PLANT LOCATION CUSTOMER JOB UNIT

JAZAN – SAUDI ARABIA SAUDI ARAMCO 240832 A07

Doc no. A07-ZA-E-7007408_BAA

PROJECT / UNIT NSH Doc no. A07-NSH-MS-CVL-046


JIGCC – SULFUR RECOVERY UNlT (SRU) - IK-EPC PACKAGE-2

Sh. 1 of 9 Rev. A

SUBCONTRACTOR SUBCONTRACTOR CONTRACT NO. SUBCONTRACTOR PROJECT NO


NSH 975964 240832

Nasser S. Al-Hajri Corporation

Method Statement for Anti-Termite Application

CONTRACT NO. 6600033161


B.I.-10-01525-0002

RAMIL ASHOKAN MOHANAN CM RAJEEV GEORGE


A ISSUED FOR REVIEW 23/5/2018
ENGINEERING CONST MANAGER HSE MANAGER PROJECT DIRECTOR

Rev. Description Prepared by Checked by Reviewed by Approved by Date


PLANT LOCATION CUSTOMER JOB UNIT
JAZAN – SAUDI ARABIA SAUDI ARAMCO 240832 A07

Doc no. A07-ZA-E-7007408_BAA

PROJECT / UNIT NSH Doc no. A07-NSH-MS-CVL-046


JIGCC – SULFUR RECOVERY UNlT (SRU) - IK-EPC PACKAGE-2

Sh. 2 of 9 Rev. A

SUBCONTRACTOR SUBCONTRACTOR CONTRACT NO. SUBCONTRACTOR PROJECT NO


NSH 975964 240832

INDEX

SECTION 1 : SCOPE

2 : PURPOSE

3 : REFERENCES

4 : TERMS AND DEFINITIONS

5 : RESPONSIBILITIES

6 : TOOLS AND EQUIPMENTS

7 : PROCEDURES

8 : QA/QC

9 : HEALTH, SAFETY AND ENVIRONMENT


PLANT LOCATION CUSTOMER JOB UNIT
JAZAN – SAUDI ARABIA SAUDI ARAMCO 240832 A07

Doc no. A07-ZA-E-7007408_BAA

PROJECT / UNIT NSH Doc no. A07-NSH-MS-CVL-046


JIGCC – SULFUR RECOVERY UNlT (SRU) - IK-EPC PACKAGE-2

Sh. 3 of 9 Rev. A

SUBCONTRACTOR SUBCONTRACTOR CONTRACT NO. SUBCONTRACTOR PROJECT NO


NSH 975964 240832

1. SCOPE

The scope of this method statement is to briefly and concisely cover suitable work
sequence during the application of anti-termite works on SS-007 & PIOB-007 of
buildings construction. Also to ensure safety during the process of anti-termite works for
Building Construction of Sulfur Recovery Unit (SRU) in Area A07 – EPC Package 2, at
Jazan Integrated Gasification Combined Cycle Project (JIGCC), Saudi Arabia.

2. PURPOSE

The purpose of this method statement describes in the work procedure for Anti-Termite
Application for Buildings is to set guidelines and methodology to be followed while doing
application of anti-termite activity in accordance to project agreement and specifications.

3. REFERENCES

3.1 All design, engineering, materials and construction shall conform to the latest
requirements of local and international standards, local regulations and the
following reference documents. Latest edition at the time of contract award shall
be applicable.

3.2 When these reference documents contain conflicting requirements, the most
stringent requirements shall be applicable. In case of doubt, mandatory
requirements of SAUDI ARAMCO STANDARD such as SAES, SAMSS, SAEP
and SASD shall be prevail over project construction method statement, IFC
drawings and Project Specification. (if any) However any discrepancies shall be
brought to the attention of the company (SA).

3.3 Code Standards

SAUDI Aramco (SA) General Instruction (GI’s)

GI 2.100 Work Permit System


PLANT LOCATION CUSTOMER JOB UNIT
JAZAN – SAUDI ARABIA SAUDI ARAMCO 240832 A07

Doc no. A07-ZA-E-7007408_BAA

PROJECT / UNIT NSH Doc no. A07-NSH-MS-CVL-046


JIGCC – SULFUR RECOVERY UNlT (SRU) - IK-EPC PACKAGE-2

Sh. 4 of 9 Rev. A

SUBCONTRACTOR SUBCONTRACTOR CONTRACT NO. SUBCONTRACTOR PROJECT NO


NSH 975964 240832

Saudi Aramco Engineering Standards (SAES’s)

SAES-M-100 Saudi Aramco Building Code

SAES-Q-001 Criteria for Design and Construction of Concrete


Structure

SAES-Q-005 Concrete Foundations

Project Specification:

A07-ZA-E-7009647_BAG_A Work Procedure for Concrete Work, Concrete


Repair and Repair in Sump

A00-ZA-E-9909612_00B Quality Control Specification for General Civil


Work

A07-ZA-E-7007380_BAB_A MAR for Termite Protection – Arabian Trading


and Services Co. / HIT Saudi Arabia

A07-ZA-E-7085000_BGG_A Project HSE & Security Plan

A07-ZA-E-7085003_BGG_A Medical and First Aid Facility Management


Plan

A07-ZA-E-7085004_BGG_00 Emergency Response Plan

General HSE Plan

A07-ZA-E-7085005_BGG_A Permit To Work Procedure (PTW)

SACSM Saudi Aramco Construction Safety Manual

Reference Issued for Construction Drawings:

A07-Q-VA-098550-11_00D SS-007 – Internal Slab Reinforcement

A07-Q-VA-099338-16_00G PIOB-007 – Internal Slab Reinforcement


PLANT LOCATION CUSTOMER JOB UNIT
JAZAN – SAUDI ARABIA SAUDI ARAMCO 240832 A07

Doc no. A07-ZA-E-7007408_BAA

PROJECT / UNIT NSH Doc no. A07-NSH-MS-CVL-046


JIGCC – SULFUR RECOVERY UNlT (SRU) - IK-EPC PACKAGE-2

Sh. 5 of 9 Rev. A

SUBCONTRACTOR SUBCONTRACTOR CONTRACT NO. SUBCONTRACTOR PROJECT NO


NSH 975964 240832

4. TERMS AND CONDITION

Client : SAUDI ARAMCO OIL COMPANY (SA)


Contractor : Snamprogetti Engineering & Contracting Co. Ltd. (KSA)
Sub-contractor : Nasser S. Al-Hajri Corporation (NSH Corp.)
SAES : Saudi Aramco Engineering Standards
ACI : American Concrete Institute
ASTM : American Society for Testing and Materials
SAMSS : Saudi Aramco Material System Specification
SACSM : Saudi Aramco Construction Safety Manual
ITP : Inspection Test Plan
QCP : Quality Control Specification
MSDS : Material Safety Data Sheet

5. RESPONSIBILITY:

5.1 Site Manager - They have the responsibility to establish and execute
Construction Plan and ensure full compliance to project safety and
requirements. Note that implementation of Construction Quality Plan apply to
all such as Construction Management, Field Engineering, Field Procurement,
Quality Personnel, etc.

5.2 Construction Manager - In charge shall be responsible for the coordination


and supervision of construction works (activities) and construction groups,
ensuring that work are done as per project specification and approved
PLANT LOCATION CUSTOMER JOB UNIT
JAZAN – SAUDI ARABIA SAUDI ARAMCO 240832 A07

Doc no. A07-ZA-E-7007408_BAA

PROJECT / UNIT NSH Doc no. A07-NSH-MS-CVL-046


JIGCC – SULFUR RECOVERY UNlT (SRU) - IK-EPC PACKAGE-2

Sh. 6 of 9 Rev. A

SUBCONTRACTOR SUBCONTRACTOR CONTRACT NO. SUBCONTRACTOR PROJECT NO


NSH 975964 240832

drawings, and all the safety measures are implemented at site construction and
report to Construction manager civil.

5.3 Site Foreman - shall supervise closely the activities designated to him
ensuring that all instructions are followed and strictly adhered to, (this may
involve providing alternative access routes for moving Traffic with Traffic Signs
prior to commencing the work, and all safety procedures of the project are
strictly followed.
5.4 QC Engineer – responsible to ensure that all activities are carried out as per
QC requirements of the project.
5.5 HSE Manager – To provide the HSE advised to the construction team and
monitors the implementation of the HSE requirements within the construction
area per Project HSE procedure.
5.6 Safety Supervisor – To be present at all time during implementation of the
activity and monitor that the work is carried out in accordance with Project
safety procedures.

6. TOOLS AND EQUIPMENT:

6.1 Eye Safety Wear Protection


6.2 Hand Gloves
6.3 Face Shield Safety Protection
6.4 Full Body Cover Barrier
6.5 Dual Anti-Dust Respiratory Mask
6.6 Electric Power Operated Drilling Machine
6.7 Air Compressor
PLANT LOCATION CUSTOMER JOB UNIT
JAZAN – SAUDI ARABIA SAUDI ARAMCO 240832 A07

Doc no. A07-ZA-E-7007408_BAA

PROJECT / UNIT NSH Doc no. A07-NSH-MS-CVL-046


JIGCC – SULFUR RECOVERY UNlT (SRU) - IK-EPC PACKAGE-2

Sh. 7 of 9 Rev. A

SUBCONTRACTOR SUBCONTRACTOR CONTRACT NO. SUBCONTRACTOR PROJECT NO


NSH 975964 240832

7. PROCEDURE:

7.1 GENERAL
This procedure describes the actual steps to be taken and sequence of events
necessary to enable satisfactory completion of each activity.
a. Ensure that all necessary IFC drawings, specification, approved procedures and
other documents associated with the anti-termite application are available before
and during the work activities.
b. Confirm and check the approved type of anti-termite materials and tools to be
used. Used anti-termite materials based on the requirements of Saudi Aramco (SA)
Specification.
c. Obtain proper relevant application of work permit.
d. Prior to anti-termite application, clean and remove all foreign materials and litigants
from concrete surface whereas, anti-termite is applicable or as per anti-termite
manufacturer recommendation prior to anti-termite activity.
e. Whereas, anti-termite application shall commence. Cleanse the area with clean
water for at least 24 hours prior to the application of anti-termite solutions or as per
manufacturer recommendation.
f. Whereas, if required coordination with all relevant parties who are required to
witness the procedure by method agreed on a project basis.
g. Use of BIFLEX TC (Pyrethroid Insecticide) as per SAES-M-100 General Section
2304.11 Protection against decay and termite and approved MAR # A07-ZA-E-
7007380_BAB_A.
PLANT LOCATION CUSTOMER JOB UNIT
JAZAN – SAUDI ARABIA SAUDI ARAMCO 240832 A07

Doc no. A07-ZA-E-7007408_BAA

PROJECT / UNIT NSH Doc no. A07-NSH-MS-CVL-046


JIGCC – SULFUR RECOVERY UNlT (SRU) - IK-EPC PACKAGE-2

Sh. 8 of 9 Rev. A

SUBCONTRACTOR SUBCONTRACTOR CONTRACT NO. SUBCONTRACTOR PROJECT NO


NSH 975964 240832

7.2 WORK PROCEDURE


a. Drill holes along the expansion and contraction joints inside building concrete
slab SS-007 and PIOB-007. The depth of the holes shall be at least 250mm,
the distance between holes will be range from 500mm to 1,000mm apart.
b. Inside each drilled hole, approximately 2.5 liters of diluted termiticide chemical
shall be injected.
c. Termite control will be apply along the expansion joints to penetrate into the
soil, for controlling termites there should be maximum chances of termiticide
chemical penetrating the soil. Termitecide forms the barrier and increases the
protection to break the chemical barrier of termite penetration.
d. Termiticide is injected into each drilled hole, using a high pressure
plunger/injection to penetrate down towards inner section of the drilled concrete
premise.
e. The chemical poured into the hole shall slowly gaze down into the soil in zigzag
manner.
f. Upon completion of the application, drilled holes shall be filled with approved
sealant (NITOSEAL 125) to keep the injected toxicants undisturbed.
g. After termite treatment completion, waste materials shall be cleared from the
surrounding of the hole.

8. QA/QC

8.1 The QA/QC inspection of NSH shall carry out all inspection and testing related to anti-
termite application/work. All inspection and test activities shall be raise thru Request
for Inspection (RFI) as per compliance with schedule “Q” and approved ITP.
PLANT LOCATION CUSTOMER JOB UNIT
JAZAN – SAUDI ARABIA SAUDI ARAMCO 240832 A07

Doc no. A07-ZA-E-7007408_BAA

PROJECT / UNIT NSH Doc no. A07-NSH-MS-CVL-046


JIGCC – SULFUR RECOVERY UNlT (SRU) - IK-EPC PACKAGE-2

Sh. 9 of 9 Rev. A

SUBCONTRACTOR SUBCONTRACTOR CONTRACT NO. SUBCONTRACTOR PROJECT NO


NSH 975964 240832

9. HEALTH, SAFETY & ENVIRONMENT:

9.1 Hazard and Risk Assessment report is intended as a guide, which the company
uses for the purposes of attempting to reduce the possibility of accidents or ill
health occurring record.

9.2 Site supervisor shall check all personnel involved in the above activities and shall
follow the requirements of HSE plan.

9.3 Standard PPE & breathing apparatus is required for this task as per required in
MSDS. (if any)

9.4 Always check proper caution instruction for materials prior to starting the work.

9.5 Every effort shall be made to assure that employees can accomplish their
assigned scope of work safely.

9.6 Adequate welfare and drinking water facilities should be provided

9.7 Contractor/ Sub-contractor shall comply with the requirements for controlling
safety hazards associated with anti-termite application activities as per Saudi
Aramco Standards, Specification, Saudi Aramco General Instruction, Construction
Safety Manual and Manufacturer Recommendation.

10. ATTACHEMENTS:

10.1 Job Safety Analysis for Anti-Termite Application

10.2 MSDS for Termiticide solution (BITFLEX TC)

10.3 IFC DRAWINGS:

a. A07-Q-VA-098550-11_00D SS-007 – Internal Slab Reinforcement

b. A07-Q-VA-099338-16_00G PIOB-007 – Internal Slab Reinforcement