
01
NHMN 4ET3 41 GA 001 00 / NHMN NHMN 4EC3 41 DD 101 02 / NHMN 4EC3 41 DD 160m x 42m with cut sliope of 1(V):1(H) for
4ET3 41 GA 002 00 102 04 / NHMN 4EC3 41 DD 103 04 / NHMN 4EC3 first halve and 1.3:1 for second halve.
41 DD 104 04 / (El.1083m)
NHMN 4DT3 41 GA 001 00 NHMN 4DC3 41 DD 001 02 / NHMN 4DC3 41 DD 8m dia. horse-shoe shaped and 1333.564m
103 00 / NHMN 4DC3 41 DD 106 01 long.
NHMN 4DT3 41 GA 005 00 NHMN 4DC3 41 DD 002 00 / NHMN 4DC3 41 DD 5 No. 4.5m x 5m D-haped, and length
107 00 / NHMN 4DC3 41 DD 109 00 147.402m, 121.419m, 95.435m and 90.819m
long
- 9.606m each till the wall of Machine hall
Cavern - 4 Nos.
Change in design
Reason of Change Attributed
to
additional requirement to
expedite VL-1 excavation
Item
Description Unit
No. Completed upto
Balance Total
March 2016 Price
Qty. Rate Amt. Qty. Amt.
Escalation
Qty. Amt. Qty. Rate Amt. Qty. Amt.
Core Drilling (965 m @ Nu. 10000) LS 9.65 0.00 9.65 9.65 0.00
Drifting (160 m @ Nu. 13570) LS 2.17 0.00 2.17 2.17 0.00
Hydrometrological Observations (6.5+2yrs @ Nu.
4
1 Million per year) LS 8.50 0.00 8.50 8.50 0.00
5 Model Studies
Additional
Change in Inadequate Change Other
/ New
Scope Provision in Design Reason
Item
2.50
2.50
632.00
10.00
Qty Rate (Nu) Amount Qty Rate (Nu) Amount Qty Rate Amount Qty Rate Amount Qty Amount Qty Amount
1 2 3 4 5 6 10 11 12 13 14 15 16 17 18 19 21
A Land Acquisition
2 Lease Charge for Government Land for 7 Ha 28.47 17297 5.13 28.47 17297
years including Permanent, Temporary
and Unclassified Land @ Nu2471 per Ha
per year
B Compensation Purpose
b Class-2 (Wheat) Ha 8.69 24710 0.21 8.69 24710 10.24 16.080 7.170 23.250
13.010
10.24 16.080 7.170 23.250
13.010
c Class-3 (Wheat) Ha 0.07 24710 0.00 0.07 24710
d Class-4 (Wheat) Ha 3.8 24710 0.09 3.8 24710
e Class-5 (Wheat) Ha 7.8 24710 0.19 7.8 24710
Total 28.47 0.935959 28.47
II Compensation for fruit bearing trees No 2194 648 1.42 2194 648
22 23 24 25 26
13.010
13.010
14.518
0.00 0.00 0.00 27.53 0.00
NAME OF WORK : CONSTRUCTION OF DIVERSION TUNNEL, INLET, OUTLET & PORTAL AND PLUG(PACKAGE-C1)
1 2 3 7
1 Site Clearance
2 Surface Excavation at Portals
A2.1 Common Excavation m³ 228,640.51 298.00 68,134,871.98 228,640.51
A2.2 Rock excavation m³ 66,609.07 459.00 30,573,563.13 66,609.07
A2.4 Line drilling m 288.00 350.00 100,800.00 288.00
A2.5 Dental excavation m³ 1,000.00 438.00 438,000.00
A2.8 Extra for hauling excavated materials beyond 1 m3
km upto 3km 108,460.56 105.00 11,388,358.80 108,460.56
A2.8.1 Extra for hauling excavated materials beyond 3 km m³ 3,746.00 210.00 786,660.00
and upto 5 km
- -
A4 Rock Stabilization and Supports - -
A4.1 Rock Anchors /Bolts - -
A4.1.1 25 mm dia. - -
A4.1.1.1 - Length up to 4.0 m m 765.00 744.00 569,160.00 765.00
A4.1.1.3 - Length 4.0 m to 6.0 m m 7,107.00 700.00 4,974,900.00 2,130.00
Swellex anchors upto 3.0m long m - - -
A4.1.1.4 Extensions for embedding into concrete m 100.00 268.00 26,800.00
- - -
A4.1.2 32 mm dia - - -
A4.1.2.1 - Length up tp 6.0 m 876.00 875.00 766,500.00 876.00
A4.1.2.2 - Length 6.0 m to 9.0 m m 100.00 831.00 83,100.00
A4.1.2.3 - Length 9.0 m to 12.0 m m 100.00 831.00 83,100.00
Approved 1st RCE at March,2014 P.L.
A4.1.2.4 Extensions for embedding into concrete m 100.00 350.00 35,000.00
A4.1.3 36 mm dia of Items - - - Completed Wor
Sl.No. Description Unit
A4.1.3.1 - Length up tp 6.0 m m 100.00 963.00 96,300.00
A4.1.3.2 - Length 6.0 m to 9.0 m m 8,248.00 919.00 7,579,912.00
A4.1.3.4 Extensions for embedding into concrete m 100.00 438.00 43,800.00
A4.2 Testing of rock reinforcing elements No. 100.00 875.00 87,500.00
A4.3 Grouted anchor bars (for concrete) 25 mm dia m 1,460.00 656.00 957,760.00
A4.6 Mesh reinforcement - -
A4.6.1 Chain link fabric m2 2,039.63 350.00 713,870.50 2,039.63
A4.6.2 Wire mesh m2 5,504.00 241.00 1,326,464.00
- -
A5 Shotcrete - -
A5.1 Shotcrete in surface excavations m3 605.00 9,625.00 5,823,125.00 222.36
A5.2 Cement variation in shotcrete kg 8.00 -
A5.3 Superplasticsier kg 4,840.00 26.00 125,840.00
- -
A6 Embankment Construction and Backfill - -
A6.1 U/s and downstream coffer dams - -
A6.1.2 Zone 2 material m³ 1,293.27 963.00 1,245,419.01 1,293.27
- -
- -
A6.2 Backfill - -
A6.2.1 Random backfill m3 112,919.45 219.00 24,729,359.55
Quantity Upto BoQ+25% - - 25,555.45
Note:Certified that the quantities executed/to be executed as considered in Revised Cost Estimate above ar
consultants.
Variation w.r.t 1st RC
Second Revised Cost Estimate (March 2016 PL)
2014 P.L.
Quantity
- 350.00 - - - -100.00
Completed Work upto March, 2016 - Balance work to be- executed - - Total - -
- 963.00 - - - -100.00
Quantity
- 919.00 - - - -8,248.00
- 438.00 - - - -100.00
- 875.00 - - - -100.00
- 656.00 - - - -1,460.00
- - - - -
350.00 713,870.50 350.00 - 2,039.63 713,870.50 -
241.00 - 241.00 - - - -5,504.00
- - - - -
- - - - -
9,625.00 2,140,215.00 9,625.00 - 222.36 2,140,215.00 -382.64
- - - - -
- 26.00 - - - -4,840.00
- - - - -
- - - - -
- - - - -
963.00 1,245,419.01 963.00 - 1,293.27 1,245,419.01 -
- - - - -
- - - - -
- - - - -
219.00 - - - -
219.00 5,596,643.55 - 25,555.45 5,596,643.55
939.97
20,125.00 - - - -655.00
- - - - - -
- - - - - -
3,150.00 - - -
4,595.02 - - - -
- 24.00 - - - -1,035.00
- - - - - -
1,225.00 56,816,872.00 1,225.00 - 46,381.12 56,816,872.00 -
1,444.00 15,231,557.48 1,444.00 - 10,548.17 15,231,557.48 -
Completed Work394.00
upto March, 2016
1,513,219.25 Balance work394.00
to be executed - 3,840.66 Total 1,513,219.25 -594.34
Quantity
105.00 2,705,425.80 105.00 - 25,765.96 2,705,425.80 -
- 210.00 - - - -1,497.00
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
744.00 7,264,416.00 744.00 - 9,764.00 7,264,416.00 -
722.00 3,973,527.00 722.00 - 5,503.50 3,973,527.00 -15,275.50
- - - - - -
- - - - -
267.00 - 267.00 - - - -
65,625.00 2,359,875.00 65,625.00 - 35.96 2,359,875.00 -12.07
65,625.00 - 65,625.00 - - - -7.00
- - - - - -
- - - - - -
- - - - - -
306.00 415,391.94 306.00 - 1,357.49 415,391.94 -
306.00 - - - - -
- - - - - -
- - - - - -
306.00 708,696.00 300.00 306.00 91,800.00 2,616.00 800,496.00 300.00
306.00 - 306.00 - - - -285.00
1,750.00 - 95.00 1,750.00 166,250.00 95.00 166,250.00 -
- - - - - -
- - - - - -
Completed Work upto March, 2016 Balance work to be executed Total
- - - - -
Quantity -
2,625.00 1,036,875.00 380.00 2,625.00 997,500.00 775.00 2,034,375.00 -
- 1,750.00 - - - -57.00
- - - - - -
8,750.00 1,017,187.50 8,750.00 - 116.25 1,017,187.50 -585.75
- 963.00 - - - -1.00
- 11,375.00 - - - -1.00
- 66.00 - - - -585.00
- 11,375.00 - - - -6.00
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
3,938.00 12,282,031.30 3,938.00 - 3,118.85 12,282,031.30 -194.15
- - - - - -
4,113.00 55,795,633.61 4,113.00 - 13,565.68 55,795,633.61 1,082.72
4,375.00 4,046,306.25 1,500.00 4,375.00 6,562,500.00 2,424.87 10,608,806.25 824.87
- - - - - -
- - - - - -
- - - - - -
- - - - - -
Completed Work upto
8.00 March, 2016
12,901,297.52 Balance work to8.00
112,500.00 be executed900,000.00 1,725,162.19 Total 13,801,297.52 112,500.00
- - - - Quantity -
- 22.00 - - - -2,285.00
- - - - - -
788.00 157,600.00 788.00 - 200.00 157,600.00 -
- - - - - -
- - - - - -
- - - - - -
1,313.00 26,260.00 1,313.00 - 20.00 26,260.00 -
Variation w.r.t 1st RC
Second Revised Cost Estimate (March 2016 PL)
2014 P.L.
2,188.00 - 2,188.00 - - - -
Completed Work upto March, 2016
2,625.00
Balance work to be executed Total
60,375.00 2,625.00 - 23.00 60,375.00 -
2,188.00 41,572.00 2,188.00 - 19.00 41,572.00 Quantity -
- - - - - -
1,313.00 6,565.00 1,313.00 - 5.00 6,565.00 -
- - - - - -
2,625.00 65,625.00 2,625.00 - 25.00 65,625.00 -
- - - - - -
1,313.00 7,878.00 1,313.00 - 6.00 7,878.00 -
525.00 3,150.00 525.00 - 6.00 3,150.00 -
- - - - - -
- - - - - -
963.00 5,778.00 963.00 - 6.00 5,778.00 -
- - - - - -
66.00 19,602.00 66.00 - 297.00 19,602.00 -
39.00 41,184.00 39.00 - 1,056.00 41,184.00 -
- - - - - -
- -
- - -
- - -
31,358.31 31,358.31
1,684,208.27 1,684,208.27
219,219.65 219,219.65
-122,717,903.63
Estimate above are as per the site conditions, construction/planning/Specification drawings issued by the
ANNEXURE-XIV
Inadequate Additional
Amount Price Escalation Change in scope change in design Other causes
provision requirements
19 20 21 22 23 24 25
-
-
- -
- -
- -
-438,000.00 -438,000.00
- -
-786,660.00 -786,660.00
-
-
-
-
- -
-3,483,900.00 -3,483,900.00
- -
-26,800.00 -26,800.00
- - -
- - -
- - -
-83,100.00 -83,100.00
-83,100.00 -83,100.00
Variation w.r.t 1st RCE @ March-
Variation due to
2014 P.L.
-35,000.00 -35,000.00
- - -
-96,300.00 Inadequate Additional
Amount Price Escalation Change in scope change in design Other causes-96,300.00
-7,579,912.00 provision requirements -7,579,912.00
-43,800.00 -43,800.00
-87,500.00 -87,500.00
-957,760.00 -957,760.00
- - -
- - -
-1,326,464.00 -1,326,464.00
- -
- -
-3,682,910.00 -3,682,910.00
- -
-125,840.00 -125,840.00
-
-
-
- -
-
-
-
- -
-2,796,481.55
-2,796,481.55
-24,100.00 -24,100.00
-87,500.00 -87,500.00
-87,500.00 -87,500.00
- - -
Variation w.r.t 1st RCE @ March-
Variation due to
2014 P.L.
- -
- Inadequate Additional -
Amount Price Escalation Change in scope change in design Other causes
-136,497.00 provision requirements -136,497.00
-612,004.80 -612,004.80
- -
- -
-65,600.00 -65,600.00
-65,600.00 -65,600.00
-188,168.00 -188,168.00
- -
-136,062.50 -136,062.50
-5,742.00 -5,742.00
- - -
- - -
-13,181,875.00 -13,181,875.00
-
-
892,376.78
892,376.78
-589,316.00 -589,316.00
- - -
-446,300.00 -446,300.00
Variation w.r.t 1st RCE @ March-
Variation due to
2014 P.L.
-79,377.12 -79,377.12
Inadequate Additional
Amount Price Escalation Change in scope change in design Other causes
- provision - requirements -
- - -
- - -
- - - -
-24,840.00 -24,840.00
- - -
- - - -
- - - -
-534,456.54 -534,456.54
-23,068.50 -23,068.50
-688,080.12 -688,080.12
-52,500.00 -52,500.00
- -
- -
-
-
- -
- -
- -
- -
- -
- -
- -
- -
- -
Variation w.r.t 1st RCE @ March-
Variation due to
2014 P.L.
Inadequate Additional -
Amount Price Escalation Change in scope change in design Other causes
provision requirements
-
- -
-
- -
221,492.41 221,492.41
- -
- -
-
-253,128.75 -253,128.75
- -
-
-
-
-
-
- -
- -
-962,500.00 -962,500.00
- -
-262,500.00 -262,500.00
Variation w.r.t 1st RCE @ March-
Variation due to
2014 P.L.
-234,170.75 -234,170.75
Inadequate Additional
Amount Price Escalation Change in scope change in design Other causes
- provision requirements- -
-314,370.00 -314,370.00
- -
- -
- -
- -
- -
- - -
-11,028,911.00 -11,028,911.00
- -
- - -
- - -
- - -
- - -
- -
-792,093.75 -792,093.75
-459,375.00 -459,375.00
-16,597,700.00 -16,597,700.00
-892,500.00 -892,500.00
-110,160.00 -110,160.00
-210,000.00 -210,000.00
-1,024,200.00 -1,024,200.00
-1,050,000.00 -1,050,000.00
Variation w.r.t 1st RCE @ March-
Variation due to
2014 P.L.
-52,500.00 -52,500.00
-
- Inadequate Additional
Amount Price Escalation Change in scope change in design Other causes
- provision - requirements
- -
- -
- -
-202,976.02 -202,976.02
- - -
- - -
-19,700.00 -19,700.00
- - -
- -
- -
- -
- - -
- -
- -
- -
91,800.00 91,800.00
-87,210.00 -87,210.00
- -
- - -
-1,371,798.00 -1,371,798.00
- -
-100,450.00 -100,450.00
- -
Variation w.r.t 1st RCE @ March-
Variation due to
2014 P.L.
- - -
- Inadequate Additional -
Amount Price Escalation Change in scope change in design Other causes
- provision requirements -
-99,750.00 -99,750.00
- -
-5,125,312.50 -5,125,312.50
-963.00 -963.00
-11,375.00 -11,375.00
-38,610.00 -38,610.00
-68,250.00 -68,250.00
- -
-
-
-
-
-764,562.70 -764,562.70
- -
4,453,219.13 4,453,219.13
3,608,806.25 3,608,806.25
-
- -
-
-765,168.03 -765,168.03
- - -
Variation w.r.t 1st RCE @ March-
Variation due to
2014 P.L.
- - -
900,000.00 900,000.00
- Inadequate - Additional -
Amount Price Escalation Change in scope change in design Other causes
provision requirements
-50,270.00 -50,270.00
131,100.00 131,100.00
- -
- -
45,900.00 45,900.00
- -
- -
- -
- -
- -
-42,199,543.75 -42,199,543.75
- - -
- - -
-568,750.00 -568,750.00
- - -
- - -
-13,300.00 -13,300.00
-2,100.00 -2,100.00
-
-
-
- -
-
-
-
- -
Variation w.r.t 1st RCE @ March-
Variation due to
2014 P.L.
- -
- -
Inadequate Additional
Amount - Price Escalation Change in scope change in design - Other causes
provision requirements
- -
- -
- -
- -
- -
- -
- -
-
-
- -
- -
- -
- -
-
-3,117,355.56 -3,117,355.56
`` -
-
- -
-
Variation w.r.t 1st RCE @ March-
Variation due to
2014 P.L.
- Inadequate Additional -
Amount Price Escalation Change in scope change in design Other causes
provision requirements
-5,548,929.27 -5,548,929.27
26
Remarks if Any
Analyzed Rate as
per the provision of
Contract
Remarks if Any
Analyzed Rate as
per provision of
Contract
Remarks if Any
Remarks if Any
Analyzed Rate as
per the provision of
Contract
Remarks if Any
Remarks if Any
Remarks if Any
Remarks if Any
Remarks if Any
Remarks if Any
NAME OF WORK : CONSTRUCTION OF DAM, SPILLWAY AND COFFER DAM (PACKAGE-C1)
A2 Surface Excavation
A2.1 Common Excavation m³ 743,587.00 298.00 221,588,926.00
A2.2 Rock excavation m³ 426,383.38 459.00 195,709,972.80
Quantity Upto BoQ+25% - -
Quantity Beyond BoQ+25% - -
A2.4 Line drilling m - 350.00 -
A2.5 Dental excavation 200.00 438.00 87,600.00
A2.6 Minor excavation work 200.00 438.00 87,600.00
Extra for hauling excavated materials 301,619.00 105.00 31,669,995.00
A2.8 m³
beyond 1 km upto 3km
Extra for hauling excavated materials 130,257.60 210.00 27,354,094.95
A2.8.1 m³
beyond 3 km and upto 5 km
Quantity Upto BoQ+25% 210.00 -
A9.7 -M25 /A40 in Piers and Training walls m³ 76,867.00 3,938.00 302,702,246.00
A9.19 Admixtures - - -
- Air-entraining agent (Brand as Agreed 2,039.00 24.00 48,936.00
A9.19.1 kg
during Bid)*
- Water-reducing agent (Brand as Agreed 80,480.00 25.00 2,012,000.00
A9.19.2 kg
during Bid)*
A10 Formwork - - -
- - -
Part-B :Equipment - - -
B1 Earthmoving and excavation equipment - - -
B1.1 Tracked/wheeled excavators and loaders - - -
B 1.1.1 Excavator below 1.2m3 85.00 1,313.00 111,605.00
Sl.No. Description of Items Unit
Approved RCE at March,2014 P.L.
Dewatering of underground
Construction Sites including 5,156,818.00 22.00 113,449,996.00
supply,installation and removal of
pumping equipment from the Site
m3
m
Grouted Anchor Bar-32mm dia of length
EI.4.4 -
upto 6m
m2
Formwork used for cladding wall concrete
EI.4.5 -
at R/B Slided area
7.4 Formwork F2 m2
-
Claims
Certified that the quantities executed/to be executed as considered in Revised Cost Estimate above are as per
Revised Cost Estimate (March 2016 PL)
- - - - -
- - - - -
Revised Cost Estimate (March 2016 PL)
- 963.00 - -
- 11,375.00 - -
- 500.00 66.00 33,000.00 500.00
- - - - -
- - - - -
- - - 6,562,500.00 -
- - - - -
- - - - -
- - - - -
- - - - -
- 105.00 - -
Revised Cost Estimate (March 2016 PL)
- 210.00 - -
- - 1,050.00 - -
- - - - -
- - - - -
- - - - -
- 744.00 - -
- 267.00 - -
- 65,625.00 - -
- 8,750.00 - -
- - - - -
491.22 10,500.00 5,157,810.00 10,500.00 - 491.22
29,472.96 8.00 235,783.68 8.00 - 29,472.96
4,730.41 31.00 146,642.71 31.00 - 4,730.41
19,648.64 83.00 1,630,837.12 83.00 - 19,648.64
48,187.63 13.00 626,439.19 13.00 - 48,187.63
- - - - -
- - - - -
- - - - -
- 306.00 - -
- 432.00 123.00 53,136.00 432.00
- 175.00 - -
- - - -
- - - -
- - - -
Revised Cost Estimate (March 2016 PL)
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
416.41 1,313.00 546,741.08 1,313.00 - 416.41
Revised Cost Estimate (March 2016 PL)
- -
- - - - -
859,921,532.54 - 31,351,292.03 -
1,087
- 3,914.50 1,087.34 4,256,392.43 3,914.50
4,595.02
- - - -
3,371.990 4,595.02
3,450.000 875
3,018,750.00 1,242.00 875.00 1,086,750.00 4,692.00
1,140.431
306 348,971.89 1,009.62 306.00 308,943.41 2,150.05
181.574 1,313
29.538 56,875
1,679,973.75 0.67 56,875.00 38,333.75 30.21
134,227,125 -
41,074,656.45
1,663,002.38
Revised Cost Estimate (March 2016 PL)
482,372.36
3,536,108.82
-164,050.01
1,139,709.92
83,603,791.64 102,017,406.86
Revised Cost Estimate (March 2016 PL)
10,189,990.57
100,000,000.00
3,209,812,695.96 - 3,002,742,303.83
- -
-
- - -
Cost Estimate above are as per the site conditions, construction/planning/Specification drawings issued by the consultants.
Variation w.r.t RCE @ March-
Variation due to
2014 Price Level
- -
- -
221,097,189.94 -1,650.12 -491,736.06 -491,736.06
- -
93,632,410.62
293,881.10 276,350,036.66 276,350,036.66
378,427,598.83
264,047.00 754.42 264,047.00
525,602.19 1,000.01 438,002.19 438,002.19
- -200.00 -87,600.00
-
26,084,362.50
30,451,109.65
628,509.78 169,890,799.81 169,890,799.81
140,709,422.60
- - -
- - -
Variation w.r.t RCE @ March-
Variation due to
2014 Price Level
1,451,358.00 - -
Variation w.r.t RCE @ March-
Variation due to
2014 Price Level
2,768,500.00 - -
7,382,345.88
4,328.65 41,836,592.90 41,836,592.90
24,146,309.52
- -1.00 -963.00
- -1.00 -11,375.00
33,000.00 -201.00 -13,266.00 -13,266.00
- - -
- - -
6,562,500.00 - -
- - -
892,600.00 - - -
- - -
787,600.00 - -
30,047,500.00 - -
302,702,246.00 - -
34,361,250.00 - - -
3,005,625.00 - -
Variation w.r.t RCE @ March-
Variation due to
2014 Price Level
- - - -
- - -
12,213,072.00 - -
6,464,850.00 - -
494,550.00 - -
Variation w.r.t RCE @ March-
Variation due to
2014 Price Level
1,261,554.00 - -
- - -
5,687,500.00 - -
- - -
262,500.00 - -
263,000.00 - -
- - -
- - -
- - -
- - - -
219,000.00 - - -
263,000.00 - - -
455,700.00 - -
1,139,684.00 - -
455,700.00 - -
532,084.00 - -
- - -
- - -
330,000.00 - -
Variation w.r.t RCE @ March-
Variation due to
2014 Price Level
- -293.00 -30,765.00
Variation w.r.t RCE @ March-
Variation due to
2014 Price Level
- -88.00 -18,480.00
- - -
- - -
- - -
- - -
- -432.00 -321,408.00
- -103.00 -27,501.00
- -9.00 -590,625.00
- -17.00 -148,750.00
- - - -
5,157,810.00 388.22 4,076,310.00 4,076,310.00
235,783.68 29,472.96 235,783.68
146,642.71 3,906.41 121,098.71 121,098.71
1,630,837.12 15,528.64 1,288,877.12 1,288,877.12
626,439.19 12,281.40 159,658.20 159,658.20
- - -
- - -
- - -
- -432.00 -132,192.00
53,136.00 - -
- -10.00 -1,750.00
- - -
- - -
- - -
Variation w.r.t RCE @ March-
Variation due to
2014 Price Level
- - -
- - -
- - -
- - -
- - -
546,741.08 331.41 435,136.08 435,136.08
Variation w.r.t RCE @ March-
Variation due to
2014 Price Level
- - -
- - -
- - -
891,272,824.57 -
- - -
- - -
- - -
134,227,124.68 - 134,227,124.68
- - -
- - -
41,074,656.45
1,663,002.38
Variation w.r.t RCE @ March-
Variation due to
2014 Price Level
482,372.36
3,536,108.82
-164,050.01 -
1,139,709.92
10,189,990.57
100,000,000.00 100,000,000.00
- -
- -
the consultants.
-
-
Annexure-XV
ue to
Remarks, If any
Additional
Other causes
requirements
24 25 26
-
-87,600.00
Remarks, If any
Additional
Other causes
requirements
3,032,023.20
53,600.00
581,700.00
22,225.00
3,378,204.00
- -
ue to
Remarks, If any
Additional
Other causes
requirements
-1,289,910.00
-
-1,202,056.00
-
Analyzed Rate as per
provision of Contract
-
ue to
Remarks, If any
Additional
Other causes
requirements
327,250.00
-
-
-
-350,000.00
-262,500.00
-525,000.00
-
-
-
ue to
Remarks, If any
Additional
Other causes
requirements
-
-
-
-963.00
-11,375.00
-
ue to
Remarks, If any
Additional
Other causes
requirements
-
-
190,256,712.14
-
ue to
Remarks, If any
Additional
Other causes
requirements
-210,000.00
-
-
-
-
-
ue to
Remarks, If any
Additional
Other causes
requirements
-
-
-
-
-
-
-
-
-
ue to
Remarks, If any
Additional
Other causes
requirements
-
-
-
-
-
-
700,341.78
-
-
-
-
-
-
-
-
ue to
Remarks, If any
Additional
Other causes
requirements
-
-
-
-
-
-
-
-21,340.80
-
-
-
-
-
-
-
-
-
Analyzed Rate as per
provision of Contract
10,755,973.20
ue to
Remarks, If any
Additional
Other causes
requirements
-
ue to
Remarks, If any
Additional
Other causes
requirements
ue to
Remarks, If any
Additional
Other causes
requirements
ue to
Remarks, If any
Additional
Other causes
requirements
-177,612.00
-30,765.00
ue to
Remarks, If any
Additional
Other causes
requirements
-18,480.00
-321,408.00
-27,501.00
-590,625.00
-148,750.00
-
235,783.68
-
-
-
-132,192.00
- -
-1,750.00
ue to
Remarks, If any
Additional
Other causes
requirements
-
5,769,531.25
827,249.68
-176.00
-
-
-
-
-
-284,375.00
-56,875.00
ue to
Remarks, If any
Additional
Other causes
requirements
-
-
-
-
-
36,750.00
-
-
1,750.00
-
-
67,410.00
-
52,272.00
1,452.00
-
-
ue to
Remarks, If any
Additional
Other causes
requirements
-
-
-
-
-
7,797,240.00
ue to
Remarks, If any
Additional
Other causes
requirements
19,096,988.14
129,997,074.93
4,256,392.43
1,614,862.98
580,575.78
6,373,591.42
ue to
Remarks, If any
Additional
Other causes
requirements
3,595,869.56
4,207.35
137,760.00
546,975.00
1,265,820.00
18,223,624.16
ue to
Remarks, If any
Additional
Other causes
requirements
4,971,802.46
4,105,500.00
657,915.30
238,406.66
1,718,307.50
649,077.00
ue to
Remarks, If any
Additional
Other causes
requirements
134,227,124.68
1,937,223.71
1,883,291.40
3,469,221.00
2,217,145.42
19,008.00
424,632.00
ue to
Remarks, If any
Additional
Other causes
requirements
3,286,722.00
910,000.00
168,000.00
45,500.00
-
ue to
Remarks, If any
Additional
Other causes
requirements
ue to
Remarks, If any
Additional
Other causes
requirements
Deployment of
additional resources for
completion of diversion
tunnel and also the cost
of idling due to delay in
100,000,000.00 handing over of balley
bridgeon
Claim at account
site of
additional expenditure
due to incomplete and
- bad condition of access
Additional
road cost for civil
works for setting up
CBP & APPs at new
- location & also
additional cost for
setting up higher
670,784,133.80 -5,751,253.80 capacity CBP and ABPs.
REVISED COST ESTIMATE AT MARCH,16 PRICE LEVEL - HM works-C works(including material, transportation and installation cost) Sp
Approved 1st RCE at March,14
P.L.
Item Description of Item Qty.
No.
Amount
1 2 3
(IN EURO) (IN INR/ NU)
1.0 Diversion Tunnel Gate and Hoist
1.1 Diversion Tunnel Gate(Fixed wheel Type) 2 - 9,448,975.64
1.2 First Stage Embedded Parts for 1.1 2 - 171,866.54
1.3 Second Stage Embedded Parts including Dogging,etc. for 1.1 2 - 6,817,385.04
1.4 Rope Drum Hoist complete in all Respect and control equipment for 1.1 2 - 5,601,519.14
1.5 Common Hoist supportign structure and Trestle, etc. for both DT gates etc. for 1.1 2 - 4,826,776.93
1.6 Mandatory Spare parts (As per Statement 1B) - 192,884.50
1.7 Dummy Frame - 480,000.00
SUBTOTAL 27,539,407.79
Total amount including foerign component(conversion factor 1 Euro=Rs 68.65 for 471,148,214.78
completed works & Rs.76 for balance works)
- -
- -
- -
- -
- -
- -
- - 346,251.20 - 1,385,004.80 - 1,731,256.00 - -
3,843,438.77 17,329,211.98 21,172,650.75 - -
- -
- -
- - 767,545.49 - 3,419,381.91 - 4,186,927.40 - -
- -
- - 37,636.00 - 150,544.00 - 188,180.00 - -
805,181.49 3,569,925.91 4,375,107.40 - -
-
227,430.08 86,429,689.01 909,720.32 451,153,150.81 1,137,150.40 537,582,839.82 144,500,000.00
- - - 6,686,444.35
Variation Due to
23 24 25 26 27 28
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
144,500,000.00 ###
- - 144,500,000.00 -
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
- - - - 144,500,000.00 -
19,128,345.42
6,686,444.35
Sl.No. Description of Items Unit Approved 1st RCE at March,2014 P.L. Completed Work upto M
- - -
A4 Rock Stabilization and Supports - - -
A4.1 Rock Anchors /Bolts - - -
A4.1.1 25 mm dia. - - -
Sl.No. Description of Items Unit Approved 1st RCE at March,2014 P.L. Completed Work upto M
- - -
A4.1.2 32 mm dia - - -
A4.1.2.2 - Length 6.0 m to 9.0 m m - 831.00 -
A4.1.2.3 - Length 9.0 m to 12.0 m m 44,812.00 831.00 37,238,772.00
A4.1.2.4 Extensions for embedding into m
concrete 6,651.00 350.00 2,327,850.00
A4.1.3 36 mm dia - - -
A4.1.3.1 - Length up tp 6.0 m m 100.00 963.00 96,300.00
A4.1.3.2 - Length 6.0 m to 9.0 m m 100.00 919.00 91,900.00
A4.1.3.4 Extensions for embedding into m 27.00 438.00 11,826.00
A4.2 concrete
Testing of rock reinforcing elements No. 100.00 875.00 87,500.00
A4.3 Grouted anchor bars (for concrete) 25 m 3,325.00 656.00 2,181,200.00
A4.6 mm
Meshdia
reinforcement - - -
A4.6.1 Chain link fabric m2 2,000.00 350.00 700,000.00
A4.6.2 Wire mesh m2 16,016.00 241.00 3,859,856.00
- - -
A5 Shotcrete - - -
A5.1 Shotcrete in surface excavations m3 1,602.00 9,625.00 15,419,250.00
A5.3 Superplasticsier kg 12,816.00 26.00 333,216.00
- -
A6 Embankment Construction and - -
A6.2 Backfill - -
Sl.No. Description of Items Unit Approved 1st RCE at March,2014 P.L. Completed Work upto M
equipment embeddment
- 4,463.00 -
Other Items - - -
Swellex Anchor upto 6m long m - - -
PCC M20/ A40 m3 - - -
- - -
- - -
Dewatering of underground
Construction Sites including 232,727.00 22.00 5,119,994.00
supply,installation and removal of
pumping equipment from the Site
Certified that the quantities executed/to be executed as considered in Revised Cost Estimate above are as per
UCTURE (C1- Package)
2nd Revised Cost Estimate (March 2016 P.L)
114.00 - 114.00 - - -
105.00 - 105.00 - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
2nd Revised Cost Estimate (March 2016 P.L)
- - - - - - -
- - - - - - -
831.00 - - - -
831.00 - - 831.00 - - -
- - - - - - -
963.00 - 963.00 - - -
919.00 - 919.00 - - -
438.00 - 438.00 - - -
875.00 - 875.00 - - -
656.00 - 656.00 - - -
- - - - - - -
350.00 - 350.00 - - -
241.00 - 241.00 - - -
- - - - - - -
- - - - - - -
9,625.00 - 9,625.00 - - -
26.00 - 26.00 - - -
- - - - - -
- - - - - -
- - - - - -
2nd Revised Cost Estimate (March 2016 P.L)
306.00 - - 306.00 - - -
- - - - - - -
- - - - - -
- - - - - -
306.00 - 400.00 306.00 122,400.00 400.00 122,400.00
123.00 - 123.00 - - -
263.00 - 92.00 263.00 24,196.00 92.00 24,196.00
- - - - - -
700.00 - 100.00 700.00 70,000.00 100.00 70,000.00
- - - - - - -
656.00 - 100.00 656.00 65,600.00 100.00 65,600.00
656.00 - 656.00 - - -
2,188.00 293,192.00 2,188.00 - 134.00 293,192.00
- - - - - -
2nd Revised Cost Estimate (March 2016 P.L)
963.00 - 963.00 - - -
11,375.00 - 11,375.00 - - -
66.00 - 3,629.00 66.00 239,514.00 3,629.00 239,514.00
- - - - - -
3,150.00 - 100.00 4,595.02 459,502.00 100.00 459,502.00
3,238.00 - 3,238.00 - - -
- - - - - -
4,463.00 - 300.00 4,463.00 1,338,900.00 300.00 1,338,900.00
- - - - - -
- - - - - -
- - - - - -
- - - - - -
3,763.00 - 3,763.00 - - -
- - - -
- - - - - -
- - - - - - -
312.00 13,618.80 312.00 - 43.65 13,618.80
4,198.00 - - 4,198.00 - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
3,150.00 - 1.00 3,150.00 3,150.00 1.00 3,150.00
6,300.00 - 2.00 6,300.00 12,600.00 2.00 12,600.00
38,500.00 - 2.00 38,500.00 77,000.00 2.00 77,000.00
2nd Revised Cost Estimate (March 2016 P.L)
4,463.00 - - 4,463.00 - - -
- - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
22.00 - 22.00 - - -
- - -
2nd Revised Cost Estimate (March 2016 P.L)
706,110.93 706,110.93
-313,384,899.60
ost Estimate above are as per the site conditions, construction/planning/Specification drawings issued by the consultants.
Annexure-XVII
Inadequate change in
Quantity Amount Price Escalation Change in scope
provision design
18 19 20 21 22 23
- -
- -
-151,965.00 -45,285,570.00
-14,080.00 -6,462,720.00
-500.00 -219,000.00
-400.00 -140,000.00
- -
- - -
-16,605.00 -1,892,970.00
-50,655.00 -5,318,775.00
- -
- -
- -
- -
Variation w.r.t 1st RCE (March-2014 P.L.) Variation due to
Inadequate change in
Quantity Amount Price Escalation Change in scope
provision design
-200.00 -140,000.00
- -
- -
- -
- -
-44,812.00 -37,238,772.00
- -
-100.00 -96,300.00
-100.00 -91,900.00
-27.00 -11,826.00
-100.00 -87,500.00
-3,325.00 -2,181,200.00
- -
-2,000.00 -700,000.00
-16,016.00 -3,859,856.00
- -
- -
-1,602.00 -15,419,250.00
-12,816.00 -333,216.00
- -
- -
- -
Variation w.r.t 1st RCE (March-2014 P.L.) Variation due to
Inadequate change in
Quantity Amount Price Escalation Change in scope
provision design
-24,459.00 -5,356,521.00
-100.00 -24,100.00
-100.00 -87,500.00
-100.00 -87,500.00
- -
- -
- -
- -
- -
- -
-7,082.00 -2,167,092.00 -2,167,092.00
-7,482.00 -920,286.00 -920,286.00
- -
- -
- -
- -
- -
-100.00 -65,600.00
-562.00 -1,229,656.00 -1,229,656.00
- -
Variation w.r.t 1st RCE (March-2014 P.L.) Variation due to
Inadequate change in
Quantity Amount Price Escalation Change in scope
provision design
- -
-18.00 -17,334.00
-18.00 -204,750.00
- -
- -
- 144,502.00 144,502.00
-54,221.00 -175,567,598.00
- -
- -
- -
- -
- -
- -
780.62 4,098,255.00
16.72 219,423.75
- -
Variation w.r.t 1st RCE (March-2014 P.L.) Variation due to
Inadequate change in
Quantity Amount Price Escalation Change in scope
provision design
-100.00 -376,300.00
- -
- -
- -
- -
- -
- -
3,938,962.88 31,511,703.04
- -
- -
- -
- -
- -
- -
520.63 182,220.50
243.55 117,148.51
-2,200.20 -866,878.80
- -
- -
132.15 7,515,917.50 7,515,917.50
- - -
- -
- -
- -
-1,450.00 -253,750.00 -253,750.00
Variation w.r.t 1st RCE (March-2014 P.L.) Variation due to
Inadequate change in
Quantity Amount Price Escalation Change in scope
provision design
12,152.89 255,210.65
- -
- -
- -
43.65 13,618.80
- -
- -
- -
- -
- -
- -
- -
- -
Variation w.r.t 1st RCE (March-2014 P.L.) Variation due to
Inadequate change in
Quantity Amount Price Escalation Change in scope
provision design
- -
- -
- -
- -
- -
- -
- -
- -
- -
-232,727.00 -5,119,994.00
- -
-
Variation w.r.t 1st RCE (March-2014 P.L.) Variation due to
Inadequate change in
Quantity Amount Price Escalation Change in scope
provision design
- -
- -33,682,062.85 -33,682,062.85
Additional
Other causes
requirements
Remarks if any
24 25
-
-45,285,570.00
-6,462,720.00
-219,000.00
-140,000.00
-1,892,970.00
-5,318,775.00
-
-
-
-
ue to
Additional
Other causes
requirements
Remarks if any
-140,000.00
- -
-
-
-
-37,238,772.00
-
-96,300.00
-91,900.00
-11,826.00
-87,500.00
-2,181,200.00
-
-700,000.00
-3,859,856.00
-
-
-15,419,250.00
-333,216.00
-
-
-
ue to
Additional
Other causes
requirements
Remarks if any
-5,356,521.00
-24,100.00
-87,500.00
-87,500.00
-
-
-
-
- -
- -
- -
- -
- -
-65,600.00
-
ue to
Additional
Other causes
requirements
Remarks if any
- -
Analyzed Rate
beyond 125% as
per the provision
of Contract
-17,334.00
-204,750.00
- -
-
-175,567,598.00
4,098,255.00
219,423.75
ue to
Additional
Other causes
requirements
Remarks if any
-376,300.00
31,511,703.04
-
-
-
-
-
182,220.50
117,148.51
-866,878.80
-
ue to
Additional
Other causes
requirements
Remarks if any
-
7,665.00
20,777.00
-
-
-
-
255,210.65
13,618.80
-
-
-
-
ue to
Additional
Other causes
requirements
Remarks if any
-
-
-5,119,994.00
ue to
Additional
Other causes
requirements
Remarks if any
35,559,143.45 -306,386,052.00
NAME OF WORK : CONSTRUCTION OF INTAKE TUNNELS, BRANCH HRT, SFT,BRANCH SFT, ADIT TO DC & ADIT TO GOC-SFT, GOC-DC, ADIT TO G
Sl.No. Description of Items Unit Approved 1st RCE at March,2014 P.L. Completed W
- - -
B7.2 Drilling of 45 mm dia. holes for consolidation
grouting - - -
B7.2.2 In the Desilting Chambers m
306.00 -
B7.2.3 - In HRT and other tunnels m
2,185.00 306.00 668,610.00
B7.3 Drilling for Curtain Grouting for Tunnel Plugs m
180.00 306.00 55,080.00
- - -
B.7.9 Grouting materials - - -
Sl.No. Description of Items Unit Approved 1st RCE at March,2014 P.L. Completed W
B9.1.1.1 In invert - - -
B9.1.1.1.1 -M 20/ A40 m3 2,003.00 3,850.00 7,711,550.00 1,411.90
B9.1.1.1.2 -M 25/ A40 m3 2,081.00 3,938.00 8,194,978.00 321.45
B9.1.1.2 In sidewalls and vaults (Overt) - - -
B9.1.1.2.1 -M 20/ A20 m3 200.00 3,938.00 787,600.00
B9.1.1.2.3 -M 25/ A40 m3 8,388.00 4,113.00 34,499,844.00 6,371.84
B9.1.2 Tunnel plugs - M20/ A40 m3 2,678.00 4,375.00 11,716,250.00
Sl.No. Description of Items Unit Approved 1st RCE at March,2014 P.L. Completed W
fume and steel fibres) in Silt Flushing Tunnel 270.00 5,250.00 1,417,500.00 576.97
Claims
607,461,000.64
GRAND TOTAL
Nu./Rs
AMOUNT OF REVISED ESTIMATE AT MARCH 2016 533.63 Millions
Certified that the quantities executed/to be executed as considered in Revised Cost Estimate above are as p
FT, GOC-DC, ADIT TO GOC-DC, ADIT TO ACCESS SHAFT 1 & 2, ACCESS SHAFT, ADIT TO INTAKE TUNNEL AND GOC-SFT (PACKAGE-C1)
- 210.00 - - -
- - - - - -
- - - - - -
- - - - - -
- - - - -
744.00 470,096.40 744.00 - 631.85 470,096.40
700.00 176,400.00 700.00 - 252.00 176,400.00
- 268.00 - - -
- - - - - -
875.00 514,500.00 875.00 - 588.00 514,500.00
- 656.00 - - -
2nd Revised Cost Estimate (March 2016 PL)
3,763.00 - - -
8.00 189,925.20 8.00 - 23,740.65 189,925.20
- - - - - -
- 24.00 - - -
- - - -
- - - -
350.00 - - -
210.00 - - -
- 2,625.00 - - -
- 569.00 - - -
- 1,750.00 - - -
- 2,625.00 - - -
- - - - - -
- - - - - -
10,500.00 37,604,121.45 10,500.00 - 3,581.34 37,604,121.45
- 9,625.00 - - -
8.00 3,556,621.63 8.00 - 444,577.70 3,556,621.63
31.00 1,128,286.03 31.00 - 36,396.32 1,128,286.03
- 66.00 - - -
13.00 1,313,566.57 13.00 101,043.58 1,313,566.57
2nd Revised Cost Estimate (March 2016 PL)
- - - - - -
- - - - - -
306.00 245,259.00 116.50 306.00 35,649.00 918.00 280,908.00
- - - - - -
- - - - - -
306.00 - - -
- - - - - -
306.00 - - - - -
- 100.00 66.00 6,600.00 100.00 6,600.00
- - - - - -
- 100.00 656.00 65,600.00 100.00 65,600.00
- - - - - -
- 656.00 - - -
- 656.00 - - -
- - - - - -
2,625.00 1,220,625.00 1,860.00 2,625.00 4,882,500.00 2,325.00 6,103,125.00
- - - - - -
- - - - - -
2nd Revised Cost Estimate (March 2016 PL)
- - - - - -
- - - - - -
3,850.00 5,435,807.30 591.10 3,850.00 2,275,742.70 2,003.00 7,711,550.00
3,938.00 1,265,850.41 1,759.56 3,938.00 6,929,127.59 2,081.00 8,194,978.00
- - - - - -
- 200.00 3,938.00 787,600.00 200.00 787,600.00
4,113.00 26,207,397.66 2,016.16 4,113.00 8,292,446.34 8,388.00 34,499,844.00
4,375.00 - 2,678.00 4,375.00 11,716,250.00 2,678.00 11,716,250.00
2nd Revised Cost Estimate (March 2016 PL)
- - - - - -
- - - - -
8.00 12,374,732.41 619,395.27 8.00 4,955,162.17 2,166,236.82 17,329,894.57
- - - - - -
- 22.00 - - -
2nd Revised Cost Estimate (March 2016 PL)
- - -
- - - -
- -
2nd Revised Cost Estimate (March 2016 PL)
159,430.04 159,430.04
50,000,000.00 50,000,000.00
2nd Revised Cost Estimate (March 2016 PL)
ate above are as per the site conditions, construction/planning/Specification drawings issued by the consultants.
Annexure-XVIII
change in Additional
Quantity Amount Price Escalation Change in scope Inadequate provision
design requirements
18 19 20 21 22 23 24
- -
-1,440.00 -660,960.00
- - -
-720.00 -75,600.00
-72.00 -15,120.00
- - -
- -
- -
- -
-2,400.15 -1,785,711.60 -1,785,711.60
- - -
-948.00 -254,064.00 -254,064.00
- - -
- - -
-293.00 -192,208.00
Variation w.r.t 1st RCE March-2014
Variation due to
P.L.
change in Additional
Quantity Amount Price Escalation Change in scope Inadequate provision
design requirements
18 19 20 21 22 23 24
- -
- - -
-2,454.00 -591,414.00
- -
- -
-231.94 -2,232,422.50 -2,232,422.50
- -
-1,960.00 -50,960.00
- -
- -
- -
-15.97 -50,305.50 -50,305.50
- -
-200.05 -752,788.15
- -
- -
-46.00 -1,104.00
change in Additional
Quantity Amount Price Escalation Change in scope Inadequate provision
design requirements
18 19 20 21 22 23 24
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
-0.62 -35,262.50 -35,262.50
- - -
- - -
2,324.23 153,399.31 153,399.31
- -
- -
- -
- - -
- - -
- -
- -
- -
- -
- -
Variation w.r.t 1st RCE March-2014
Variation due to
P.L.
change in Additional
Quantity Amount Price Escalation Change in scope Inadequate provision
design requirements
18 19 20 21 22 23 24
- -
-17,254.34 -21,136,562.09 -21,136,562.09
-84,259.02 -121,670,029.21 -121,670,029.21
-9,484.00 -16,597,000.00
- -
- -
-100.00 -35,000.00
change in Additional
Quantity Amount Price Escalation Change in scope Inadequate provision
design requirements
18 19 20 21 22 23 24
- -
- -
- -
- -
- -
4,115.78 3,062,140.32 3,062,140.32
1,186.00 856,292.00 856,292.00
- - -
1,302.00 1,139,250.00 1,139,250.00
- - -
1,443.00 694,083.00 694,083.00
- - -
-100.00 -175,000.00
-100.00 -262,500.00
change in Additional
Quantity Amount Price Escalation Change in scope Inadequate provision
design requirements
18 19 20 21 22 23 24
- -
-89.20 -5,853,946.88 -5,853,946.88
-700.00 -398,300.00
-700.00 -1,225,000.00
-700.00 -1,837,500.00
- -
- -
291.26 3,058,228.95 3,058,228.95
-100.00 -962,500.00
137,739.07 1,101,912.59 1,101,912.59
2,937.90 91,074.98 91,074.98
-1,500.00 -99,000.00
-20,956.42 -272,433.43 -272,433.43
Variation w.r.t 1st RCE March-2014
Variation due to
P.L.
change in Additional
Quantity Amount Price Escalation Change in scope Inadequate provision
design requirements
18 19 20 21 22 23 24
- -
- -
- -
- - -
- -
- -
- - -
- - -
- -
- -
- - -
- - -
- - -
- - -
Variation w.r.t 1st RCE March-2014
Variation due to
P.L.
change in Additional
Quantity Amount Price Escalation Change in scope Inadequate provision
design requirements
18 19 20 21 22 23 24
- -
-6,961.00 -2,130,066.00 -2,130,066.00
- - -
- -
- - -
- - - -
- - - -
- - - -
- - - -
-100.00 -65,600.00
-100.00 -65,600.00
- - -
- - - -
- - -
- -
- -
Variation w.r.t 1st RCE March-2014
Variation due to
P.L.
change in Additional
Quantity Amount Price Escalation Change in scope Inadequate provision
design requirements
18 19 20 21 22 23 24
- - -
-1.00 -963.00
- - -
-237.00 -15,642.00
-2.00 -22,750.00
- -
- -
- -
- -
- -
- -
- -
- -
- - -
- -
- - -
Variation w.r.t 1st RCE March-2014
Variation due to
P.L.
change in Additional
Quantity Amount Price Escalation Change in scope Inadequate provision
design requirements
18 19 20 21 22 23 24
- -
5.53 -
- -
- - -
- - -
1,927,811.17 15,422,489.37 15,422,489.37
- - -
-1,070.00 -23,540.00
Variation w.r.t 1st RCE March-2014
Variation due to
P.L.
change in Additional
Quantity Amount Price Escalation Change in scope Inadequate provision
design requirements
18 19 20 21 22 23 24
59,694.55 1,372,974.62 1,372,974.62
- - -
- - -
1,150.00 351,900.00 351,900.00
- - -
- -
- -
- -
257.10 14,622,466.95 14,622,466.95
- -
- -
- -
- - -
1,521.04 31,941.84 31,941.84
- -
- -
- - -
- -
- -
change in Additional
Quantity Amount Price Escalation Change in scope Inadequate provision
design requirements
18 19 20 21 22 23 24
4.25 4,092.75 4,092.75
- - -
16.00 624.00 624.00
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
Variation w.r.t 1st RCE March-2014
Variation due to
P.L.
change in Additional
Quantity Amount Price Escalation Change in scope Inadequate provision
design requirements
18 19 20 21 22 23 24
- -13,544,584.48 -13,544,584.48
- -
50,000,000.00 50,000,000.00
Variation w.r.t 1st RCE March-2014
Variation due to
P.L.
change in Additional
Quantity Amount Price Escalation Change in scope Inadequate provision
design requirements
18 19 20 21 22 23 24
-73,833,750.52
Variation due to
Other causes
Remarks If Any
25 26
-
-
-660,960.00
-
-75,600.00
-15,120.00
-
-
-
-
-
-
-192,208.00
Variation due to
Other causes
Remarks If Any
25 26
-
-
-591,414.00
-
-
-
-50,960.00
-
-
-
-752,788.15
-
-
-1,104.00
Variation due to
Other causes
Remarks If Any
25 26
-
-
-
-
-
-
-
-
Variation due to
Other causes
Remarks If Any
25 26
-16,597,000.00
-
-
-35,000.00
Analyzed Rate as
per the Provision
of Contract
Variation due to
Other causes
Remarks If Any
25 26
Analyzed Rate as
per the Provision
of Contract
-175,000.00
-262,500.00
Variation due to
Other causes
Remarks If Any
25 26
-
-42,840.00
-735,000.00
-398,300.00
-1,225,000.00
-1,837,500.00
-962,500.00
-99,000.00
Variation due to
Other causes
Remarks If Any
25 26
-
-
-
Variation due to
Other causes
Remarks If Any
25 26
-65,600.00
-65,600.00
Variation due to
Other causes
Remarks If Any
25 26
-963.00
-
-15,642.00
-22,750.00
-
-
-
Variation due to
Other causes
Remarks If Any
25 26
-23,540.00
Variation due to
Other causes
Remarks If Any
25 26
-
Variation due to
Other causes
Remarks If Any
25 26
-
-
-
-
Variation due to
Other causes
Remarks If Any
25 26
Other causes
Remarks If Any
25 26
-24,903,889.15
NAME OF WORK: CONSTRUCTION OF DESILTING CHAMBERS(PACKAGE-C1)
1 2 3 7
B3 Underground Excavation
1 2 3 7
Quantity Upto BoQ+25% 210.00 - 6,787.22
Quantity Beyond BoQ+25% (Quantity Executed Till
August 2014)
241.92 - 70,040.59
Quantity Beyond BoQ+25% (Quantity Executed
after September 2014)
260.07 - 46,363.28
- -
B3.8 Excavation for enlarging the investigation drift m3 - - -
- -
B4 Rock Stabilization and Supports - -
B4.1 Rockbolts - -
B4.1.1 25 mm dia. - -
B4.1.1.1 - Length up to 4.0 m m 6,600.00 744.00 4,910,400.00 6,954.43
B4.1.1.2 - Length from 4.0m to 6.0 m m 100.00 722.00 72,200.00
B4.1.2 32 mm - - -
B4.1.2.1 - Length up to 6.0 m m 92,520.00 875.00 80,955,000.00 61,360.00
Rock Anchors 32mm dia. Upto 6m length m
- -
1 2 3 7
B4.1.3.2 - Length up to 9 m m 369.00 919.00 339,111.00 369.00
B4.2 Extensions for embedding into concrete,where m
required 8,000.00 481.00 3,848,000.00 8,307.50
1 2 3 7
B4.11 Forepoling (Drilling & Installation) m 820.00 569.00 466,580.00
B4.11.1 Grouting Operations Nos 246.00 1,750.00 430,500.00
B4.12 Piperoofing m 20.00 2,625.00 52,500.00
- - -
B5 Shotcrete - - -
B5.1 SFR Shotcrete in underground works m3 3,881.00 10,500.00 40,750,500.00 3,642.71
B5.4 Cement Variation in Shotcrete kg 122,596.43 8.00 980,771.44 134,973.16
B5.5 Superplasticizer kg 31,052.00 31.00 962,612.00 35,279.58
B5.6 Steel Fibre kg 155,258.00 83.00 12,886,414.00 153,112.64
B5.7 Poly Fibre kg - 66.00 -
B5.8 Micro Silica kg 155,258.00 13.00 2,018,354.00 93,188.91
- - -
B6 Embankment Construction and Backfill - - -
B6.1 Backfill - Random backfill m3 100.00 197.00 19,700.00
- - -
B7 Drilling, Grouting and Pressure Relief Holes
- - -
- - -
Approved 1st RCE at March,2014 P.L.
Completed Work upto Ma
Sl.No. Description of Items Unit
1 2 3 7
B7.1 Drilling for contact grouting - - -
B7.1.1 - In the vault m 867.00 306.00 265,302.00 1,870.20
- - -
B7.2 Drilling of 45 mm dia. holes for consolidation
grouting - - -
B7.2.2 - In the desilting chambers m 21,920.00 306.00 6,707,520.00 11,670.05
B7.4 Drilling of Pressure Relief Holes in the tunnels or
caverns - - -
B7.4.1 - Drilling of 45 mm dia. holes m 6,435.00 306.00 1,969,110.00 3,748.81
B7.4.2 - Supply & installation of PVC pipe 36 mm dia. m 6,435.00 123.00 791,505.00
B7.4.3 - Supply and installation of drain outlet devices Nos.
1,950.00 175.00 341,250.00
B7.5 Drilling of exploratory holes, check holes and holes
for instrumentation in tunnels and caverns - - -
B7.5.1 - Drilling of 45 mm dia. holes m
110.00 306.00 33,660.00
B7.5.2 - Drilling of 76 mm dia. Holes m
260.00 438.00 113,880.00 380.00
B7.5.3 - Drilling of 98 mm dia. Holes m 250.00 875.00 218,750.00 20.00
Approved 1st RCE at March,2014 P.L.
Completed Work upto Ma
Sl.No. Description of Items Unit
1 2 3 7
B7.5.4 - Extra for core recovery m
50.00 2,625.00 131,250.00
1 2 3 7
B9.1 Concrete in Tunnels - - -
B9.4 M25 / A 40 Reinforced Cement Concrete in Desilting m 3
- - -
B10 Formwork - - -
Approved 1st RCE at March,2014 P.L.
Completed Work upto Ma
Sl.No. Description of Items Unit
1 2 3 7
- - -
B10.1 Class F1 m 2
200.00 306.00 61,200.00
B10.2 Class F2 m 2
100.00 350.00 35,000.00
B10.3 Class F3 m 2
17,885.00 394.00 7,046,690.00 16,722.45
B10.4 Class F1C m 2
100.00 481.00 48,100.00
B10.5 Class F2C m 2
100.00 560.00 56,000.00
B10.6 Class F3C m 2
13,724.00 613.00 8,412,812.00 15,047.91
- - -
B11 Reinforcing Steel - - -
- - -
B11.1 Deformed reinforcing bars - Grade Fe 500 Ton 2,267.00 56,875.00 128,935,625.00 2,444.14
B11.2 Plain reinforcing bars Ton 25.00 56,875.00 1,421,875.00
- - -
B13 Metalworks - - -
B13.1 Climbing irons Nos. 270.00 133.00 35,910.00
B13.2 Installation of metalworks supplied by others kg 50,000.00 21.00 1,050,000.00
- - -
B18 Monitoring Instruments - - -
Approved 1st RCE at March,2014 P.L.
Completed Work upto Ma
Sl.No. Description of Items Unit
1 2 3 7
B18.1 Supply , installation and commisioning of monitoring
instruments - - -
B18.1.1 - Load Cells Nos. 20.00 12,600.00 252,000.00 20.00
B18.1.2 - Tape convergence points Nos. 50.00 210.00 10,500.00 44.00
B18.1.3 - Single point borehole extensometer Nos. 10.00 15,400.00 154,000.00 10.00
B18.1.4 - Multiple point borehole extensometer Nos. 20.00 24,500.00 490,000.00 20.00
B18.1.5 - Piezometers Nos. 20.00 6,300.00 126,000.00 20.00
GROUP C : (DAYWORKS) - -
B3 Drilling and Grouting equipment - -
B4.6 Steel cutting, bending and welding equipment - - -
B4.6.2 Welding machine 350.00 - 85.00
Part-C :Labour - -
C2 Category II 66.00 - 129.00
C5.1 Category V (Male) 39.00 - 480.00
- -
- -
Miscelleneous steel works, handrails, rung ladders - - -
etc. MT
- - -
Approved 1st RCE at March,2014 P.L.
Completed Work upto Ma
Sl.No. Description of Items Unit
1 2 3 7
- - -
- - -
Dewatering of underground Construction Sites
including supply,installation and removal of
pumping equipment from the Site 702,727.00 22.00 15,459,994.00
E.I. 1
Approved 1st RCE at March,2014 P.L.
Completed Work upto Ma
Sl.No. Description of Items Unit
1 2 3 7
E.I. 2
Escalation forDeviated Item
1 2 3 7
Certified that the quantities executed/to be executed as considered in Revised Cost Estimate above are as per
consultants.
Variation w.r.t 1st R
2nd Revised Cost Estimate (March 2016 P.L.)
March-2014 Price Le
Quantity
Rate Amount Quantity Rate Amount Quantity Amount
- - - - -
210.00 - - - -
Variation w.r.t 1st R
2nd Revised Cost Estimate (March 2016 P.L.)
March-2014 Price Le
Quantity
Rate Amount Quantity Rate Amount Quantity Amount
- - - - - -
Quantity
Rate Amount Quantity Rate Amount Quantity Amount
- - - - - - -
- - - - - - -
1,750.00 - 1,750.00 - - - -100.00
2,625.00 - 2,625.00 - - - -100.00
267.00 - - 267.00 - - - -
65,625.00 - 2.50 65,625.00 164,062.50 2.50 164,062.50 -47.50
65,625.00 - - 65,625.00 - - - -
70,000.00 - - 70,000.00 - - - -
Quantity
Rate Amount Quantity Rate Amount Quantity Amount
- - - - - - -
- - - - - - -
Variation w.r.t 1st R
2nd Revised Cost Estimate (March 2016 P.L.)
March-2014 Price Le
Quantity
Rate Amount Quantity Rate Amount Quantity Amount
- - - - - - -
- - - - - - -
- - - - - - -
Quantity
Rate Amount Quantity Rate Amount Quantity Amount
- - - - - - -
Quantity
Rate Amount Quantity Rate Amount Quantity Amount
- - - - - -
- - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
Variation w.r.t 1st R
2nd Revised Cost Estimate (March 2016 P.L.)
March-2014 Price Le
Quantity
Rate Amount Quantity Rate Amount Quantity Amount
Quantity
Rate Amount Quantity Rate Amount Quantity Amount
- - - - - - -
- - - - - - -
- - - - - - -
Variation w.r.t 1st R
2nd Revised Cost Estimate (March 2016 P.L.)
March-2014 Price Le
Quantity
Rate Amount Quantity Rate Amount Quantity Amount
- - - - - -
22.00 - - - -702,727.00
- - - - - -
- - - - - -
- - - - - -
Quantity
Rate Amount Quantity Rate Amount Quantity Amount
- - -
366,353.29 366,353.29
13,711.24 13,711.24
Variation w.r.t 1st R
2nd Revised Cost Estimate (March 2016 P.L.)
March-2014 Price Le
Quantity
Rate Amount Quantity Rate Amount Quantity Amount
timate above are as per the site conditions, construction/planning/Specification drawings issued by the
ANNEXURE- XIX
Remarks If
Price Inadequate change in Additional Any
Amount Change in scope Other causes
Escalation provision design requirements
19 20 21 22 23 24 25
280,501.20 280,501.20
-21,943,937.35 -21,943,937.35
4,460,473.50 4,460,473.50
4,592,646.80 4,592,646.80
-
-4,668,905.91 -4,668,905.91
-1,269,842.28 -1,269,842.28
- -
Variation w.r.t 1st RCE
Variation due to
March-2014 Price Level
Remarks If
Price Inadequate change in Additional Any
Amount Change in scope Other causes
Escalation provision design requirements
19 20 21 22 23 24 25
Based on
Analyzed
23,497,520.66 23,497,520.66 Rate as per
the provision
of Contract
-
-
-
-
-
-
390,916.20 390,916.20
1,371,800.00 1,371,800.00
-
-24,202,500.00 -24,202,500.00
- -
11,689,677.00 11,689,677.00
-
-192,600.00 -192,600.00
Variation w.r.t 1st RCE
Variation due to
March-2014 Price Level
Remarks If
Price Inadequate change in Additional Any
Amount Change in scope Other causes
Escalation provision design requirements
19 20 21 22 23 24 25
- -
510,100.50 510,100.50
-
-175,000.00 -175,000.00
-262,500.00 -262,500.00
-3,308,375.00 -3,308,375.00
- -
-3,117,187.50 -3,117,187.50
- - -
- - -
-262,500.00 -262,500.00
-55,080.00 -55,080.00
-94,500.00 -94,500.00
Variation w.r.t 1st RCE
Variation due to
March-2014 Price Level
Remarks If
Price Inadequate change in Additional Any
Amount Change in scope Other causes
Escalation provision design requirements
19 20 21 22 23 24 25
-466,580.00 -466,580.00
-430,500.00 -430,500.00
-52,500.00 -52,500.00
- - -
- - -
-2,502,076.50 -2,502,076.50
99,013.87 99,013.87
131,054.89 131,054.89
-178,064.63 -178,064.63
- - -
-806,898.16 -806,898.16
- - -
- - -
- -
- - -
- - -
- - -
Variation w.r.t 1st RCE
Variation due to
March-2014 Price Level
Remarks If
Price Inadequate change in Additional Any
Amount Change in scope Other causes
Escalation provision design requirements
19 20 21 22 23 24 25
- - -
306,979.20 306,979.20
- -
- -
- -
- -
-821,974.14 -821,974.14
- - -
-341,250.00 -341,250.00
-33,660.00 -33,660.00
52,560.00 52,560.00
-201,250.00 -201,250.00
Variation w.r.t 1st RCE
Variation due to
March-2014 Price Level
Remarks If
Price Inadequate change in Additional Any
Amount Change in scope Other causes
Escalation provision design requirements
19 20 21 22 23 24 25
- -
-61,250.00 -61,250.00
- -
- -
- -
-
-
- -
41,177.88 41,177.88
- -
- -
- -
-
-
Variation w.r.t 1st RCE
Variation due to
March-2014 Price Level
Remarks If
Price Inadequate change in Additional Any
Amount Change in scope Other causes
Escalation provision design requirements
19 20 21 22 23 24 25
-
-13,989,106.78 -13,989,106.78
-
-
- -
-87,500.00 -87,500.00
- - -
21,892,837.04 21,892,837.04
- - -
-130,482.00 -130,482.00
- -
-
-
Variation w.r.t 1st RCE
Variation due to
March-2014 Price Level
Remarks If
Price Inadequate change in Additional Any
Amount Change in scope Other causes
Escalation provision design requirements
19 20 21 22 23 24 25
-
- -
- -
- -
-48,100.00 -48,100.00
-56,000.00 -56,000.00
811,556.83 811,556.83
-
-
-
26,587,356.25 26,587,356.25
-1,308,125.00 -1,308,125.00
- -
- -
- - -
-1,029,000.00 -1,029,000.00
- -
- -
Variation w.r.t 1st RCE
Variation due to
March-2014 Price Level
Remarks If
Price Inadequate change in Additional Any
Amount Change in scope Other causes
Escalation provision design requirements
19 20 21 22 23 24 25
- -
- -
- -
- -
- -
- -
-
-
- -
29,750.00 29,750.00
- -
8,514.00 8,514.00
18,720.00 18,720.00
-
-
- -
-
Variation w.r.t 1st RCE
Variation due to
March-2014 Price Level
Remarks If
Price Inadequate change in Additional Any
Amount Change in scope Other causes
Escalation provision design requirements
19 20 21 22 23 24 25
-
-15,459,994.00 -15,459,994.00
- -
345,885.12 345,885.12
Variation w.r.t 1st RCE
Variation due to
March-2014 Price Level
Remarks If
Price Inadequate change in Additional Any
Amount Change in scope Other causes
Escalation provision design requirements
19 20 21 22 23 24 25
2,791,479.60 2,791,479.60
-8,787,990.11 -8,787,990.11
Variation w.r.t 1st RCE
Variation due to
March-2014 Price Level
Remarks If
Price Inadequate change in Additional Any
Amount Change in scope Other causes
Escalation provision design requirements
19 20 21 22 23 24 25
-6,434,708.82 -8,787,990.11 -79,408,493.26 95,344,371.82 - 4,566,148.72 -18,148,746.00
-6,434,708.82
MANGDECHHU HYDRO
SECOND REVISED CO
Name of work: Head Race Tunnel (PACKAGE-C2)
SECOND REVISED COST ESTIMATE AT MARCH
Approved 1st RCE at March,14 P.L.
Sl. No Description Unit Completed upto March 2016 Balance Works
1.1 Dewatering of Surface Construction Sites KWh 600000.00 22.00 13,200,000.00 0.00 22.00 - 0.00 22.00
2.1 Common excavation Cum 23,627.38 225.00 5,316,160.95 22,272.78 225.00 5,011,375.95 0.00 225.00
2.2 Rock excavation Cum 15296.53 405.00 6,195,094.65 3296.53 405.00 1,335,094.65 0.00 405.00
2.3 Control perimeter blasting Sqm 200.00 450.00 90,000.00 79.96 450.00 35,982.00 0.00 450.00
2.4 Line drilling m 500.00 360.00 180,000.00 360.00 - 0.00 360.00
2.5 Dental excavation Cum 100.00 450.00 45,000.00 450.00 - 0.00 450.00
2.6 Minor excavation Cum 104.27 450.00 46,921.50 540.17 450.00 243,076.50 0.00 450.00
2.7 Removal of material arising from overbreak Cum 3300.00 108.00 356,400.00 28.094 108.00 3,034.15 0.00 108.00
7.3.1 Drilling of 45 mm dia hole m 332.20 360.00 119,592.00 332.20 360.00 119,592.00 0.00 360.00
Supply and installation of 36 mm dia PVC
7.3.2 m 271.40 126.00 34,196.40 271.40 126.00 34,196.40 0.00 126.00
pipes
7.3.3 Supply and installation of drain outlet devices Nos. 50.00 270.00 13,500.00 270.00 - 0.00 270.00
- - 0.00
7.4 Grouting materials - - 0.00
7.4.1 Cement MT 110.80 9000.00 997,200.00 110.80 9000.00 997,200.00 0.00 9000.00
7.4.2 Sand MT 2.92 990.00 2,890.80 2.92 990.00 2,890.80 0.00 990.00
7.4.3 Bentonite MT 0.00 11700.00 - 11700.00 - 0.00 11700.00
7.4.4 Admixtures Kg 0.00 68.00 - 68.00 - 0.00 68.00
- - 0.00
A8 Not Used - - 0.00
- - 0.00
A9 Concrete - - 0.00
9.1 M15/A40 grade concrete Cum 606.35 3240.00 1,964,567.52 1069.84 3240.00 3,466,281.60 0.00 3240.00
9.2 M25/A40 grade concrete Cum 291.49 3960.00 1,154,300.40 291.49 3960.00 1,154,300.40 0.00 3960.00
9.3 Cement variation in concrete Kg 20622.12 8.00 164,976.96 49882.92 8.00 399,063.36 0.00 8.00
9.4 Admixtures -
9.4.1 Air-entraining agent kg 0.00 23.00 - 23.00 - 0.00 23.00
9.4.2 Water-reducing agent kg 1091.76 24.00 26,202.29 2127.05 24.00 51,049.25 0.00 24.00
- - 0.00
A10 Formwork - - 0.00
Name of work: Head Race Tunnel (PACKAGE-C2)
SECOND REVISED COST ESTIMATE AT MARCH
Approved 1st RCE at March,14 P.L.
Sl. No Description Unit Completed upto March 2016 Balance Works
10.1 Class F1 Sqm 306.30 360.00 110,269.44 306.30 360.00 110,269.44 0.00 360.00
10.2 Class F2 Sqm 93.90 405.00 38,029.91 157.62 405.00 63,836.51 0.00 405.00
10.3 Class F1C Sqm 0.00 540.00 - 540.00 - 0.00 540.00
10.4 Class F2C Sqm 33.93 585.00 19,849.05 33.93 585.00 19,849.05 0.00 585.00
- - 0.00
A11 Reinforcing Steel - - 0.00
11.1 Deformed Reinforcing bars - Grade Fe 500 MT 3.71 54000.00 200,340.00 6.99 54000.00 377,460.00 0.00 54000.00
11.2 Plain reinforcing bars MT 0.00 53105.00 - 53105.00 - 0.00 53105.00
- - 0.00
A12 Not Used - - 0.00
A13 Not Used - - 0.00
A14 Not Used - - 0.00
A15 Not Used - - 0.00
- - 0.00
A16 Miscellaneous and Ancillary Works - - 0.00
16.1 Fencing and gates - - 0.00
16.1.1 Fencing m 125.00 900.00 112,500.00 900.00 - 125.00 900.00
16.1.2 Gates Nos. 5.00 90000.00 450,000.00 90000.00 - 5.00 90000.00
- - 0.00
16.2 Weep holes Nos. 100.00 186.00 18,600.00 186.00 - 0.00 186.00
- - 0.00
16.3 PVC Pipes - - 0.00
16.3.1 50 mm dia m 692.90 124.00 85,919.60 302.05 124.00 37,454.20 0.00 124.00
16.3.2 75 mm dia m 548.00 319.00 174,812.00 48.00 319.00 15,312.00 0.00 319.00
- -
-
B2 Not Used -
-
B3 Underground Excavation -
-
Excavation of Head Race Tunnel &
3.1 -
Construction Adits
3.1.1 Class I, II, & III Cum 528000.00 1215.00 641,520,000.00 446498.52 1215.00 542,495,695.73 116700.00 1215.00
3.1.2 Class IV and V Cum 203000.00 1350.00 274,050,000.00 141016.07 1350.00 190,371,694.50 39800.00 1350.00
Excavation by multidrifting due to geological
3.1.3 Cum 34842.31 1800.00 62,716,166.31 16927.17 1800.00 30,468,904.20 200.00 1800.00
reasons
3.2 Line drilling m 36977.91 360.00 13,312,046.90 13736.50 360.00 4,945,140.00 600.00 360.00
3.3 Dental excavation Cum 1000.00 540.00 540,000.00 540.00 - 0.00 540.00
4.1.2 Length more than 4.0m and upto 6.0 m m 12858.40 675.00 8,679,417.45 22610.20 675.00 15,261,885.00 675.00
4.8 Steel lagging including all the steel accessories MT 251.79 67500.00 16,995,487.50 38.90 67500.00 2,625,750.00 67500.00
Deviated
Steel lagging including all the steel accessories - 286.408 73823.00 21,143,497.78 20.00 73823.00
Item
4.9 Precast concrete lagging Cum 4600.00 8550.00 39,330,000.00 1910.63 8550.00 16,335,912.15 1000.00 8550.00
4.10 Pregrouting 0.00 - -
4.10.1 Drilling for Pregrouting m 16900.00 360.00 6,084,000.00 1388.60 360.00 499,896.00 60.00 360.00
4.10.2 Grouting Operations Nos. 1700.00 1800.00 3,060,000.00 272.00 1800.00 489,600.00 15.00 1800.00
4.11 Fore poling 0.00 - -
4.11.1 Fore poling m 29511.30 585.00 17,264,110.50 26781.30 585.00 15,667,060.50 720.00 585.00
4.11.2 Grouting Operations Nos. 1800.00 1800.00 3,240,000.00 156.00 1800.00 280,800.00 70.00 1800.00
Miscellaneous steel MT 0.00 - -
4.12 Pipe Roofing m 20000.00 900.00 18,000,000.00 7133.00 900.00 6,419,700.00 6200.00 900.00
- -
B5 Shotcrete - -
5.1 SFR Shotcrete without SFR Cum 20000.00 10800.00 216,000,000.00 19356.06 10800.00 209,045,480.40 6100.00 10800.00
5.2 Plain Shotcrete Cum 3000.00 9900.00 29,700,000.00 1605.32 9900.00 15,892,677.90 1100.00 9900.00
5.3 PFR excluding (Polyfibres) Shotcrete Cum 4357.76 10800.00 47,063,797.20 4530.22 10800.00 48,926,343.60 10800.00
5.4 Cement variation in shotcrete Kg 166844.80 8.00 1131941.30 8.00 9,055,530.36 413410.00 8.00
5.5 Superplasticizer Kg 217000.00 32.00 6,944,000.00 176085.95 32.00 5,634,750.53 67830.00 32.00
5.6 Steel fibre Kg 700000.00 86.00 60,200,000.00 774167.48 86.00 66,578,403.54 241120.00 86.00
5.7 Poly Fibre Kg 12300.00 68.00 836,400.00 9060.42 68.00 616,108.63 0.00 68.00
5.8 Micro silica Kg 800000.00 14.00 11,200,000.00 568899.32 14.00 7,964,590.48 176570.00 14.00
- -
B6 Not Used - -
Name of work: Head Race Tunnel (PACKAGE-C2)
SECOND REVISED COST ESTIMATE AT MARCH
Approved 1st RCE at March,14 P.L.
Sl. No Description Unit Completed upto March 2016 Balance Works
- -
Drilling, Grouting and Pressure Relief
B7 - -
Holes
- -
7.1 Drilling for contact grouting - -
7.1.1 In the HRT m 17000.00 360.00 6,120,000.00 3.95 360.00 1,422.00 17000.00 360.00
7.1.2 For tunnel plug m 850.00 360.00 306,000.00 360.00 - 850.00 360.00
- -
Drilling of 45 dia holes for Consolidation
7.2 - -
grouting
7.2.1 In HRT m 54000.00 360.00 19,440,000.00 102.00 360.00 36,720.00 66560.00 360.00
7.2.2 In Adits m 4100.00 360.00 1,476,000.00 807.60 360.00 290,736.00 0.00 360.00
7.2.3 For grouting of tunnel plug m 6600.00 360.00 2,376,000.00 360.00 - 6600.00 360.00
- -
7.3 Curtain Grouting - -
7.3.1 Drilling for curtain grouting for tunnel plugs m 1100.00 360.00 396,000.00 360.00 - 1100.00 360.00
7.3.2 Grouting operations Nos. 50.00 1800.00 90,000.00 1800.00 - 50.00 1800.00
- -
7.4.1 Drilling of 45 mm dia hole m 45000.00 360.00 16,200,000.00 2872.00 360.00 1,033,920.00 39090.00 360.00
7.4.2 36 mm dia PVC pipes m 45000.00 126.00 5,670,000.00 32.90 126.00 4,145.40 39570.00 126.00
7.4.3 Drain outlet devices Nos. 200.00 270.00 54,000.00 270.00 - 200.00 270.00
- -
Drilling of exploratory holes, check holes and
7.5 - -
holes for instrumentation
7.5.1 Drilling of 45mm dia holes m 3400.00 360.00 1,224,000.00 71.00 360.00 25,560.00 0.00 360.00
7.5.2 Drilling of 76mm dia holes m 2400.00 540.00 1,296,000.00 4560.50 540.00 2,462,670.00 15.00 540.00
7.5.3 Drilling of 98mm dia holes m 100.00 900.00 90,000.00 900.00 - 90.00 900.00
7.5.4 Extra for core recovery m 2000.00 3600.00 7,200,000.00 3600.00 - 0.00 3600.00
- -
7.6 Water pressure testing - simple water test No.s 150.00 900.00 135,000.00 900.00 - 0.00 900.00
- -
Embedded pipes and fittings for grouting left
7.7 Kg 2000.00 68.00 136,000.00 568.59 68.00 38,664.12 1660.00 68.00
permanently in place
- -
7.8 Placing grout (Excluding cement) - -
7.8.1 Contact grouting m 500.00 720.00 360,000.00 720.00 - 500.00 720.00
- -
7.8.2 Fill grouting - -
7.8.2.1 In Temporary drainage system m 500.00 720.00 360,000.00 720.00 - 0.00 720.00
7.8.2.2 In exploratory holes m 300.00 720.00 216,000.00 720.00 - 0.00 720.00
- -
Consolidation grouting including grouting for
7.8.3 - -
tunnel plug
7.8.3.1 -Single stage grouting Nos. 9600.00 2250.00 21,600,000.00 157.00 2250.00 353,250.00 8300.00 2250.00
Name of work: Head Race Tunnel (PACKAGE-C2)
SECOND REVISED COST ESTIMATE AT MARCH
Approved 1st RCE at March,14 P.L.
Sl. No Description Unit Completed upto March 2016 Balance Works
7.8.3.2 -Multiple stage grouting Stage 500.00 1800.00 900,000.00 2095.00 1800.00 3,771,000.00 100.00 1800.00
7.9 Grouting materials - -
- -
7.9.1 Cement MT 12000.00 9000.00 108,000,000.00 2875.53 9000.00 25,879,788.00 9500.00 9000.00
7.9.2 Sand MT 110.63 900.00 99,566.00 40.00 900.00 36,000.00 1.00 900.00
7.9.3 Bentonite MT 10.00 11700.00 117,000.00 112.46 11700.00 1,315,782.00 8.00 11700.00
7.9.4 Admixtures Kg 10000.00 68.00 680,000.00 280.00 68.00 19,040.00 9270.00 68.00
7.9.5 Microfine/ Ultrafine Cement MT 100.00 13500.00 1,350,000.00 28.26 13500.00 381,550.50 72.00 13500.00
-
B8 Not Used -
-
B9 Concrete -
-
9.1 Concrete in Tunnels -
9.1.1.1 In Invert - -
9.1.1.1.1 -M 25/ A40 Cum 42000.00 4050.00 170,100,000.00 1315.75 4050.00 5,328,771.30 41800.00 4050.00
9.1.1.1.2 -M 20/ A40 Cum 4500.00 3780.00 17,010,000.00 3625.83 3780.00 13,705,637.40 980.00 3780.00
9.1.1.2 In sidewalls and vaults (Overt) - -
9.1.1.2.1 -M 25/ A40 Cum 141000.00 4230.00 596,430,000.00 15150.04 4230.00 64,084,656.51 158660.00 4230.00
9.1.1.2.2 -M 20/ A40 Cum 50.00 4050.00 202,500.00 96.85 4050.00 392,242.50 44.00 4050.00
9.1.2 -M25/ A40 Reinforced Cement Concrete Cum 8000.00 4320.00 34,560,000.00 320.43 4320.00 1,384,257.60 6720.00 4320.00
9.1.3 Tunnel plugs - M20/ A40 Cum 4100.00 3849.00 15,780,900.00 224.49 3849.00 864,062.01 2780.00 3849.00
Blockout concrete M30/A20 for gates
9.2 Cum 10.00 4500.00 45,000.00 4500.00 - 10.00 4500.00
equipmenmt embeddment
M15/A40 backfill concrete in underground
9.3 excavations in geologically approved Cum 24007.30 3060.00 73,462,328.35 21245.12 3060.00 65,010,067.20 0.00 3060.00
overbreaks
9.4 Cement variation in concrete kg 484687.90 8.00 3,877,503.21 5239797.75 8.00 41,918,382.01 22693700.00 8.00
9.5 Admixtures - -
9.5.1 Air-entraining agent kg 33000.00 23.00 759,000.00 23.00 - 23.00
9.5.2 Water-reducing agent kg 1290000.00 26.00 33,540,000.00 208557.56 26.00 5,422,496.51 11518900.00 26.00
- -
B10 Not Used - -
- -
B11 Reinforcement Steel - -
Name of work: Head Race Tunnel (PACKAGE-C2)
SECOND REVISED COST ESTIMATE AT MARCH
Approved 1st RCE at March,14 P.L.
Sl. No Description Unit Completed upto March 2016 Balance Works
11.1 Deformed Reinforcing bars - Grade Fe 500 MT 800.00 54000.00 43,200,000.00 148.87 54000.00 8,038,872.00 550.00 54000.00
11.2 Plain reinforcing bars MT 5.00 54000.00 270,000.00 54000.00 - 0.00 54000.00
- -
B12 Not Used - -
- -
B13 Metalworks - -
13.1 Installation of metalworks supplied by others Kg 600.00 22.00 13,200.00 22.00 - 600.00 22.00
- -
B14 Not Used - -
B15 Not Used - -
B16 Not Used - -
B17 Not Used - -
- -
B18 Monitoring Instruments - -
Supply, installation and commissioning of
18.1 - -
monitoring instrument
18.1.1 Load cells Nos. 30.00 41040.00 1,231,200.00 10.00 41040.00 410,400.00 10.00 41040.00
18.1.2 Tape convergence points Nos. 120.00 216.00 25,920.00 72.00 216.00 15,552.00 28.00 216.00
18.1.3 Single point borehole extensometer Nos. 30.00 15840.00 475,200.00 15840.00 - 0.00 15840.00
18.1.4 Multi point borehole extensometer Nos. 10.00 25200.00 252,000.00 3.00 25200.00 75,600.00 7.00 25200.00
18.1.5 Piezometers Nos. 20.00 6480.00 129,600.00 6480.00 - 20.00 6480.00
The monitoring instruments taken as 1% of
-
Group A&B Total
Extra Items - -
32mm dia Forepoling. m 23383.80 936.00 21,887,236.80 26391.80 766.00 20,216,118.80 1150.00 766.00
60.3mm dia Piperoofing. m 1791.61 1034.71 1,853,796.78 1791.61 753.59 1,350,139.38 90.00 753.59
Boulder Wall Cum 783.10 614.21 480,986.62 783.10 614.21 480,986.62 0.00 614.21
Drilling of 125mm dia holes for grouting
m - 4362.00 4845.36 21,135,460.32 4845.36
operations
DAY WORK - -
Group C: Part-A, Material 0.00 15,385,500.00 0.00 - 0.00
Concrete aggregate & cement at
A1 batching plants - -
A1.1 Course aggregate cum 720.00 - 363.21 720.00 261,511.20 300.00 720.00
A1.1 Fine Aggregate cum 300.00 765.00
A1.3 Cement t 200.00 7200.00
Name of work: Head Race Tunnel (PACKAGE-C2)
SECOND REVISED COST ESTIMATE AT MARCH
Approved 1st RCE at March,14 P.L.
Sl. No Description Unit Completed upto March 2016 Balance Works
A2 Explosives kg 72.00 - 1.56 72.00 112.32 100.00 72.00
A2.1 Detonator nos 20.00 - 14.00 20.00 280.00 20.00 20.00
A3 Steel - - 0.00
A3.1 Reinforcing Steel t 45000.00 - 2.406 45000.00 108,270.00 98.00 45000.00
A3.2 Structural steel t 45000.00 - 16.36 45000.00 736,200.00 85.00 45000.00
- -
Group C:- Part-B, Equipments 35,715,000.00 -
B1.1.1 Excavator below 1.2cum Hrs 1350.00 - 41.00 1350.00 55,350.00 20.00 1350.00
B1.1.2 Excavator 1.2 to 2.4cum Hrs 2250.00 - 156.92 2250.00 353,070.00 80.00 2250.00
B1.1.4 Loaders below 2 cum Hrs 1350.00 - 81.17 1350.00 109,579.50 40.00 1350.00
B1.1.5 Loaders 2cum to 3.5cum Hrs 2250.00 - 43.67 2250.00 98,257.50 25.00 2250.00
B1.2.1 Dumpers below 15 T Hrs 900.00 - 20.50 900.00 18,450.00 10.00 900.00
B1.2.2 Dumpers 15 - 35 T Hrs 1350.00 - 114.75 1350.00 154,912.50 60.00 1350.00
B1.4.3 Jack Hammers heavy duty Hrs 540.00 - 144.80 540.00 78,192.00 70.00 540.00
B1.4.4 Drilling Jumbos 2 booms Hrs 6300.00 - 213.10 6300.00 1,342,530.00 50.00 6300.00
B2.2.1 Transit Mixer 6cum or less Hrs 1350.00 - 113.30 1350.00 152,955.00 60.00 1350.00
0.00
0.00 0.00 0.00 0.00 0.00
0.00 2127.05 51049.25 1035.29 24846.96 24846.96
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
TE AT MARCH,16 PRICE LEVEL Variation due to
Variation w.r.t. 1st RCE March 2014 P.L.
Balance Works Total
Change in Additional
Price escalation Change in scope Inadequate provision
0.00 306.30 110269.44 0.00 0.00 Design requirement
0.00 0.00
0.00 0.00
15367500.00 274103.38 61673260.50 -139896.62 -31476739.50 -31476739.50
22086000.00 94554.39 51059370.60 25554.39 13799370.60 13799370.60
0.00 0.00 0.00 0.00 0.00
0.00 1303.54 1994420.79 -9696.46 -14835579.21 -14835579.21
0.00 0.00 0.00 -1100.00 -1089000.00 -1089000.00
0.00 0.00 0.00 -500.00 -585000.00 -585000.00
0.00 0.00 0.00 -500.00 -2250000.00 -2250000.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
2207606688.25 0.00
TE AT MARCH,16 PRICE LEVEL Variation due to
Variation w.r.t. 1st RCE March 2014 P.L.
Balance Works Total
Change in Additional
Price escalation Change in scope Inadequate provision
Design requirement
0.00 0.00 0.00
1,335,516,943.51
Variation due to
25
Variation due to
Analyzed Rate
beyound 125%
Quantity(As per
the provision of the
Contract)
Variation due to
Analyzed Rate
beyound 125%
Quantity(As per
the provision of the
Contract)
Variation due to
-790218.00
Rate in RCE-2014
was provisional.
The Final analyzed
rate is lower than
the provisional rate
-435834.30 approved by
CEA/CWC.
-15385500.00
Variation due to
-35715000.00
Variation due to
DAB Award in
80111041.61 favour of
Contractor
The Incentive
Proposal for
Expediting &
290000000.00
Lining Works
approved by the
MHPA Authority
94571759.61
6710352.50
10000000.00
429,066,601.42
429066601.42
MANGDE CHUU HYD
3.2.3
Excavation of cable trench below EL
cu.m
934.00
0.00 - 934.00 -
934.00
1028.40 in Transformer Cavern.
3.2.4 Line drilling. m 340.00 0.00 - 340.00 - 340.00
3.2.5 Dental excavation. cu.m 509.00 0.00 - 509.00 - 509.00
Excavation of Surge shaft in all classes
3.3 0.00 -
of rock.
3.3.1 Raise boring. m 0.00 25,470.00 0.00 - 25,470.00 - 25,470.00
3.3.2 Excavation by slashing. cu.m 0.00 1,189.00 0.00 - 1,189.00 - 1,189.00
Excavation of pressure shafts in all
3.4 0.00 -
classes of rock
3.4.1 Raise boring. m 25,470.00 0.00 - 25,470.00 - 25,470.00
3.4.2 Excavation by slashing. cu.m 1,528.00 0.00 - 1,528.00 - 1,528.00
3.4.3
Excavation of horizontal portions of
cu.m
1,019.00
0.00 - 1,019.00 -
1,019.00
pressure shafts.
Excavation of vertical gate operation 2,547.00 2,547.00
3.5 shafts for TRT tunnel, cable shafts etc in cu.m 0.00 - 2,547.00 -
any material.
Removal of material arising from
3.6 cu.m
3,375.00 255.00
860,625.00 7,349.94 255.00 1,874,234.70
255.00
overbreak accepted due to geological
conditions.
3.7
Extra for hauling excavated materials
cu.m
0.00 102.00
0.00 - 102.00 -
102.00
beyond 1 km upto 3 km.
3.7.1
Extra for hauling excavated materials
cu.m
0.00 204.00
0.00 - 204.00 -
204.00
beyond 3 km upto 5km.
B4 Rock stabilization and Supports 0.00 -
4.1 Rockbolts 25 mm dia. 0.00 -
4.1.1 Length upto 4.0 m. m 637.00 0.00 - 637.00 - 637.00
4.1.2 Length more than 4.0 m and upto 6.0 m. m 616.00 0.00 - 616.00 - 616.00
4.2 Rockbolts 32 mm dia. 0.00 -
4.2.1 Length upto 6.0 m. m 2,736.00 764.00 2,090,304.00 - 764.00 - 764.00
4.2.2 Length more than 6.0 m and upto 9.0 m. m 23,000.00 722.00 16,606,000.00 612.00 722.00 441,864.00 722.00
Length more than 9.0 m and upto 12.0
4.2.3 m 700.00 0.00 - 700.00 - 700.00
m.
4.3 Rockbolts 36 mm dia. 0.00 -
4.3.1 Length upto 6.0 m. m 934.00 0.00 30.00 934.00 28,020.00 934.00
4.3.2 Length more than 6.0 m and upto 9.0 m. m 849.00 0.00 - 849.00 - 849.00
Length more than 9.0 m and upto 12.0
4.3.3 m 722.00 0.00 11,052.00 722.00 7,979,544.00 722.00
m.
4.4 Post tensioned rockbolts (tendons). 0.00 -
4.4.1 25 m long. m 1,358.00 0.00 - 1,358.00 - 1,358.00
0.00 -
4.5 Rockbolt testing No. 100.00 849.00 84,900.00 - 849.00 - 849.00
SURGE SHAFT (PACKAGE-C3)
7.9.1
Contact grouting ordered by the
m
594.00
0.00 - 594.00 -
594.00
Engineer-in-Charge.
7.9.2 Fill grouting. 0.00 -
7.9.2.1 In Temporary drainage system. m 594.00 0.00 - 594.00 - 594.00
7.9.2.2 In exploratory holes. m 594.00 0.00 - 594.00 - 594.00
Consolidation grouting including
7.9.3 0.00 -
grouting for tunnel plug.
7.9.3.1 -Single stage grouting. No. 116.00 2,123.00 246,268.00 2,357.00 2,123.00 5,003,911.00 2,123.00
7.9.3.2 -Multiple stage grouting. stage 1,698.00 0.00 111.00 1,698.00 188,478.00 1,698.00
7.10 Grouting materials 0.00 -
7.10.1 Cement MT 2,674.00 8,490.00 22,702,260.00 1,204.75 8,490.00 10,228,327.50 1,469.25 8,490.00
7.10.2 Sand MT 594.00 0.00 - 594.00 - 594.00
7.10.3 Bentonite MT 16.00 11,037.00 176,592.00 - 11,037.00 - 11,037.00
SURGE SHAFT (PACKAGE-C3)
9.2.1
Cement concrete lining M25/A40 in
cu.m
13,500.00 3,396.00
45,846,000.00 2,368.22 3,396.00 8,042,475.12
11,131.78 3,396.00
Surge Shaft
Backfill concrete M15/A40 behind steel 2,377.00 2,377.00
9.2.2 cu.m 0.00 2,377.00 -
liner in Pressure shaft
Cement concrete M25/A40 in TRT gate 3,311.00 3,311.00
9.2.3 cu.m 0.00 - 3,311.00 -
shaft & cable shaft
9.2.4 Concrete in Blockouts M30/ A20 cu.m 0.00 3,651.00 0.00 - 3,651.00 - 153.00 3,651.00
Concrete in Power house and
9.3 0.00 -
Transformer cavern
Cement concrete M25/A20 in 3,396.00 3,396.00
9.3.1 cu.m 0.00 - 3,396.00 -
substructure of power house
Cement concrete M25/A20 upto turbine 3,396.00 3,396.00
9.3.2 cu.m 0.00 - 3,396.00 -
floor of power house
9.3.3
Cement concrete M25/A20 for generator
cu.m
3,396.00
0.00 - 3,396.00 -
3,396.00
barrel in power house
9.3.4
Cement concrete M25/A40 in beams,
cu.m
3,396.00
0.00 - 3,396.00 -
3,396.00
columns, slabs, walls, raft etc.
9.3.5 Cement concrete M15/A40 cu.m 250.48 2,462.00 616,681.76 - 2,462.00 - 2,462.00
M15/A40 backfill concrete in 0.00 2,462.00 2,462.00
9.4 underground excavations in geologically cu.m 0.00 3,018.93 2,462.00 7,432,605.66
approved overbreaks
9.5
M25/A20 precast concrete including
cu.m
3,566.00
0.00 - 3,566.00 -
3,566.00
formwork
9.6 Cement variation in concrete kg 1,609,290.00 8.00 12,874,320.00 651,381.46 8.00 5,211,051.68 ### 8.00
9.7 Admixtures for concrete 0.00 -
9.7.1 Air-entraining agent kg 0.00 22.00 0.00 - 22.00 - 22.00
SURGE SHAFT (PACKAGE-C3)
14.1
Supply and erection of supporting steel
MT
63,675.00
0.00 - 63,675.00 -
63,675.00
structure for false ceiling
B15 Building and Architectural Works 0.00 -
15.1
Building and Architectural works in
L.S.
24,123,909.00
0.00 - 24,123,909.00 -
###
Power house and Transformer cavern
15.2
Building and Architectural works in D.G.
L.S.
8,490,000.00
0.00 - 8,490,000.00 -
###
building of pothead yard
15.3 Suspended ceiling sq.m 2,547.00 0.00 - 2,547.00 - 2,547.00
B16 Miscellaneous and Ancillary Works 0.00 -
16.1 Concrete pipes 0.00 -
16.1.1 Drain pipes on concrete or sand base 0.00 -
16.1.1.1 100 mm dia m 448.00 0.00 - 448.00 - 448.00
16.1.1.2 200 mm dia m 554.00 0.00 - 554.00 - 554.00
16.1.1.3 300 mm dia m 844.00 0.00 - 844.00 - 844.00
16.1.2 Pipes fully embedded in concrete 0.00 -
16.1.2.1 200 mm dia m 554.00 0.00 - 554.00 - 554.00
16.1.2.2 300 mm dia m 844.00 0.00 - 844.00 - 844.00
16.1.2.3 400 mm dia m 1,007.00 0.00 - 1,007.00 - 1,007.00
16.2 PVC Pipes 0.00 -
16.2.1 50 mm dia m 117.00 0.00 - 117.00 - 117.00
16.2.2 75 mm dia m 301.00 0.00 - 301.00 - 301.00
16.2.3 100 mm dia m 435.00 0.00 147.29 435.00 64,071.15 850.00 435.00
16.2.4 200 mm dia m 1,636.00 0.00 - 1,636.00 - 1,636.00
16.2.5 300 mm dia m 4,040.00 0.00 - 4,040.00 - 4,040.00
16.3 SWG Pipes 0.00 -
16.3.1 100 mm dia m 849.00 0.00 - 849.00 - 849.00
16.3.2 150 mm dia half round pipes m 1,698.00 0.00 - 1,698.00 - 1,698.00
B17 Not Used 0.00 -
B18 Monitoring Instruments 0.00 -
SURGE SHAFT (PACKAGE-C3)
A4.1
Cement catridges 32 mm diameter, 300
No.
8.00
0.00 8.00 -
8.00
mm long
A4.2
Resin Catridges 32 mm diameter, 300
No.
34.00
0.00 34.00 -
34.00
mm long
A4.3 Plywood 3 mm m2 255.00 0.00 255.00 - 255.00
Plywood 6 mm m2 849.00 0.00 849.00 - 849.00
Plywood 12 mm m2 1,698.00 0.00 1,698.00 - 1,698.00
A4.4 Wooden batten m3 4,245.00 0.00 4,245.00 - 4,245.00
A5 Construction Power KWH 4.00 0.00 4.00 - 4.00
Total for Group C - Part A 0.00 -
Part B Equipment 0.00 -
Earthmoving and excavation
B1 0.00 -
equipment
B1.1 Tracked/wheeled excavators and loaders 0.00 -
B 1.1.1 Excavator below 1.2m3 Hour 1,274.00 975.00 1,274.00 1,242,150.00 1,274.00
B1.1.2 Excavator 1.2M3 to 2.4 m3 Hour 2,123.00 2,123.00 - 2,123.00
B1.1.3 Excavator above 2.4 m3 Hour 2,547.00 2,547.00 - 2,547.00
B1.1.4 Loaders below 2 m3 Hour 1,274.00 1,274.00 - 1,274.00
B1.1.5 Loaders 2 M3 to 3.5 m3 Hour 2,123.00 2.00 2,123.00 4,246.00 2,123.00
B1.2 Dump trucks and lorries Hour -
B1.2.1 Dumpers below 15 T Hour 849.00 811.00 849.00 688,539.00 849.00
B1.2.2. Dumpers 15-35 T Hour 1,274.00 1,274.00 - 1,274.00
B1.3 Dozers and scrapers Hour -
B1.3.1 Dozers upto 100 HP Hour 1,698.00 1,698.00 - 1,698.00
B1.3.2 Dozers 100 HP to 300 HP Hour 2,547.00 7.00 2,547.00 17,829.00 2,547.00
Other earthmoving and excavation
B1.4 Hour -
equipment
B1.4.1 Crawler drills Hour 1,274.00 1,274.00 - 1,274.00
B1.4.2 Wagon drills Hour 1,104.00 1,104.00 - 1,104.00
B1.4.3 Jack hammers- heavy duty Hour 509.00 509.00 - 509.00
B1.4.4 Drilling Jumbos 2 booms Hour 5,943.00 5,943.00 - 5,943.00
B.1.4.5 Rockbolter Hour 4,245.00 4,245.00 - 4,245.00
Concreting mixing/placing
B2 0.00 -
equipment
Concrete batching and mixing
B2.1 0.00 -
equipment
SURGE SHAFT (PACKAGE-C3)
B2.1.2
Concrete batching and mixing plant 30
Hour
2,123.00
2,123.00 -
2,123.00
to 60 m3/hr
B2.2 Truck mixers Hour -
B2.2.1 Transit mixers 6 m3 or less Hour 1,274.00 1,274.00 - 1,274.00
B2.3 Concrete Pumps upto 30m3/hr Hour 1,189.00 1,189.00 - 1,189.00
B2.4
Concrete vibration equipment (Needle
Hour
425.00
425.00 -
425.00
type)( 90-150 mm diameter)
B2.5 Shotcreting equipment Hour -
B2.5.1 Shotcreting equipment(Dry Shotcrete) Hour 849.00 849.00 - 849.00
Shotcrete machine with robot arm (Wet 3,821.00 3,821.00
B2.5.2 Hour 3,821.00 -
Shotcrete)
B3 Drilling and Grouting equipment 0.00 -
B3.1
Percussion drilling rigs/equipment
Hour
1,274.00
1,274.00 -
1,274.00
(above and below ground)
B3.2
Rotary drilling rigs/equipment (above
Hour
2,123.00
2,123.00 -
2,123.00
and below ground)
Grout mixers and pumps (above and
B3.3 Hour -
below ground)
B3.3.1 Grout pumps (mortar grout) Hour 849.00 849.00 - 849.00
B3.3.2 Grout pumps (cement grout) Hour 594.00 594.00 - 594.00
B4 Miscellaneous equipment 0.00 -
B4.1 Mobile cranes and lifting equipment 0.00 -
B4.1.1 Mobile crane below 15 T Hour 849.00 0.00 849.00 - 849.00
B4.1.2 Mobile crane 15 to 25 T Hour 1,698.00 1,698.00 - 1,698.00
B4.2 Low pressure water pumps Hour -
B.4.2.1 Dewatering pumps below 10 HP Hour 594.00 594.00 - 594.00
B4.3 High pressure water pumps Hour -
B.4.3.1 Dewatering pumps above 10 HP Hour 849.00 849.00 - 849.00
B4.4 Air compressors Hour -
B4.4.1 Air compressors upto 300 cfm. Hour 849.00 849.00 - 849.00
B4.4.2 Air compressors above 300 cfm. Hour 934.00 934.00 - 934.00
B4.5 Generating sets Hour -
B4.5.1 Diesel generating sets upto 650 KVA Hour 5,943.00 5,943.00 - 5,943.00
B4.5.2 Diesel generating sets 750 KVA Hour 8,490.00 8,490.00 - 8,490.00
Steel cutting, bending and welding
B4.6 Hour -
equipment
B4.6.1 Rib bending machine Hour 425.00 425.00 - 425.00
B4.6.2 Welding machine Hour 340.00 340.00 - 340.00
B4.6.3 Steel bar cutting machine Hour 425.00 425.00 - 425.00
SURGE SHAFT (PACKAGE-C3)
51,818,682.72 63,376,546.26
GRAND TOTAL 903,574,484.92 1,086,097,152.52
903,574,484.92
2,267,941.89 R-communication
905,842,426.81
Annexure-XXI
DE CHUU HYDRO ELECTRIC PROJECT, BHUTAN
timate (March 2016 PL) Variation w.r.t 1st RCE March- Variation due to
2014 Price Level
Balance Works Total
Price escalation Change in scope Inadequate Change in design Additional
Amount Qty Amount provision requirements
18=16*17 19=13+16 20=19*17 21=19-10 22=20-6 23 24 25 26 27
timate (March 2016 PL) Variation w.r.t 1st RCE March- Variation due to
2014 Price Level
Balance Works Total
Price escalation Change in scope Inadequate Change in design Additional
Amount Qty Amount provision requirements
18=16*17 19=13+16 20=19*17 21=19-10 22=20-6 23 24 25 26 27
- 0.00 0.00 0.00 0.00
- 0.00 0.00 0.00 0.00
- 1,956.13 14,946,789.33 187.22 1,430,548.02 1,430,548.02
- 130,284.98 1,042,279.84 -44,539.00 -356,312.00 -356,312.00
- 15,726.19 471,785.70 -2,986.37 -89,591.10 -89,591.10
- 0.00 0.00 0.00 0.00
- 0.00 0.00 0.00 0.00
- 20.00 5,100.00 20.00 5,100.00
- 0.00 0.00 0.00 0.00
- 0.00 0.00 0.00 0.00
- 0.00 0.00 0.00 0.00
- 0.00 0.00 0.00 0.00
- 14,961.00 5,086,740.00 2,400.00 816,000.00 816,000.00
- 0.00 0.00 0.00 0.00 0.00
- 863.00 1,832,149.00 367.00 779,141.00 779,141.00
- 0.00 0.00 0.00 0.00 0.00
- 1,560.00 530,400.00 1,560.00 530,400.00 530,400.00
- 1,734.00 206,346.00 1,734.00 206,346.00 206,346.00
timate (March 2016 PL) Variation w.r.t 1st RCE March- Variation due to
2014 Price Level
Balance Works Total
Price escalation Change in scope Inadequate Change in design Additional
Amount Qty Amount provision requirements
18=16*17 19=13+16 20=19*17 21=19-10 22=20-6 23 24 25 26 27
- 0.00 0.00 -2,862.00 -60,102.00
234,000.00 17,003.17 425,079.25 -72,141.83 -1,803,545.75 -1,803,545.75
- 0.00 0.00 0.00 0.00
- 399.51 135,833.40 0.00 0.00
- 2,864.35 1,094,181.70 1,855.85 708,934.70 708,934.70
- 0.00 0.00 0.00 0.00
- 603.31 333,027.12 0.00 0.00 0.00
- 0.00 0.00 0.00 0.00
- 44.18 2,250,529.20 4.28 218,023.20 218,023.20
- 0.00 0.00 0.00 0.00
- 0.00 0.00 0.00 0.00
- 0.00 0.00 0.00 0.00
4,245,000.00 1.00 4,245,000.00 0.00 0.00
- 0.00 0.00 0.00 0.00
- 0.00 0.00 0.00 0.00
- 0.00 0.00 0.00 0.00
- 0.00 0.00 0.00 0.00
- 0.00 0.00 0.00 0.00
212,250.00 250.00 212,250.00 0.00 0.00
169,800.00 1.00 169,800.00 0.00 0.00
- 0.00 0.00 0.00 0.00
- 0.00 0.00 0.00 0.00
- 0.00 0.00 0.00 0.00
- 0.00 0.00 0.00 0.00
- 0.00 0.00 0.00 0.00
- 0.00 0.00 0.00 0.00
- 39,927.29 8,145,167.16 32,600.55 6,650,512.20 6,650,512.20
- 12,068.86 5,129,265.50 9,893.80 4,204,865.00 4,204,865.00
- 0.00 0.00 0.00 0.00 0.00
- 1,897.92 2,577,375.36 752.67 1,022,125.86 1,022,125.86
- 0.00 0.00 0.00 0.00
- 0.00 0.00 0.00 0.00
- 0.00 0.00 0.00 0.00
- 0.00 0.00 0.00 0.00
- 0.00 0.00 0.00 0.00
timate (March 2016 PL) Variation w.r.t 1st RCE March- Variation due to
2014 Price Level
Balance Works Total
Price escalation Change in scope Inadequate Change in design Additional
Amount Qty Amount provision requirements
18=16*17 19=13+16 20=19*17 21=19-10 22=20-6 23 24 25 26 27
- 1.00 14,942.00 1.00 14,942.00 14,942.00
- 0.00 0.00 0.00 0.00 0.00
- 1.00 20,376.00 1.00 20,376.00 20,376.00
- 1.00 23,772.00 1.00 23,772.00 23,772.00
- 0.00 0.00 0.00 0.00 0.00
- 0.00 0.00 0.00 0.00 0.00
- 0.00 0.00 0.00 0.00
timate (March 2016 PL) Variation w.r.t 1st RCE March- Variation due to
2014 Price Level
Balance Works Total
Price escalation Change in scope Inadequate Change in design Additional
Amount Qty Amount provision requirements
18=16*17 19=13+16 20=19*17 21=19-10 22=20-6 23 24 25 26 27
- 0.00 0.00 0.00 0.00
timate (March 2016 PL) Variation w.r.t 1st RCE March- Variation due to
2014 Price Level
Balance Works Total
Price escalation Change in scope Inadequate Change in design Additional
Amount Qty Amount provision requirements
18=16*17 19=13+16 20=19*17 21=19-10 22=20-6 23 24 25 26 27
- 0.00 0.00 -3,900.00 -1,657,500.00
timate (March 2016 PL) Variation w.r.t 1st RCE March- Variation due to
2014 Price Level
Balance Works Total
Price escalation Change in scope Inadequate Change in design Additional
Amount Qty Amount provision requirements
18=16*17 19=13+16 20=19*17 21=19-10 22=20-6 23 24 25 26 27
- 0.00 0.00 0.00 0.00
timate (March 2016 PL) Variation w.r.t 1st RCE March- Variation due to
2014 Price Level
Balance Works Total
Price escalation Change in scope Inadequate Change in design Additional
Amount Qty Amount provision requirements
18=16*17 19=13+16 20=19*17 21=19-10 22=20-6 23 24 25 26 27
- 0.00 0.00 -800.00 -51,200.00
- 0.00 0.00 -500.00 -6,367,500.00
- 0.00 0.00 0.00 0.00
- 0.00 0.00 0.00 0.00
timate (March 2016 PL) Variation w.r.t 1st RCE March- Variation due to
2014 Price Level
Balance Works Total
Price escalation Change in scope Inadequate Change in design Additional
Amount Qty Amount provision requirements
18=16*17 19=13+16 20=19*17 21=19-10 22=20-6 23 24 25 26 27
1,320,319.25 78,404.50 1,960,112.50 -1,029.46 -25,736.50 -25,736.50
timate (March 2016 PL) Variation w.r.t 1st RCE March- Variation due to
2014 Price Level
Balance Works Total
Price escalation Change in scope Inadequate Change in design Additional
Amount Qty Amount provision requirements
18=16*17 19=13+16 20=19*17 21=19-10 22=20-6 23 24 25 26 27
- 0.00 0.00 0.00 0.00
- 0.00 0.00 0.00 0.00
- 0.00 0.00 0.00 0.00
timate (March 2016 PL) Variation w.r.t 1st RCE March- Variation due to
2014 Price Level
Balance Works Total
Price escalation Change in scope Inadequate Change in design Additional
Amount Qty Amount provision requirements
18=16*17 19=13+16 20=19*17 21=19-10 22=20-6 23 24 25 26 27
- 0.00 0.00 0.00 0.00
timate (March 2016 PL) Variation w.r.t 1st RCE March- Variation due to
2014 Price Level
Balance Works Total
Price escalation Change in scope Inadequate Change in design Additional
Amount Qty Amount provision requirements
18=16*17 19=13+16 20=19*17 21=19-10 22=20-6 23 24 25 26 27
- 0.00 0.00 0.00 0.00
- 0.00 0.00 0.00 0.00
- 0.00 0.00 0.00 0.00
- 0.00 0.00 0.00 0.00
- 0.00 0.00 0.00 0.00
- 0.00 0.00 0.00 0.00
timate (March 2016 PL) Variation w.r.t 1st RCE March- Variation due to
2014 Price Level
Balance Works Total
Price escalation Change in scope Inadequate Change in design Additional
Amount Qty Amount provision requirements
18=16*17 19=13+16 20=19*17 21=19-10 22=20-6 23 24 25 26 27
- 0.00 0.00 0.00 0.00
timate (March 2016 PL) Variation w.r.t 1st RCE March- Variation due to
2014 Price Level
Balance Works Total
Price escalation Change in scope Inadequate Change in design Additional
Amount Qty Amount provision requirements
18=16*17 19=13+16 20=19*17 21=19-10 22=20-6 23 24 25 26 27
- 0.00 0.00 0.00 0.00
- 0.00 0.00 0.00 0.00
timate (March 2016 PL) Variation w.r.t 1st RCE March- Variation due to
2014 Price Level
Balance Works Total
Price escalation Change in scope Inadequate Change in design Additional
Amount Qty Amount provision requirements
18=16*17 19=13+16 20=19*17 21=19-10 22=20-6 23 24 25 26 27
- 155,234.76 45,673,171.09 155,234.76 45,673,171.09 45,673,171.09
- 2,766.24 864,615.97 2,766.24 864,615.97 864,615.97
- 0.00 0.00 0.00 0.00 0.00
- 3,660.38 38,469,166.25 3,660.38 38,469,166.25 38,469,166.25
- 734.00 6,444,520.00 734.00 6,444,520.00 6,444,520.00
- 0.00 0.00 0.00 0.00 0.00
- 0.00 0.00 0.00 0.00 0.00
- 0.00 91,451,473.31 0.00
368,981,332.22
366,680,718.60
2,300,613.62 R-communication
368,981,332.22
(fig. in Rs. /Nu.)
Variation due to
Other causes.
28
0.00
0.00
0.00
94,350.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
(fig. in Rs. /Nu.)
Variation due to
Other causes.
28
5,100.00
0.00
9,445.57
0.00
0.00
0.00
0.00
0.00
0.00
0.00
(fig. in Rs. /Nu.)
Variation due to
Other causes.
28
-60,102.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
(fig. in Rs. /Nu.)
Variation due to
Other causes.
28
0.00
0.00
-6,459,992.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
(fig. in Rs. /Nu.)
Variation due to
Other causes.
28
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
-2,090,304.00
-84,900.00
(fig. in Rs. /Nu.)
Variation due to
Other causes.
28
-1,657,500.00
0.00
-1,658,265.00
-4,204,248.00
-2,097,711.00
-2,187,024.00
(fig. in Rs. /Nu.)
Variation due to
Other causes.
28
-7,425.00
0.00
0.00
-176,592.00
(fig. in Rs. /Nu.)
Variation due to
Other causes.
28
-51,200.00
-6,367,500.00
0.00
0.00
-616,681.76
(fig. in Rs. /Nu.)
Variation due to
Other causes.
28
(fig. in Rs. /Nu.)
Variation due to
Other causes.
28
0.00
(fig. in Rs. /Nu.)
Variation due to
Other causes.
28
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
(fig. in Rs. /Nu.)
Variation due to
Other causes.
28
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
(fig. in Rs. /Nu.)
Variation due to
Other causes.
28
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
(fig. in Rs. /Nu.)
Variation due to
Other causes.
28
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
(fig. in Rs. /Nu.)
Variation due to
Other causes.
28
-27,610,549.19
MANGDECHHU HYDRO ELECTRIC PROJECT, B
SECOND REVISED COST ESTIMATE (MARCH 2016 P
PRESSURE SHAFT, BIFURCATION PRESSURE SHAFT & INTERMEDIATE ADITS(PACKAGE-C3)
SL. No. Description of item Unit Approved 1st RCE ( March 2014 Price SECOND REVISED COST ESTIMATE AT MARCH,16 PR
Level) Completed upto March ,2016
Balance Works
Quantity Rate (Nu.). Amount (Nu.) Total Qty Rate (Nu.). Amount (Nu.) Quantity Rate (Nu.).
1 2 3 10 11 12=10*11 13 14 15=13 * 14 16 17
GROUP A SURFACE WORKS
Site clearance
A1 Dewatering During Construction
1.1 Dewatering of Surface Construction Sites KWh 22.00 0.00 22.00 22.00
including supply, installation and removal of
pumping equipment from the site.
A2 Surface Excavation (Pothead yard, TRT 0.00
outlet Structure, Surge shaft & Adit portals
2.1 etc.).
Common excavation. cu.m 10,482.99 191.00 2,002,251.09 6,464.61 191.00 1,234,740.51 191.00
2.2 Rock excavation. cu.m 22,050.82 340.00 7,497,278.80 22,050.82 340.00 7,497,278.80 340.00
2.3 Control perimeter blasting. sq.m 425.00 0.00 0.00 425.00 0.00 425.00
2.4 Line drilling. m 340.00 0.00 0.00 340.00 0.00 340.00
2.5 Dental excavation. cu.m 0.00 425.00 0.00 0.00 425.00 0.00 425.00
2.6 Minor excavation. sq.m 0.00 425.00 0.00 0.00 425.00 0.00 425.00
2.7 Removal of material arising from overbreak m 0.00 119.00 0.00 0.00 119.00 0.00 119.00
accepted due to geological conditions.
2.8 Extra for hauling excavated materials beyond 1 cu.m 0.00 102.00 0.00 1,920.01 102.00 195,841.02 102.00
km and upto 3 km.
A3 Not Used 0.00 0.00 0.00
A4 Rock stabilization and Supports. 0.00 0.00 0.00
4.1 Rock Anchors 25 mm dia. 0.00 0.00 0.00
4.1.1 Length upto 4.0 m. 0 68.00 637.00 43,316.00 68.00 637.00 43,316.00 637.00
4.1.2 Length more than 4.0 m and upto 6.0 m. m 1,446.00 594.00 858,924.00 1,446.00 594.00 858,924.00 594.00
4.1.3 Length more than 6.0 m and upto 9.0 m. m 0.00 573.00 0.00 0.00 573.00 0.00 573.00
4.2 Rock Anchors 32 mm dia. 0.00 0.00 0.00
4.2.1 Length upto 6.0 m. m 722.00 0.00 0.00 722.00 0.00 722.00
4.2.2 Length more than 6.0 m and upto 9.0 m. m 679.00 0.00 0.00 679.00 0.00 679.00
4.2.3 Length more than 9.0 m and upto 12.0 m. m 679.00 0.00 0.00 679.00 0.00 679.00
4.3 Rockbolts 36 mm dia. 0.00 0.00 0.00
4.3.1 Length upto 6.0 m. m 785.00 0.00 0.00 785.00 0.00 785.00
PRESSURE SHAFT, BIFURCATION PRESSURE SHAFT & INTERMEDIATE ADITS(PACKAGE-C3)
SL. No. Description of item Unit Approved 1st RCE ( March 2014 Price SECOND REVISED COST ESTIMATE AT MARCH,16 PR
Level) Completed upto March ,2016
Balance Works
Quantity Rate (Nu.). Amount (Nu.) Total Qty Rate (Nu.). Amount (Nu.) Quantity Rate (Nu.).
4.3.2 Length more than 6.0 m and upto 9.0 m. m 0.00 764.00 0.00 0.00 764.00 0.00 764.00
4.3.3 Length more than 9.0 m and upto 12.0 m. m 722.00 0.00 0.00 722.00 0.00 722.00
4.4 Extensions for embedding into concrete where m 0.00 425.00 0.00 0.00 425.00 0.00 425.00
required.
4.5 Mesh reinforcement. 0.00 0.00 0.00
4.5.1 Welded wiremesh. sq.m 229.00 0.00 0.00 229.00 0.00 229.00
4.5.2 Chain link fabric. sq.m 576.63 255.00 147,040.65 696.63 255.00 177,640.65 255.00
0.00 0.00 0.00
A5 Shotcrete 0.00 0.00 0.00
5.1 Plain Shotcrete. cu.m 100.08 7,641.00 764,711.28 100.08 7,641.00 764,711.28 7,641.00
5.2 Cement variation in shotcrete. kg 10,007.80 8.00 80,062.40 10,007.80 8.00 80,062.40 8.00
5.3 Superplasticiser. kg 622.28 30.00 18,668.40 622.28 30.00 18,668.40 30.00
A6 Backfill 0.00 0.00 0.00
6.1 Random backfill. cu.m 0.00 212.00 0.00 0.00 212.00 0.00 23,720.00 212.00
6.2 Compacted backfill. cu.m 255.00 0.00 0.00 255.00 0.00 255.00
6.3 Free-drainage backfill. cu.m 0.00 594.00 0.00 0.00 594.00 0.00 594.00
6.4 Sand-gravel fill. cu.m 0.00 594.00 0.00 0.00 594.00 0.00 594.00
A7 Drilling, Grouting and Pressure Relief Holes 0.00 0.00 0.00
7.1 Drilling for consolidation grouting. 0.00 0.00 0.00
7.1.1 Drilling for grout holes 45 mm dia. m 340.00 0.00 0.00 340.00 0.00 340.00
7.2 Placing grout (excluding cement). 0.00 0.00 0.00
7.2.1 Consolidation grouting. No. 2,123.00 0.00 0.00 2,123.00 0.00 2,123.00
7.3 Drilling for Pressure Relief holes from open. 0.00 0.00 0.00
7.3.1 Drilling of 45 mm dia hole. m 40.00 340.00 13,600.00 49.49 340.00 16,826.60 340.00
7.3.2 Supply and installation of 36 mm dia PVC pipes. m 0.00 119.00 0.00 0.00 119.00 0.00 119.00
7.4 Drilling of exploratory holes, check holes and 0.00 0.00 0.00
holes for instrumentation.
7.4.1 Drilling of 45 dia holes. m 340.00 0.00 0.00 340.00 0.00 340.00
7.4.2 Drilling of 76 dia holes. m 425.00 0.00 0.00 425.00 0.00 425.00
7.4.3 Extra for core recovery. m 2,547.00 0.00 0.00 2,547.00 0.00 2,547.00
7.5 Grouting materials 0.00 0.00 0.00
7.5.1 Cement MT 8,490.00 0.00 0.00 8,490.00 0.00 8,490.00
7.5.2 Sand MT 0.00 594.00 0.00 0.00 594.00 0.00 594.00
7.5.3 Bentonite MT 0.00 10,613.00 0.00 0.00 10,613.00 0.00 10,613.00
7.5.4 Admixtures kg 0.00 64.00 0.00 0.00 64.00 0.00 64.00
PRESSURE SHAFT, BIFURCATION PRESSURE SHAFT & INTERMEDIATE ADITS(PACKAGE-C3)
SL. No. Description of item Unit Approved 1st RCE ( March 2014 Price SECOND REVISED COST ESTIMATE AT MARCH,16 PR
Level) Completed upto March ,2016
Balance Works
Quantity Rate (Nu.). Amount (Nu.) Total Qty Rate (Nu.). Amount (Nu.) Quantity Rate (Nu.).
SL. No. Description of item Unit Approved 1st RCE ( March 2014 Price SECOND REVISED COST ESTIMATE AT MARCH,16 PR
Level) Completed upto March ,2016
Balance Works
Quantity Rate (Nu.). Amount (Nu.) Total Qty Rate (Nu.). Amount (Nu.) Quantity Rate (Nu.).
SL. No. Description of item Unit Approved 1st RCE ( March 2014 Price SECOND REVISED COST ESTIMATE AT MARCH,16 PR
Level) Completed upto March ,2016
Balance Works
Quantity Rate (Nu.). Amount (Nu.) Total Qty Rate (Nu.). Amount (Nu.) Quantity Rate (Nu.).
0.00
0.00
0.00
TOTAL FOR GROUP A ### 0.00 ###
GROUP BUNDERGROUND WORKS
B1 Dewatering During Construction 0.00 0.00 0.00
1.1 Dewatering of Underground Construction sites KWh 314,545.00 22.00 6,919,990.00 186,362.50 22.00 4,099,975.00 128,182.50 22.00
including supply, installation and removal of
pumping equipment from the site.
B2 Not Used 0.00 0.00 0.00
B3 Underground Excavation 0.00 0.00 0.00
3.1 Excavation of all Tunnels 0.00 0.00 0.00
3.1.1 Class I, II, & III cu.m 54,825.44 1,019.00 55,867,123.36 71,420.48 1,019.00 72,777,469.12 1,019.00
3.1.2 Class IV and V cu.m 21,540.90 1,104.00 23,781,153.60 57,720.48 1,104.00 63,723,409.92 1,104.00
3.1.3 By Multiple drifting due to geological reasons. cu.m 950.00 1,528.00 1,451,600.00 7,614.29 1,528.00 11,634,635.12 1,528.00
3.2 Excavation of Power house & Transformer 0.00 0.00 0.00
caverns in all classes of rock.
3.2.1 In Power house vault (upto EL 1045). cu.m 1,019.00 0.00 0.00 1,019.00 0.00 1,019.00
3.2.2 In Power house (below EL 1045 ) & Transformer cu.m 934.00 0.00 0.00 934.00 0.00 934.00
Cavern.
3.2.3 Excavation of cable trench below EL 1028.40 in cu.m 934.00 0.00 0.00 934.00 0.00 934.00
Transformer Cavern.
3.2.4 Line drilling. m 340.00 0.00 569.00 340.00 193,460.00 340.00
3.2.5 Dental excavation. cu.m 509.00 0.00 0.00 509.00 0.00 509.00
3.3 Excavation of Surge shaft in all classes of rock. 0.00 0.00 0.00
3.3.1 Raise boring. m 25,470.00 0.00 0.00 25,470.00 0.00 25,470.00
3.3.2 Excavation by slashing. cu.m 1,189.00 0.00 0.00 1,189.00 0.00 1,189.00
3.4 Excavation of pressure shafts in all classes of 0.00 0.00 0.00
3.4.1 rock
Raise boring. m 0.00 25,470.00 0.00 0.00 25,470.00 0.00 25,470.00
3.4.2 Excavation by slashing. cu.m 0.00 1,528.00 0.00 3,335.20 1,528.00 5,096,185.60 3,250.00 1,528.00
3.4.3 Excavation of horizontal portions of pressure cu.m 70,000.00 1,019.00 71,330,000.00 69,480.12 1,019.00 70,800,242.28 2,750.00 1,019.00
3.5 shafts.
Excavation of vertical gate operation shafts for cu.m 2,547.00 0.00 0.00 2,547.00 0.00 2,547.00
TRT tunnel, cable shafts etc in any material.
3.6 Removal of material arising from overbreak cu.m 21,101.00 255.00 5,380,755.00 17,664.18 255.00 4,504,365.90 4,086.82 255.00
accepted due to geological conditions.
3.7 Extra for hauling excavated materials beyond 1 cu.m 148,602.20 102.00 15,157,424.40 126,426.12 102.00 12,895,464.24 6,836.82 102.00
km upto 3 km.
PRESSURE SHAFT, BIFURCATION PRESSURE SHAFT & INTERMEDIATE ADITS(PACKAGE-C3)
SL. No. Description of item Unit Approved 1st RCE ( March 2014 Price SECOND REVISED COST ESTIMATE AT MARCH,16 PR
Level) Completed upto March ,2016
Balance Works
Quantity Rate (Nu.). Amount (Nu.) Total Qty Rate (Nu.). Amount (Nu.) Quantity Rate (Nu.).
3.7.1 Extra for hauling excavated materials beyond 3 cu.m 45,212.05 204.00 9,223,258.20 0.00 204.00 0.00 204.00
km upto 5km.
B4 Rock stabilization and Supports 0.00 0.00 0.00
4.1 Rockbolts 25 mm dia. 0.00 0.00 0.00
4.1.1 Length upto 4.0 m. m 67,307.00 637.00 42,874,559.00 65,874.00 637.00 41,961,738.00 32,810.00 637.00
4.1.2 Length more than 4.0 m and upto 6.0 m. m 7,370.00 616.00 4,539,920.00 1,266.00 616.00 779,856.00 616.00
4.2 Rockbolts 32 mm dia. 0.00 0.00 0.00
4.2.1 Length upto 6.0 m. m 6,500.00 764.00 4,966,000.00 0.00 764.00 0.00 764.00
4.2.2 Length more than 6.0 m and upto 9.0 m. m 2,500.00 722.00 1,805,000.00 2,414.00 722.00 1,742,908.00 722.00
4.2.3 Length more than 9.0 m and upto 12.0 m. m 700.00 0.00 0.00 700.00 0.00 700.00
4.3 Rockbolts 36 mm dia. 0.00 0.00 0.00
4.3.1 Length upto 6.0 m. m 934.00 0.00 282.00 934.00 263,388.00 934.00
4.3.2 Length more than 6.0 m and upto 9.0 m. m 849.00 0.00 0.00 849.00 0.00 849.00
4.3.3 Length more than 9.0 m and upto 12.0 m. m 722.00 0.00 0.00 722.00 0.00 722.00
4.4 Post tensioned rockbolts (tendons). 0.00 0.00 0.00
4.4.1 25 m long. m 1,358.00 0.00 0.00 1,358.00 0.00 1,358.00
0.00 0.00 0.00
4.5 Rockbolt testing No. 200.00 849.00 169,800.00 0.00 849.00 0.00 849.00
4.6 Extension for embedding into concrete where m 200.00 425.00 85,000.00 0.00 425.00 0.00 425.00
4.7 required.
Grouted anchor bar: 0.00 0.00 0.00
4.7.1 25 mm dia. m 48.00 637.00 30,576.00 851.40 637.00 542,341.80 637.00
4.7.2 32 mm dia. m 644.40 764.00 492,321.60 8,079.30 764.00 6,172,585.20 16,750.00 764.00
4.8 Water expandable friction anchor. 0.00 0.00 0.00
4.8.1 Length upto 5.0 m. m 0.00 934.00 0.00 0.00 934.00 0.00 934.00
4.9 Self Drilling Hollow Core Anchor: 0.00 0.00 0.00
4.9.1 25 mm dia. m 1,000.00 1,019.00 1,019,000.00 0.00 1,019.00 0.00 1,019.00
4.9.2 32 mm dia. m 1,274.00 0.00 0.00 1,274.00 0.00 1,274.00
4.10 Mesh reinforcement. 0.00 0.00 0.00
4.10.1 Welded wiremesh. sq.m 38,463.00 255.00 9,808,065.00 769.77 255.00 196,291.35 255.00
4.11 Lattice Girder. MT 117.00 50,940.00 5,959,980.00 0.00 50,940.00 0.00 50,940.00
4.12 Steel ribs, supply and installation (including MT 684.00 55,185.00 37,746,540.00 1,123.16 55,185.00 61,981,584.60 55,185.00
4.13 accessories).
Steel lagging supply and installation. MT 38.56 55,185.00 2,127,933.60 28.38 55,185.00 1,566,150.30 55,185.00
4.14 Precast concrete lagging. cu.m 1,469.00 6,792.00 9,977,448.00 1,513.30 6,792.00 10,278,333.60 275.00 6,792.00
4.15 Drilling for Pregrouting. m 8,337.00 297.00 2,476,089.00 434.00 297.00 128,898.00 297.00
4.15.1 Grouting Operations. No. 1,012.00 1,698.00 1,718,376.00 45.00 1,698.00 76,410.00 1,698.00
PRESSURE SHAFT, BIFURCATION PRESSURE SHAFT & INTERMEDIATE ADITS(PACKAGE-C3)
SL. No. Description of item Unit Approved 1st RCE ( March 2014 Price SECOND REVISED COST ESTIMATE AT MARCH,16 PR
Level) Completed upto March ,2016
Balance Works
Quantity Rate (Nu.). Amount (Nu.) Total Qty Rate (Nu.). Amount (Nu.) Quantity Rate (Nu.).
4.16 Fore poling (Drilling & Installation). m 3,000.00 552.00 1,656,000.00 12,576.50 552.00 6,942,228.00 552.00
4.16.1 Grouting Operations. No. 335.00 1,698.00 568,830.00 72.00 1,698.00 122,256.00 1,698.00
4.17 Pipe Roofing. m 3,000.00 849.00 2,547,000.00 438.00 849.00 371,862.00 849.00
B5 Shotcrete 0.00 0.00 0.00
5.1 SFR Shotcrete excluding steel fibre cu.m 8,226.00 8,490.00 69,838,740.00 6,652.05 8,490.00 56,475,904.50 8,490.00
5.2 Plain Shotcrete cu.m 8,066.00 0.00 0.00 8,066.00 0.00 8,066.00
5.3 PFR Shotcrete excluding poly fibre cu.m 700.00 8,490.00 5,943,000.00 0.00 8,490.00 0.00 8,490.00
5.4 Cement variation in shotcrete kg 493,560.00 8.00 3,948,480.00 419,820.05 8.00 3,358,560.40 45,600.00 8.00
5.5 Superplasticizer kg 79,216.38 30.00 2,376,491.40 65,198.54 30.00 1,955,956.20 7,318.80 30.00
5.6 Steel fibre kg 329,040.00 81.00 26,652,240.00 281,100.40 81.00 22,769,132.40 81.00
5.7 Poly fibre kg 0.00 64.00 0.00 0.00 64.00 0.00 64.00
5.8 Micro silica kg 205,650.00 13.00 2,673,450.00 170,239.72 13.00 2,213,116.36 19,000.00 13.00
B6 Backfill 0.00 0.00 0.00
6.1 Sand - Gravel fill in Transformer floor cu.m 594.00 0.00 0.00 594.00 0.00 594.00
B7 Drilling, Grouting and Pressure Relief Holes 0.00 0.00 0.00
7.1 Drilling of 45 mm dia holes for contact grouting 0.00 0.00 0.00
7.1.1 In the Tunnels m 37.00 297.00 10,989.00 0.00 297.00 0.00 297.00
7.1.2 For tunnel plug m 500.00 297.00 148,500.00 0.00 297.00 0.00 297.00
7.1.3 In Surge shaft m 297.00 0.00 0.00 297.00 0.00 297.00
7.2 Drilling of 45 dia holes for Consolidation grouting 0.00 0.00 0.00
7.2.1 In Surge shaft m 382.00 0.00 0.00 382.00 0.00 382.00
7.2.2 In Pressure shaft m 1,000.00 382.00 382,000.00 3,463.00 382.00 1,322,866.00 4,850.00 382.00
7.2.3 In tunnels, cavern & tunnel plug m 72.00 297.00 21,384.00 1,542.00 297.00 457,974.00 1,440.00 297.00
7.3 Drilling for curtain grouting for tunnel plugs m 500.00 297.00 148,500.00 0.00 297.00 0.00 297.00
7.3.1 Grouting operations No. 50.00 1,868.00 93,400.00 50.00 1,868.00 93,400.00 1,868.00
7.4 45 mm dia pressure relief holes in the tunnels 0.00 0.00 0.00
and caverns
7.4.1 Drilling of 45 mm dia hole m 4,737.00 297.00 1,406,889.00 4,691.30 297.00 1,393,316.10 297.00
7.4.2 Supply and installation of 36 mm dia PVC pipes m 5,955.00 119.00 708,645.00 0.00 119.00 0.00 119.00
7.4.3 Supply and installation of drain outlet devices No. 255.00 0.00 0.00 255.00 0.00 255.00
7.5 Drilling of 45 dia pressure relief holes in drainage 0.00 0.00 0.00
gallery.
7.5.1 In Invert m 297.00 0.00 0.00 297.00 0.00 297.00
7.5.2 In Overt m 297.00 0.00 0.00 297.00 0.00 297.00
7.6 Drilling of exploratory holes, check holes and 0.00 0.00 0.00
holes for instrumentation in tunnels and caverns.
PRESSURE SHAFT, BIFURCATION PRESSURE SHAFT & INTERMEDIATE ADITS(PACKAGE-C3)
SL. No. Description of item Unit Approved 1st RCE ( March 2014 Price SECOND REVISED COST ESTIMATE AT MARCH,16 PR
Level) Completed upto March ,2016
Balance Works
Quantity Rate (Nu.). Amount (Nu.) Total Qty Rate (Nu.). Amount (Nu.) Quantity Rate (Nu.).
7.6.1 Drilling of 45 dia holes m 778.00 297.00 231,066.00 111.00 297.00 32,967.00 297.00
7.6.2 Drilling of 76 dia holes m 217.00 425.00 92,225.00 72.00 425.00 30,600.00 425.00
7.6.3 Drilling of 98 dia holes m 764.00 0.00 0.00 764.00 0.00 764.00
7.6.4 Extra for core recovery m 100.00 2,547.00 254,700.00 0.00 2,547.00 0.00 2,547.00
7.7 Water pressure testing - simple water test. No. 100.00 849.00 84,900.00 0.00 849.00 0.00 849.00
7.8 Embedded pipes and fittings for grouting left kg 64.00 0.00 318.39 64.00 20,376.96 64.00
permanently in place.
7.9 Placing grout (Excluding cement). 0.00 0.00 0.00
7.9.1 Contact grouting ordered by the Engineer-in- m 200.00 594.00 118,800.00 0.00 594.00 0.00 594.00
7.9.2 Charge.
Fill grouting. 0.00 0.00 0.00
7.9.2.1 In Temporary drainage system. m 594.00 0.00 0.00 594.00 0.00 594.00
7.9.2.2 In exploratory holes. m 594.00 0.00 0.00 594.00 0.00 594.00
7.9.3 Consolidation grouting including grouting for 0.00 0.00 0.00
tunnel plug.
7.9.3.1 -Single stage grouting. No. 27.00 2,123.00 57,321.00 870.00 2,123.00 1,847,010.00 1,015.00 2,123.00
7.9.3.2 -Multiple stage grouting. stage 1,698.00 0.00 0.00 1,698.00 0.00 1,698.00
7.10 Grouting materials 0.00 0.00 0.00
7.10.1 Cement MT 1,764.00 8,490.00 14,976,360.00 702.70 8,490.00 5,965,923.00 270.00 8,490.00
7.10.2 Sand MT 11.00 594.00 6,534.00 0.00 594.00 0.00 594.00
7.10.3 Bentonite MT 22.00 11,037.00 242,814.00 0.00 11,037.00 0.00 11,037.00
7.10.4 Admixtures kg 1,200.00 64.00 76,800.00 0.00 64.00 0.00 64.00
7.10.5 Microfine/ Ultrafine Cement MT 1.09 12,735.00 13,881.15 0.00 12,735.00 0.00 12,735.00
B8 Not Used 0.00 0.00 0.00
B9 Concrete 0.00 0.00 0.00
9.1 Concrete lining including formwork in all tunnels 0.00 0.00 0.00
9.1.1 Plain Cement Concrete lining 0.00 0.00 0.00
9.1.1.1 In Invert 0.00 0.00 0.00
9.1.1.1.1 -M 25/ A40 cu.m 62.00 3,141.00 194,742.00 0.00 3,141.00 0.00 3,141.00
9.1.1.1.2 -M 20/ A40 cu.m 4,900.00 2,972.00 14,562,800.00 1,529.54 2,972.00 4,545,792.88 2,972.00
9.1.1.2 In sidewalls and vaults (Overt) 0.00 0.00 0.00
9.1.1.2.1 -M 25/ A40 cu.m 3,396.00 0.00 36.65 3,396.00 124,463.40 3,396.00
-M20/A40 0.00 0.00 0.00
9.1.2 -M25/ A40 Reinforced Cement Concrete cu.m 199.00 3,311.00 658,889.00 0.00 3,311.00 0.00 3,311.00
9.1.3 Tunnel plugs - M20/ A40 cu.m 2,300.00 3,226.00 7,419,800.00 0.00 3,226.00 0.00 7,170.00 3,226.00
9.2 Concrete in Shafts including formwork 0.00 0.00 0.00
PRESSURE SHAFT, BIFURCATION PRESSURE SHAFT & INTERMEDIATE ADITS(PACKAGE-C3)
SL. No. Description of item Unit Approved 1st RCE ( March 2014 Price SECOND REVISED COST ESTIMATE AT MARCH,16 PR
Level) Completed upto March ,2016
Balance Works
Quantity Rate (Nu.). Amount (Nu.) Total Qty Rate (Nu.). Amount (Nu.) Quantity Rate (Nu.).
9.2.1 Cement concrete lining M25/A40 in Surge Shaft cu.m 3,396.00 0.00 0.00 3,396.00 0.00 3,396.00
9.2.2 Backfill concrete M15/A40 behind steel liner in cu.m 67,500.00 2,377.00 160,447,500.00 11,872.14 2,377.00 28,220,076.78 55,627.86 2,377.00
Pressure shaft
9.2.3 Cement concrete M25/A40 in TRT gate shaft & cu.m 3,311.00 0.00 0.00 3,311.00 0.00 3,311.00
cable shaft
9.2.4 Concrete in Blockouts M30/ A20 cu.m 3,651.00 0.00 0.00 3,651.00 0.00 3,651.00
9.3 Concrete in Power house and Transformer cavern 0.00 0.00 0.00
9.3.1 Cement concrete M25/A20 in substructure of cu.m 3,396.00 0.00 0.00 3,396.00 0.00 3,396.00
power house
9.3.2 Cement concrete M25/A20 upto turbine floor of cu.m 3,396.00 0.00 0.00 3,396.00 0.00 3,396.00
power house
9.3.3 Cement concrete M25/A20 for generator barrel in cu.m 3,396.00 0.00 0.00 3,396.00 0.00 3,396.00
power house
9.3.4 Cement concrete M25/A40 in beams, columns, cu.m 3,396.00 0.00 0.00 3,396.00 0.00 1,040.00 3,396.00
slabs, walls, raft etc.
9.3.5 Cement concrete M15/A40 cu.m 1,525.71 2,462.00 3,756,298.02 0.00 2,462.00 0.00 2,462.00
9.4 M15/A40 backfill concrete in underground cu.m 2,732.00 2,462.00 6,726,184.00 18,180.02 2,462.00 44,759,209.24 2,462.00
excavations in geologically approved overbreaks
9.5 M25/A20 precast concrete including formwork cu.m 3,566.00 0.00 0.00 3,566.00 0.00 3,566.00
9.6 Cement variation in concrete kg 6,992,370.00 8.00 55,938,960.00 3,019,248.87 8.00 24,153,990.96 6,388,081.20 8.00
9.7 Admixtures for concrete 0.00 0.00 0.00
9.7.1 Air-entraining agent kg 8,723.00 22.00 191,906.00 0.00 22.00 0.00 22.00
9.7.2 Water-reducing agent kg 245,899.56 25.00 6,147,489.00 89,546.26 25.00 2,238,656.50 189,431.79 25.00
9.8 Grouting of equipment foundations/ Bearing kg 64.00 0.00 0.00 64.00 0.00 64.00
plates and anchors
B10 Formwork 0.00 0.00 0.00
10.1 Class F1 sq.m 831.75 318.00 264,496.50 831.75 318.00 264,496.50 318.00
10.2 Class F2 sq.m 361.00 0.00 480.65 361.00 173,514.65 685.00 361.00
10.3 Class F3 sq.m 403.00 0.00 0.00 403.00 0.00 403.00
10.4 Class F1C sq.m 488.00 0.00 910.56 488.00 444,353.28 5,590.00 488.00
10.5 Class F2C sq.m 552.00 0.00 0.00 552.00 0.00 552.00
10.6 Class F3C sq.m 594.00 0.00 0.00 594.00 0.00 594.00
B11 Reinforcement Steel 0.00 0.00 0.00
11.1 Deformed Reinforcing bars - Grade Fe 500 MT 67.00 51,789.00 3,469,863.00 4.93 51,789.00 255,319.77 75.00 51,789.00
11.2 Plain reinforcing bars MT 10.00 49,242.00 492,420.00 0.00 49,242.00 0.00 49,242.00
11.3 Couplers 0.00 0.00 0.00
11.3.1 32 mm dia No. 170.00 0.00 0.00 170.00 0.00 170.00
PRESSURE SHAFT, BIFURCATION PRESSURE SHAFT & INTERMEDIATE ADITS(PACKAGE-C3)
SL. No. Description of item Unit Approved 1st RCE ( March 2014 Price SECOND REVISED COST ESTIMATE AT MARCH,16 PR
Level) Completed upto March ,2016
Balance Works
Quantity Rate (Nu.). Amount (Nu.) Total Qty Rate (Nu.). Amount (Nu.) Quantity Rate (Nu.).
SL. No. Description of item Unit Approved 1st RCE ( March 2014 Price SECOND REVISED COST ESTIMATE AT MARCH,16 PR
Level) Completed upto March ,2016
Balance Works
Quantity Rate (Nu.). Amount (Nu.) Total Qty Rate (Nu.). Amount (Nu.) Quantity Rate (Nu.).
14.1 Supply and erection of supporting steel structure MT 63,675.00 0.00 0.00 63,675.00 0.00 63,675.00
for false ceiling
B15 Building and Architectural Works 0.00 0.00 0.00
15.1 Building and Architectural works in Power house L.S. 24,123,909.00 0.00 0.00 24,123,909.00 0.00 ###
and Transformer cavern
15.2 Building and Architectural works in D.G. building L.S. 8,490,000.00 0.00 0.00 8,490,000.00 0.00 ###
of pothead yard
15.3 Suspended ceiling sq.m 2,547.00 0.00 0.00 2,547.00 0.00 630.00 2,547.00
B16 Miscellaneous and Ancillary Works 0.00 0.00 0.00
16.1 Concrete pipes 0.00 0.00 0.00
16.1.1 Drain pipes on concrete or sand base 0.00 0.00 0.00
16.1.1.1 100 mm dia m 16.20 448.00 7,257.60 30.20 448.00 13,529.60 448.00
16.1.1.2 200 mm dia m 554.00 0.00 0.00 554.00 0.00 554.00
16.1.1.3 300 mm dia m 844.00 0.00 0.00 844.00 0.00 844.00
16.1.2 Pipes fully embedded in concrete 0.00 0.00 0.00
16.1.2.1 200 mm dia m 554.00 0.00 0.00 554.00 0.00 554.00
16.1.2.2 300 mm dia m 844.00 0.00 0.00 844.00 0.00 844.00
16.1.2.3 400 mm dia m 1,007.00 0.00 0.00 1,007.00 0.00 1,007.00
16.2 PVC Pipes 0.00 0.00 0.00
16.2.1 50 mm dia m 117.00 0.00 0.00 117.00 0.00 117.00
16.2.2 75 mm dia m 301.00 0.00 60.00 301.00 18,060.00 301.00
16.2.3 100 mm dia m 435.00 0.00 38.00 435.00 16,530.00 435.00
16.2.4 200 mm dia m 1,636.00 0.00 0.00 1,636.00 0.00 1,636.00
16.2.5 300 mm dia m 4,040.00 0.00 0.00 4,040.00 0.00 4,040.00
16.3 SWG Pipes 0.00 0.00 0.00
16.3.1 100 mm dia m 849.00 0.00 0.00 849.00 0.00 849.00
16.3.2 150 mm dia half round pipes m 1,698.00 0.00 0.00 1,698.00 0.00 1,698.00
B17 Not Used 0.00 0.00 0.00
B18 Monitoring Instruments 0.00 0.00 0.00
18.1 Supply, installation and commissioning of 0.00 0.00 0.00
monitoring instrument as per tech. spec.
18.1.1 Load cells No. 38,714.00 0.00 1.00 38,714.00 38,714.00 1.00 38,714.00
18.1.2 Tape convergence points. No. 204.00 0.00 20.00 204.00 4,080.00 204.00
18.1.3 Single point borehole extensometer. 0.00 0.00 0.00
18.1.3.1 Mechanical type. No. 10,867.00 0.00 4.00 10,867.00 43,468.00 10,867.00
18.1.3.2 Electrical type. No. 14,942.00 0.00 8.00 14,942.00 119,536.00 14,942.00
PRESSURE SHAFT, BIFURCATION PRESSURE SHAFT & INTERMEDIATE ADITS(PACKAGE-C3)
SL. No. Description of item Unit Approved 1st RCE ( March 2014 Price SECOND REVISED COST ESTIMATE AT MARCH,16 PR
Level) Completed upto March ,2016
Balance Works
Quantity Rate (Nu.). Amount (Nu.) Total Qty Rate (Nu.). Amount (Nu.) Quantity Rate (Nu.).
SL. No. Description of item Unit Approved 1st RCE ( March 2014 Price SECOND REVISED COST ESTIMATE AT MARCH,16 PR
Level) Completed upto March ,2016
Balance Works
Quantity Rate (Nu.). Amount (Nu.) Total Qty Rate (Nu.). Amount (Nu.) Quantity Rate (Nu.).
SL. No. Description of item Unit Approved 1st RCE ( March 2014 Price SECOND REVISED COST ESTIMATE AT MARCH,16 PR
Level) Completed upto March ,2016
Balance Works
Quantity Rate (Nu.). Amount (Nu.) Total Qty Rate (Nu.). Amount (Nu.) Quantity Rate (Nu.).
B2.3 Concrete Pumps upto 30m3/hr Hour 1,189.00 0.00 1,189.00 0.00 1,189.00
B2.4 Concrete vibration equipment (Needle type)( 90- Hour 425.00 0.00 425.00 0.00 425.00
150 mm diameter)
B2.5 Shotcreting equipment Hour 0.00 0.00
B2.5.1 Shotcreting equipment(Dry Shotcrete) Hour 849.00 0.00 849.00 0.00 849.00
B2.5.2 Shotcrete machine with robot arm ( Wet Hour 3,821.00 0.00 3,821.00 0.00 3,821.00
B3 Shotcrete)
Drilling and Grouting equipment 0.00 0.00
B3.1 Percussion drilling rigs/equipment (above and Hour 1,274.00 0.00 1,274.00 0.00 1,274.00
below ground)
B3.2 Rotary drilling rigs/equipment (above and below Hour 2,123.00 0.00 2,123.00 0.00 2,123.00
ground)
B3.3 Grout mixers and pumps (above and below Hour 0.00 0.00
B3.3.1 ground)
Grout pumps (mortar grout) Hour 849.00 0.00 849.00 0.00 849.00
B3.3.2 Grout pumps (cement grout) Hour 594.00 0.00 594.00 0.00 594.00
B4 Miscellaneous equipment 0.00 0.00
B4.1 Mobile cranes and lifting equipment 0.00 0.00
B4.1.1 Mobile crane below 15 T Hour 849.00 0.00 849.00 0.00 849.00
B4.1.2 Mobile crane 15 to 25 T Hour 1,698.00 0.00 1,698.00 0.00 1,698.00
B4.2 Low pressure water pumps Hour 0.00 0.00
B.4.2.1 Dewatering pumps below 10 HP Hour 594.00 0.00 594.00 0.00 594.00
B4.3 High pressure water pumps Hour 0.00 0.00
B.4.3.1 Dewatering pumps above 10 HP Hour 849.00 0.00 849.00 0.00 849.00
B4.4 Air compressors Hour 0.00 0.00
B4.4.1 Air compressors upto 300 cfm. Hour 849.00 0.00 849.00 0.00 849.00
B4.4.2 Air compressors above 300 cfm. Hour 934.00 0.00 934.00 0.00 934.00
B4.5 Generating sets Hour 0.00 0.00
B4.5.1 Diesel generating sets upto 650 KVA Hour 5,943.00 0.00 5,943.00 0.00 5,943.00
B4.5.2 Diesel generating sets 750 KVA Hour 8,490.00 0.00 8,490.00 0.00 8,490.00
B4.6 Steel cutting, bending and welding equipment Hour 0.00 0.00
B4.6.1 Rib bending machine Hour 425.00 0.00 425.00 0.00 425.00
B4.6.2 Welding machine Hour 340.00 0.00 340.00 0.00 340.00
B4.6.3 Steel bar cutting machine Hour 425.00 0.00 425.00 0.00 425.00
B4.7 Water tankers Hour 764.00 0.00 764.00 0.00 764.00
Total for Group C - Part B 0.00 0.00
GROUP C Labour 0.00 0.00
- Part C
PRESSURE SHAFT, BIFURCATION PRESSURE SHAFT & INTERMEDIATE ADITS(PACKAGE-C3)
SL. No. Description of item Unit Approved 1st RCE ( March 2014 Price SECOND REVISED COST ESTIMATE AT MARCH,16 PR
Level) Completed upto March ,2016
Balance Works
Quantity Rate (Nu.). Amount (Nu.) Total Qty Rate (Nu.). Amount (Nu.) Quantity Rate (Nu.).
SL. No. Description of item Unit Approved 1st RCE ( March 2014 Price SECOND REVISED COST ESTIMATE AT MARCH,16 PR
Level) Completed upto March ,2016
Balance Works
Quantity Rate (Nu.). Amount (Nu.) Total Qty Rate (Nu.). Amount (Nu.) Quantity Rate (Nu.).
CLAIMS
0.00
ESCALATION
ES1 Escalation on BOQ item. LS 18,065,572.56 49,484,506.44
ES2 Escalation on extra item. LS 1,176,514.24 11,124,315.50
Escalation on Balance work % 41,737,718.15
###
GRAND TOTAL ### ###
942,636,873.43
2,986,951.80 R-communication
945,623,825.23 ###
Annexure-XXII
HU HYDRO ELECTRIC PROJECT, BHUTAN
COST ESTIMATE (MARCH 2016 PRICE LEVEL)
OST ESTIMATE AT MARCH,16 PRICE LEVEL Variation w.r.t 1st RCE at Variation due to
Total March-2014 Price Level
Balance Works Price Change in Inadequate Change in Additional Other
escalation scope provision design requireme causes.
nts
Amount (Nu.) Quantity Amount (Nu.) Quantity Amount (Nu.)
0.00 0.00
419,340,310.20
5,295,045.96 R-communication
424,635,356.16
0.00 424,635,356.16
MANGDE
SECOND REVIS
MAIN ACCESS TUNNEL TO PH INCLUDING PORTAL, APPROACH ADIT TO TRANSFORMER CAVERN, ADIT TO TRANSFORMER FLOO
6.4 Sand-gravel fill. cu.m 0.00 594.00 0.00 0.00 594.00 0.00
A7 Drilling, Grouting and 0.00 0.00 0.00
Pressure Relief Holes
7.1 Drilling for consolidation 0.00 0.00 0.00
grouting.
7.1.1 Drilling for grout holes 45 m 340.00 0.00 435.00 340.00 147,900.00
mm dia.
7.2 Placing grout (excluding 0.00 0.00 0.00
cement).
7.2.1 Consolidation grouting. No. 2,123.00 0.00 29.00 2,123.00 61,567.00
7.3 Drilling for Pressure Relief 0.00 0.00 0.00
holes from open.
7.3.1 Drilling of 45 mm dia hole. m 933.00 340.00 317,220.00 350.00 340.00 119,000.00
7.3.2 Supply and installation of 36 m 433.00 119.00 51,527.00 0.00 119.00 0.00
mm dia PVC pipes.
7.4 Drilling of exploratory holes, 0.00 0.00 0.00
check holes and holes for
instrumentation.
7.4.1 Drilling of 45 dia holes. m 340.00 0.00 0.00 340.00 0.00
7.4.2 Drilling of 76 dia holes. m 425.00 0.00 0.00 425.00 0.00
7.4.3 Extra for core recovery. m 2,547.00 0.00 0.00 2,547.00 0.00
7.5 Grouting materials 0.00 0.00 0.00
7.5.1 Cement MT 8,490.00 0.00 0.00 8,490.00 0.00
7.5.2 Sand MT 0.00 594.00 0.00 0.00 594.00 0.00
7.5.3 Bentonite MT 0.00 10,613.00 0.00 0.00 10,613.00 0.00
7.5.4 Admixtures kg 0.00 64.00 0.00 0.00 64.00 0.00
A8 Not Used 0.00 0.00 0.00
A9 Concrete 0.00 0.00 0.00
9.1 Concrete in surface works 0.00 0.00 0.00
9.1.1 Lean concrete M10/A80 cu.m 2,377.00 0.00 0.00 2,377.00 0.00
9.1.2 Cement concrete M15/A40 cu.m 1,600.00 2,547.00 4,075,200.00 62.81 2,547.00 159,977.07
9.1.3 Cement concrete M25/A40 cu.m 96.00 3,226.00 309,696.00 0.00 3,226.00 0.00
9.2 M15/A40 backfill concrete in cu.m 2,717.00 0.00 0.00 2,717.00 0.00
surface excavations in
geologically approved
overbreaks.
9.3 Cement variation in kg 153,000.00 8.00 1,224,000.00 5,652.90 8.00 45,223.20
concrete.
9.4 Admixtures for concrete. 0.00 0.00 0.00
9.4.1 Air-entraining agent. kg 32.00 21.00 672.00 0.00 21.00 0.00
9.4.2 Water-reducing agent. kg 1,248.00 25.00 31,200.00 182.15 25.00 4,553.75
A10 Formwork 0.00 0.00 0.00
10.1 Class F1 sq.m 22.00 340.00 7,480.00 0.00 340.00 0.00
10.2 Class F2 sq.m 255.00 382.00 97,410.00 0.00 382.00 0.00
10.3 Class F1C sq.m 10.00 509.00 5,090.00 0.00 509.00 0.00
10.4 Class F2C sq.m 13.00 552.00 7,176.00 0.00 552.00 0.00
A11 Reinforcing Steel 0.00 0.00 0.00
11.1 Deformed Reinforcing bars - MT 50,940.00 0.00 0.00 50,940.00 0.00
Grade Fe 500.
11.2 Plain reinforcing bars. MT 1.00 49,242.00 49,242.00 0.00 49,242.00 0.00
A12 Not Used 0.00 0.00 0.00
A13 Metalworks 0.00 0.00 0.00
13.1 Protective net on top of L.S. 4,245,000.00 0.00 0.00 4,245,000.00 0.00
surge shaft.
0.00 0.00 0.00
A14 Not Used 0.00 0.00 0.00
A15 Not Used 0.00 0.00 0.00
A16 Miscellaneous and 0.00 0.00 0.00
Ancillary Works
16.1 Fencing and gates 0.00 0.00 0.00
16.1.1 Fencing m 50.00 849.00 42,450.00 0.00 849.00 0.00
16.1.2 Gates No. 2.00 169,800.00 339,600.00 0.00 169,800.00 0.00
16.2 Weep holes No. 40.00 176.00 7,040.00 0.00 176.00 0.00
16.3 PVC Pipes 0.00 0.00 0.00
16.3.1 50 mm dia m 200.00 119.00 23,800.00 0.00 119.00 0.00
16.3.2 75 mm dia m 200.00 297.00 59,400.00 0.00 297.00 0.00
A17 Slope protection 0.00 0.00 0.00
17.1 Wire crates/ Gabions 0.00 0.00 0.00
17.1.1 Wire crates sq.m 64,500.00 204.00 13,158,000.00 12,568.79 204.00 2,564,033.16
17.1.2 Boulder filling in wire crates cu.m 17,500.00 425.00 7,437,500.00 4,137.60 425.00 1,758,480.00
17.2 Random Rubble Masonry 0.00 0.00 0.00
17.2.1 Wall
Wet R R Masonry cu.m 1,358.00 0.00 0.00 1,358.00 0.00
17.2.2 Dry R R Masonry cu.m 100.00 764.00 76,400.00 0.00 764.00 0.00
Slope protection works LS 0.00 0.00 0.00
17.3 Rock paving in mortar cu.m 1,358.00 0.00 0.00 1,358.00 0.00
17.4 Concrete blocks cu.m 3,396.00 0.00 0.00 3,396.00 0.00
A18 Monitoring Instruments 0.00 0.00 0.00
18.1 Supply, installation and 0.00 0.00 0.00
commissioning of monitoring
instrument as per tech. spec.
18.1.1 Survey target point No. 611.00 0.00 0.00 611.00 0.00
18.1.2 Single point borehole 0.00 0.00 0.00
extensometer
18.1.2.1 Mechanical type No. 10,867.00 0.00 0.00 10,867.00 0.00
18.1.2.2 Electrical type No. 14,942.00 0.00 0.00 14,942.00 0.00
18.1.3 Multi point borehole 0.00 0.00 0.00
extensometer
18.1.3.1 Mechanical type No. 20,376.00 0.00 0.00 20,376.00 0.00
18.1.3.2 Electrical type No. 23,772.00 0.00 0.00 23,772.00 0.00
A19 Not Used 0.00 0.00 0.00
A20 Not Used 0.00 0.00 0.00
A21 Roadworks 0.00 0.00 0.00
21.1 Preparation of sub grade 0.00 0.00
complete in all respects as
per Technical specification
and as directed by Engineer
in-Charge.
21.1.1 All kinds of soil cu.m 0.00 679.00 0.00
21.1.2 Rock cu.m 0.00 1,019.00 0.00
21.2 Cement Concrete (M25/A40) cu.m 0.00 3,226.00 0.00
pavements laid to required
slope and camber complete
in all respects as per Shifted to R-communication
Technical specification and
as directed by Engineer in-
21.3 Charge.
Construction of lined drain m 0.00 849.00 0.00
complete in all respects as
per Technical specification
and as directed by Engineer
in-Charge.
21.4 Maintenance and repair of km- 0.00 29,715.00 0.00
access roads. month
21.5 Turfing Sqm 0.00 170.00 0.00
0.00
0.00
0.00
TOTAL FOR GROUP A ### 0.00 ###
GROUP BUNDERGROUND WORKS
B1 Dewatering During 0.00 0.00 0.00
Construction
1.1 Dewatering of Underground KWh 285,818.00 22.00 6,287,996.00 448,275.56 22.00 9,862,062.32
Construction sites including
supply, installation and
removal of pumping
equipment from the site.
B2 Not Used 0.00 0.00 0.00
B3 Underground Excavation 0.00 0.00 0.00
3.1 Excavation of all Tunnels 0.00 0.00 0.00
3.1.1 Class I, II, & III cu.m 127,554.00 1,019.00 ### 89,903.61 1,019.00 91,611,778.59
3.1.2 Class IV and V cu.m 40,356.00 1,104.00 44,553,024.00 19,179.68 1,104.00 21,174,366.72
3.1.3 By Multiple drifting due to cu.m 1,528.00 0.00 0.00 1,528.00 0.00
geological reasons.
3.2 Excavation of Power house & 0.00 0.00 0.00
Transformer caverns in all
classes of rock.
3.2.1 In Power house vault (upto cu.m 1,019.00 0.00 0.00 1,019.00 0.00
EL 1045).
3.2.2 In Power house (below EL cu.m 934.00 0.00 0.00 934.00 0.00
1045 ) & Transformer
3.2.3 Cavern.
Excavation of cable trench cu.m 934.00 0.00 0.00 934.00 0.00
below EL 1028.40 in
Transformer Cavern.
3.2.4 Line drilling. m 340.00 0.00 0.00 340.00 0.00
3.2.5 Dental excavation. cu.m 509.00 0.00 0.00 509.00 0.00
3.3 Excavation of Surge shaft in 0.00 0.00 0.00
all classes of rock.
3.3.1 Raise boring. m 25,470.00 0.00 0.00 25,470.00 0.00
3.3.2 Excavation by slashing. cu.m 1,189.00 0.00 0.00 1,189.00 0.00
3.4 Excavation of pressure shafts 0.00 0.00 0.00
in all classes of rock
3.4.1 Raise boring. m 25,470.00 0.00 0.00 25,470.00 0.00
3.4.2 Excavation by slashing. cu.m 1,528.00 0.00 0.00 1,528.00 0.00
###
GRAND TOTAL ### ###
MANGDECHHU HYDRO ELECTRIC PROJECT, BHUTAN
2nd Revised Cost Estimate(March,2016 Price Level) Variation w.r.t 1st RCE Variat
March-2014 Price
Balance works Total
Level
Price Change in
escalation scope
Quantity Rate (Nu.). Amount Quantity Amount (Nu.) Quantity Amount
(Nu.) (Nu.)
16 17 18=16*17 19=13+16 20=19*17 21=19-10 22=20-6 23 24
0.00 0.00
0.00 0.00
0.00
4,869,221.06 ###
### ### 0.00 -25,470.42 ### ###
Annexure- XXIII
Variation due to
25 26 27 28
0.00
516,215.70
-254,800.00
692,180.00
147,900.00
61,567.00
0.00
0.00
0.00
0.00
0.00
-672.00
164,437.00
0.00
0.00
0.00
0.00
-49,242.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
8,414,066.32
0.00
942,390.00
###
108,416.00
0.00
1,083,408.90
0.00
0.00
1,175,276.40
357,433.50
2,356,111.80
0.00
491,738.78
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
-118,800.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
209,228.80
0.00
0.00
6,405,943.69
662,200.00
0.00
0.00
-3,557,590.00
0.00
-3,432.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
247,568.40
48,412.00
0.00
###
851,200.00
###
16,530.00
3,552.00
3,868.40
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
34,398.00
19,107.00
0.00
0.00
70,059.00
0.00
7,641.00
3,822.00
0.00
0.00
25,470.00
0.00
0.00
0.00
0.00
0.00
0.00
704.67
13,023.66
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
256.00
0.00
6,688.00
0.00
0.00
0.00
650,289.49
102,264.91
###
0.00
4,793,958.60
0.00
###
4,758,104.16
69,378.72
965,984.79
6,270,910.24
###
###
6,409,970.24
###
Quantity Rate (Nu.). Amount (Nu.) Total Rate (Nu.). Amount (Nu.) Quantity Rate (Nu.). Amount (Nu.)
1 2 3 10 11 12=10*11 13 14 15=13 * 14 16 17 18=16*17
GROUP A SURFACE WORKS
A6 Backfill 0.00 0.00
6.1 Random backfill. cu.m 2,731.86 212.00 579,154.32 212.00 0.00
TOTAL FOR GROUP A 0.00 0.00 579,154.32 0.00
GROUP B UNDERGROUND WORKS
B1 Dewatering During Construction 0.00 0.00 0.00
1.1 Dewatering of Underground KWh 955,001.00 22.00 21,010,022.00 52,229.00 22.00 1,149,038.00 902,772.00 22.00 19,860,984.00
Construction sites including supply,
installation and removal of pumping
equipment from the site.
B2 Not Used 0.00 0.00 0.00 0.00
B3 Underground Excavation 0.00 0.00 0.00 0.00
3.1 Excavation of all Tunnels 0.00 0.00 0.00 0.00
3.1.1 Class I, II, & III cu.m 1,019.00 0.00 10,254.15 1,019.00 10,448,978.85 1,019.00 0.00
3.1.2 Class IV and V cu.m 1,104.00 0.00 2,047.20 1,104.00 2,260,108.80 1,104.00 0.00
3.1.3 By Multiple drifting due to geological cu.m 1,528.00 0.00 0.00 1,528.00 0.00 1,528.00 0.00
reasons.
3.2 Excavation of Power house & 0.00 0.00 0.00 0.00
Transformer caverns in all classes of
3.2.1 rock.
In Power house vault (upto EL 1045). cu.m 29,562.91 1,019.00 30,124,605.29 26,147.51 1,019.00 26,644,312.69 1,019.00 0.00
3.2.2 In Power house (below EL 1045 ) & cu.m 212,000.00 934.00 198,008,000.00 197,964.57 934.00 184,898,908.38 934.00 0.00
Transformer Cavern.
3.2.3 Excavation of cable trench below EL cu.m 6,000.00 934.00 5,604,000.00 0.00 934.00 0.00 934.00 0.00
1028.40 in Transformer Cavern.
3.2.4 Line drilling. m 32,000.00 340.00 10,880,000.00 39,431.00 340.00 13,406,540.00 340.00 0.00
3.2.5 Dental excavation. cu.m 500.00 509.00 254,500.00 3.19 509.00 1,623.71 10.00 509.00 5,090.00
3.3 Excavation of Surge shaft in all classes 0.00 0.00 0.00 0.00 0.00 0.00
of rock.
3.3.1 Raise boring. m 25,470.00 0.00 0.00 0.00 0.00 0.00 25,470.00 0.00
3.3.2 Excavation by slashing. cu.m 1,189.00 0.00 0.00 0.00 0.00 0.00 1,189.00 0.00
3.4 Excavation of pressure shafts in all 0.00 0.00 0.00 0.00
classes of rock
3.4.1 Raise boring. m 25,470.00 0.00 0.00 25,470.00 0.00 25,470.00 0.00
3.4.2 Excavation by slashing. cu.m 1,528.00 0.00 0.00 1,528.00 0.00 1,528.00 0.00
3.4.3 Excavation of horizontal portions of cu.m 1,019.00 0.00 0.00 1,019.00 0.00 1,019.00 0.00
pressure shafts.
POWERHOUSE AND TRANSFORMER CAVERN (PACKAGE-C3) 0 0 0
SL. No. Description of item Unit Approved 1st RCE-March 2014 Price Level Revised Cost Estimate (March 2016 PL)
Works Completed up to March 2016 Balance works
3.5 Excavation of vertical gate operation cu.m 2,547.00 0.00 0.00 2,547.00 0.00 2,547.00 0.00
shafts for TRT tunnel, cable shafts etc
in any material.
3.6 Removal of material arising from cu.m 24,343.00 255.00 6,207,465.00 12,344.43 255.00 3,147,829.65 255.00 0.00
overbreak accepted due to geological
3.7 conditions.
Extra for hauling excavated materials cu.m 102.00 0.00 0.00 102.00 0.00 102.00 0.00
beyond 1 km upto 3 km.
3.7.1 Extra for hauling excavated materials cu.m 241,562.91 204.00 49,278,833.64 14,381.35 204.00 2,933,795.40 204.00 0.00
beyond 3 km upto 5km.
B4 Rock stabilization and Supports 0.00 0.00 0.00 0.00
4.1 Rockbolts 25 mm dia. 0.00 0.00 0.00 0.00
4.1.1 Length upto 4.0 m. m 0.00 637.00 0.00 3,648.00 637.00 2,323,776.00 637.00 0.00
4.1.2 Length more than 4.0 m and upto 6.0 m 616.00 0.00 42.00 616.00 25,872.00 616.00 0.00
4.2 m.
Rockbolts 32 mm dia. 0.00 0.00 0.00 0.00
4.2.1 Length upto 6.0 m. m 4,404.00 764.00 3,364,656.00 36.00 764.00 27,504.00 764.00 0.00
4.2.2 Length more than 6.0 m and upto 9.0 m 1,494.00 722.00 1,078,668.00 1,494.00 722.00 1,078,668.00 722.00 0.00
4.2.3 m.
Length more than 9.0 m and upto 12.0 m 16,000.00 700.00 11,200,000.00 1,368.00 700.00 957,600.00 700.00 0.00
4.3 m.
Rockbolts 36 mm dia. 0.00 0.00 0.00 0.00
4.3.1 Length upto 6.0 m. m 1,200.00 934.00 1,120,800.00 1,364.00 934.00 1,273,976.00 934.00 0.00
4.3.2 Length more than 6.0 m and upto 9.0 m 40,000.00 849.00 33,960,000.00 19,375.00 849.00 16,449,375.00 849.00 0.00
4.3.3 m.
Length more than 9.0 m and upto 12.0 m 123,000.00 722.00 88,806,000.00 82,293.00 722.00 59,415,546.00 722.00 0.00
4.4 m. tensioned rockbolts (tendons).
Post 0.00 0.00 0.00 0.00
4.4.1 25 m long. m 6,500.00 1,358.00 8,827,000.00 2,346.00 1,358.00 3,185,868.00 1,358.00 0.00
Post tensioned rock bolts (tendon) No. 0.00 0.00 0.00 0.00
upto 18m length.
4.5 Rockbolt testing No. 400.00 849.00 339,600.00 0.00 849.00 0.00 849.00 0.00
4.6 Extension for embedding into concrete m 600.00 425.00 255,000.00 0.00 425.00 0.00 425.00 0.00
where required.
4.7 Grouted anchor bar: 0.00 0.00 0.00 0.00
4.7.1 25 mm dia. m 1,000.00 637.00 637,000.00 1,969.70 637.00 1,254,698.90 637.00 0.00
4.7.2 32 mm dia (45mm dia). m 8,000.00 764.00 6,112,000.00 1,277.40 764.00 975,933.60 764.00 0.00
4.8 Water expandable friction anchor. 0.00 0.00 0.00 0.00
4.8.1 Length upto 5.0 m. m 0.00 934.00 0.00 0.00 934.00 0.00 934.00 0.00
4.9 Self Drilling Hollow Core Anchor: 0.00 0.00 0.00 0.00
4.9.1 25 mm dia. m 1,019.00 0.00 0.00 1,019.00 0.00 1,019.00 0.00
4.9.2 32 mm dia. m 1,274.00 0.00 0.00 1,274.00 0.00 1,274.00 0.00
4.10 Mesh reinforcement. 0.00 0.00 0.00 0.00
4.10.1 Welded wiremesh. sq.m 5,000.00 255.00 1,275,000.00 1,063.70 255.00 271,243.50 255.00 0.00
4.11 Lattice Girder. MT 50,940.00 0.00 0.00 50,940.00 0.00 50,940.00 0.00
4.12 Steel ribs, supply and installation MT 0.00 55,185.00 0.00 193.67 55,185.00 10,687,678.95 55,185.00 0.00
(including accessories).
4.13 Steel lagging supply and installation. MT 55,185.00 0.00 16.64 55,185.00 918,278.40 55,185.00 0.00
4.14 Precast concrete lagging. cu.m 6,792.00 0.00 197.77 6,792.00 1,343,253.84 6,792.00 0.00
POWERHOUSE AND TRANSFORMER CAVERN (PACKAGE-C3) 0 0 0
SL. No. Description of item Unit Approved 1st RCE-March 2014 Price Level Revised Cost Estimate (March 2016 PL)
Works Completed up to March 2016 Balance works
4.15 Drilling for Pregrouting. m 1,500.00 297.00 445,500.00 0.00 297.00 0.00 297.00 0.00
4.15.1 Grouting Operations. No. 400.00 1,698.00 679,200.00 0.00 1,698.00 0.00 1,698.00 0.00
4.16 Fore poling (Drilling & Installation). m 552.00 0.00 0.00 552.00 0.00 552.00 0.00
4.16.1 Grouting Operations. No. 365.00 1,698.00 619,770.00 0.00 1,698.00 0.00 1,698.00 0.00
4.17 Pipe Roofing. m 849.00 0.00 0.00 849.00 0.00 849.00 0.00
B5 Shotcrete 0.00 0.00 0.00 0.00
5.1 SFR Shotcrete excluding steel fibre cu.m 5,189.00 8,490.00 44,054,610.00 7,740.25 8,490.00 65,714,722.50 8,490.00 0.00
5.2 Plain Shotcrete cu.m 2,000.00 8,066.00 16,132,000.00 0.00 8,066.00 0.00 8,066.00 0.00
5.3 PFR Shotcrete excluding poly fibre cu.m 1,000.00 8,490.00 8,490,000.00 0.00 8,490.00 0.00 8,490.00 0.00
5.4 Cement variation in shotcrete kg 432,000.00 8.00 3,456,000.00 543,963.40 8.00 4,351,707.20 8.00 0.00
5.5 Superplasticizer kg 69,336.00 30.00 2,080,080.00 76,070.03 30.00 2,282,100.90 30.00 0.00
5.6 Steel fibre kg 288,000.00 81.00 23,328,000.00 148,240.20 81.00 12,007,456.20 81.00 0.00
5.7 Poly fibre kg 0.00 64.00 0.00 0.00 64.00 0.00 64.00 0.00
5.8 Micro silica kg 184,746.00 13.00 2,401,698.00 209,845.42 13.00 2,727,990.46 13.00 0.00
B6 Backfill 0.00 0.00 0.00 0.00
6.1 Sand - Gravel fill in Transformer floor cu.m 594.00 0.00 0.00 594.00 0.00 594.00 0.00
B7 Drilling, Grouting and Pressure Relief 0.00 0.00 0.00 0.00
7.1 Holes of 45 mm dia holes for contact
Drilling 0.00 0.00 0.00 0.00
grouting
7.1.1 In the Tunnels m 700.00 297.00 207,900.00 0.00 297.00 0.00 700.00 297.00 207,900.00
7.1.2 For tunnel plug m 297.00 0.00 0.00 297.00 0.00 297.00 0.00
7.1.3 In Surge shaft m 297.00 0.00 0.00 297.00 0.00 297.00 0.00
7.2 Drilling of 45 dia holes for 0.00 0.00 0.00 0.00
Consolidation grouting
7.2.1 In Surge shaft m 382.00 0.00 0.00 382.00 0.00 382.00 0.00
7.2.2 In Pressure shaft m 382.00 0.00 0.00 382.00 0.00 382.00 0.00
7.2.3 In tunnels, cavern & tunnel plug m 5,275.00 297.00 1,566,675.00 15,011.40 297.00 4,458,385.80 297.00 0.00
7.3 Drilling for curtain grouting for tunnel m 297.00 0.00 0.00 297.00 0.00 297.00 0.00
7.3.1 plugs
Grouting operations No. 1,868.00 0.00 0.00 1,868.00 0.00 1,868.00 0.00
7.4 45 mm dia pressure relief holes in the 0.00 0.00 0.00 0.00
tunnels and caverns
7.4.1 Drilling of 45 mm dia hole m 29,000.00 297.00 8,613,000.00 8,092.50 297.00 2,403,472.50 297.00 0.00
7.4.2 Supply and installation of 36 mm dia m 29,000.00 119.00 3,451,000.00 2,320.00 119.00 276,080.00 119.00 0.00
PVC pipes
7.4.3 Supply and installation of drain outlet No. 500.00 255.00 127,500.00 0.00 255.00 0.00 255.00 0.00
devices
7.5 Drilling of 45 dia pressure relief holes 0.00 0.00 0.00 0.00
in drainage gallery.
7.5.1 In Invert m 2,000.00 297.00 594,000.00 0.00 297.00 0.00 297.00 0.00
7.5.2 In Overt m 3,000.00 297.00 891,000.00 0.00 297.00 0.00 297.00 0.00
7.6 Drilling of exploratory holes, check 0.00 0.00 0.00 0.00
holes and holes for instrumentation in
tunnels and caverns.
POWERHOUSE AND TRANSFORMER CAVERN (PACKAGE-C3) 0 0 0
SL. No. Description of item Unit Approved 1st RCE-March 2014 Price Level Revised Cost Estimate (March 2016 PL)
Works Completed up to March 2016 Balance works
7.6.1 Drilling of 45 dia holes m 1,700.00 297.00 504,900.00 876.00 297.00 260,172.00 297.00 0.00
7.6.2 Drilling of 76 dia holes m 1,148.00 425.00 487,900.00 1,441.00 425.00 612,425.00 425.00 0.00
7.6.3 Drilling of 98 dia holes m 700.00 764.00 534,800.00 56.00 764.00 42,784.00 764.00 0.00
7.6.4 Extra for core recovery m 2,547.00 0.00 0.00 2,547.00 0.00 2,547.00 0.00
7.7 Water pressure testing - simple water No. 849.00 0.00 0.00 849.00 0.00 849.00 0.00
7.8 test.
Embedded pipes and fittings for kg 8,757.35 64.00 560,470.40 6,419.72 64.00 410,862.08 64.00 0.00
grouting left permanently in place.
7.9 Placing grout (Excluding cement). 0.00 0.00 0.00 0.00
7.9.1 Contact grouting ordered by the m 594.00 0.00 0.00 594.00 0.00 594.00 0.00
Engineer-in-Charge.
7.9.2 Fill grouting. 0.00 0.00 0.00 0.00
7.9.2.1 In Temporary drainage system. m 500.00 594.00 297,000.00 0.00 594.00 0.00 594.00 0.00
7.9.2.2 In exploratory holes. m 300.00 594.00 178,200.00 30.00 594.00 17,820.00 270.00 594.00 160,380.00
7.9.3 Consolidation grouting including 0.00 0.00 0.00 0.00
grouting for tunnel plug.
7.9.3.1 -Single stage grouting. No. 2,000.00 2,123.00 4,246,000.00 2,078.00 2,123.00 4,411,594.00 2,123.00 0.00
7.9.3.2 -Multiple stage grouting. stage 1,000.00 1,698.00 1,698,000.00 56.00 1,698.00 95,088.00 1,698.00 0.00
7.10 Grouting materials 0.00 0.00 0.00 0.00
7.10.1 Cement MT 400.00 8,490.00 3,396,000.00 218.36 8,490.00 1,853,876.40 180.00 8,490.00 1,528,200.00
7.10.2 Sand MT 10.00 594.00 5,940.00 0.00 0.00 0.00 0.00 594.00 0.00
7.10.3 Bentonite MT 20.00 11,037.00 220,740.00 0.00 0.00 0.00 0.00 11,037.00 0.00
7.10.4 Admixtures kg 1,000.00 64.00 64,000.00 5.44 64.00 348.16 600.00 64.00 38,400.00
7.10.5 Microfine/ Ultrafine Cement MT 20.00 12,735.00 254,700.00 18.60 12,735.00 236,871.00 10.00 12,735.00 127,350.00
B8 Not Used 0.00 0.00 0.00 0.00 0.00 0.00
B9 Concrete 0.00 0.00 0.00 0.00 0.00 0.00
9.1 Concrete lining including formwork in 0.00 0.00 0.00 0.00 0.00 0.00
all tunnels
9.1.1 Plain Cement Concrete lining 0.00 0.00 0.00 0.00 0.00 0.00
9.1.1.1 In Invert 0.00 0.00 0.00 0.00 0.00 0.00
9.1.1.1.1 -M 25/ A40 cu.m 3,141.00 0.00 0.00 3,141.00 0.00 620.00 3,141.00 1,947,420.00
9.1.1.1.2 -M 20/ A40 cu.m 1,132.04 2,972.00 3,364,422.88 793.28 2,972.00 2,357,628.16 2,972.00 0.00
9.1.1.2 In sidewalls and vaults (Overt) 0.00 0.00 0.00 0.00
9.1.1.2.1 -M 25/ A40 cu.m 3,396.00 3,396.00 11,532,816.00 10.01 3,396.00 33,993.96 1,105.00 3,396.00 3,752,580.00
-M20/A40 0.00 0.00 0.00 0.00
9.1.2 -M25/ A40 Reinforced Cement cu.m 500.00 3,311.00 1,655,500.00 0.00 3,311.00 0.00 3,311.00 0.00
9.1.3 Concrete
Tunnel plugs - M20/ A40 cu.m 500.00 3,226.00 1,613,000.00 221.26 3,226.00 713,784.76 3,226.00 0.00
9.2 Concrete in Shafts including formwork 0.00 0.00 0.00 0.00
9.2.1 Cement concrete lining M25/A40 in cu.m 3,396.00 0.00 0.00 3,396.00 0.00 3,396.00 0.00
Surge Shaft
9.2.2 Backfill concrete M15/A40 behind steel cu.m 11,349.58 2,377.00 26,977,951.66 406.86 2,377.00 967,106.22 2,377.00 0.00
liner in Pressure shaft
POWERHOUSE AND TRANSFORMER CAVERN (PACKAGE-C3) 0 0 0
SL. No. Description of item Unit Approved 1st RCE-March 2014 Price Level Revised Cost Estimate (March 2016 PL)
Works Completed up to March 2016 Balance works
9.2.3 Cement concrete M25/A40 in TRT gate cu.m 3,311.00 0.00 0.00 3,311.00 0.00 3,311.00 0.00
shaft & cable shaft
9.2.4 Concrete in Blockouts M30/ A20 cu.m 3,651.00 0.00 523.32 3,651.00 1,910,641.32 3,651.00 0.00
9.3 Concrete in Power house and 0.00 0.00 0.00 0.00
Transformer cavern
9.3.1 Cement concrete M25/A20 in cu.m 8,000.00 3,396.00 27,168,000.00 0.00 3,396.00 0.00 3,396.00 0.00
substructure of power house
9.3.2 Cement concrete M25/A20 upto cu.m 6,500.00 3,396.00 22,074,000.00 4,201.36 3,396.00 14,267,818.56 2,300.00 3,396.00 7,810,800.00
turbine floor of power house
9.3.3 Cement concrete M25/A20 for cu.m 4,000.00 3,396.00 13,584,000.00 0.00 3,396.00 0.00 4,000.00 3,396.00 13,584,000.00
generator barrel in power house
9.3.4 Cement concrete M25/A40 in beams, cu.m 13,000.00 3,396.00 44,148,000.00 7,770.65 3,396.00 26,389,127.40 5,230.00 3,396.00 17,761,080.00
columns, slabs, walls, raft etc.
9.3.5 Cement concrete M15/A40 cu.m 1,000.00 2,462.00 2,462,000.00 488.36 2,462.00 1,202,342.32 515.00 2,462.00 1,267,930.00
9.4 M15/A40 backfill concrete in cu.m 9,000.00 2,462.00 22,158,000.00 20,308.09 2,462.00 49,998,517.58 2,462.00 0.00
underground excavations in
geologically approved overbreaks
9.5 M25/A20 precast concrete including cu.m 100.00 3,566.00 356,600.00 0.00 3,566.00 0.00 100.00 3,566.00 356,600.00
formwork
9.6 Cement variation in concrete kg 3,780,000.00 8.00 30,240,000.00 2,414,294.00 8.00 19,314,352.00 1,239,300.00 8.00 9,914,400.00
9.7 Admixtures for concrete 0.00 0.00 0.00 0.00
9.7.1 Air-entraining agent kg 44,000.00 22.00 968,000.00 0.00 22.00 0.00 22.00 0.00
9.7.2 Water-reducing agent kg 201,000.00 25.00 5,025,000.00 100,695.74 25.00 2,517,393.50 64,444.00 25.00 1,611,100.00
9.8 Grouting of equipment foundations/ kg 5,000.00 64.00 320,000.00 0.00 64.00 0.00 64.00 0.00
Bearing plates and anchors
B10 Formwork 0.00 0.00 0.00 0.00
10.1 Class F1 sq.m 2,000.00 318.00 636,000.00 0.00 318.00 0.00 2,000.00 318.00 636,000.00
10.2 Class F2 sq.m 33,000.00 361.00 11,913,000.00 12,071.40 361.00 4,357,775.40 20,900.00 361.00 7,544,900.00
10.3 Class F3 sq.m 3,000.00 403.00 1,209,000.00 3,157.57 403.00 1,272,500.71 5,000.00 403.00 2,015,000.00
10.4 Class F1C sq.m 500.00 488.00 244,000.00 339.84 488.00 165,841.92 200.00 488.00 97,600.00
10.5 Class F2C sq.m 1,500.00 552.00 828,000.00 0.00 552.00 0.00 1,500.00 552.00 828,000.00
10.6 Class F3C sq.m 2,000.00 594.00 1,188,000.00 175.94 594.00 104,508.36 2,000.00 594.00 1,188,000.00
B11 Reinforcement Steel 0.00 0.00 0.00 0.00
11.1 Deformed Reinforcing bars - Grade Fe MT 5,000.00 51,789.00 258,945,000.00 1,427.43 51,789.00 73,925,172.27 3,572.57 51,789.00 ###
11.2 500 reinforcing bars
Plain MT 50.00 49,242.00 2,462,100.00 0.00 49,242.00 0.00 49,242.00 0.00
11.3 Couplers 0.00 0.00 0.00 0.00
11.3.1 32 mm dia No. 3,000.00 170.00 510,000.00 40.00 170.00 6,800.00 2,960.00 170.00 503,200.00
11.3.2 36 mm dia No. 3,000.00 255.00 765,000.00 350.00 255.00 89,250.00 2,650.00 255.00 675,750.00
B12 Waterstops and joints 0.00 0.00 0.00 0.00
12.1 P.V.C. water stops m 800.00 297.00 237,600.00 0.00 297.00 0.00 800.00 297.00 237,600.00
12.2 Joint fillers sq.m 2,500.00 1,698.00 4,245,000.00 0.00 1,698.00 0.00 2,500.00 1,698.00 4,245,000.00
12.3 Joint Sealing Compound m 100.00 594.00 59,400.00 0.00 594.00 0.00 100.00 594.00 59,400.00
12.4 Bituminous compound sq.m 2,700.00 212.00 572,400.00 0.00 212.00 0.00 2,700.00 212.00 572,400.00
POWERHOUSE AND TRANSFORMER CAVERN (PACKAGE-C3) 0 0 0
SL. No. Description of item Unit Approved 1st RCE-March 2014 Price Level Revised Cost Estimate (March 2016 PL)
Works Completed up to March 2016 Balance works
12.5 Joint Sealant (Including primer) m 100.00 594.00 59,400.00 0.00 594.00 0.00 100.00 594.00 59,400.00
B13 Metalworks 0.00 0.00 0.00 0.00
13.1 Railing m 1,100.00 1,274.00 1,401,400.00 0.00 1,274.00 0.00 1,100.00 1,274.00 1,401,400.00
13.2 Steel pipe handrail m 600.00 340.00 204,000.00 0.00 340.00 0.00 600.00 340.00 204,000.00
13.3 Ladders m 200.00 1,698.00 339,600.00 0.00 1,698.00 0.00 200.00 1,698.00 339,600.00
13.4 Gratings kg 2,000.00 64.00 128,000.00 0.00 64.00 0.00 2,000.00 64.00 128,000.00
13.5 Watertight steel cover, Frames kg 1,000.00 68.00 68,000.00 0.00 68.00 0.00 1,000.00 68.00 68,000.00
13.6 Climbing irons No. 700.00 64.00 44,800.00 0.00 64.00 0.00 700.00 64.00 44,800.00
13.7 Erection hooks kg 700.00 64.00 44,800.00 0.00 64.00 0.00 700.00 64.00 44,800.00
13.8 Steel anchorings kg 700.00 64.00 44,800.00 0.00 64.00 0.00 700.00 64.00 44,800.00
13.9 Steel pipes 0.00 0.00 0.00 0.00
13.9.1 100 mm dia m 300.00 849.00 254,700.00 38.10 849.00 32,346.90 261.90 849.00 222,353.10
13.9.2 150 mm dia m 300.00 1,274.00 382,200.00 0.00 1,274.00 0.00 300.00 1,274.00 382,200.00
13.9.3 200 mm dia m 300.00 1,698.00 509,400.00 0.00 1,698.00 0.00 300.00 1,698.00 509,400.00
13.9.4 300 mm dia m 300.00 2,547.00 764,100.00 0.00 2,547.00 0.00 300.00 2,547.00 764,100.00
13.10 Cast iron pipes 0.00 0.00 0.00 0.00
13.10.1 100 mm dia m 300.00 679.00 203,700.00 0.00 679.00 0.00 300.00 679.00 203,700.00
13.10.2 150 mm dia m 1,000.00 1,274.00 1,274,000.00 0.00 1,274.00 0.00 1,000.00 1,274.00 1,274,000.00
13.10.3 200 mm dia m 300.00 2,123.00 636,900.00 0.00 2,123.00 0.00 300.00 2,123.00 636,900.00
13.10.4 300 mm dia m 300.00 2,972.00 891,600.00 0.00 2,972.00 0.00 300.00 2,972.00 891,600.00
13.10.5 500 mm dia m 100.00 4,245.00 424,500.00 0.00 4,245.00 0.00 100.00 4,245.00 424,500.00
13.11 Cable Channels kg 1,000.00 85.00 85,000.00 0.00 85.00 0.00 1,000.00 85.00 85,000.00
13.12 Miscellaneous steel sections as edge kg 26,000.00 64.00 1,664,000.00 64.00 711,104.00 14,900.00 64.00 953,600.00
protection, frames, bearing plates,
brackets, etc. of various dimensions,
including bolts, screws, anchors and 11,111.00
other accessories for interior and
exterior purpose.
13.13 Installation of metalworks supplied by kg 5,000.00 20.00 100,000.00 0.00 20.00 0.00 5,000.00 20.00 100,000.00
others
B14 Structural Steel Work 0.00 0.00 0.00 0.00 0.00
14.1 Supply and erection of supporting MT 70.00 63,675.00 4,457,250.00 0.00 63,675.00 0.00 70.00 63,675.00 4,457,250.00
steel structure for false ceiling
B15 Building and Architectural Works 0.00 0.00 0.00 0.00
15.1 Building and Architectural works in L.S. 1.00 ### 24,123,909.00 0.00 24,123,909.00 0.00 1.00 24,123,909.00 24,123,909.00
Power house and Transformer cavern
15.2 Building and Architectural works in L.S. 8,490,000.00 0.00 0.00 8,490,000.00 0.00 12,500,000.00 0.00
D.G. building of pothead yard
15.3 Suspended ceiling sq.m 4,000.00 2,547.00 10,188,000.00 0.00 2,547.00 0.00 4,000.00 2,547.00 10,188,000.00
B16 Miscellaneous and Ancillary Works 0.00 0.00 0.00 0.00
16.1 Concrete pipes 0.00 0.00 0.00 0.00
16.1.1 Drain pipes on concrete or sand base 0.00 0.00 0.00 0.00
16.1.1.1 100 mm dia m 200.00 448.00 89,600.00 0.00 448.00 0.00 200.00 448.00 89,600.00
POWERHOUSE AND TRANSFORMER CAVERN (PACKAGE-C3) 0 0 0
SL. No. Description of item Unit Approved 1st RCE-March 2014 Price Level Revised Cost Estimate (March 2016 PL)
Works Completed up to March 2016 Balance works
16.1.1.2 200 mm dia m 200.00 554.00 110,800.00 0.00 554.00 0.00 200.00 554.00 110,800.00
16.1.1.3 300 mm dia m 100.00 844.00 84,400.00 0.00 844.00 0.00 100.00 844.00 84,400.00
16.1.2 Pipes fully embedded in concrete 0.00 0.00 0.00 0.00
16.1.2.1 200 mm dia m 150.00 554.00 83,100.00 0.00 554.00 0.00 150.00 554.00 83,100.00
16.1.2.2 300 mm dia m 150.00 844.00 126,600.00 0.00 844.00 0.00 150.00 844.00 126,600.00
16.1.2.3 400 mm dia m 50.00 1,007.00 50,350.00 0.00 1,007.00 0.00 50.00 1,007.00 50,350.00
16.2 PVC Pipes 0.00 0.00 0.00 0.00
16.2.1 50 mm dia m 500.00 117.00 58,500.00 0.00 117.00 0.00 500.00 117.00 58,500.00
16.2.2 75 mm dia m 500.00 301.00 150,500.00 0.00 301.00 0.00 500.00 301.00 150,500.00
16.2.3 100 mm dia m 4,000.00 435.00 1,740,000.00 267.60 435.00 116,406.00 3,732.40 435.00 1,623,594.00
16.2.4 200 mm dia m 2,000.00 1,636.00 3,272,000.00 0.00 1,636.00 0.00 2,000.00 1,636.00 3,272,000.00
16.2.5 300 mm dia m 500.00 4,040.00 2,020,000.00 0.00 4,040.00 0.00 500.00 4,040.00 2,020,000.00
16.3 SWG Pipes 0.00 0.00 0.00 0.00
16.3.1 100 mm dia m 150.00 849.00 127,350.00 0.00 849.00 0.00 150.00 849.00 127,350.00
16.3.2 150 mm dia half round pipes m 700.00 1,698.00 1,188,600.00 0.00 1,698.00 0.00 700.00 1,698.00 1,188,600.00
B17 Not Used 0.00 0.00 0.00 0.00
B18 Monitoring Instruments 0.00 0.00 0.00 0.00
18.1 Supply, installation and commissioning 0.00 0.00 0.00 0.00 0.00
of monitoring instrument as per tech.
18.1.1 spec. cells
Load No. 30.00 38,714.00 1,161,420.00 44.00 38,714.00 1,703,416.00 38,714.00 0.00
18.1.2 Tape convergence points. No. 55.00 204.00 11,220.00 70.00 204.00 14,280.00 204.00 0.00
18.1.3 Single point borehole extensometer. 0.00 0.00 0.00 0.00
18.1.3.1 Mechanical type. No. 6.00 10,867.00 65,202.00 15.00 10,867.00 163,005.00 10,867.00 0.00
18.1.3.2 Electrical type. No. 15.00 14,942.00 224,130.00 22.00 14,942.00 328,724.00 14,942.00 0.00
18.1.4 Multi point borehole extensometer. 0.00 0.00 0.00 0.00
18.1.4.1 Mechanical type. No. 7.00 20,376.00 142,632.00 27.00 20,376.00 550,152.00 20,376.00 0.00
18.1.4.2 Electrical type. No. 22.00 23,772.00 522,984.00 33.00 23,772.00 784,476.00 23,772.00 0.00
18.1.5 Total pressure cell. No. 5.00 12,226.00 61,130.00 0.00 12,226.00 0.00 5.00 12,226.00 61,130.00
18.1.6 Piezometers. No. 15.00 6,113.00 91,695.00 0.00 6,113.00 0.00 15.00 6,113.00 91,695.00
18.1.7 Water level measuring gauge. No. 5.00 27,168.00 135,840.00 0.00 27,168.00 0.00 5.00 27,168.00 135,840.00
B19 Water Supply & Sewerage. 0.00 0.00 0.00 0.00
19.1 Laying of water pipe line. 0.00 0.00 0.00 0.00
19.1.1 150 mm nominal dia. m 1,350.00 2,168.00 2,926,800.00 0.00 2,168.00 0.00 1,350.00 2,168.00 2,926,800.00
19.1.2 100 mm nominal dia. m 700.00 1,084.00 758,800.00 0.00 1,084.00 0.00 700.00 1,084.00 758,800.00
19.1.3 75 mm nominal dia. m 300.00 814.00 244,200.00 0.00 814.00 0.00 300.00 814.00 244,200.00
19.1.4 50 mm nominal dia. m 700.00 465.00 325,500.00 0.00 465.00 0.00 700.00 465.00 325,500.00
19.1.5 25 mm nominal dia. m 700.00 255.00 178,500.00 0.00 255.00 0.00 700.00 255.00 178,500.00
19.2 Supply & installation of pump & filter No. 1.00 4,245,000.00 4,245,000.00 0.00 4,245,000.00 0.00 1.00 4,245,000.00 4,245,000.00
for water supply.
19.3 Supply & installation of water No. 1.00 4,245,000.00 4,245,000.00 0.00 4,245,000.00 0.00 1.00 4,245,000.00 4,245,000.00
treatment plant.
19.4 Laying of sewage pipe line. 0.00 0.00 0.00 0.00
POWERHOUSE AND TRANSFORMER CAVERN (PACKAGE-C3) 0 0 0
SL. No. Description of item Unit Approved 1st RCE-March 2014 Price Level Revised Cost Estimate (March 2016 PL)
Works Completed up to March 2016 Balance works
19.4.1 150 mm nominal dia. m 400.00 1,698.00 679,200.00 0.00 1,698.00 0.00 400.00 1,698.00 679,200.00
19.4.2 100 mm nominal dia. m 150.00 1,274.00 191,100.00 0.00 1,274.00 0.00 150.00 1,274.00 191,100.00
19.5 Supply & Installation of Pumping unit No. 1.00 2,122,500.00 2,122,500.00 0.00 2,122,500.00 0.00 1.00 2,122,500.00 2,122,500.00
for sewage system.
B20 Not Used 0.00 0.00 0.00 0.00
B21 Not Used 0.00 0.00 0.00 0.00
TOTAL FOR GROUP B ### ### ###
GROUP C DAYWORKS-PART A-MATERIALS
Group C - Materials 0.00 0.00 0.00 0.00
Part A
A1 Concrete aggregates and Cement at 0.00 0.00 0.00 0.00
batching plant
A1.1 Coarse aggregates m3 1,000.00 480.00 480,000.00 0.00 480.00 0.00 480.00 0.00
A1.2 Fine aggregates m3 1,000.00 509.00 509,000.00 4.25 509.00 2,163.25 509.00 0.00
A1.3 Cement t 500.00 6,792.00 3,396,000.00 3.05 6,792.00 20,715.60 6,792.00 0.00
A2 Explosives kg 5,000.00 68.00 340,000.00 0.00 68.00 0.00 68.00 0.00
A2.1 Detonator No. 1,000.00 19.00 19,000.00 0.00 19.00 0.00 19.00 0.00
A3 Steel 0.00 0.00 0.00 0.00
A3.1 Reinforcing Steel t 100.00 42,450.00 4,245,000.00 3.25 42,450.00 137,962.50 42,450.00 0.00
A3.2 Structural Steel t 100.00 42,450.00 4,245,000.00 0.00 42,450.00 0.00 42,450.00 0.00
A4 Misc. Items 0.00 0.00 0.00 0.00
A4.1 Cement catridges 32 mm diameter, No. 2,000.00 8.00 16,000.00 0.00 8.00 0.00 8.00 0.00
300 mm long
A4.2 Resin Catridges 32 mm diameter, 300 No. 1,000.00 34.00 34,000.00 0.00 34.00 0.00 34.00 0.00
mm long
A4.3 Plywood 3 mm m2 200.00 255.00 51,000.00 0.00 255.00 0.00 255.00 0.00
Plywood 6 mm m2 200.00 849.00 169,800.00 0.00 849.00 0.00 849.00 0.00
Plywood 12 mm m2 200.00 1,698.00 339,600.00 0.00 1,698.00 0.00 1,698.00 0.00
A4.4 Wooden batten m3 5.00 4,245.00 21,225.00 0.00 4,245.00 0.00 4,245.00 0.00
A5 Construction Power KWH 50,000.00 4.00 200,000.00 0.00 4.00 0.00 4.00 0.00
Total for Group C - Part A 0.00 0.00 0.00 0.00
Part B Equipment 0.00 0.00 0.00 0.00
B1 Earthmoving and excavation 0.00 0.00 0.00
B1.1 equipment
Tracked/wheeled excavators and 0.00 0.00 0.00
loaders
B 1.1.1 Excavator below 1.2m3 Hour 5,000.00 2,056.00 10,280,000.00 206.42 1,274.00 262,979.08 1,274.00 0.00
B1.1.2 Excavator 1.2M3 to 2.4 m3 Hour 21.00 2,123.00 44,583.00 2,123.00 0.00
B1.1.3 Excavator above 2.4 m3 Hour 0.00 2,547.00 0.00 2,547.00 0.00
B1.1.4 Loaders below 2 m3 Hour 0.00 1,274.00 0.00 1,274.00 0.00
B1.1.5 Loaders 2 M3 to 3.5 m3 Hour 20.00 2,123.00 42,460.00 2,123.00 0.00
B1.2 Dump trucks and lorries Hour 0.00 0.00 0.00
B1.2.1 Dumpers below 15 T Hour 79.25 849.00 67,283.25 849.00 0.00
B1.2.2. Dumpers 15-35 T Hour 107.00 1,274.00 136,318.00 1,274.00 0.00
POWERHOUSE AND TRANSFORMER CAVERN (PACKAGE-C3) 0 0 0
SL. No. Description of item Unit Approved 1st RCE-March 2014 Price Level Revised Cost Estimate (March 2016 PL)
Works Completed up to March 2016 Balance works
ate (March 2016 PL) Variation w.r.t 1st RCE at Variation due to
Total March-2014 Price Level
Price Change in Inadequate Change in Additional Other causes.
escalation scope provision design requireme
Quantity Amount (Nu.) Quantity Amount (Nu.) nts
19=13+16 20=19*17 21=19-10 22=20-6 23 24 25 26 27 28
0.00 1,010,669,179.16
0.00 210,568,354.35
53,524,628.00
Quantity Rate (Nu.). Amount (Nu.) Quantity Rate (Nu.). Amount (Nu.) Quantity Rate (Nu.).
1 2 3 10 11 12=10*11 13 14 15=13 * 14 16 17
GROUP SURFACE WORKS
A
Site clearance LS
A1 Dewatering During Construction
1.1 Dewatering of Surface Construction Sites KWh 0.00 22.00 0.00 0.00 22.00 0.00 22.00
including supply, installation and removal
of pumping equipment from the site.
A2 Surface Excavation (Pothead yard, 0.00 0.00
TRT outlet Structure, Surge shaft &
2.1 Adit portals
Common etc.).
excavation. cu.m 49,353.95 191.00 9,426,604.45 0.00 191.00 0.00 191.00
2.2 Rock excavation. cu.m 444,185.55 340.00 151,023,087.00 169,675.58 340.00 57,689,697.20 340.00
2.3 Control perimeter blasting. sq.m 425.00 0.00 0.00 425.00 0.00 425.00
2.4 Line drilling. m 340.00 0.00 0.00 340.00 0.00 340.00
2.5 Dental excavation. cu.m 425.00 0.00 0.00 425.00 0.00 425.00
2.6 Minor excavation. sq.m 425.00 0.00 989.84 425.00 420,682.00 3,600.00 425.00
2.7 Removal of material arising from overbreak m 119.00 0.00 119.00 0.00 119.00
accepted due to geological conditions.
2.8 Extra for hauling excavated materials cu.m 102.00 0.00 3,484.48 102.00 355,416.96 44,600.00 102.00
beyond 1 km and upto 3 km.
t Estimate at March,2016 Price Level Variation w.r.t 1st RCE Variation due to
Balance works Total March-2014 Price Level
Price Change in Inadequate Change in Additional Other
escalation scope provision design requireme causes.
Amount (Nu.) Quantity Amount (Nu.) Quantity Amount (Nu.) nts
Quantity Rate (Nu.). Amount (Nu.) Quantity Rate (Nu.). Amount (Nu.) Quantity Rate (Nu.). Amount (Nu.)
1 2 3 10 11 12=10*11 13 14 15=13 * 14 16 17 18=16*17
GROUP SURFACE WORKS
A Site clearance LS
A1 Dewatering During
1.1 Construction
Dewatering of Surface Construction KWh 22.00 22.00 22.00 0.00
Sites including supply, installation
and removal of pumping equipment
from the site.
A2 Surface Excavation (Pothead
yard, TRT outlet Structure,
Surge shaft & Adit portals etc.).
2.1 Common excavation. cu.m 12,255.00 191.00 2,340,705.00 7,971.45 191.00 1,522,546.95 191.00 0.00
2.2 Rock excavation. cu.m 28,595.00 340.00 9,722,300.00 124.58 340.00 42,357.20 340.00 0.00
2.3 Control perimeter blasting. sq.m 425.00 0.00 0.00 425.00 0.00 425.00 0.00
2.4 Line drilling. m 340.00 0.00 0.00 340.00 0.00 340.00 0.00
2.5 Dental excavation. cu.m 425.00 0.00 0.00 425.00 0.00 425.00 0.00
2.6 Minor excavation. sq.m 425.00 0.00 0.00 425.00 0.00 425.00 0.00
2.7 Removal of material arising from m 119.00 0.00 0.00 119.00 0.00 119.00 0.00
overbreak accepted due to
geological conditions.
2.8 Extra for hauling excavated cu.m 102.00 0.00 0.00 102.00 0.00 102.00 0.00
materials beyond 1 km and upto 3
A3 km.
Not Used 0.00 0.00 0.00 0.00
A4 Rock stabilization and 0.00 0.00 0.00 0.00
4.1 Supports.
Rock Anchors 25 mm dia. 0.00 0.00 0.00 0.00
4.1.1 Length upto 4.0 m. m 548.00 637.00 349,076.00 548.00 637.00 349,076.00 637.00 0.00
4.1.2 Length more than 4.0 m and upto m 3,120.00 594.00 1,853,280.00 1,338.00 594.00 794,772.00 594.00 0.00
4.1.3 6.0 m. more than 6.0 m and upto
Length m 500.00 573.00 286,500.00 0.00 573.00 0.00 573.00 0.00
4.2 9.0
Rockm.Anchors 32 mm dia. 0.00 0.00 0.00 0.00
4.2.1 Length upto 6.0 m. m 722.00 0.00 0.00 722.00 0.00 722.00 0.00
4.2.2 Length more than 6.0 m and upto m 679.00 0.00 0.00 679.00 0.00 679.00 0.00
4.2.3 9.0 m. more than 9.0 m and upto
Length m 679.00 0.00 0.00 679.00 0.00 679.00 0.00
12.0 m.
4.3 Rockbolts 36 mm dia. 0.00 0.00 0.00 0.00
4.3.1 Length upto 6.0 m. m 785.00 0.00 0.00 785.00 0.00 785.00 0.00
Tail Race Tunnel(PACKAGE-C3)
SL. No. Description of item Unit Approved 1st RCE-March 2014 Price SECOND REVISED COST ESTIMATE AT MARCH,2016 PRICE LEVEL
Level
Works Completed up to March, 2016 Balance works
4.3.2 Length more than 6.0 m and upto m 764.00 0.00 0.00 764.00 0.00 764.00 0.00
4.3.3 9.0 m. more than 9.0 m and upto
Length m 722.00 0.00 0.00 722.00 0.00 722.00 0.00
12.0 m.
4.4 Extensions for embedding into m 200.00 425.00 85,000.00 0.00 425.00 0.00 425.00 0.00
concrete where required.
4.5 Mesh reinforcement. 0.00 0.00 0.00 0.00
4.5.1 Welded wiremesh. sq.m 1,110.00 229.00 254,190.00 0.00 229.00 0.00 229.00 0.00
4.5.2 Chain link fabric. sq.m 363.35 255.00 92,654.25 363.35 255.00 92,654.25 150.00 255.00 38,250.00
Prestressed anchors of 60 MT No. 0.00 0.00 0.00 0.00
capacity and 20m long at portal
A5 Shotcrete 0.00 0.00 0.00 0.00
5.1 Plain Shotcrete. cu.m 50.00 7,641.00 382,050.00 28.63 7,641.00 218,761.83 7,641.00 0.00
5.2 Cement variation in shotcrete. kg 5,000.00 8.00 40,000.00 2,004.10 8.00 16,032.80 4,000.00 8.00 32,000.00
5.3 Superplasticiser. kg 412.00 30.00 12,360.00 235.19 30.00 7,055.70 30.00 0.00
A6 Backfill 0.00 0.00 0.00 0.00
6.1 Random backfill. cu.m 700.00 212.00 148,400.00 0.00 212.00 0.00 2,560.00 212.00 542,720.00
6.2 Compacted backfill. cu.m 255.00 0.00 0.00 255.00 0.00 255.00 0.00
6.3 Free-drainage backfill. cu.m 400.00 594.00 237,600.00 0.00 594.00 0.00 594.00 0.00
6.4 Sand-gravel fill. cu.m 400.00 594.00 237,600.00 0.00 594.00 0.00 594.00 0.00
A7 Drilling, Grouting and Pressure 0.00 0.00 0.00 0.00
Relief Holes
7.1 Drilling for consolidation grouting. 0.00 0.00 0.00 0.00
7.1.1 Drilling for grout holes 45 mm dia. m 340.00 0.00 0.00 340.00 0.00 505.00 340.00 171,700.00
7.2 Placing grout (excluding cement). 0.00 0.00 0.00 0.00
7.2.1 Consolidation grouting. No. 2,123.00 0.00 0.00 2,123.00 0.00 2,123.00 0.00
7.3 Drilling for Pressure Relief holes 0.00 0.00 0.00 0.00
from open.
7.3.1 Drilling of 45 mm dia hole. m 500.00 340.00 170,000.00 225.00 340.00 76,500.00 275.00 340.00 93,500.00
7.3.2 Supply and installation of 36 mm m 500.00 119.00 59,500.00 0.00 119.00 0.00 500.00 119.00 59,500.00
dia PVC pipes.
7.4 Drilling of exploratory holes, check 0.00 0.00 0.00 0.00
holes and holes for
7.4.1 instrumentation.
Drilling of 45 dia holes. m 340.00 0.00 0.00 340.00 0.00 340.00 0.00
7.4.2 Drilling of 76 dia holes. m 425.00 0.00 0.00 425.00 0.00 425.00 0.00
7.4.3 Extra for core recovery. m 2,547.00 0.00 0.00 2,547.00 0.00 2,547.00 0.00
7.5 Grouting materials 0.00 0.00 0.00 0.00
7.5.1 Cement MT 8,490.00 0.00 0.00 8,490.00 0.00 8,490.00 0.00
7.5.2 Sand MT 1.00 594.00 594.00 0.00 594.00 0.00 594.00 0.00
7.5.3 Bentonite MT 2.00 10,613.00 21,226.00 0.00 10,613.00 0.00 10,613.00 0.00
7.5.4 Admixtures kg 500.00 64.00 32,000.00 0.00 64.00 0.00 64.00 0.00
A8 Not Used 0.00 0.00 0.00 0.00
A9 Concrete 0.00 0.00 0.00 0.00
9.1 Concrete in surface works 0.00 0.00 0.00 0.00
Tail Race Tunnel(PACKAGE-C3)
SL. No. Description of item Unit Approved 1st RCE-March 2014 Price SECOND REVISED COST ESTIMATE AT MARCH,2016 PRICE LEVEL
Level
Works Completed up to March, 2016 Balance works
9.1.1 Lean concrete M10/A80 cu.m 2,377.00 0.00 0.00 2,377.00 0.00 2,377.00 0.00
9.1.2 Cement concrete M15/A40 cu.m 600.00 2,547.00 1,528,200.00 342.33 2,547.00 871,914.51 257.67 2,547.00 656,285.49
9.1.3 Cement concrete M25/A40 cu.m 49.00 3,226.00 158,074.00 0.00 3,226.00 0.00 770.00 3,226.00 2,484,020.00
9.2 M15/A40 backfill concrete in cu.m 2,717.00 0.00 0.00 2,717.00 0.00 2,717.00 0.00
surface excavations in geologically
approved overbreaks.
9.3 Cement variation in concrete. kg 72,000.00 8.00 576,000.00 46,621.76 8.00 372,974.08 92,490.30 8.00 739,922.40
9.4 Admixtures for concrete. 0.00 0.00 0.00 0.00
9.4.1 Air-entraining agent. kg 21.00 0.00 0.00 21.00 0.00 21.00 0.00
9.4.2 Water-reducing agent. kg 806.00 25.00 20,150.00 1,572.98 25.00 39,324.50 4,350.84 25.00 108,771.00
A10 Formwork 0.00 0.00 0.00 0.00
10.1 Class F1 sq.m 22.00 340.00 7,480.00 0.00 340.00 0.00 22.00 340.00 7,480.00
10.2 Class F2 sq.m 167.00 382.00 63,794.00 148.99 382.00 56,914.18 18.00 382.00 6,876.00
10.3 Class F1C sq.m 10.00 509.00 5,090.00 0.00 509.00 0.00 10.00 509.00 5,090.00
10.4 Class F2C sq.m 13.00 552.00 7,176.00 0.00 552.00 0.00 13.00 552.00 7,176.00
A11 Reinforcing Steel 0.00 0.00 0.00 0.00
11.1 Deformed Reinforcing bars - Grade MT 50,940.00 0.00 0.00 50,940.00 0.00 50,940.00 0.00
Fe 500.
11.2 Plain reinforcing bars. MT 1.00 49,242.00 49,242.00 0.00 49,242.00 0.00 49,242.00 0.00
A12 Not Used 0.00 0.00 0.00 0.00
A13 Metalworks 0.00 0.00 0.00 0.00
13.1 Protective net on top of surge shaft. L.S. ### 0.00 0.00 4,245,000.00 0.00 4,245,000.00 0.00
0.00 0.00 0.00 0.00
A14 Not Used 0.00 0.00 0.00 0.00
A15 Not Used 0.00 0.00 0.00 0.00
A16 Miscellaneous and Ancillary 0.00 0.00 0.00 0.00
16.1 Works
Fencing and gates 0.00 0.00 0.00 0.00
16.1.1 Fencing m 30.00 849.00 25,470.00 0.00 849.00 0.00 30.00 849.00 25,470.00
16.1.2 Gates No. 169,800.00 0.00 0.00 169,800.00 0.00 169,800.00 0.00
16.2 Weep holes No. 20.00 176.00 3,520.00 0.00 176.00 0.00 20.00 176.00 3,520.00
16.3 PVC Pipes 0.00 0.00 0.00 0.00
16.3.1 50 mm dia m 100.00 119.00 11,900.00 0.00 119.00 0.00 100.00 119.00 11,900.00
16.3.2 75 mm dia m 100.00 297.00 29,700.00 0.00 297.00 0.00 100.00 297.00 29,700.00
A17 Slope protection 0.00 0.00 0.00 0.00
17.1 Wire crates/ Gabions 0.00 0.00 0.00 0.00
17.1.1 Wire crates sq.m 275,000.00 204.00 56,100,000.00 26,570.29 204.00 5,420,339.16 500.00 204.00 102,000.00
17.1.2 Boulder filling in wire crates cu.m 40,000.00 425.00 17,000,000.00 7,808.57 425.00 3,318,642.25 300.00 425.00 127,500.00
17.2 Random Rubble Masonry Wall 0.00 0.00 0.00 0.00
17.2.1 Wet R R Masonry cu.m 1,893.00 1,358.00 2,570,694.00 0.00 1,358.00 0.00 1,893.00 1,358.00 2,570,694.00
17.2.2 Dry R R Masonry cu.m 99.00 764.00 75,636.00 0.00 764.00 0.00 99.00 764.00 75,636.00
Slope protection works LS 0.00 0.00 0.00 0.00
17.3 Rock paving in mortar cu.m 1,358.00 0.00 0.00 1,358.00 0.00 1,358.00 0.00
Tail Race Tunnel(PACKAGE-C3)
SL. No. Description of item Unit Approved 1st RCE-March 2014 Price SECOND REVISED COST ESTIMATE AT MARCH,2016 PRICE LEVEL
Level
Works Completed up to March, 2016 Balance works
17.4 Concrete blocks cu.m 25.00 3,396.00 84,900.00 0.00 3,396.00 0.00 25.00 3,396.00 84,900.00
A18 Monitoring Instruments 0.00 0.00 0.00 0.00
18.1 Supply, installation and 0.00 0.00 0.00 0.00
commissioning of monitoring
18.1.1 instrument
Survey targetas point
per tech. spec. No. 611.00 0.00 0.00 611.00 0.00 611.00 0.00
18.1.2 Single point borehole extensometer 0.00 0.00 0.00 0.00
18.1.2.1 Mechanical type No. 10,867.00 0.00 0.00 10,867.00 0.00 10,867.00 0.00
18.1.2.2 Electrical type No. 14,942.00 0.00 0.00 14,942.00 0.00 14,942.00 0.00
18.1.3 Multi point borehole extensometer 0.00 0.00 0.00 0.00
18.1.3.1 Mechanical type No. 20,376.00 0.00 0.00 20,376.00 0.00 20,376.00 0.00
18.1.3.2 Electrical type No. 23,772.00 0.00 0.00 23,772.00 0.00 23,772.00 0.00
A19 Not Used 0.00 0.00 0.00 0.00
A20 Not Used 0.00 0.00 0.00 0.00
A21 Roadworks 0.00 0.00 0.00 0.00
21.1 Preparation of sub grade complete 0.00 0.00 0.00
in all respects as per Technical
specification and as directed by
Engineer in-Charge.
21.1.1 All kinds of soil cu.m 0.00 679.00 0.00 679.00 0.00
21.1.2 Rock cu.m 0.00 1,019.00 0.00 1,019.00 0.00
21.2 Cement Concrete (M25/A40) cu.m 3,226.00 0.00 3,226.00 0.00
pavements laid to required slope
and camber complete in all
respects as per Technical Shifted to R-communication
specification and as directed by
Engineer in-Charge.
21.3 Construction of lined drain m 0.00 849.00 0.00 849.00 0.00
complete in all respects as per
Technical specification and as
directed by Engineer in-Charge.
21.4 Maintenance and repair of access km-month 29,715.00 0.00 29,715.00 0.00
roads.
21.5 Turfing Sqm 0.00 170.00 0.00 170.00 0.00
0.00
0.00
0.00
TOTAL FOR GROUP A ### 0.00 13,199,865.41 7,984,610.89
GROUP BUNDERGROUND WORKS
B1 Dewatering During Construction 0.00 0.00 0.00 0.00
1.1 Dewatering of Underground KWh 25,000.00 22.00 550,000.00 23,628.00 22.00 519,816.00 25,000.00 22.00 550,000.00
Construction sites including supply,
installation and removal of pumping
equipment from the site.
B2 Not Used 0.00 0.00 0.00 0.00
B3 Underground Excavation 0.00 0.00 0.00 0.00
Tail Race Tunnel(PACKAGE-C3)
SL. No. Description of item Unit Approved 1st RCE-March 2014 Price SECOND REVISED COST ESTIMATE AT MARCH,2016 PRICE LEVEL
Level
Works Completed up to March, 2016 Balance works
3.1 Excavation of all Tunnels 0.00 0.00 0.00 0.00
3.1.1 Class I, II, & III cu.m 108,946.00 1,019.00 ### 125,605.73 1,019.00 127,992,238.87 1,019.00 0.00
3.1.2 Class IV and V cu.m 10,000.00 1,104.00 11,040,000.00 6,035.85 1,104.00 6,663,578.40 1,104.00 0.00
3.1.3 By Multiple drifting due to cu.m 1,528.00 0.00 0.00 1,528.00 0.00 1,528.00 0.00
geological reasons.
3.2 Excavation of Power house & 0.00 0.00 0.00 0.00
Transformer caverns in all classes of
rock.
3.2.1 In Power house vault (upto EL cu.m 1,019.00 0.00 0.00 1,019.00 0.00 1,019.00 0.00
3.2.2 1045).
In Power house (below EL 1045 ) & cu.m 934.00 0.00 0.00 934.00 0.00 934.00 0.00
Transformer Cavern.
3.2.3 Excavation of cable trench below EL cu.m 934.00 0.00 0.00 934.00 0.00 934.00 0.00
1028.40 in Transformer Cavern.
3.2.4 Line drilling. m 340.00 0.00 0.00 340.00 0.00 340.00 0.00
3.2.5 Dental excavation. cu.m 509.00 0.00 0.00 509.00 0.00 509.00 0.00
3.3 Excavation of Surge shaft in all 0.00 0.00 0.00 0.00
classes of rock.
3.3.1 Raise boring. m 25,470.00 0.00 0.00 25,470.00 0.00 25,470.00 0.00
3.3.2 Excavation by slashing. cu.m 1,189.00 0.00 0.00 1,189.00 0.00 1,189.00 0.00
3.4 Excavation of pressure shafts in all 0.00 0.00 0.00 0.00
classes of rock
3.4.1 Raise boring. m 25,470.00 0.00 0.00 25,470.00 0.00 25,470.00 0.00
3.4.2 Excavation by slashing. cu.m 1,528.00 0.00 0.00 1,528.00 0.00 1,528.00 0.00
3.4.3 Excavation of horizontal portions of cu.m 1,019.00 0.00 0.00 1,019.00 0.00 1,019.00 0.00
pressure shafts.
3.5 Excavation of vertical gate cu.m 3,000.00 2,547.00 7,641,000.00 1,563.12 2,547.00 3,981,266.64 2,547.00 0.00
operation shafts for TRT tunnel,
cable shafts etc in any material.
3.6 Removal of material arising from cu.m 10,710.00 255.00 2,731,050.00 9,672.10 255.00 2,466,385.50 3,300.00 255.00 841,500.00
overbreak accepted due to
geological conditions.
3.7 Extra for hauling excavated cu.m 0.00 102.00 0.00 0.00 102.00 0.00 102.00 0.00
materials beyond 1 km upto 3 km.
3.7.1 Extra for hauling excavated cu.m 21,870.00 204.00 4,461,480.00 204.00 0.00 204.00 0.00
materials beyond 3 km upto 5km.
B4 Rock stabilization and Supports 0.00 0.00 0.00 0.00
4.1 Rockbolts 25 mm dia. 0.00 0.00 0.00 0.00
4.1.1 Length upto 4.0 m. m 50,000.00 637.00 31,850,000.00 46,191.00 637.00 29,423,667.00 450.00 637.00 286,650.00
4.1.2 Length more than 4.0 m and upto m 8,000.00 616.00 4,928,000.00 4,023.00 616.00 2,478,168.00 616.00 0.00
4.2 6.0 m.
Rockbolts 32 mm dia. 0.00 0.00 0.00 0.00
4.2.1 Length upto 6.0 m. m 1,200.00 764.00 916,800.00 0.00 764.00 0.00 764.00 0.00
4.2.2 Length more than 6.0 m and upto m 722.00 0.00 0.00 722.00 0.00 722.00 0.00
4.2.3 9.0 m. more than 9.0 m and upto
Length m 700.00 0.00 0.00 700.00 0.00 700.00 0.00
12.0 m.
Tail Race Tunnel(PACKAGE-C3)
SL. No. Description of item Unit Approved 1st RCE-March 2014 Price SECOND REVISED COST ESTIMATE AT MARCH,2016 PRICE LEVEL
Level
Works Completed up to March, 2016 Balance works
4.3 Rockbolts 36 mm dia. 0.00 0.00 0.00 0.00
4.3.1 Length upto 6.0 m. m 934.00 0.00 0.00 934.00 0.00 934.00 0.00
4.3.2 Length more than 6.0 m and upto m 849.00 0.00 0.00 849.00 0.00 849.00 0.00
4.3.3 9.0 m. more than 9.0 m and upto
Length m 722.00 0.00 0.00 722.00 0.00 722.00 0.00
12.0 m.
4.4 Post tensioned rockbolts (tendons). 0.00 0.00 0.00 0.00
4.4.1 25 m long. m 1,358.00 0.00 0.00 1,358.00 0.00 1,358.00 0.00
Prestressed anchor of 60 MT No. 0.00 0.00 0.00 0.00
capacity and 20m long at portal.
4.5 Rockbolt testing No. 200.00 849.00 169,800.00 0.00 849.00 0.00 849.00 0.00
4.6 Extension for embedding into m 200.00 425.00 85,000.00 0.00 425.00 0.00 425.00 0.00
concrete where required.
4.7 Grouted anchor bar: 0.00 0.00 0.00 0.00
4.7.1 25 mm dia. m 637.00 0.00 0.00 637.00 0.00 637.00 0.00
4.7.2 32 mm dia. m 764.00 0.00 0.00 764.00 0.00 764.00 0.00
4.8 Water expandable friction anchor. 0.00 0.00 0.00 0.00
4.8.1 Length upto 5.0 m. m 0.00 934.00 0.00 0.00 934.00 0.00 934.00 0.00
4.9 Self Drilling Hollow Core Anchor: 0.00 0.00 0.00 0.00
4.9.1 25 mm dia. m 1,019.00 0.00 0.00 1,019.00 0.00 1,019.00 0.00
4.9.2 32 mm dia. m 0.00 1,274.00 0.00 0.00 1,274.00 0.00 1,274.00 0.00
4.10 Mesh reinforcement. 0.00 0.00 0.00 0.00
4.10.1 Welded wiremesh. sq.m 1,000.00 255.00 255,000.00 0.00 255.00 0.00 255.00 0.00
4.11 Lattice Girder. MT 0.00 50,940.00 0.00 0.00 50,940.00 0.00 50,940.00 0.00
4.12 Steel ribs, supply and installation MT 100.00 55,185.00 5,518,500.00 89.78 55,185.00 4,954,509.30 55,185.00 0.00
(including accessories).
4.13 Steel lagging supply and MT 9.92 55,185.00 547,435.20 3.43 55,185.00 189,284.55 55,185.00 0.00
4.14 installation.
Precast concrete lagging. cu.m 50.00 6,792.00 339,600.00 65.54 6,792.00 445,147.68 6,792.00 0.00
4.15 Drilling for Pregrouting. m 0.00 297.00 0.00 0.00 297.00 0.00 297.00 0.00
4.15.1 Grouting Operations. No. 1,698.00 0.00 0.00 1,698.00 0.00 1,698.00 0.00
4.16 Fore poling (Drilling & Installation). m 0.00 552.00 0.00 0.00 552.00 0.00 552.00 0.00
4.16.1 Grouting Operations. No. 1,698.00 0.00 0.00 1,698.00 0.00 1,698.00 0.00
4.17 Pipe Roofing. m 0.00 849.00 0.00 0.00 849.00 0.00 849.00 0.00
B5 Shotcrete 0.00 0.00 0.00 0.00
5.1 SFR Shotcrete excluding steel fibre cu.m 3,122.00 8,490.00 26,505,780.00 3,498.54 8,490.00 29,702,604.60 8,490.00 0.00
5.2 Plain Shotcrete cu.m 8,066.00 0.00 0.00 8,066.00 0.00 8,066.00 0.00
5.3 PFR Shotcrete excluding poly fibre cu.m 0.00 8,490.00 0.00 0.00 8,490.00 0.00 8,490.00 0.00
5.4 Cement variation in shotcrete kg 187,320.00 8.00 1,498,560.00 253,373.60 8.00 2,026,988.80 0.00 8.00 0.00
5.5 Superplasticizer kg 30,064.86 30.00 901,945.80 34,527.77 30.00 1,035,833.10 0.00 30.00 0.00
5.6 Steel fibre kg 124,880.00 81.00 10,115,280.00 130,799.20 81.00 10,594,735.20 81.00 0.00
5.7 Poly fibre kg 0.00 64.00 0.00 0.00 64.00 0.00 64.00 0.00
5.8 Micro silica kg 78,050.00 13.00 1,014,650.00 90,179.87 13.00 1,172,338.31 0.00 13.00 0.00
B6 Backfill 0.00 0.00 0.00 0.00
Tail Race Tunnel(PACKAGE-C3)
SL. No. Description of item Unit Approved 1st RCE-March 2014 Price SECOND REVISED COST ESTIMATE AT MARCH,2016 PRICE LEVEL
Level
Works Completed up to March, 2016 Balance works
6.1 Sand - Gravel fill in Transformer cu.m 594.00 0.00 0.00 594.00 0.00 594.00 0.00
B7 floor
Drilling, Grouting and Pressure 0.00 0.00 0.00 0.00
Relief Holes
7.1 Drilling of 45 mm dia holes for 0.00 0.00 0.00 0.00
contact grouting
7.1.1 In the Tunnels m 2,740.00 297.00 813,780.00 1,059.10 297.00 314,552.70 1,680.90 297.00 499,227.30
7.1.2 For tunnel plug m 297.00 0.00 0.00 297.00 0.00 297.00 0.00
7.1.3 In Surge shaft m 297.00 0.00 0.00 297.00 0.00 297.00 0.00
7.2 Drilling of 45 dia holes for 0.00 0.00 0.00 0.00
Consolidation grouting
7.2.1 In Surge shaft m 382.00 0.00 0.00 382.00 0.00 382.00 0.00
7.2.2 In Pressure shaft m 382.00 0.00 0.00 382.00 0.00 382.00 0.00
7.2.3 In tunnels, cavern & tunnel plug m 8,825.00 297.00 2,621,025.00 326.40 297.00 96,940.80 640.00 297.00 190,080.00
7.3 Drilling for curtain grouting for m 297.00 0.00 0.00 297.00 0.00 297.00 0.00
tunnel plugs
7.3.1 Grouting operations No. 1,868.00 0.00 0.00 1,868.00 0.00 1,868.00 0.00
7.4 45 mm dia pressure relief holes in 0.00 0.00 0.00 0.00
the tunnels and caverns
7.4.1 Drilling of 45 mm dia hole m 5,607.00 297.00 1,665,279.00 3,554.40 297.00 1,055,656.80 3,852.00 297.00 1,144,044.00
7.4.2 Supply and installation of 36 mm m 5,607.00 119.00 667,233.00 0.00 119.00 0.00 3,852.00 119.00 458,388.00
dia PVC pipes
7.4.3 Supply and installation of drain No. 255.00 0.00 0.00 255.00 0.00 255.00 0.00
outlet devices
7.5 Drilling of 45 dia pressure relief 0.00 0.00 0.00 0.00
holes in drainage gallery.
7.5.1 In Invert m 297.00 0.00 0.00 297.00 0.00 297.00 0.00
7.5.2 In Overt m 297.00 0.00 0.00 297.00 0.00 297.00 0.00
7.6 Drilling of exploratory holes, check 0.00 0.00 0.00 0.00
holes and holes for instrumentation
in tunnels and caverns.
7.6.1 Drilling of 45 dia holes m 297.00 0.00 153.00 297.00 45,441.00 297.00 0.00
7.6.2 Drilling of 76 dia holes m 425.00 0.00 171.60 425.00 72,930.00 425.00 0.00
7.6.3 Drilling of 98 dia holes m 764.00 0.00 0.00 764.00 0.00 764.00 0.00
7.6.4 Extra for core recovery m 2,547.00 0.00 0.00 2,547.00 0.00 2,547.00 0.00
7.7 Water pressure testing - simple No. 50.00 849.00 42,450.00 0.00 849.00 0.00 849.00 0.00
water test.
7.8 Embedded pipes and fittings for kg 1,000.00 64.00 64,000.00 0.00 64.00 0.00 100.00 64.00 6,400.00
grouting left permanently in place.
7.9 Placing grout (Excluding cement). 0.00 0.00 0.00 0.00
7.9.1 Contact grouting ordered by the m 594.00 0.00 0.00 594.00 0.00 594.00 0.00
Engineer-in-Charge.
7.9.2 Fill grouting. 0.00 0.00 0.00 0.00
7.9.2.1 In Temporary drainage system. m 594.00 0.00 0.00 594.00 0.00 594.00 0.00
7.9.2.2 In exploratory holes. m 594.00 0.00 0.00 594.00 0.00 594.00 0.00
Tail Race Tunnel(PACKAGE-C3)
SL. No. Description of item Unit Approved 1st RCE-March 2014 Price SECOND REVISED COST ESTIMATE AT MARCH,2016 PRICE LEVEL
Level
Works Completed up to March, 2016 Balance works
7.9.3 Consolidation grouting including 0.00 0.00 0.00 0.00
grouting for tunnel plug.
7.9.3.1 -Single stage grouting. No. 2,123.00 0.00 46.00 2,123.00 97,658.00 640.00 2,123.00 1,358,720.00
7.9.3.2 -Multiple stage grouting. stage 1,698.00 0.00 0.00 1,698.00 0.00 1,698.00 0.00
7.10 Grouting materials 0.00 0.00 0.00 0.00
7.10.1 Cement MT 1,323.00 8,490.00 11,232,270.00 78.70 8,490.00 668,163.00 1,244.30 8,490.00 10,564,107.00
7.10.2 Sand MT 10.00 594.00 5,940.00 0.00 594.00 0.00 594.00 0.00
7.10.3 Bentonite MT 20.00 11,037.00 220,740.00 0.00 11,037.00 0.00 11,037.00 0.00
7.10.4 Admixtures kg 1,000.00 64.00 64,000.00 0.00 64.00 0.00 64.00 0.00
7.10.5 Microfine/ Ultrafine Cement MT 12,735.00 0.00 0.00 12,735.00 0.00 12,735.00 0.00
B8 Not Used 0.00 0.00 0.00 0.00
B9 Concrete 0.00 0.00 0.00 0.00
9.1 Concrete lining including formwork 0.00 0.00 0.00 0.00
in all tunnels
9.1.1 Plain Cement Concrete lining 0.00 0.00 0.00 0.00
9.1.1.1 In Invert 0.00 0.00 0.00 0.00
9.1.1.1.1 -M 25/ A40 cu.m 8,406.00 3,141.00 26,403,246.00 1,860.23 3,141.00 5,842,982.43 6,545.77 3,141.00 20,560,263.57
9.1.1.1.2 -M 20/ A40 cu.m 2,972.00 0.00 0.00 2,972.00 0.00 2,972.00 0.00
9.1.1.2 In sidewalls and vaults (Overt) 0.00 0.00 0.00 0.00
9.1.1.2.1 -M 25/ A40 cu.m 23,847.00 3,396.00 80,984,412.00 15,727.17 3,396.00 53,409,469.32 8,119.83 3,396.00 27,574,942.68
-M20/A40 0.00 0.00 0.00 0.00
9.1.2 -M25/ A40 Reinforced Cement cu.m 1,048.00 3,311.00 3,469,928.00 0.00 3,311.00 0.00 1,048.00 3,311.00 3,469,928.00
Concrete
9.1.3 Tunnel plugs - M20/ A40 cu.m 3,226.00 0.00 0.00 3,226.00 0.00 475.00 3,226.00 1,532,350.00
9.2 Concrete in Shafts including 0.00 0.00 0.00 0.00
9.2.1 formwork
Cement concrete lining M25/A40 in cu.m 3,396.00 0.00 0.00 3,396.00 0.00 3,396.00 0.00
Surge Shaft
9.2.2 Backfill concrete M15/A40 behind cu.m 350.00 2,377.00 831,950.00 535.92 2,377.00 1,273,881.84 2,377.00 0.00
steel liner in Pressure shaft
9.2.3 Cement concrete M25/A40 in TRT cu.m 3,311.00 0.00 0.00 3,311.00 0.00 900.00 3,311.00 2,979,900.00
gate shaft & cable shaft
9.2.4 Concrete in Blockouts M30/ A20 cu.m 200.00 3,651.00 730,200.00 0.00 3,651.00 0.00 3,651.00 0.00
9.3 Concrete in Power house and 0.00 0.00 0.00 0.00
Transformer cavern
9.3.1 Cement concrete M25/A20 in cu.m 3,396.00 0.00 0.00 3,396.00 0.00 3,396.00 0.00
substructure of power house
9.3.2 Cement concrete M25/A20 upto cu.m 3,396.00 0.00 0.00 3,396.00 0.00 3,396.00 0.00
turbine floor of power house
9.3.3 Cement concrete M25/A20 for cu.m 3,396.00 0.00 0.00 3,396.00 0.00 3,396.00 0.00
generator barrel in power house
9.3.4 Cement concrete M25/A40 in cu.m 3,396.00 0.00 0.00 3,396.00 0.00 3,396.00 0.00
beams, columns, slabs, walls, raft
9.3.5 etc.
Cement concrete M15/A40 cu.m 2,462.00 0.00 25.54 2,462.00 62,879.48 2,462.00 0.00
Tail Race Tunnel(PACKAGE-C3)
SL. No. Description of item Unit Approved 1st RCE-March 2014 Price SECOND REVISED COST ESTIMATE AT MARCH,2016 PRICE LEVEL
Level
Works Completed up to March, 2016 Balance works
9.4 M15/A40 backfill concrete in cu.m 3,595.00 2,462.00 8,850,890.00 5,051.05 2,462.00 12,435,685.10 2,462.00 0.00
underground excavations in
geologically approved overbreaks
9.5 M25/A20 precast concrete including cu.m 3,566.00 0.00 0.00 3,566.00 0.00 3,566.00 0.00
formwork
9.6 Cement variation in concrete kg 3,338,640.00 8.00 26,709,120.00 2,448,946.60 8.00 19,591,572.80 1,827,849.00 8.00 14,622,792.00
9.7 Admixtures for concrete 0.00 0.00 0.00 0.00
9.7.1 Air-entraining agent kg 22.00 0.00 0.00 22.00 0.00 22.00 0.00
9.7.2 Water-reducing agent kg 175,250.42 25.00 4,381,260.50 109,451.75 25.00 2,736,293.75 88,984.15 25.00 2,224,603.75
9.8 Grouting of equipment foundations/ kg 64.00 0.00 0.00 64.00 0.00 64.00 0.00
Bearing plates and anchors
B10 Formwork 0.00 0.00 0.00 0.00
10.1 Class F1 sq.m 130.79 318.00 41,591.22 130.79 318.00 41,591.22 318.00 0.00
10.2 Class F2 sq.m 361.00 0.00 0.00 361.00 0.00 361.00 0.00
10.3 Class F3 sq.m 403.00 0.00 0.00 403.00 0.00 403.00 0.00
10.4 Class F1C sq.m 488.00 0.00 0.00 488.00 0.00 488.00 0.00
10.5 Class F2C sq.m 552.00 0.00 0.00 552.00 0.00 552.00 0.00
10.6 Class F3C sq.m 594.00 0.00 0.00 594.00 0.00 594.00 0.00
B11 Reinforcement Steel 0.00 0.00 0.00 0.00
11.1 Deformed Reinforcing bars - Grade MT 222.00 51,789.00 11,497,158.00 0.00 51,789.00 0.00 222.00 51,789.00 11,497,158.00
Fe 500
11.2 Plain reinforcing bars MT 49,242.00 0.00 0.00 49,242.00 0.00 49,242.00 0.00
11.3 Couplers 0.00 0.00 0.00 0.00
11.3.1 32 mm dia No. 170.00 0.00 0.00 170.00 0.00 170.00 0.00
11.3.2 36 mm dia No. 255.00 0.00 0.00 255.00 0.00 255.00 0.00
B12 Waterstops and joints 0.00 0.00 0.00 0.00
12.1 P.V.C. water stops m 297.00 0.00 0.00 297.00 0.00 297.00 0.00
12.2 Joint fillers sq.m 1,698.00 0.00 0.00 1,698.00 0.00 1,698.00 0.00
12.3 Joint Sealing Compound m 594.00 0.00 0.00 594.00 0.00 594.00 0.00
12.4 Bituminous compound sq.m 212.00 0.00 0.00 212.00 0.00 212.00 0.00
12.5 Joint Sealant (Including primer) m 594.00 0.00 0.00 594.00 0.00 594.00 0.00
B13 Metalworks 0.00 0.00 0.00 0.00
13.1 Railing m 1,274.00 0.00 0.00 1,274.00 0.00 1,274.00 0.00
13.2 Steel pipe handrail m 340.00 0.00 0.00 340.00 0.00 340.00 0.00
13.3 Ladders m 1,698.00 0.00 0.00 1,698.00 0.00 1,698.00 0.00
13.4 Gratings kg 64.00 0.00 0.00 64.00 0.00 64.00 0.00
13.5 Watertight steel cover, Frames kg 68.00 0.00 0.00 68.00 0.00 68.00 0.00
13.6 Climbing irons No. 64.00 0.00 0.00 64.00 0.00 64.00 0.00
13.7 Erection hooks kg 64.00 0.00 0.00 64.00 0.00 64.00 0.00
13.8 Steel anchorings kg 64.00 0.00 0.00 64.00 0.00 64.00 0.00
13.9 Steel pipes 0.00 0.00 0.00 0.00
13.9.1 100 mm dia m 849.00 0.00 0.00 849.00 0.00 849.00 0.00
Tail Race Tunnel(PACKAGE-C3)
SL. No. Description of item Unit Approved 1st RCE-March 2014 Price SECOND REVISED COST ESTIMATE AT MARCH,2016 PRICE LEVEL
Level
Works Completed up to March, 2016 Balance works
13.9.2 150 mm dia m 1,274.00 0.00 0.00 1,274.00 0.00 1,274.00 0.00
13.9.3 200 mm dia m 1,698.00 0.00 0.00 1,698.00 0.00 1,698.00 0.00
13.9.4 300 mm dia m 2,547.00 0.00 0.00 2,547.00 0.00 2,547.00 0.00
13.10 Cast iron pipes 0.00 0.00 0.00 0.00
13.10.1 100 mm dia m 679.00 0.00 0.00 679.00 0.00 679.00 0.00
13.10.2 150 mm dia m 1,274.00 0.00 0.00 1,274.00 0.00 1,274.00 0.00
13.10.3 200 mm dia m 2,123.00 0.00 0.00 2,123.00 0.00 2,123.00 0.00
13.10.4 300 mm dia m 2,972.00 0.00 0.00 2,972.00 0.00 2,972.00 0.00
13.10.5 500 mm dia m 4,245.00 0.00 0.00 4,245.00 0.00 4,245.00 0.00
13.11 Cable Channels kg 85.00 0.00 0.00 85.00 0.00 85.00 0.00
13.12 Miscellaneous steel sectins as edge kg 64.00 0.00 0.00 64.00 0.00 64.00 0.00
protection, frames, bearing plates,
brackets, etc. of various
dimensions, including bolts, screws,
anchors and other accessories for
interior and exterior purpose.
13.13 Installation of metalworks supplied kg 20.00 0.00 0.00 20.00 0.00 20.00 0.00
by others
B14 Structural Steel Work 0.00 0.00 0.00 0.00
14.1 Supply and erection of supporting MT 63,675.00 0.00 0.00 63,675.00 0.00 63,675.00 0.00
steel structure for false ceiling
B15 Building and Architectural Works 0.00 0.00 0.00 0.00
15.1 Building and Architectural works in L.S. ### 0.00 0.00 ### 0.00 ### 0.00
Power house and Transformer
15.2 cavern
Building and Architectural works in L.S. ### 0.00 0.00 8,490,000.00 0.00 ### 0.00
D.G. building of pothead yard
15.3 Suspended ceiling sq.m 2,547.00 0.00 0.00 2,547.00 0.00 2,547.00 0.00
B16 Miscellaneous and Ancillary Works 0.00 0.00 0.00 0.00
16.1 Concrete pipes 0.00 0.00 0.00 0.00
16.1.1 Drain pipes on concrete or sand 0.00 0.00 0.00 0.00
16.1.1.1 base
100 mm dia m 448.00 0.00 0.00 448.00 0.00 448.00 0.00
16.1.1.2 200 mm dia m 554.00 0.00 0.00 554.00 0.00 554.00 0.00
16.1.1.3 300 mm dia m 844.00 0.00 0.00 844.00 0.00 844.00 0.00
16.1.2 Pipes fully embedded in concrete 0.00 0.00 0.00 0.00
16.1.2.1 200 mm dia m 554.00 0.00 0.00 554.00 0.00 554.00 0.00
16.1.2.2 300 mm dia m 844.00 0.00 0.00 844.00 0.00 844.00 0.00
16.1.2.3 400 mm dia m 1,007.00 0.00 0.00 1,007.00 0.00 1,007.00 0.00
16.2 PVC Pipes 0.00 0.00 0.00 0.00
16.2.1 50 mm dia m 117.00 0.00 0.00 117.00 0.00 117.00 0.00
16.2.2 75 mm dia m 301.00 0.00 0.00 301.00 0.00 301.00 0.00
16.2.3 100 mm dia m 435.00 0.00 0.00 435.00 0.00 435.00 0.00
16.2.4 200 mm dia m 1,636.00 0.00 0.00 1,636.00 0.00 1,636.00 0.00
16.2.5 300 mm dia m 4,040.00 0.00 0.00 4,040.00 0.00 4,040.00 0.00
Tail Race Tunnel(PACKAGE-C3)
SL. No. Description of item Unit Approved 1st RCE-March 2014 Price SECOND REVISED COST ESTIMATE AT MARCH,2016 PRICE LEVEL
Level
Works Completed up to March, 2016 Balance works
16.3 SWG Pipes 0.00 0.00 0.00 0.00
16.3.1 100 mm dia m 849.00 0.00 0.00 849.00 0.00 849.00 0.00
16.3.2 150 mm dia half round pipes m 1,698.00 0.00 0.00 1,698.00 0.00 1,698.00 0.00
B17 Not Used 0.00 0.00 0.00 0.00
B18 Monitoring Instruments 0.00 0.00 0.00 0.00
18.1 Supply, installation and LS 0.00 0.00 0.00 3,460,000.00 0.00
commissioning of monitoring
18.1.1 instrument
Load cells as per tech. spec. No. 38,714.00 0.00 0.00 38,714.00 0.00 38,714.00 0.00
18.1.2 Tape convergence points. No. 204.00 0.00 0.00 204.00 204.00
18.1.3 Single point borehole 0.00 0.00
18.1.3.1 extensometer.
Mechanical type. No. 10,867.00 0.00 0.00 10,867.00 10,867.00
18.1.3.2 Electrical type. No. 14,942.00 0.00 0.00 14,942.00 14,942.00
18.1.4 Multi point borehole extensometer. 0.00 0.00
18.1.4.1 Mechanical type. No. 20,376.00 0.00 0.00 20,376.00 20,376.00
18.1.4.2 Electrical type. No. 23,772.00 0.00 0.00 23,772.00 23,772.00
18.1.5 Total pressure cell. No. 12,226.00 0.00 0.00 12,226.00 12,226.00
18.1.6 Piezometers. No. 6,113.00 0.00 0.00 6,113.00 6,113.00
18.1.7 Water level measuring gauge. No. 27,168.00 0.00 0.00 27,168.00 27,168.00
B19 Water Supply & Sewerage. 0.00 0.00 0.00 0.00
19.1 Laying of water pipe line. 0.00 0.00 0.00 0.00
19.1.1 150 mm nominal dia. m 2,168.00 0.00 0.00 2,168.00 0.00 2,168.00 0.00
19.1.2 100 mm nominal dia. m 1,084.00 0.00 0.00 1,084.00 0.00 1,084.00 0.00
19.1.3 75 mm nominal dia. m 814.00 0.00 0.00 814.00 0.00 814.00 0.00
19.1.4 50 mm nominal dia. m 465.00 0.00 0.00 465.00 0.00 465.00 0.00
19.1.5 25 mm nominal dia. m 255.00 0.00 0.00 255.00 0.00 255.00 0.00
19.2 Supply & installation of pump & No. ### 0.00 0.00 4,245,000.00 0.00 4,245,000.00 0.00
filter for water supply.
19.3 Supply & installation of water No. ### 0.00 0.00 4,245,000.00 0.00 4,245,000.00 0.00
treatment plant.
19.4 Laying of sewage pipe line. 0.00 0.00 0.00 0.00
19.4.1 150 mm nominal dia. m 1,698.00 0.00 0.00 1,698.00 0.00 1,698.00 0.00
19.4.2 100 mm nominal dia. m 1,274.00 0.00 0.00 1,274.00 0.00 1,274.00 0.00
19.5 Supply & Installation of Pumping No. ### 0.00 0.00 2,122,500.00 0.00 2,122,500.00 0.00
unit for sewage system.
B20 Not Used 0.00 0.00 0.00 0.00
B21 Not Used 0.00 0.00 0.00 0.00
TOTAL FOR GROUP B ### 0.00 ### 100,361,054.30
GROUP C DAYWORKS-PART A-MATERIALS 0.00 0.00 0.00 0.00 0.00 0.00
Group C - Materials 0.00 0.00 0.00
Part A
A1 Concrete aggregates and Cement 0.00 0.00 0.00
at batching plant
A1.1 Coarse aggregates m3 480.00 2.93 480.00 1,406.40 480.00 0.00
Tail Race Tunnel(PACKAGE-C3)
SL. No. Description of item Unit Approved 1st RCE-March 2014 Price SECOND REVISED COST ESTIMATE AT MARCH,2016 PRICE LEVEL
Level
Works Completed up to March, 2016 Balance works
A1.2 Fine aggregates m3 509.00 1.40 509.00 712.60 509.00 0.00
A1.3 Cement t 6,792.00 0.80 6,792.00 5,433.60 6,792.00 0.00
A2 Explosives kg 68.00 0.00 68.00 0.00 68.00 0.00
A2.1 Detonator No. 19.00 0.00 19.00 0.00 19.00 0.00
A3 Steel 0.00 0.00 0.00
A3.1 Reinforcing Steel t 42,450.00 0.00 42,450.00 0.00 42,450.00 0.00
A3.2 Structural Steel t 42,450.00 0.00 42,450.00 0.00 42,450.00 0.00
A4 Misc. Items 0.00 0.00 0.00
A4.1 Cement catridges 32 mm diameter, No. 8.00 0.00 8.00 0.00 8.00 0.00
300 mm long
A4.2 Resin Catridges 32 mm diameter, No. 34.00 0.00 34.00 0.00 34.00 0.00
300 mm long
A4.3 Plywood 3 mm m2 255.00 0.00 255.00 0.00 255.00 0.00
Plywood 6 mm m2 849.00 0.00 849.00 0.00 849.00 0.00
Plywood 12 mm m2 1,698.00 0.00 1,698.00 0.00 1,698.00 0.00
A4.4 Wooden batten m3 4,245.00 0.00 4,245.00 0.00 4,245.00 0.00
A5 Construction Power KWH 4.00 0.00 4.00 0.00 4.00 0.00
Total for Group C - Part A 0.00 0.00 0.00
Part B Equipment 0.00 0.00 0.00
B1 Earthmoving and excavation 0.00 0.00 0.00
equipment
B1.1 Tracked/wheeled excavators and 0.00 0.00 0.00
loaders
B 1.1.1 Excavator below 1.2m3 Hour 1,274.00 5.17 1,274.00 6,586.58 1,274.00 0.00
B1.1.2 Excavator 1.2M3 to 2.4 m3 Hour 2,123.00 0.00 2,123.00 0.00 2,123.00 0.00
B1.1.3 Excavator above 2.4 m3 Hour 2,547.00 0.00 2,547.00 0.00 2,547.00 0.00
B1.1.4 Loaders below 2 m3 Hour 1,274.00 37.50 1,274.00 47,775.00 1,274.00 0.00
B1.1.5 Loaders 2 M3 to 3.5 m3 Hour 2,123.00 0.00 2,123.00 0.00 2,123.00 0.00
B1.2 Dump trucks and lorries Hour 0.00 0.00 0.00
B1.2.1 Dumpers below 15 T Hour 849.00 10.50 849.00 8,914.50 849.00 0.00
B1.2.2. Dumpers 15-35 T Hour 1,274.00 0.00 1,274.00 0.00 1,274.00 0.00
B1.3 Dozers and scrapers Hour 0.00 0.00 0.00
B1.3.1 Dozers upto 100 HP Hour 1,698.00 0.00 1,698.00 0.00 1,698.00 0.00
B1.3.2 Dozers 100 HP to 300 HP Hour 2,547.00 0.00 2,547.00 0.00 2,547.00 0.00
B1.4 Other earthmoving and excavation Hour 0.00 0.00 0.00
B1.4.1 Crawler drills
equipment Hour 1,274.00 0.00 1,274.00 0.00 1,274.00 0.00
B1.4.2 Wagon drills Hour 1,104.00 0.00 1,104.00 0.00 1,104.00 0.00
B1.4.3 Jack hammers- heavy duty Hour 509.00 0.00 509.00 0.00 509.00 0.00
B1.4.4 Drilling Jumbos 2 booms Hour 5,943.00 0.00 5,943.00 0.00 5,943.00 0.00
B.1.4.5 Rockbolter Hour 4,245.00 0.00 4,245.00 0.00 4,245.00 0.00
B2 Concreting mixing/placing 0.00 0.00 0.00
B2.1 equipment
Concrete batching and mixing 0.00 0.00 0.00
equipment
B2.1.1 Concrete batching and mixing Hour 1,698.00 0.00 1,698.00 0.00 1,698.00 0.00
plant upto 30 m3/hr
Tail Race Tunnel(PACKAGE-C3)
SL. No. Description of item Unit Approved 1st RCE-March 2014 Price SECOND REVISED COST ESTIMATE AT MARCH,2016 PRICE LEVEL
Level
Works Completed up to March, 2016 Balance works
B2.1.2 Concrete batching and mixing plant Hour 2,123.00 0.00 2,123.00 0.00 2,123.00 0.00
30 to 60 m3/hr
B2.2 Truck mixers Hour 0.00 0.00 0.00
B2.2.1 Transit mixers 6 m3 or less Hour 1,274.00 0.00 1,274.00 0.00 1,274.00 0.00
B2.3 Concrete Pumps upto 30m3/hr Hour 1,189.00 0.00 1,189.00 0.00 1,189.00 0.00
B2.4 Concrete vibration equipment Hour 425.00 0.00 425.00 0.00 425.00 0.00
(Needle type)( 90-150 mm
B2.5 Shotcreting equipment
diameter) Hour 0.00 0.00 0.00
B2.5.1 Shotcreting equipment(Dry Hour 849.00 0.00 849.00 0.00 849.00 0.00
B2.5.2 Shotcrete)
Shotcrete machine with robot arm ( Hour 3,821.00 0.00 3,821.00 0.00 3,821.00 0.00
Wet Shotcrete)
B3 Drilling and Grouting Equipment 0.00 0.00 0.00
B3.1 Percussion drilling rigs/equipment Hour 1,274.00 0.00 1,274.00 0.00 1,274.00 0.00
(above and below ground)
B3.2 Rotary drilling rigs/equipment Hour 2,123.00 0.00 2,123.00 0.00 2,123.00 0.00
(above and below ground)
B3.3 Grout mixers and pumps (above Hour 0.00 0.00 0.00
and below ground)
B3.3.1 Grout pumps (mortar grout) Hour 849.00 0.00 849.00 0.00 849.00 0.00
B3.3.2 Grout pumps (cement grout) Hour 594.00 0.00 594.00 0.00 594.00 0.00
B4 Miscellaneous equipment 0.00 0.00 0.00
B4.1 Mobile cranes and lifting equipment 0.00 0.00 0.00
B4.1.1 Mobile crane below 15 T Hour 849.00 0.00 849.00 0.00 849.00 0.00
B4.1.2 Mobile crane 15 to 25 T Hour 1,698.00 0.00 1,698.00 0.00 1,698.00 0.00
B4.2 Low pressure water pumps Hour 0.00 0.00 0.00
B.4.2.1 Dewatering pumps below 10 HP Hour 594.00 0.00 594.00 0.00 594.00 0.00
B4.3 High pressure water pumps Hour 0.00 0.00 0.00
B.4.3.1 Dewatering pumps above 10 HP Hour 849.00 0.00 849.00 0.00 849.00 0.00
B4.4 Air compressors Hour 0.00 0.00 0.00
B4.4.1 Air compressors upto 300 cfm. Hour 849.00 0.00 849.00 0.00 849.00 0.00
B4.4.2 Air compressors above 300 cfm. Hour 934.00 0.00 934.00 0.00 934.00 0.00
B4.5 Generating sets Hour 0.00 0.00 0.00
B4.5.1 Diesel generating sets upto 650 Hour 5,943.00 0.00 5,943.00 0.00 5,943.00 0.00
B4.5.2 KVA
Diesel generating sets 750 KVA Hour 8,490.00 0.00 8,490.00 0.00 8,490.00 0.00
B4.6 Steel cutting, bending and welding Hour 0.00 0.00 0.00
B4.6.1 equipment
Rib bending machine Hour 425.00 0.00 425.00 0.00 425.00 0.00
B4.6.2 Welding machine Hour 340.00 0.00 340.00 0.00 340.00 0.00
B4.6.3 Steel bar cutting machine Hour 425.00 0.00 425.00 0.00 425.00 0.00
B4.7 Water tankers Hour 764.00 0.00 764.00 0.00 764.00 0.00
Total for Group C - Part B 0.00 0.00 0.00
GROUP C Labour 0.00 0.00 0.00
- Part C
C1 Category I Hour 85.00 2.00 85.00 170.00 85.00 0.00
C2 Category II Hour 64.00 38.50 64.00 2,464.00 64.00 0.00
C3 Category III Hour 51.00 14.50 51.00 739.50 51.00 0.00
C4 Category IV Hour 42.00 0.00 42.00 0.00 42.00 0.00
C5.1 Category V ( Male ) Hour 38.00 150.00 38.00 5,700.00 38.00 0.00
C5.2 Category V ( Female ) Hour 38.00 0.00 38.00 0.00 38.00 0.00
Total for Group C - Part C 0.00 0.00 0.00
TOTAL FOR GROUP C 0.00 0.00 79,902.18 0.00
Tail Race Tunnel(PACKAGE-C3)
SL. No. Description of item Unit Approved 1st RCE-March 2014 Price SECOND REVISED COST ESTIMATE AT MARCH,2016 PRICE LEVEL
Level
Works Completed up to March, 2016 Balance works
Contingencies and LS 0.00 0.00
Workcharged establishment @
5% of above items except LS
items
GRAND TOTAL (GROUP A + ### 0.00 ### 108,345,665.19
GROUP B+ GROUP C)
EXTRA ITEM-UNDERGROUND WORKS
Reaming of hole from 76mm dia to m 1,939.38
125mm dia hole 3m long in invert 153.00 1939.38 296,725.14 105.00 203,634.90
for fixing of earth mat rod
M05/A40 grade Concrete for Earth cum 1,617.90 3,563.25 232.10 3,563.25
5,764,982.18 827,030.33
Mat
Total -Extra item-Underground 0.00 6,061,707.32 1,030,665.23
Deviated works:
Item-Surface works
A2.1 Common Excavation upto Mar-2014 cu.m 4,065.10 294.22 1,196,033.72 294.22 0.00
Common Excavation beyond Mar- cu.m 312.56 5,700.00 312.56 1,781,592.00
A2.2.2 2015
Rock Excavation cu.m 3,800.00 774.55 2,943,290.00
Grouting Material- cement- upto
10509.61 0.00
Dec.14
A7.7.5.1 Grouting Material- cement- from 42.00 368,760.00
8780
Jan-15
A5.5.3 Superplasticizer kg 378.00 36 13,608.00
A5.5.1 Plain Shotcrete 40 10485 419,400.00
Total -Deviated Item-Surface 0.00 1,196,033.72 5,526,650.00
Deviated Works
Item-Underground Works
B3.3.7.1 Extra for hauling excavated Cum 26,734.52 318.45
8,513,607.89 318.45 0
materials beyond 3 km upto 5km.
B4.4.2.1 Rock bolt 32mm Dia - Length upto m 693.00 1315.12 911,378.16 1315.12 0
B4.13 6m
Steel lagging-supply and installation MT 9.47 77032.28 729,495.69 77032.28 0
B4.12 Steel Ribs MT 8.07 87656 707,383.92 87,656.00 0
B5.5.6 Steel Fibre kg 20,007.20 135.99 2,720,779.13 0.00 135.99 -
Cement concrete M15/A40 in
Cum 4,288.36 4500 19,297,620.00 3,300.00 4500 14,850,000.00
B9.4 geologically approved
overbreaks
Total -Deviated Item- 0.00 32,880,264.79 14,850,000.00
Underground Works
ESCALATION
ES1 Escalation on BOQ item. LS 6,461,137.67 27,195,242.86
ES2 Escalation on extra item. LS 2,289,647.24
Escalation on Balance work 35,864,215.58 6,773,105.58
29,484,890.10 6,773,105.58
GRAND TOTAL ### ### 136,526,086.00
Annexure-XXVI
U HYDRO ELECTRIC PROJECT, BHUTAN
0.00 0.00
5.4 Rope drum hoist complete in all respect and control equipment 2 - 6,538,131.74 -
for 5.1
5.5 Mandatory Spare Part (As per statement 1B) - 578,653.50 -
SUBTOTAL 17,618,455.32
6.4 Rope drum hoist complete in all respect and control equipment 2 - 6,408,287.54 -
for 6.1
6.5 Common hoist supporting structure & trestle etc for Intake Gate 2 - 8,724,265.36 -
& intake Bulkhead
Gate for item no. 5.1 & 6.1 -
6.6 Mandatory Spare Part (As per statement 1B) - 89,385.50 -
SUBTOTAL 24,499,691.58
8.4 EOT Crane complete in all respect including controls, Rails and 1 - 5,130,963.41 -
Fixtures etc.
8.5 Mandatory Spare Parts (As per statement 1B) - 221,111.50 -
SUBTOTAL 12,206,566.33
9.5 Hydraulic Cylinder (double acting) complete in all respect along 4 242,682.36 1,086,400.00 48,536.47
with arrangement
for gate position indication
9.6 Hydraulic Power pack complete in all respect including Electrical 4 - 7,229,720.40 -
Control, piping
etc. for a set of service & emergency gates
9.7 Mandatory Spare Parts (As per statement 1B) - 145,839.50 -
SUBTOTAL 42,923,553.42
SUBTOTAL 22,043,088.98
SUBTOTAL 4,689,614.38
-
13.8 Steel lining, bottom horizontal portion of internal diameter 3.5m 4,315,642.52 147,944,838.04 3,937,594.47
up to bifurcation
13.9 Bifurcation from 3.5m to 2.5m internal diameter 394,727.92 13,303,237.66 358,209.25
13.10 Steel lining horizontal bend with horizontal portion of internal 666,925.44 22,476,265.76 606,746.59
diameter 2.5m upto
MIV -
13.11 Thrust Collar (2.5m diameter) 79,512.84 2,679,244.76 72,363.41
13.12 Manholes (800mm diameter)-Provision of hoist cage for 23,844.54 9,803,538.30 21,543.59
maintenance of vertical pressure shaft steel liner from each
manhole
17.0 Mandatory tools & tackles (As per Statement -1A) - 188,180.00 -
SUBTOTAL - 188,180.00
Second Revised Cost Estimate at March 2016 Price Level Variation wrt Approved RCE at
ompleted work upto March 2016 Balance work to be executed Total March,14 Price Level
Price Escalation
Amount Amount Amount Qty. Amount
10 16 18 21 22
(IN INR/ NU) (IN EURO) (IN INR/ NU) (IN EURO) (IN INR/ NU) (IN EURO) (IN INR/ NU)
- -
11,173.19 78,212.31 - 89,385.50 - - -
10,320,204.65 14,179,486.93 24,499,691.58 - -
-
123,578.00 494,312.00 - 617,890.00 - - -
829,757.41 3,939,829.59 - 4,769,587.00 - - -
- -
- -
176,540.00 803,160.00 - 979,700.00 - - -
- -
143,016.80 572,067.20 - 715,084.00 - - -
- -
- -
1,368,344.08 5,861,376.32 - 7,229,720.40 - - -
- - -
29,167.90 116,671.60 - 145,839.50 - - -
- - -
68,769,696.31 49,531,953.77 - 118,301,650.08 - - -
- - -
147,089,312.83 105,420,084.17 - 252,509,397.00 - - -
- - -
50,695,689.82 95,624.78 37,142,503.04 1,015,762.66 87,838,192.86 - - -
- - - - -
49,389,697.15 343,744.00 82,077,471.33 3,900,887.98 131,467,168.48 - - -
- - - - -
34,399,379.08 204,102.72 53,631,488.62 2,226,312.96 88,030,867.70 - - -
- - - - -
85,586,163.30 378,048.05 62,358,674.74 4,315,642.52 147,944,838.04 - - -
- - - - -
1,541,452.45 7,149.43 1,137,792.31 79,512.84 2,679,244.76 - - -
287,565.27 2,300.95 9,515,973.03 23,844.54 9,803,538.30 - - -
Escalation on
58698771.8663733 Balance 37,446,548.50 96,145,320.37 96,145,320.37 96,145,320.37
Works(@6%)
13,973,635.88
1,476,797,577.52 806,044,986.39 2,282,842,563.90 250,751,867.30 96,145,320.37
Annexure-XXVII
Variation Due To
Change in Inadequate Change in Additional Other Causes
scope provision design requirement
24 25 26 27 28
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
2,633,549.05
- - - 2,633,549.05 -
110,000,000.00
2,158,903.00
16,626,336.00
2,500,000.00
1,714,123.00
5,000,000.00
- - 2,500,000.00 8,873,026.00 126,626,336.00
13,973,635.88
- - 2,500,000.00 11,506,575.05 140,599,971.88
MANGDECHHU HYDROELECTRIC PROJECT, BHUTAN
SECOND REVISED COST ESTIMATE (MARCH 2016 PRICE LEVEL
K-Buildings
Item Descripiton of item unit As per Approved 1st RCE As per 2nd Revised Cost Estimate(March, 2016 P.L) Variation w.r.t. RC
No. (March, 2014 PL) 2014 PL
Qty. Rate Amount Work completed upto March, Balance Works Total Qty.
2016
4 5 6 7 8 9 10 11 12 13 14 15
1 Residential Buildings (Permanent) Sqm 19888 434.54 475.07 103.18 578.25
16 17 18 19 20 21 22
143.71 17.25 126.46
Item Description of Work As per 1st As per 2nd Revised Cost Estimate (March,16 PL) Variation w.r.t.
No. Approved RCE Completed upto Balance Total 1st RCE Price
(March. 2014 PL) March 2016 March,14 PL Escalation
Rate Amt. Rate Amt. Rate Amt. Qty. Amt. Qty Amt.
1 Capital Cost
1.1 Electrification (As per Details in DPR) 249.91 246.00 9.00 255.00 5.09 0.61
1.2 Providing and fixing Fire Fighting Equipments 2.00 3.51 0.99 4.50 2.50 0.30
1.3 Purchase of Equipment for Quality Control/Field labs 2.00 1.80 2.00 3.80 1.80 0.22
Providing telecomminication system, faxes and wireless
1.4 42.87 66.93 9.07 76.00 33.13 3.98
equipments
1.6 Children Park and Welfare Centres for Officials and labour 2.00 0.00 2.00 2.00 0.00
1.9 Furnishing and equipping rest houses and Field hostels 5.00 25.83 4.17 30.00 25.00 3.00
2 Maintenance Cost
2.3 R& M of sanitation and Drainage 2.50 0.00 2.50 2.50 0.00
2.4 Sweeping/Cleaning and Mtc of Horticulture & Floriculture 2.90 0.00 2.90 2.90 0.00
2.5 R & M of the Fire Fighting Equipments 1.00 0.00 1.00 1.00 0.00
2.8 Maintenance of Parks and Welfare Centres 5.00 0.00 5.00 5.00 0.00
2.9 R & M of Field Hostels and rest houses 9.15 0.32 8.83 9.15 0.00
2.10 R & M of Quality Control and research labs 3.13 0.00 3.13 3.13 0.00
2.11 Labour Welfare Compensation and retrenchment benefits 7.50 0.00 7.50 7.50 0.00
2.12 Security Staff 12.50 7.88 13.12 21.00 8.50 1.02
2.13 Repair and Mtc of Hiring of Vehicles and pool vehicles 24.81 163.71 66.29 230.00 205.19 24.62
2.14 Repair/Mtc of Staff Buses 6.36 10.91 5.10 16.01 9.65 1.16
2.15 R & M of Ambulance 1.35 0.65 2.50 3.15 1.80 0.22
2.16 R & M of lighting fixtures for offices and residential complexes 4.43 1.98 3.52 5.50 1.07 0.13
3.1 Foundation Stone laying ceremonies and visit of dignataries 1.50 17.41 4.59 22.00 20.50 2.46
3.2 Mtc of Petrol/Diesel pumps 1.00 0.00 2.00 2.00 1.00 0.12
3.3 Procurement of technical literatures 1.00 0.65 1.35 2.00 1.00 0.12
3.4 Model Exhibition 2.50 1.95 1.55 3.50 1.00 0.12
3.5 Canteen facilities and cooperatives stores 1.00 0.00 1.00 1.00 0.00
3.6 Running of School 15.21 0.00 15.21 15.21 0.00
Photographic and cinematographic equipments and
3.7 0.50 0.00 0.50 0.50 0.00
maintenance
3.8 Group Insurance 1.50 2.76 0.74 3.50 2.00 0.24
3.9 Publication of Pamphlets 1.00 0.00 1.00 1.00 0.00
3.10 Time Keeping Cabin 0.50 0.00 0.50 0.50 0.00
3.11 Flood Alarming system 2.50 0.00 2.50 2.50 0.00
3.12 Publicity and Information Center 1.00 6.42 1.58 8.00 7.00
3.13 Compensation for accidents 2.50 0.91 1.59 2.50 0.00
3.14 Training of personnel abroad including study 1.00 12.27 2.73 15.00 14.00
3.15 Award to workers 1.50 0.00 1.50 1.50 0.00
sub-total 34.21 42.37 38.34 80.71 46.50 3.06
Total 539.77 738.61 279.89 1018.50 478.73 54.93
Annexure-XXIX
(Amount in Rs Million)
4.48
2.20
1.58
29.15
65.56
51.04
22.00
5.28
180.57
8.49
1.58
0.94
18.04
0.88
0.88
0.88
1.76
1.50 5.50
14.00
Qty Rate Amount Qty Rate Amount Qty Rate Amount Qty Rate Amount Qty
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Note As per direction of CWC, Maintenance on Approach Raods to Project Sites have been shifted from C Works and shown under P:Maintenance
Annexure-XXX
OST ESTIMATE AT MARCH,2016 PRICE LEVEL
(fig. in Rs. /Nu. million)
Variation w.r.t. Variation on Account of
RCE 2014 PL
16 17 18 19 20 21 22
R-COMMUNICATION
Second Revised Cost Estimate (March 2016 PL)
(Road Works from C-1 Dam Package Shifted to R-Communication as per the Direction of CWC)
Second Revised Cost Estimate (March 2016 PL)
Approved 1st RCE at March,2014 P.L.
Description of Items
Unit Completed Work upto March, 2016 Balance work to be executed
Sl.No.
Quantity Rate Amount Quantity Rate Amount Quantity Rate Amount
1 2 3 7 8 9 10 11 12
A21 Road works LS - - - -
Preparation of sub grade complete in all respects
A.21.1 as per Technical specification and as directed by - - - -
Engineer in-charge.
A.21.1.1 All kinds of soil Cum 893.45 1,173,099.85 1,814.27 1,313.00 2,382,136.51 1,313.00 -
A.21.1.2 Rock Cum 1,500.00 2,625,000.00 - 1,750.00 - 1,750.00 -
R-COMMUNICATION
Second Revised Cost Estimate (March 2016 PL)
(Road Works from C-3- UGPH Package Shifted to R-Communication as per the Direction of CWC)
SURGE SHAFT
Unit 2nd Revised Estimate (March 2016)
Aproved 1st REC - March 2014 Pice
level Completed upto March, 2016 Balance work to be executed
Sl.No Description of Item
403.11 0.00
122.27 0.00
36.39 0.00
33.39 0.00
Total
Price Inadequate change in Additional
Quantity Amount Change in scope Other Causes
Escalation provision design requirements
Quantity Amount
13 14 15 16 20 17 18 19 20 21
- - - -
- - -
Variation
As per DPR As Per Approved 1st RCE
Item w.r.t.1st RCE
Description Unit (March, 2008 PL) (March 2014 P.L.)
No. Completed upto March 2014 P.L
Balance Total
2016
Qty. Rate Amt. Qty. Rate Amt. Qty. Rate Amt. Qty. Rate Amt. Qty. Amt. Qty.
EQUIPMENT
1 Truck, 10t 10 0.80 8.00 7.54 7.54 0.00 7.54
No.
2 Water Tanker Sprinkler (10 KL) 4 1.30 5.20 2.85 2.85 2.35 5.20
No.
3 Bus/Mini Bus 8 1.00 8.00 9.69 11.92 0.00 11.92
No.
4 Car/MUV 5 0.45 2.25 9.09 11.32 0.00 11.32
No.
5 Jeep (Bolero Campers and Scorpios) 30 0.45 13.50 26.75 29.72 8.25 37.97
No.
6 Ambulance 2 0.80 1.60 7.46 7.46 0.00 7.46
No.
7 Fire Tender 2 2.00 4.00 3.85 3.85 0.15 4.00
No.
8 Recovery Van 1 1.50 1.50 0.00 0.00 1.50 1.50
No.
9 Pick up Van/L.C.V 4 0.50 2.00 0.42 0.42 2.08 2.50
No.
10 Tipper 4.5/6 Cum 10 1.00 10.00 0.00 0.00 0.00 0.00
No.
11 Explosive Van 5/10 T 2 1.20 2.40 0.00 0.00 0.00 0.00
No.
12 Petrol/Diesel Tanker 10 KL 4 1.20 4.80 0.00 0.00 0.00 0.00
No.
Total 63.25 67.65 75.08 14.33 89.41
Annexure-XXXI
STIMATE AT MARCH,2016 PRICE LEVEL
(fig. in Rs. /Nu. Million)
Variation
w.r.t.1st RCE
2014 P.L Price Change in Inadequate Change in Additional Other
Escalation Scope Provision Design requirement causes
Amt.
0.00
2.35 2.35
2.23 2.23
2.23 2.23
11.22 11.22
0.00
0.15 0.15
1.50 1.50
2.08 2.08
0.00
0.00
0.00
Rate Amount Rate Amount Rate Amount Rate Amount Rate Amount Amount
1 Restoration plan for Quarry sites 5.00 6.00 3.80 3.40 7.20 1.20 0.14
2 Rejuvenation of Muck Dumping sites 20.00 24.00 19.25 9.55 28.80 4.80 0.58
3
Landscaping and Green Belt 4.51 14.40 2.40 0.29
10.00 12.00 9.89
Development
4 Compensatory Afforestation 15.00 18.00 15.38 6.22 21.60 3.60 0.43
5 Fishery Management Plan 20.00 24.00 18.65 10.15 28.80 4.80 0.58
6 Biodiversity Conservation Plan 25.50 30.60 25.20 11.52 36.72 6.12 0.73
8 Reservoir Rim Treatment Plan 30.00 36.00 21.98 21.22 43.20 7.20 0.86
7 Catchment Area Treatment Plan 66.10 79.32 69.65 25.53 95.18 15.86 1.90
9 Health Management Plan 26.82 32.18 18.36 20.26 38.62 6.44 0.77
11 Solid Waste Management Plan 11.60 13.92 11.25 5.45 16.70 2.78 0.33
12 Water Quality Management Plan 3.00 3.60 1.20 3.12 4.32 0.72 0.09
13 Air & Noise Quality Management Plan 4.00 4.80 2.79 2.97 5.76 0.96 0.12
14 Disaster Management Plan 23.00 27.60 21.85 11.27 33.12 5.52 0.66
15 Environment Monitoring Plan 15.00 12.00 8.68 3.32 12.00 0.00
16
Management Plan for Transmission 9.32 12.00 0.00
14.98 12.00 2.68
Line
Total 300.00 348.02 260.06 152.76 412.82 64.80 7.78
Additional
Change in Inadequate Change in Other
Requiremen
Scope provision Design Causes
t
1.06
4.22
2.11
3.17
4.22
5.39
6.34
13.96
5.66
2.11
2.45
0.63
0.84
4.86
0.00
0.00
Qty Amt
Variation due to
Higher Recovery of
House Rent from the
9.71 MHPA Employees
allotted accomodation in
Project Colonies
0.432 Higher receipt from Sale
of Tender Documents
Higher receipt of
2 Interest from Deposit in
Bank
ACTUAL PROPOSED
1 2 3 4 5 6 7 8
Supply of materials-
5 100.01.05 stationery/periodicals, 7,420,727 37,897,492 7,791,763 8,181,351 -
Office Contingencies, etc.
Telecommunication &
6 100.01.08 5,307,977 19,545,901 5,573,375 5,852,044 -
Postage
Entertainment/
7 100.01.09 2,834,792 17,230,054 2,976,532 3,125,358 -
Refreshments
CPF-Employer's Matching
8 100.01.10 10,231,097 39,226,111 10,742,652 11,279,784 -
Contribution/EPF
Note:
1 Provision for Salaries have been made based on actual expenditure during FY 2015-2016 and 5% enhancement for FY 2016-17, 2017-18 respectively.
2 Enhancement in salariesis considered for absorbing the annual increments and salary raise due to promotion and other factors
3 Provision for Medical, Sattionery and Office contingenicies, Telecommunication and Postage, CPF/EPF Employers matching Contribution etc. has been k
expenditure by 5% for every Financial Year.
4 Provision for Travel / Tours and Entertainment / Refreshments has been kept enhancing the actual expenditure of FY 2013-14 by 5% for every Financial
5 Provision for Bank Charges and Rent has been kept enhancing the actual expenditure of FY 2013-14 by 5% for every Financial Year.
6 Provision for EJG Secretariat has been kept enhancing the actual expenditure of FY 2013-14 by 15% for every Financial Year.
*** Since the Establishment Cost of Rs.48.60 Cr has been included in E&M Works, this amount has been deducted from total Establishment Cost to a
amount under Establishment head is Rs.216.80 Cr (265.40-48.60).
Annexure-XXXV
ELECTRIC PROJECT, BHUTAN
ncluding Terminal Benefits)
All amount in Rs./Nu.
Net Establishment
Cost for Civil
Works ***
Total E&M
9=sum(5 to 8) 10 11=(9-10)
2,235,866,425
9,929,985
177,252,694
896,389
53,870,606
23,331,944
61,248,547
49,451,893
2,642,819,803
11,279,231
d Postage, CPF/EPF Employers matching Contribution etc. has been kept enhancing the catual
his amount has been deducted from total Establishment Cost to avoid double counting. Therefore, the net
Annexure-XXXVI
MANGDECHHU HYDRO ELECRIC PROJECT, BHUTAN
SECOND REVISED COST ESTIMATE FOR ELECTRO-MECHANICAL WORKS AT MARCH,2016 PRICE LEVEL
As per BOQ
As per approved 1st RCE (March (Contract As per Revised Cost Estimate Variation from
Variation on Account of:
2014) Awarded) ( March, 2016) RCE-1
Item
Item Particulars Unit Reason for Variation/Remarks
No.
Completed
Price
Work up to Balance Total
Escalation Change in Inadequate Change in Additional/New Other
Qty. Rate Amount Amount March 2016 Amount
upto March Scope Provision Design Items Causes
Amount Amount Amount 2016
1 2 3 4 5 6 9 12 15 17 19 20 21 22 23 24 25 26
included in TG
2 Model Test included in TG Package 0 0.00
Package
3 Construction Power
a) D.G.Sets
b) Substation
c) Transmission Line
d) Distribution Line
f) LT Switchgear, cable
TOTAL 26.60 0 0.00 26.60 26.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00
GENERATOR, TURBINE AND ACCESSORIES
Spares
included in Change in scope in drainage water
2 Spares for item (1) above 0.239 0 0.75 0.75 0.51 0.51
individual scheme
equipment cost
The scope/qunantity defined in the DPR
Bus duct for GT connection (13.8 kV,
3 Set 58.53 149.00 12.722 136.29 149.01 90.48 90.48 is not sufficient to meet the functional
10000A)
requirements
Spares
included in
7 Spares on item 3 to 6 above 1.756 1.76 1.76 0.00
individual
equipment cost
Total 6107.355 5953.368 2179.825 6231.50 124.14 0.00 16.13 90.48 17.53 0.00 0.00
As per BOQ
As per approved 1st RCE (March (Contract As per Revised Cost Estimate Variation from
Variation on Account of:
2014) Awarded) ( March, 2016) RCE-1
Item
Item Particulars Unit Reason for Variation/Remarks
No.
Completed
Price
Work up to Balance Total
Escalation Change in Inadequate Change in Additional/New Other
Qty. Rate Amount Amount March 2016 Amount
upto March Scope Provision Design Items Causes
Amount Amount Amount 2016
1 2 3 4 5 6 9 12 15 17 19 20 21 22 23 24 25 26
AUXILIARY ELECTRICAL EQUIPMENT FOR POWER STATION
Step up transformer including oil for first
1 filling (Rating 13.8/)400/sqrt 3) kV, 75 Nos. 549.50 549.50 44.975 504.52 549.50 0.00
MVA, single phase
1) actual awarded cost.
Unit tap-off Transformer (Rating 13.8/11 2) 11kv switchgear was covered under
2 Nos. 21.28 68.843 68.43 68.43 47.15 47.15
kV, 400 kVA) the same award hence covered under
this head.
included in 1
13 Transformer track rails LS included in 1 above 0 0.00 0.00 0.00
above
Yet to be
14 Illumination system LS 26.6 26.60 26.60 0.00
awarded.
Yet to be
15 Electrical workshop and Testing Equipment LS 22.61 22.61 22.61 0.00
awarded.
Sub-Total (item 2 to 8) 829.332 630.30 44.98 830.96 875.94 46.61 0.00 0.00 57.91 0.00 0.00 -11.31
Spares
included in
16 Spares @3% for items 2 to 8 4.888 4.89 4.89 0.00
individual
equipment cost
Total 834.22 630.30 44.98 835.85 880.83 46.61 0.00 0.00 57.91 0.00 0.00 -11.31
AUXILIARY EQUIPMENT AND SERVICES FOR POWER ST
(a) Electrical Overhead travelling crane for
Sets 69.16 80.472 6.9631 73.51 80.47 11.31 11.31 Actual awarded cost
PH (capacity 225T/30T/10T)
1 (b) GIS crane (5T) Set 3.325 8.0354 0.6864 7.35 8.04 4.71 4.71 Actual awarded cost
(c) Electrical Overhead travelling crane for
Set 14.963 11.763 1.0264 13.94 14.96 0.00
Butterfly Valve (75T)
Yet to be
2 Electrical lifts and Elevators Set 13.3 13.30 13.30 0.00
awarded.
Butterfly Valve of 3.5m dia alongwith oil
3 Nos 143.976 133.708 23.399 120.58 143.98 0.00
pressure unit and ventillation unit
Valve House Transformer 500 kVA 3 phase,
4 Nos 0.00 0.00 0.00 0.00 0.00
dry type
Fire Protection System with storage tanks, Yet to be
5 Set 53.20 53.20 53.20 0.00
pipes, pumps, valves etc. awarded.
1 2 3 4 5 6 9 12 15 17 19 20 21 22 23 24 25 26
Oil handling equipment with pipes, valves, Included in TG
8 Set 14.543 0.00 0.00 -14.54 -14.54 Included in TG Package
tanks, purifiers Package
Yet to be
9 Workshop machines and equipments Set 22.61 22.61 22.61 0.00
awarded.
Sub-Total (item 1 to 8) 424.19 233.978 32.075 393.592 425.666 1.479 0.000 0.000 16.022 0.000 0.000 -14.543
Spares
included in
10 Spares @3% for item 1 to 8 12.05 12.05 12.05 0.00
individual
equipment cost
Total 436.234 233.978 32.075 405.639 437.714 1.480 0.000 0.000 16.022 0.000 0.000 -14.543
400 KV Substation Equipment & Aux. Equipment & Services for Switchyard
1 Switchyard Equipment
Spares
included in Included in 2(a) above, hence provision
(d) Spares for 2(b) & 2(c ) above @3% 0.801 0.00 0.00 -0.80
individual deleted
equipment cost
Sub-Total 108.399 135.987 17.748 124.839 142.587 34.188 0.000 0.000 15.849 0.000 0.000 18.339
Total (1+2) 754.19 688.02 96.95 786.75 883.70 129.51 0.00 0.00 15.85 0.00 0.00 113.66
MANGDECHHU HYDROELECTRIC PROJECT (4x180=720MW)
Second Revised Cost Estimate for Transmission Line and Associated Works at March,2016
1 2 3 4 5 6 10 11 12 13 14 15 16 17 18
400 kV Transmission Lines
400 kV Mangdechhu HEP - Goling
1 Switching station 2xS/C on D/C tower km 35 - 2850.00* 3635.470 3853.598
lines **
400 kV Goling- Jigmeling one no. D/C included in included in included in (1) included in (1) included in
2 km 45 _ above above (1) above
Transmission line *** (1) above (1) above
* Exact quantification of cost/expenditure of individual items not possible as these are part of various EPC Contracts
** Price Escalation @3% P.A. considered between March 2014 and March 2016
Annexure-XXXVII
ELECTRIC PROJECT (4x180=720MW)
ssion Line and Associated Works at March,2016 Price Level
(fig. in Rs./Nu. million)
Variation w.r.t. 1st Variation on Account of:
RCE (March,14 PL)
19 20 21 22 23 24 25
218.128 218.128
included in
(1) above
218.128 218.128
13.906 13.906
13.188 13.188
5.876 5.876
10.115 10.115
51.216 51.216
9.795 9.795
8.300 8.300
48.546 48.546
Temporary Colony DAM Plinth area of various buildings at Temporary Colony, Power House (MHPA).
Plinth Area Residential building Plinth area (m2)
No.of Structure
Sl.No Type/ Description No. of structures For One Unit (sqm) For Total Unit (sqm) For one Unit Total
Residential Type -I 30 45 1350.00
1 Type-I - 16 Units 3 47.239 755.824 Type -II 9 75 675.00
2 Type-II - 4 Units 1 78.4 313.6 Type - III 20 85 1700.00
3 Type-III- 9 Units 3 86.297 776.673 Type -IV 3 100 300.00
4 Type-IV -5 Units 2 98.209 491.045 Type -V 1 145 145.00
5 Types-V- 1 Unit 1 145.652 145.652 Type - VI 2 160 320.00
6 Type-VI - 4 Units 4 160 640 Total residential 65 4490.00
No. of
Sl Awarded Contract Work Type of Building Unit
A. RESIDENTIAL BUILDING
160.00 320.00 166.89 333.78
140.00 420.00 166.89 500.67
100.00 800.00 145.43 1163.44
85.00 1020.00 99.35 1192.2
70.00 1680.00 89.77 2154.48
50.00 2100.00 89.77 3770.34
60.00 1800.00 99.35 2980.5
B. NON-RESIDENTIAL BUILDING
1000.00 2000.00 793.91 793.91
400.00 400.00 450.00 450.00
Construction of diversion tunnel, inlet & outlet portal and plug of Package C-1
1 460,398,991.92
Construction of intake tunnels, branch HRT, SFT, branch SFT, Adit to DC & Adit to GOC-
SFT, GOC-DC, Adit to GOC-DC, Adit to Access shaft 1 & 2, Access shaft, Adit to intake
2
tunnel and GOC-SFT of package C-1 358,541,514.66
3 Construction of Desilting chambers of Package C-1 615,785,306.94
4 Construction of Dam, Spillway and Coffer Dam of package C-1 1,123,768,618.83
5 Construction of power intake structure of package C-1 335,290,870.19
6 Total 2,893,785,302.53
7 Total % of Ecscalation Paid C-1 Package = (escalation paid /work done @ march 2016)*100 % 7.4396%
34,251,803.04
215,285,797.66
26,674,023.09
45,811,909.71
83,603,791.64
24,944,270.18
215,285,797.66 215,285,797.66
7.4396%
210741.578751697 -0.0367553296
21838099.0382199 -0.0324456822
78208085.9328476 0.0804851556
44804.0043106733 0.0904726572
6844732.80952917 0.0962022182
0.0395918038
3.96
ANNEXURE- XXXXI
ESCALATION CALCULATION FOR HRT(C2 PACKAGE)
Certified
Categ Net/adjusted
Materials
ory Workdone value Recovery of 43rd MSA value of F s
advance in this
no. workdone(CCo)
RA bill
I 1,290,586.39 - 2,501,856.00 (1,211,269.61) 0.2 0.49
-
II 7,240,401.00 510,241.88 1,050,000.00 6,700,642.88 0.2 0.28
-
III 14,310,181.32 6,479,550.00 5,016,825.00 15,772,906.32 0.2
-
IV 22,942,791.23 22,942,791.23 0.2
-
RE PRICE ADJUSTMENT
Certified
Categ Net/adjusted
Materials
ory Workdone value Recovery of 43rd MSA value of F s
advance in this
no. workdone(CCo)
RA bill
I 1,290,586.39 - 2,501,856.00 (1,211,269.61) 0.2 0.49
-
II 7,240,401.00 510,241.88 1,050,000.00 6,700,642.88 0.2 0.28
-
III 14,310,181.32 6,479,550.00 5,016,825.00 15,772,906.32 0.2
-
IV 22,942,791.23 22,942,791.23 0.2
-
V 1,917,036.73 3,022,593.75 1,517,156.25 3,422,474.23 0.2
47,700,996.66 10,012,385.63 10,085,837.25 47,627,545.04
S1 S0 l L1 L0 m M1 M0 u U1
142.5 159.8 0.04 267 199 0.14 174 157.4 0.05 125
142.5 159.8 0.07 267 199 0.37 174 157.4 0.08 125
S1 S0 l L1 L0 m M1 M0 u U1
142.6 159.8 0.04 267 199 0.14 174.1 157.4 0.05 125
142.6 159.8 0.07 267 199 0.37 174.1 157.4 0.08 125
100
U0 b B1 B0 e E1 E0 C C1 C0 d D1 D0 P
100
(1,201,010.96) 10,258.65
7,053,286.38 352,643.50
17,298,832.69 1,525,926.38
135.1 125.5 25,706,571.34 2,763,780.12
3,824,066.47 401,592.24
52,681,745.92 5,054,200.89
(1,202,208.35) (9,061.26)
7,056,035.58 355,392.70
17,255,751.41 1,482,845.09
3,825,284.12 402,809.90
52,642,736.19 4,997,068.63
Percentage
Escalation For 10.49
March,2016
ESCALATION CALCULATION FOR UGPH(C-3 PACKAGE)
arch-2016
TCH & MCH MAT/VT/CT Total
654,370,316.33 247,738,581.27 2,143,284,873.10
198,725,937.13 752,554.40 1,312,682,702.25
210,568,354.35 85,238,358.22 870,959,917.33
1,063,664,607.81 333,729,493.89 4,326,927,492.68
53,173,728.89 20,131,084.54 174,162,008.78
- 378,421.33 16,322,406.06
ESCALATION CALCULATION FOR HM -C WORKS
As Per BOQ
Item Description of Item Actual Escalation Paid Till Mar
No.
Amount Supply Transport (INR)
1 2 8
SUBTOTAL 27,059,407.79
ANNEXURE-XXXXIII
83,458.41 358,673.73
2,182.89 6,978.40
63,667.51 248,093.05
27,981.17 234,838.80
55,506.83 233,635.42
1,082,219.39
% Escalation Paid 4.00%
ESCALATION CALCULATION FOR HM - J works (as on 31st March 2016)
SUBTOTAL 17,618,455.32
SUBTOTAL 24,499,691.58
SUBTOTAL 12,206,566.33
10.3 Second Stage Embedded Parts for 10.1 including dogging arrangement - 8,435,449.80
10.4 Rope drum hoist complete in all respect and control equipment for 10.1 - 15,192,093.44
10.5 Hoist supporting structure incl. Trestle, foundation anchor etc for 10.1 - 3,820,841.64
10.6 Mandatory Spare Parts (As per statement 1B) - 131,726.00
SUBTOTAL 42,923,553.42
SUBTOTAL 22,043,088.98
17.0 Mandatory tools & tackles (As per Statement -1A) - 188,180.00
SUBTOTAL 188,180.00
Fabrication Installation
Supply Transport (INR) Total
(INR) (INR)
INR
-
-
225,780.79 180,288.12 - - 406,068.91
-
-
-
29,759.93 14,468.71 - - 44,228.64
-
-
41,615.17 8,101.94 - 49,717.11
77,815.06 45,492.61 - 123,307.67
-
119,430.23 53,594.55 - - 173,024.78
-
-
-
-
-
-
-
-
413,890.71 141,051.30 554,942.01
1,041,188.96 801,665.68 1,842,854.64
-
3,835,804.40 2,482,411.37 6,318,215.77
-
8,235,091.49 5,448,331.70 13,683,423.19
-
2,401,486.18 1,502,864.11 3,904,350.29
-
4,010,386.79 3,352,168.59 2,876,056.32 10,238,611.70
-
2,830,510.91 1,361,674.62 4,192,185.53
-
6,064,526.02 4,255,905.63 3,548,217.51 13,868,649.16
492,507.23 284,461.39 776,968.62
766,257.00 637,475.78 534,694.14 1,938,426.92
-
91600.55 83,830.69 74,871.58 250,302.82
30517.42 30,517.42
-
-
-
-
-
13,525,975.56 25,561,252.15 11,478,380.81 7,033,839.55 57,599,448.07
14,169,364.80 26,017,186.71 11,478,380.81 7,033,839.55 58,698,771.87
Actual
Escalation Paid
upto March,16
(in HM J
WORKS) 6%
Escalation Amount as per
Sl.No. Description of Works for Package C-1
1st RCE @ March 2014 PL
4 291,967,234.18
Construction of Dam, Spillway and Coffer
Dam of package C-1
5 65,532,303.69
Construction of power intake structure of
package C-1
TOTAL AMOUNT IN RS/NU. 500,661,765.70
Note :
1 For Escalation % refer Escalation Sheet for BOQ Items and Deviated Items
A
BOQ ITEMS
ed Items
ABSTRACT OF ESCALATION FOR DAM WORKS(C-1 PACK
MS
Balance Escalation to be
Total Escalation for BOQ Items
Paid(3.96% of thebalance work
@ March 2016 PL
value )
(vi) (vii)
377,833.14 34,629,636.18
2,569,015.39 29,243,038.48
3,121,858.81 48,933,768.51
102,017,406.86 185,621,198.50
6,199,859.72 31,144,129.90
114,285,973.92 329,571,771.57
0.00
N FOR DAM WORKS(C-1 PACKAGE)
DEVIATED IETMS
(ix)
1,934,786.22
159,430.04
137,525.02 366,353.29
102,206,525.28 46,756,140.01
7,082,356.40
49,216,709.57
EVIATED IETMS
Balance Escalation to be
Total Escalation for Deviated
Paid(9.97 % of thebalance
Items @ March 2016 PL
work value
- 1,934,786.22
- 159,430.04
13,711.24 380,064.54
10,189,990.57 56,946,130.58
706,110.93 706,110.93
10,909,812.75 60,126,522.31
EXTRA ITEMS Total Escalation @ March
2016 PL
(x) (xi)
36,564,422.40
29,402,468.52
49,313,833.05
975,659.91 243,542,988.99
31,850,240.83
975,659.91 390,673,953.80
-109,987,811.90
104,452,029.00
Variation wrt
Approved RCE
@March 2014 PL
(xii)
-5,548,929.27
-13,544,584.48
-8,787,990.11
-48,424,245.19
-33,682,062.85
-109,987,811.90
(5,548,929.27)
(13,544,584.48)
(8,787,990.11)
(48,424,245.19)
(33,682,062.85)
(109,987,811.90)
#NAME?
CONTRACT PACKAGE NO.C-1 (NAME OF CONTRACTOR : M/s.JAL )
RAB-07 (December)
0.04475231 0.04566501 0.06321143 0.05947638 0.06592560
RAB-08 (January) 0.04316425 0.04406357 0.06026980 0.06314407 0.06910618
RAB-09 (February) 0.04204090 0.04353209 0.06592281 0.06343581 0.07114070
RAB-10 (March) 0.04170494 0.04343032 0.07252212 0.06783614 0.07602179
RAB-11 (April) 0.04074676 0.04236659 0.07778124 0.06905701 0.07590133
RAB-12 (May) 0.04058747 0.04256241 0.07195021 0.06655755 0.07479163
RAB-13 (June) 0.04029398 0.04262148 0.07439750 0.07196280 0.07908630
2013
RAB-14 (July) 0.04073789 0.04361608 0.08205328 0.08029293 0.08909239
RAB-15 (August) 0.04041899 0.04389971 0.09855804 0.09646596 0.10680343
Average Escalation
Incremental Factor Remarks
Factor Billwise
0.02398758
0.03188672 0.00789914
0.03573837 0.00385165
0.04266509 0.00692672
0.05150356 0.00883848
0.05594673 0.00444317
0.05580615 -0.00014058
0.05594957 0.00014343
0.05721446 0.00126489
0.06030306 0.00308860
0.06117058 0.00086752
0.05928985 -0.00188073
0.06167241 0.00238256
0.06715852 0.00548610
0.07722923 0.01007071
0.07926743 0.00203821
0.08030595 0.00103852
0.08315329 0.00284734
0.08597227 0.00281898
0.08378300 -0.00218927
0.08757924 0.00379623
0.09461467 0.00703544
0.09469979 0.00008512
0.09448794 -0.00021185
0.09844131 0.00395336
0.10675526 0.00831396
0.11523260 0.00847734
0.12101184 0.00577923
0.12103087 0.00001903
0.11784296 -0.00318791
0.09986598 -0.01797698
0.08949339 -0.01037259
0.08134850 -0.00814489
0.07245317 -0.00889533
0.07861593 0.00616277
0.07488419 -0.00373174
0.08117115 0.00628696
0.08243656 0.00126541
0.07029286 -0.01214370
0.05198658 -0.01830628
0.05417234 0.00218575
0.05475861 0.00058627
0.05380904 -0.00094957
0.04009606 -0.01371298
0.04256980 0.00247374
0.03959180 -0.00297800
0.07237492 0.00034676
7.24 0.03 %
0.03959180
3.96 %
Price Adjustment/Escalation
YEAR RA Bill No.
Category-I Category-II Category-III
RAB-12 (May)
RAB-13 (June)
RAB-14 (July)
0.00675231
RAB-15 (August)
0.02124165
2013
RAB-16 (September)
0.01948301
RAB-17 (Oct,2013) 0.01302521
RAB-18 (Nov,2013) 0.01475075
RAB-19 (Dec,2013) 0.01736045
RAB-20 (Jan,2014) 0.01705339
RAB-21 (Feb,2014) 0.02146797
RAB-22 (Mar,2014) 0.03009684
RAB-23rd (April,14) - 0.02728049
RAB-24 (May,14) - 0.02806101
2014 RAB-25 (June,14) 0.03199305
RAB-26 (July,14) 0.04257388
RAB-27 (August,14) 0.05047815
RAB-28 (Sep,14) 0.06222388
RAB-29(Oct,14) 0.07044671
RAB-30(Nov,14) 0.06500982
RAB-31(Dec,14) 0.04312868
RAB-32 (Jan.,2015) 0.03071511
RAB-33 (Feb.,2015) 0.02275011
RAB-34 (March,2015) 0.01857818
RAB-35 (April,2015) 0.01879237
RAB-36 (May,2015) 0.01874120
2015 RAB-37 (June, 2015) 0.01878061
RAB-38 (July, 2015) 0.01894904
RAB-39 (Aug, 2015) 0.01880478
RAB-40 (Sep, 2015) 0.00879630
RAB-41 (Oct, 2015) 0.01890766
RAB-42 (Nov, 2015) 0.01896100
RAB-43 (Dec, 2015) 0.02378858
RAB-44 (Jan, 2016) 0.01897763
2016 RAB-45 (Feb, 2016) 0.01892016
RAB-46 (March, 2016) 0.02077566
i The Average Escalation Factor
ii The Average Escalation in Percentage
iii The Average Escalation Factor in March 2016(as base date for Balance Escalation)
iv The Average Escalation % for Balance work is
Price Adjustment/Escalation Factor (Deviated Items)
Average Escalation Incremental
Category-IV Category-V Remarks
Factor Billwise Factor
0.05617699 0.05617699
Executed Amount
6.4.4.10 TRT, Branch Tunnel and 498,024,388.97 6,951,695.25 42,325,353.25 547,301,437.47 334,672,027.78
Outlet Portal and TRT.
Remarks