EX 3

a Cost of design = 240000


b cost of programming= 120000
c Cost of in-house testing= 240000
Weaknesses inherent :
1 Requires good and realistic historical data
2 If total cost estimate is off, all other costs will be off
3 Project must be similar to past projects fot suv-deliverables to be useful
EX 4
Total function point count:
Compllexity Weighting
Element Count Low Average High Total
Inputs 10 2 20
Outputs 20 6 120
Inquiries 10 4 40
Files 30 12 360
Interfaces 50 15 750
Total 1290

a. Number pf persons/months= 258


For six people available, Project duration will be 43

b If 20 people are available, Project duration will be 12.9

c If the project must be completed in 6 months, X people needed to complete the project = 258/X=6, X=
ject = 258/X=6, X= 43