ALL PROJECTS MONTH WISE INSTALLATION TIME LINE 20-May-18

1 2 3 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23

PROJECT
S NO PROJECT NAME May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19
NO
INSTALALTION
1 P1410 MANAR MALL RE- DEVELOPMENT & EXPANSION 34 34
2 P1416 ATRIA TOWER - AL ROSTOMANI 12 24 8

3 P1430 HAMENI TOWER - CHINA CONTRUCTION 2 10 10 10 13 15 15 10


4 P1433 ZULEKHA HOSPITAL 19 19
5 P1440 PORT VIEW MIX USE PROJECT - WASL 1 75 25 15
6 P1441 DEYYAR HOTEL AND RESIDENTIAL BUILDING 61 35 25 20 15

66 P1444 JUMEIRAH PLOTS DEVELOPMENT - WASEL 2 66 40 30 20 10

8 P1445 WARSAN SOUQ - SKYLIGHTS (GINCO) 16 15 10 5

9 P1446 MAG230 - SEIDCO 10 10 25 40 45 50 50 45 40 30


10 P1447 ARJAN B+G+10 BUILDING 15 30 30 20 10
11 P1448 AG TOWER - BEIJING EMIRATES 20 30 35 45 60 60 65 55 50 40 30 25 20 10

12 P1449 ACACIA 1- B+G+9 -DUBAI HILLS 30 55 60 55 45 30 20


13 P1451 BELLUVE TOWERS 5 20 25 25 40 50 55 50 45 36 20
14 P1452 JANANA TOWER 8 15 25 25 15 12
15 P1453 KEMPINSKY HOTEL 10 15 25 35 45 55 60 65 60 40 25 15

16 P1454 JULFAR TOWER 10 25 45 65 65 55 45 25 20


17 P1455 DUBAI HILLS CINEMA BOX 25 40 55 50 35

18 CREEK RISE, DUBAI CREEK HARBOUR 12 24 24 24 32 40 80 102 102 102 102 80 60 40

TOTAL INSTALLATION 315 297 243 240 231 237 234 224 219 234 230 266 282 257 232 207 165 120 80

TOTAL FACTORY 90 90 90 90 90 90 90 90 90 90 90 90 90 90 90 90 90 90 90

TOTAL LABOUR REQUIREMENT 405 387 333 330 321 327 324 314 309 324 320 356 372 347 322 297 255 210 170

PRESENT AVAILABILITY 405

In house 318
Hired Labor 87